EARLY DEVELOPMENT AGREEMENT BETWEEN THE FEDERAL HIGHWAY ADMINISTRATION AND THE STATE OF OREGON
Table of Contents
No. 1 of 2 Executed
Original Counterparts
EARLY
DEVELOPMENT AGREEMENT BETWEEN THE FEDERAL
HIGHWAY
ADMINISTRATION AND THE STATE OF OREGON, BY AND THROUGH THE OREGON
DEPARTMENT OF TRANSPORTATION FOR THE CONSTRUCTION OF
HIGHWAY PROJECTS UNDER THE OREGON INNOVATIVE
PARTNERSHIPS PROGRAM
THIS EARLY DEVELOPMENT AGREEMENT (hereinafter "EDA"), made and entered into 14th this day
of October 2005, by and between the STATE OF OREGON,
BY AND THROUGH THE OREGON DEPARTMENT OF TRANSPORTATION (hereinafter "ODOT") and
the FEDERAL HIGHWAY ADMINISTRATION, UNITED STATES DEPARTMENT OF TRANSPORTATION (hereinafter "FHWA"):
WITNESSETH
WHEREAS, ODOT desires to develop three construction undertakings under the Oregon
Innovative Partnerships Program (that program being more particularly described in
Oregon Revised Statutes 367.800-367.826), which generally include a proposed widening
of 1-205 (the "South 1-205 Corridor Undertaking"), the proposed construction of a new
facility between 1-205 and US 26 (the "Sunrise Undertaking"), and the proposed
construction of a new bypass between the cities of Newberg and Dayton (the "Newberg-
Dundee ~rans~ortatioImnp rovement Undertaking") (collectively, the "OIPP Initiative");
WHEREAS, on October 6, 2004, the FHWA
announced, in the
Federal Register at 69 Fed. Reg.
59983, a new special experimental project to explore alternative and
innovative approaches to the overall project development process known
as Special Experimental Project No. 15 (collectively,
"SEP-15");
WHEREAS, on December 17,2004, ODOT submitted an application to use an
innovative procurement approach, which included certain specified modifications or
deviations from the current requirements and policies contained in title 23 of the United
States Code and title 23 of the Code of Federal Regulations, for the OIPP Initiative under
the SEP-15, and ODOT submitted a supplement to its application dated January 25,2005;
WHEREAS, on May 6,2005, the FHWA approved ODOT's SEP-15 application;
WHEREAS, ODOT issued a Request for Proposals ("FWP") pertaining to the OIPP
Initiative on April 29,2005, as contemplated by the SEP-15 application, with a current
proposal due date of August 29, 2005;
WHEREAS, SEP-15 is designed to permit tests and experimentation in the entire Federal-aid highway project development process that are specifically aimed at attracting private investment and lead to increased project management, flexibility, more innovation, improved efficiency, timely project implementation, and new revenue streams;
WHEREAS, under SEP-15, in order to facilitate tests and experimentation in the project
development process, the FHWA may grant modifications or deviations from the current
requirements and policies contained in title 23 of the United States Code and title 23 of
the Code of Federal Regulations; and,
WHEREAS, under SEP-15, an EDA is required in order to contain the parameters of the modifications or deviations from Federal requirements that are granted for projects within the OIPP Initiative as well as to identify the reporting requirements that will be used to evaluate the extent to which the modifications or deviations contributed to the success of the process;
NOW THEREFORE, ODOT and FHWA hereby agree as follows:
SECTION 1. SCOPE OF EARLY DEVELOPMENT AGREEMENT
This EDA is intended to identifj and establish the parameters of the modifications or
deviations from title 23 of the United States Code and title 23, Code of Federal
Regulations, for projects within the OIPP Initiative, which shall be hereinafter referred to
as the "Experimental Features." The Experimental Features identified in this EDA will
apply to each project until such time (if any) as ODOT decides not to use Title 23 funds
for the project. Nothing in this EDA shall be construed as a relinquishment of any
Federal oversight or stewardship responsibility.
SECTION 2. DEFINITIONS
2.1 Developer
"Developer"means each
entity with whom ODOT has executed a Predevelopment or
Implementation Agreement for the development, design, construction,
financing, operation, and maintenance of one or more projects.
