Accelerated Bridge Construction List
Excel Version (40 kb)
Updated 11/03/04
| State |
Location & name |
year completed |
Prefab elements |
time of completion |
est. non-ABC time |
incentive/ savings ($) |
construction comments |
Reference |
| Alabama |
I-65 / I-59 Interchange, Birmingham |
2002 |
prestressed girders |
37 days |
90 days |
reward $25,000 /day |
15 girders replaced in 12 nighttime hours |
1,2 |
| Alabama |
Dauphin Island Bridge, near Mobile |
1982 |
superstructure |
34 months |
|
|
|
|
| Alaska |
Pelican Creek, Chicagof Island |
1992 |
pile caps, superstruct |
5 weeks |
|
|
typical ADOT decked bulb-tees |
1,3 |
| Alaska |
Kouwegok Slough, Unalakleet |
2000 |
pile caps, deck panels |
55 days |
|
|
typical ADOT deck panels |
1 |
| California |
IH80 / Carquinez Strait |
2003 |
box girders, bent caps, cofferdams |
|
|
|
improved constructability, safety |
1 |
| California |
580 / 680 Interchange, San Francisco |
2002 |
girders |
|
|
|
|
|
| California |
Interstate 5, Orange County |
2000 |
girders |
|
|
|
built with in 10 feet of a large office building - girders placed at night |
1,3 |
| California |
Richmond-San Rafael Bridge |
|
bent caps, girders |
|
|
|
|
|
| Colorado |
French Creek Viaduct |
1994 |
|
|
|
|
|
4 |
| Colorado |
Hanging Lake Viaduct |
1993 |
superstructure |
|
|
|
built from above to protect environment |
4 |
| Colorado |
SH 66 Michell Gulch |
2002 |
girders, bent caps |
48 hours |
2-3 months |
|
curbs precast with outside girders |
1,3,4 |
| Connecticut |
Church Street, New Haven |
2003 |
steel through truss |
|
year longer |
saved 1.1 mil. |
320-ft long 850 ton prefab truss |
1,3 |
| Connecticut |
I-84 / Rt.8 Interchange, Waterburg |
1999 |
deck |
48 days |
|
|
slightly more expesive than cast-in-place |
4 |
| Connecticut |
Rt. 8 Viaduct, Seymour |
|
deck |
2 seasons |
|
|
weekend closures only |
4 |
| Delaware |
Magazine Ditch Bridge |
|
superstructure. |
1 day |
|
|
FRP composite materials |
5 |
| Delaware |
Chesapeake and Delaware Canal |
1995 |
substructure |
|
|
|
|
6 |
| Florida |
Edison Bridge, Fort Meyer |
|
|
|
|
|
|
6 |
| Florida |
Garcon Point Bridge, Santa Rosa County |
1999 |
total bridge |
7 days |
|
|
set a world record for precast segmental span-by-span construction |
|
| Florida |
Reedy Creek Bridge, Orlando |
1997 |
total prefab bridge |
19 months |
|
|
top down construction |
1,3 |
| Florida |
Seven Mile Bridge, Florida Keys |
1982 |
girders, substructure |
|
|
saved $7 mil. |
|
4,5 |
| Florida |
Skyway Bridge, Tampa |
|
segmental piers |
|
|
|
|
5 |
| Hawaii |
H-3 Windward Viaduct, Oahu |
**** |
|
|
|
|
|
4 |
| Hawaii |
Keaiwa Stream Bridge, Pahala |
2000 |
deck |
6.5 months |
13 months |
|
only route - 3 hour detour |
1,2 |
| Illinois |
Well Street, Chicago |
2002 |
steel through truss |
single weekend |
6 months |
|
contractor's V-E proposal to prebuild |
1,3 |
| Illinois |
Route 29 over Sugar Creek |
2001 |
decks |
|
|
|
|
1 |
| Illinois |
Rt. 136 over Illinois River, Havana |
|
exodermic deck |
|
|
|
|
4 |
| Illinois-Indiana |
Milton-Madison Bridge over Ohio River |
|
exodermic deck |
|
|
|
|
4 |
| Iowa |
Iowa River ,US20 |
2003 |
