PBES Innovative Projects
I-65/I-59 Interchange |
| Location | Birmingham |
| State | AL |
| Completion Date | 2002 |
| Contact Person | Fred Conway P.E. Alabama Department of Transportation Phone: (334) 242-6007 Email: conwayf@dot.state.al.us |
| Description | When a fuel truck collision damaged a Birmingham bridge in the I-65/I-59 interchange, the Alabama Department of Transportation opted for a wider replacement bridge with a longer span over the northbound lanes of I-65, the main north-south route through Alabama. The interchange carries an estimated 100,000 vehicles per day, and the bridge needed to be replaced quickly. For the 140-foot main span and the 75-foot approaches, the contractor proposed a value-engineering girder re-design using AASHTO BT-54 Modified Bulb Tee girders with a 14-day strength of 8,000 psi. Traffic was stopped on I-65 north for only 12 nighttime hours to set the 15 girders on the 140-foot span overhead. Construction was completed in just 37 days. |
| Photo |  |
| Other Keywords | precast prestressed girders (long span) |
| Advantages | Minimized traffic disruption by reducing construction time and limiting lane closures. |
| Contract Elements | The contract time was set at 90 calendar days with a penalty of $25,000 per day for finishing late and a reward of $25,000 per day for finishing ahead of the 90-day deadline. |
| Photo Credits | Alabama Department of Transportation |
|