Depending on the context, the term "Developer"may mean
all such entities, as well as affiliated entities.
Implementation
Agreement
"Implementation
Agreement" means an agreement, or agreements, to be entered
into by ODOT with the Developer after completion of the activities
contemplated in the Development Agreement, for one or more of the
following activities: acquisition, financing, design, construction,
operation, or maintenance of any project, and any other services
relating to project development not performed under the
Pre-Development Agreement. An Implementation Agreement may
cover one or more projects.
NEPA
"NEPA" means the National Environmental Policy Act of 1969, as amended, 42 U.S.C. §§ 4321 to 4370f.
2.4
Predevelopment
Agreement
"Predevelopment Agreement" means each agreement by and between ODOT and a Developer, which provides the framework for the Developer to collaborate with ODOT for the conceptual, preliminary and final planning for a project, along with performance of certain services relating to development of the project. A Predevelopment Agreement is expected to include all, or some, of the followi~~acgt ivities: preparation of a predevelopment plan, pre-development community outreach plan, financing plan and implementation plan, and contribution towards ODOT activities related to Oregon's Collaborative Environmental and Transportation Agreement for Streamlining ("CETAS"), environmental approvals and public information, and related preliminary engineering. A Predevelopment Agreement may cover one or more projects.
Project
"Project" means an undertaking to design and construct all, or a particular portion of, the South 1-205 Corridor Undertaking, the Sunrise Undertaking or the Newberg-Dundee Transportation Improvement Undertaking, including all improvements, amenities, and related development. Unless both parties agree otherwise, each project shall be considered a separate project for purposes of Title 23 funding requirements, even though more than one project may be included in a single Predevelopment Agreement or Implementation Agreement.
Project
Agreement
"Project Agreementy' means the formal instrument to be executed between the FHWA and ODOT as required by 23 U.S.C. 106.
2.7
Proposal
"Proposal"means a
proposed Developer's submission in response to the
RFP.
Proposer
"Proposer" means
each entity or team of entities that submitted a proposal in
response to the RFP.
2.9
Request
for Proposals
"Request for Proposals" or "RFP" means the Request for Proposals #73000-22313-NT-5 issued by ODOT on April 29,2005, as amended. The RFP shall constitute the request for proposals for purposes of 23 C.F.R. Part 636 with respect to each project developed pursuant to an Implementation Agreement with a Developer.
2.10 Uniform Act
"Uniform Act" means the Uniform Relocation Assistance and Real Property Acquisition Policies Act of 1970, as amended, 42 U.S.C. $8 4601, et seq., and FHWA's implementing regulations found at 49 C.F.R. part 24.
SECTION 3. GENERAL PROVISIONS
3.1
Applicability
of Federal Law
Except as
otherwise specified herein:
3.1.1 Federal laws, rules and
regulations applicable to projects as a result of use of Title
23 funds for construction of the project shall be applicable to
each of the projects, including, but not limited to, the
requirements set forth in titles 23 and 49 of the United States
Code, and titles 23 and 49 of the Code of Federal Regulations,
the Uniform Act, and NEPA, except as otherwise specified
herein.
3.1.2 If ODOT decides not to
use Title 23 funds for a project, Federal requirements
applicable to projects as a result of use of Title 23 funds
shall no longer be applicable to the Project.
3.1.3 With respect to title 23
of the United States Code and title 23 of the Code of Federal
Regulations, ODOT may use the Experimental Features described
in Sections 4 through
8.
use of such
Experimental Features shall be deemed to be in full compliance
with Federal law, rules, and regulations.
3.2
Withdrawal
of Approval for Experimental Features
3.2.1 The FHWA's approval
to use the Experimental Features identified in Sections 4
through 8 may be withdrawn from one or
more of the projects at any time by the FHWA if the FHWA
determines that the OIPP experiment for that project has failed
and does not merit further Federal participation. In addition,
the FHWA's approval of an individual Experimental Feature
may be withdrawn at any time by the FHWA, if it has determined
that such feature is not in the public interest, which may be
based on experience from other projects or the OIPP program or
other appropriate factors, and therefore that further Federal
participation in such Experimental Feature is not warranted.