girders |
|
|
|
1st launched I-girder highway bridge in US |
4 |
| Kentucky |
US 27 over Pitman Creek |
1993 |
deck |
|
|
|
nighttime work 6pm - 6am |
1 |
| Louisiana |
I-10 over Lake Pontchartrain |
2002 |
superstructure units |
|
|
$20,000 / span |
remove / replace span 24 hours |
1,4 |
| Maine |
Sagadahoc Bridge, Bath-Woolwich |
2000 |
girders |
|
|
|
longest precast segmental span built in the balanced cantalever fashion |
|
| Maryland |
MD 24 over Deer Creek |
2001 |
deck |
|
|
|
FRP deck panels facilitated erection |
3 |
| Minnesota |
Highway 47 over Seelye Brook |
2001 |
beams |
|
|
|
no detour route available |
1,2 |
| Mississippi |
Biloxi I-110 |
1988 |
|
|
|
saved $4.2 mil. |
|
|
| Missouri |
Eads Bridge over Mississippi, St. Louis |
|
exodermic deck |
|
|
|
|
4 |
| Missouri |
IH70 over Lake St. Louis Blvd |
2003 |
precast deck & beams section |
|
|
saved months |
reduced number of spans |
1 |
| Nebraska |
Fairview Bridge over I-80, Sarpy County |
|
precast deck panels |
|
|
|
|
5 |
| New Hampshire |
Mill Street Bridge in Epping |
2004 |
footings, abutments, wings & superstructure |
8 days |
5 months |
incentive /disincentive $30K/day less/more than 14 days |
grouted splice sleeves used for ftg to abutment/wing connection |
9 |
| New Jersey |
Airport Monorail, Newark |
|
substructure |
|
|
|
|
4 |
| New Jersey |
Driscoll Bridge, Garden State Parkway |
|
exodermic deck |
|
|
|
|
4 |
| New Mexico |
Mountain Valley Road over I-40, Tijeras |
### |
bent caps |
45 days |
|
|
|
4 |
| New York |
JFK Light Rail System, New York |
2003 |
superstructure |
|
|
|
most segments of any segmental bridge in America - each one unique |
|
| New York |
Cross Westchester Expressway I-287, |
|
precast piers |
|
|
|
|
4,5 |
| New York |
Bronx River Parkway Viaduct, |
|
precast piers |
|
|
|
|
4 |
| New York |
Saw Mill River Parkway Viaduct |
|
precast piers |
|
|
|
|
4 |
| New York |
Main Street over Metro North RR, Tuckahoe |
2000 |
superstructure |
|
|
|
construction done btwn 2-4 am, 2 lanes kept open, RR nondisrupted |
1,2,4 |
| New York |
Long Island Expressway over 58th St., Queens |
2002 |
superstructure |
2 weekends |
|
|
two spans using "Inverset" units |
4 |
| New York |
Horse Shoe Bridge, Rt. 23A, Catskill |
1988 |
superstructure |
|
|
|
first span using "Inverset" units |
4 |
| New York |
NYS Thruway over Central Avenue (Rt. 100) |
1999 |
superstructure |
2 weekends |
|
|
two spans continuous, "Inverset" units |
4 |
| New York |
Belt Parkway over Ocean Parkway |
2002 |
total bridge |
|
|
|
extentive use of precast elements, temporary bridge to maintain traffic |
4 |
| New York |
I-287 Viaduct, Westchester County |
1999 |
total bridge |
26 months |
34 months |
|
|
1,2,4 |
| New York |
Kingston-Rhinecliff Bridge Hudson River |
|
exodermic deck |
|
|
|
|
4 |
| New York |
Verrazano Narrows Bridge |
|
steel grid deck |
|
|
|
|
4 |
| New York |
Brooklyn Bridge |
|
filled steel grid deck |
nighttime re-decking |
|
|
stringers and deck units replaced at night |
4 |
| New York |
Tappan Zee Hudson River |
1998 |
deck |
10 hours |
|
|
construction at night |
1,4,5 |
| New York |
NY367, Bentley Creek, Chemung County |
1999 |
deck |
|
|
|
FRP composite bridge deck |
4 |
| New York |
Route 9 / Metro North Pedestrain Bridge |
1998 |
total bridge |
|
|
|
|
1,2 |
| New York |
Troy-Menands Bridge, Near Albany |
1995 |
decks |
|
|
|
If failed to open bridge by 6am there was a penalalty of $10,000 / hour |
1 |
| New York |
Robert Moses Causeway |
$$$ |
bent caps / decks |
|
|
|
|
4,5 |
| New York |
Channel Bridge, Upstate NY |
$$$ |
superstructure |
|
|
|
|
4,5,7 |
| New York |
Route 17 M |
|
deck panels |
14 months |
|
|
3 span continuous |
5,7 |
| New York |
Carpenter Road |
|
deck panels |
6 months |
|
|
single span |
5,7 |
| New York |
Cross Bay Blvd over North Channel |
|
precast system |
|
|
|
cyl piles, precast pier cap form, prestressed I beams, precast diaphragm
forms, prestressed subdeck panels, precast barrier |
5 |
| North Carolina |
Beaufort Morehead RR Trestle |
1999 |
bent caps |
|
|
|
weekly track outages of 4 day duration |
1 |
| North Carolina |
Linn Cove Viaduct, Grandfather Mountain |
1983 |
total prefab bridge |
|
|
|
first to be built from the top down to protect the environment |
1,4 |
| Ohio |
Fairgrounds Road Between Xenia and Beaverbrook |
2002 |
deck |
|
|
|
FRP deck panels |
1 |
| Oklahoma |
I-40 Arkansas River Bridge |
2002 |
sub and superstructure |
64 days |
|
|
After barge collision, and demolition reconstruction took 47 days, expedited
design and construction |
4 |
| Oregon |
Mill Creek Bridge |
|
exodermic deck |
4 weeks |
|
|
redecking with no weekend closures |
4 |
| Pennsylvania |
South 10th St. Bridge, Pittsburgh |
1920s |
filled steel grid deck |
|
|
|
|
4 |
| Pennsylvania |
Jerome St. Bridge, Mckeesport |
1920s |
filled steel grid deck |
|
|
|
|
4 |
| Pennsylvania |
Norfolk Southern RR Bridge over I-76 |
2002 |
superstructure |
one weekend |
|
|
|
1 |
| Pennsylvania |
I-95 / Chester Creek |
1998 |
girders |
approx. 3 weeks |
|
|
crash on Memorial Day weekend, open by July 4th |
1 |
| Pennsylvania |
I-95 / Westmoreland Viaduct, Philadelphia |
1996 |
I-beams |
126 days after fire |
250 days |
user savings $1 million/day |
declared a disaster emergency (150,000 vehicles/day) |
1 |
| Puerto Rico |
Baldority de Castro Avenue, San Juan |
2003 |
total bridge |
21-36 hours /overpass |
|
|
construction lasted 1 weekend |
1,4 |
| Tennessee |
Route 57 over Wolf River |
1999 |
bent caps |
11 months |
|
|
one lane always open - bent caps fabed in segments to accommodate, equipment
never placed in wetlands |
1,2,4 |
| Tennessee |
Natchez Trace Parkway Arches |
1994 |
|
|
|
|
America's first precast segmental technology for arches |
|
| Texas |
IH-35, Austin |
1974 |
girders |
|
|
|
early precast girders |
4 |
| Texas |
IH-35, Bell, McLennan, Bosque Counties |
2004 |
total bridge |
|
|
|
initially 5, then about 200 bridges |
4,5,7,8 |
| Texas |
Dallas/Fortworth International Airport |
2004 |
columns |
|
|
|
11 minutes transport time |
1 |
| Texas |
High Five Interchange US 75-IH635, Dallas County |
2007 |
total bridge |
|
|
|
Contractor redesigned to precast fron Cpi segmental |
4,8 |
| Texas |
SH 36 over Lake Belton, Waco |
2004 |
bent caps, decks |
|
|