Under either scenario, in determining whether to withdraw
approval, FHWA shall consider the current status of the projects
and the implications of modifying a program that is already
underway. Prior to any such withdrawal, the FHWA will issue a
written notice to ODOT describing the FHWA's concerns,
consult with ODOT regarding FHWA's concerns and the
implications of modifying the program, and give ODOT a
reasonable period of time to address the FHWA's concerns.
However, during such period of time, except as specified
in Section
3.2.2 below, no further work shall
be conducted based on the approval at issue, until such time as
the FHWA determines that ODOT has fully addressed the FHWA's
concerns.
3.2.2 Upon the effective date
of the withdrawal of approval of an Experimental Feature, the
applicable requirements of title 23 of the United States Code
and title 23 of the Code of Federal Regulations shall
immediately apply. Notwithstanding the foregoing, any withdrawal
of an approval under this Section
3.2 only
affects Title 23 funding eligibility for projects, or elements
thereof, not subject to a Project Agreement and shall not (a)
invalidate or require modification of any previously executed
contracts (including the Predevelopment Agreement and any
Implementation Agreement) entered into in reliance upon such
approval, (b) affect the obligations of the parties under a
previously executed contract, and (c) otherwise apply
retroactively to any completed elements or activities.
Furthermore, withdrawal of an approval shall not affect
ODOT's ability to issue change orders or execute
modifications, amendments and supplemental agreements for
previously executed contracts.
3.3
Access to
Documents and Confidentiality
As provided in
23 C.F.R. 1.5, ODOT shall furnish, or make available, to the
FHWA such information as the FHWA deems desirable in order to
administer Title 23 funds within the OIPP Initiative and
ensure compliance with any applicable Federal requirements.
Any records that ODOT or a Proposer does not want to be made
publicly available shall be reviewed by the FHWA on
ODOT's or the Proposer's premises in accordance with
the procedures outlined in the FHWA Chief Counsel's
January 26,2005 memorandum concerning "Pre-Submission
Evaluation of Information under the Freedom of Information
Act." The confidentiality of any records obtained by the
FHWA shall be determined in accordance with 49 C.F.R. Part 7.
3.4
Oversight
Agreement
FHWA project
oversight for design and construction shall be determined by
a separate formal oversight Agreement between the FHWA and
ODOT.
3.5
Order of
Precedence
Except as otherwise specified herein, this EDA supercedes the December 17,2004 SEP-15 application and supplement thereto and the FHWA's May 6,2005 SEP-15 approval. The December 17,2004 SEP-15 application (as supplemented) and the May 6,2005 SEP-15 approval are attached to this EDA as Attachments A and B, and may be used for historical and interpretive purposes, provided that this EDA shall be given effect to the extent there is any conflict. Any modifications to this EDA shall supercede any conflicting provisions of the December 17,2004 SEP-15 application (as supplemented), the FHWA's May 6,2005 SEP-15 approval, this EDA, and any prior modifications to this EDA.
SECTION 4. EXPERIMENTAL FEATURES: PROCESS
4.1
Deviations
from 23 C.F.R. 636.109 -Issuance of and Executing a
Predevelopment Agreement prior to completion of NEPA.
4.1.1 FHWA acknowledges and agrees to ODOT's deviation from 23 C.F.R. 636.109: as provided in the FHWA's May 6,2005 SEP-15 approval, by issuance of the RFP and execution and delivery of the Predevelopment Agreement, prior to the conclusion of the NEPA process. FHWA acknowledges its concurrence in the issuance of the WP. ODOT may permit the Developer to provide NEPA support services, including preliminary engineering, tests, studies, data, analyses and reports, and may permit the Developer to perform limited non-construction work under the Predevelopment Agreement prior to the conclusion of the NEPA review process.
4.1.2 The purpose of 23 C.F.R.
636.109 is to ensure that there is an unbiased NEPA decision
making process, that public and citizens have the necessary
environmental impact information for federally-funded actions
before actions are taken, and that design-build proposers do not
assume an unnecessary amount of risk in
the event the NEPA process results in a significant change in
the proposal.
4.1.3 In order to ensure that
the purposes of 23 C.F.R. 636.109, as listed in are protected,
the following conditions must be met:
4.1.3.1
FHWA, with
participation, will, at all times, direct and control the NEPA
process.
4.1.3.2
FHWA and ODOT will
participate in all phases of the NEPA review process. FHWA is
solely responsible for the project approval process under
NEPA.
4.1.3.3
ODOT will include
appropriate provisions in the Predevelopment Agreement to ensure
that no commitment to any alternative that could be evaluated
during the NEPA review process is made prior to the completion
of the NEPA review process, and to allow all alternatives
presented in the NEPA document, including the build alternative,
to be equally evaluated.
4.1.3.4
The selection of
any preferred alternative throughout the NEPA process must be
the sole responsibility of ODOT in cooperation with the
FHWA.
4.1.3.5
ODOT must ensure
that no decision regarding a preferred alternative will be made
before all necessary environmental impact information is
available for review and comment by both the decision makers and
the general public.
4.1.3.6
ODOT must ensure
that any project using Title 23 funds will address how
environmental commitments and mitigation measures identified
during the NEPA process will be implemented.
4.1.3.7
Should ODOT engage a consultant to provide NEPA-related services 3r a project, ODOT shall ensure that the organizational conflict of interest requirements Page 6 of 17 of 23 C.F.R. 636.1 16 and 40 C.F.R. 1506.5(c) are met with respect to such consultant's participation in the Developer's activities. Moreover, any such consultant for NEPA services must be independent fiom the Developer.
4.1.3.8 ODOT must ensure that final design and construction of a project
does not commence before the conclusion of the NEPA process for that project.
4.2
Deviations from 23 C.F.R. 636.409,636.507,636.509, and 636.513 - Communicating with Proposer and negotiations prior to award.
4.2.1 FHWA acknowledges and agrees to the deviation fiom 23 C.F.R. 636.409, 636.507,636.509, and 636.513, as provided in FHWA's May 6,2005 SEP-15 approval, associated with the one-on-one negotiations conducted by ODOT with the selected Proposer prior to award of the Predevelopment Agreement, allowing proposal revisions, requesting substantive supplemental information to be used in evaluating a proposal, and disclosing and using ideas from unsuccessfid Proposers.
4.2.2 The purpose for the general prohibition on the activities described in Section 4.2.1 under 23 C.F.R. 636.507,636.509, & 636.513 is to enhance competition and ensure that the procurement process is fair and transparent to all Proposers.
4.2.3 The following provisions
have been included in the RFP to ensure the purpose described
in Section
4.2.2 is
protected:
4.2.3.1
Provisions allowing ODOT to suspend, discontinue, terminate, recontinue and/or begin new Predevelopment Agreement negotiations with any Proposer for a project at any time prior to execution of a Predevelopment Agreement by all parties for that project.
4.2.3.2
Provisions
notifying Proposers of the process that will be used in awarding
the Predevelopment Agreement and advising Proposers of the
possibility that a Proposer's ideas may be used and
disclosed by ODOT to another Proposer during negotiations, that
an unsuccessful Proposer's ideas may be used by ODOT, and
that substantive changes may be made to a Proposal during
negotiations.
4.2.4 In order to further
ensure the purpose described in Section
4.2.2 is
protected, ODOT will comply with the following requirements
associated with the deviation stated in Section
4.2.1 :
4.2.4.1
ODOT will provide
the FHWA with the opportunity to observe and participate in the
evaluation, selection and negotiation process between ODOT and
the selected Proposers.
4.2.4.2
ODOT will submit
major amendments to the RFP and the subsequently executed
Predevelopment Agreement (including any major amendments) to
FHWA for review and concurrence.
4.2.4.3
Prior to award of
the Predevelopment Agreement, ODOT will request FHWA concurrence
accompanied by a timetable showing the major steps in the
procurement process, a summary of ODOT's rationale for the
selection, and a description of any material changes made to the
Predevelopment Agreement during negotiations.
4.2.4.4
ODOT must obtain
the consent of the unsuccessful Proposers to use their work
product.
4.3
Deviation
from 23 C.F.R. 636.302
-Consideration
of price.
4.3.1 ODOT may deviate from
the requirement in 23 C.F.R. 302 to evaluate price in the source
selection process for contracts where construction is a
significant component of the scope of work.