|
|
1,3,4,5,7,8 |
| Texas |
Wesley Street Bridge |
2002 |
deck |
4 months |
|
|
|
|
| Texas |
SH 66 / Lake Ray Hubbard Bridge, Dallas |
2002 |
bent caps / decks |
|
|
|
80% of work done off-site |
1,2,4 |
| Texas |
NASA Road over I-45, Houston |
2002 |
columns |
10 days |
|
|
|
1 |
| Texas |
I-45 Pierce Elevated, Houston |
1997 |
bent caps |
190 days |
550 days |
$100,000 user savings/day |
226 spans replaced |
1,2,4,5,6,7,8 |
| Texas |
US 290 Ramp E-3, Austin |
1996 |
bent caps |
4 hours |
7 days |
|
|
1,4,8 |
| Texas |
US 59 under Dunlavy, Hazard, Mandel & Woodhead Streets, Houston |
1995 |
deck |
|
|
|
no disruption to below traffic, widened from 6 to 10 lanes, tied arch
bridge |
1,4,7,8 |
| Texas |
SH 249/ Louetta Road Overpass, Houston |
1994 |
total substructure system |
|
|
|
|
1,4,5,7,8 |
| Texas |
SH 361 over Redfish Bay and Morris Cumings Cut |
1994 |
bent caps |
|
|
|
reduced duration by 40% |
1,4,5,6,7,8 |
| Texas |
San Antonio "Y" Bridges |
1989 |
superstructure |
|
|
|
|
1 |
| Texas |
Spur Overpass over AT&SF Railroad, Lubbock |
1988 |
decks |
couple of days |
Texas |
|
|
5,7,8 |
| Texas |
|
1963 |
deck |
|
|
|
|
|
| Texas |
Lavaca Bay Causeway |
1961 |
deck |
|
|
|
|
1,4 |
| Texas |
US 290 Ramps G, and K, Austin |
### |
bent caps |
8 hours |
42 days |
|
|
4,5,7,8 |
| Texas |
Wesley Street Bridge, Jacksonville |
2002 |
decks |
4 months |
|
|
precast slab beams |
1,2 |
| Texas |
FM 528 / NASA Rd. 1 (EB) Underpass |
|
precast system |
|
|
|
precast box girders, precast bent cap, precast piles |
5 |
| Texas |
US183 Austin |
1999 |
precast substructure |
|
|
|
|
6,8 |
| Texas |
East Fork Trinity River Bridge |
|
|
|
|
|
|
6,7 |
| Vermont |
Richville Road, Manchester |
2001 |
superstructure |
14 days |
|
saved $20,000 |
Inverset System total prefabrication |
1,3 |
| Virginia |
I-95 James River Bridge, Richmond |
2002 |
superstructure |
|
|
|
construction at night 7pm to 6am Thursday - Sunday, lanes kept open |
1,2,4,5 |
| Virginia |
Smart Bridge |
|
|
|
|
|
segmental construction |
4 |
| Virginia |
Route 7 over Route 50, Falls Church |
1999 |
deck |
|
|
|
only nighttime construction |
1,2,5 |
| Virginia |
Dead Run and Turkey Run, GWMP |
1998 |
deck |
10 weekends |
|
|
open to commuter traffic |
1,3,4 |
| Virginia |
George P. Coleman, Yorktown |
1995 |
superstructure |
9 days |
|
|
largest double-swing bridge - 6 truss span bridge |
1,2,4,5 |
| Virginia |
Culpeper District Secondary Replacement Program |
|
deck panels |
|
|
|
|
5 |
| Virginia |
Route 612 over Bull Run, Prince William County |
|
precast components |
|
|
$25,000 |
replace and widen superstructure |
5 |
| Virginia |
Robert Norris Bridge, Lancaster and Middlesex Counties |
|
replace deck |
|
|
|
night work |
5 |
| Washington |
Parker Road over Yakima River |
|
girders |
|
|
|
200 feet postensioned super-girders |
4 |
| Washington |
Temporary bridge, Pend Oreille County |
|
superstructure |
|
|
|
temporary rail car bridge |
4 |
| Washington |
St. John |
|
superstructure |
|
|
|
|
4 |
| Washington |
I-5/South 38th Street, Tacoma |
2001 |
deck |
|
|
|
766 panels were placed within a week of limited nightime I-5 lane closures |