4.3.2 The purpose of the price
consideration requirement in 23 C.F.R. 636.302 is to ensure that
the cost of the proposals received in response to a request for
proposals, as defined in 23 C.F.R. 636.103, are competitive and
that a State takes the cost of a proposal into consideration
whenever awarding a Federal-aid project.
4.3.3 In order to ensure that
the purpose described in Section
4.3.2 is
met, selection of a Developer must be based on the evaluation
process that includes a consideration of public need, technical
and financial feasibility, transportation cost effectiveness,
and acceleration of project delivery, as set forth in the RFP.
However, ODOT must not commit to using the Developer for the
final design or construction of any project unless ODOT
determines that the price for such services is reasonable. In
order to determine price reasonableness, ODOT must establish a
process through which this determination will be made. Upon
determining that the project price is reasonable, ODOT shall
request the concurrence, as provided in Section
5.1.3.3.
SECTION 5.
EXPERIMENTAL FEATURES: PROJECT AUTHORIZATION
5.1
Deviations from 23 C.F.R. 635.112(i)(l) & 635.114(k)-Project authorization.
5.1.1
ODOT may deviate from 23 C.F.R. 635.1 12(i)(l) and 635.1 1 4 0 to permit project authorization to occur for each project after final environmental approval by FHWA has been issued, in compliance with NEPA, for the project.
5.1.2
The purpose of the project authorization requirements in 23 C.F.R. 635.112(i)(l) and 635.1 14(k) is to ensure that the FHWA is involved in the project development process at a time that is sufficient to permit the FHWA to adequately review and oversee compliance with all appropriate Federal requirements and that costs are not incurred prior to authorization. Moreover, the project authorization requirements of 23 C.F.R. 635.1 12(i)(l) and 635.1 14(k) are consistent with 23 C.F.R. 636.109, which does not permit a State to issue a request for proposals until the NEPA process is complete. Here, however, as explained in Section 4.1, ODOT was permitted to issue the RFP and execute the Predevelopment Agreement prior to the completion of the NEPA process. The FHWA and ODOT do not believe issuance of the RFP or execution of the Predevelopment Agreement was the appropriate point at which to authorize Title 23
funding for the entire OIPP Initiative since the NEPA process has not yet been completed and financing decisions for each project will not be made by ODOT until the NEPA process has been completed for that project.
5.1.3
In order to
ensure that the purposes described
in
Section 5.1.2 are satisfied, the
following stipulations shall apply:
5.1.3.1 ODOT and the FHWA
will develop a formal oversight agreement for the projects
that will enable the FHWA to be appropriately involved in
the development process for federally-funded projects and
to monitor the overall effectiveness of the process. The
FHWA's involvement in any design and construction of
any federally-funded project is determined by this EDA, as
well as a separate oversight and stewardship Agreement
between ODOT and the FHWA.
5.1.3.2 ODOT shall request
FHWA's concurrence in any Implementation Agreement
that contemplates the use of Title 23 funds. Concurrently
with such request, ODOT shall transmit to FHWA all
relevant and necessary documents, including the
Implementation Agreement and a summary of the process
followed in developing the Implementation Agreement. ODOT
shall also request FHWA concurrence in any major changes
that will be made to an approved Implementation Agreement.
FHWA concurrence in the Implementation Agreement shall be
subject to the completion of the NEPA review process for
the project underlying the Implementation Agreement and
all applicable conditions listed in 23 C.F.R. 635.309
being satisfied for such project.
5.1.3.3 FHWA concurrence
in an Implementation Agreement under
Section 5.1.3.2 will also be conditioned
upon the FHWA's review of price reasonableness as well
as a determination that all applicable Federal
requirements have been, and will be, complied with and
that the Implementation Agreement includes all relevant
Federal provisions. The Predevelopment Agreement must
include provisions requiring, as a prerequisite to
entering into a federally-funded Implementation Agreement
with the Developer, that the contract price of the
Implementation Agreement is reasonable. The Predevelopment
Agreement must include a process for determining price and
verifying price reasonableness with respect to such
Implementation Agreements. Upon concurrence in an
Implementation Agreement, ODOT and the Developer may
proceed to execute the Implementation Agreement. Once the
Implementation Agreement has been executed, and the FHWA
determines that all the applicable conditions have been
satisfied, Federal-aid procedures governing the obligation
of funds shall apply.