1,2,4 |
| Washington |
Mill Creek, Pend Oreille County |
1998 |
Arch ribs, footings |
5 days |
|
|
washout, temporary bridge built and open 4 days later |
4 |
| Washington |
Parvin Creek, Whitman County |
|
deck |
18 days |
|
|
replacement |
4 |
| Washington |
City of Almira |
|
deck |
60 days |
|
|
Timber Slab Bridge, replacement |
4 |
| Washington |
Columbus Avenue Bridge, Goldendale |
|
T-beams |
|
|
|
scour problems, widened for sidewalk - safer, replacement |
4 |
| Washington |
3 NE bridge, Grant County |
|
deck |
|
|
|
|
4 |
| Washington |
Port of Longview |
|
girders, bankment walls |
200 days |
|
|
|
4 |
| Washington |
Port of Kalama |
|
girders |
|
|
|
|
4 |
| Washington |
Monroe Street Bridge, Spokane |
|
rail, deck |
|
|
|
|
4 |
| Washington |
New Lake Washinton Boulevard, |
|
rail |
4 days |
|
|
rehabilitation |
4 |
| Washington |
La Center Bridge, La Center |
|
girders |
|
|
|
|
4 |
| Washington |
Don E. Wickstrom, Kent |
|
girders |
|
|
|
|
4 |
| Washington |
Lewis and Clark, SR 433 over Columbia River |
2004 |
decks |
|
|
|
precast deck replacement limited closures |
1,3 |
| Washington |
NE 8th over IH 405 in Bellevue |
2004 |
total prefab bridge |
|
|
|
|
1 |
| Washington |
Eddy Evers Bridge, Mason County |
|
timber panel deck |
|
|
|
Fiber Reinforced Polymer FRP deck repair |
4 |
| Washington |
Chief Joseph Dam Bridge, Douglas County |
|
FRP deck replacement |
|
|
|
Historic timber truss bridge widened and lightened with FRP deck system |
4 |
| Washington |
SR410 over Greenwater River, North of Mt. Rainer |
|
prefab scour protection |
|
|
|
prefabricatedarticulated concrete mattress provided for scour mitigation |
4 |
| West Virginia |
Howell's Mill, County Rd 1 over Mud River |
2003 |
decks |
3 days |
|
|
FRP deck panels |
1 |
| West Virginia |
Market Street, Wheeling |
2001 |
decks |
|
|
|
FRP sidewalks |
1 |
| Wisconsin |
US 14/61/WIS 16 over Mississippi |
2003 |
steel arch |
|
|
|
totally prefabricated superstructure |
1 |
References
- Website - Bridge Technology / Prefabricated Bridge Elements and Systems Project, http://www.fhwa.dot.gov/bridge
- Prefabricated Bridges, 2002, AASHTO Implementation Group (TIG), Panel on Prefabricated Bridge Elements and Systems
- Prefabricated Bridges, 2004, June 2004, AASHTO Implementation Group (TIG), Panel on Prefabricated Bridge Elements and Systems
- National Prefabricated Bridge Elements and Systems Conference, Feb. 18-20, 2003 , AASHTO, FHWA, Midwest Trans. Consortium and U of MO-Columbia.
- TXDOT/FHWA Workshop on Prefabricated Bridge Systems to Eliminate Traffic Disruptions, Austin,
- TX, Sept. 11, 2001 (C/D presentations)
- Development of a Precast Bent Cap System, Research Report 1748-2, January 2001, University of Texas at Austin, by E. Matsumo, M. Waggoner, G. Sumen, M. Kreger, S.Wood, and J. Breen
- Precast Concrete Bent Cap Demonstration Workshop, Lake Ray Hubbard Bridge , Dallas, Texas, March 28, 2002 (C/D of paper and presentations)
- Lake Belton Workshop (C/D of Research Report 1748-2 and presentations)
|
Events
More Information
Contact
Raj Ailaney
Office of Bridge Technology 202-366-6749 E-mail Raj
|