5.1.3.4 ODOT
may proceed with a competitive procurement process or
processes for the design, construction or combined design
and construction of a project should ODOT
choose not to enter into an Implementation Agreement with
the Developer. In such case, should ODOT choose to use Title 23
funds, ODOT shall follow the aid procurement requirements
in 23 C.F.R. Parts 635 and 636. Should ODOT choose to
deviate from any of the requirements in 23 C.F.R. Parts
635 or 636, ODOT shall request FHWA's approval of any
such deviation at least 30 days prior to the scheduled
date for advertisement (for a procurement subject to Part
635) and for issuance of the request for proposals (for a
procurement subject to Part 636). FHWA will respond to
such request within 30 days and, upon approval, an
appropriate modification shall be made to this EDA to
provide for the approved deviation. In any Predevelopment
Agreement with a Developer, ODOT shall include provisions
that disqualify the Developer from participation in any
competitive procurement process for an Implementation
Agreement should ODOT determine that the Developer's
participation in such process would give the Developer an
unfair competitive advantage or would otherwise
constitute
an impermissible conflict
of interest as provide in 23 C.F.R. 1.33. determination
with respect to the Developer's participation shall be
subject to FHWA concurrence.
SECTION 6.
EXPERIMENTAL FEATURES: PROCUREMENT REQUIREMENTS FOR
DEVELOPER
6.1 Deviation from 23 C.F.R. 636.119(b) -Determining price and assumption of risk between ODOT and the Developer.
6.1.1
ODOT may deviate from 23 C.F.R. 636.1 19(b) to determine price and assignment of risk in each Implementation Agreements rather than in the Predevelopment Agreement, for purposes of determining whether the contracts to be awarded by the Developer under the Implementation Agreement are subcontracts or prime contracts.
6.1.2
The purpose of 23 C.F.R. 636.1 19(b) is to ensure that Federal competition requirements are followed in the procurement of services under certain public-private agreements depending upon whether such agreement establishes price and an assignment of risk. If the agreement does not establish price and an assignment of risk, then the Developer must follow the appropriate FHWA procurement requirements in procuring services under the agreement and all subsequent contracts executed by the Developer are considered to be prime contracts. However, if the agreement does establish price and an assignment of risk, then the Developer is not bound by the FHWA procurement requirements and all subsequent contracts executed by the Developer are considered subcontracts. The Predevelopment Agreement does not itself establish a price or assignment of risk for design and construction of the project, and instead establishes a framework for establishing price and an assignment of risk in the Implementation Agreement. Thus, under the process contemplated by ODOT, it will not be appropriate to look at the Predevelopment Agreement to determine whether price and risk have been assigned for purposes of 23 C.F.R. 636.1 19(b).
6.1.3
In order to ensure that the purpose of 23 C.F.R. 636.1 19(b) is met, each Implementation Agreement between ODOT and the Developer must clearly establish price and assignment of risk. The Implementation Agreement may establish the price through a requirement that the subcontracts for construction of the project be competitively procured using a procurement process approved by ODOT. Should any Implementation Agreement not establish the price and assignment of risk, then the Developer must follow the applicable FHWA procurement requirements in procuring services under the Implementation Agreement.
SECTION 7.
EXPERIMENTAL FEATURES: LONG-TERM WARRANTY, ROUTINE MAINTENANCE AND
FORM 1273
7.1 Deviation from 23 C.F.R. 635.413(e) -Inclusion of a long-term warranty with some routine maintenance in an Implementation Agreement.
7.1.1
ODOT may
deviate from 23 C.F.R. 635.413(e) to
allow a long-term warranty and to permit the Developer to
undertake responsibility for both preventative and some
routine maintenance services in any Implementation Agreement
with the Developer.
7.1.2 The
purpose for the restriction on long-term warranties and the
inclusion of routine maintenance services in design-build
contracts in 23 C.F.R. is because a short term, 2 year
warranty has been determined to be sufficient for the State
to uncover most defects and to ensure that Title 23 funds do
not participate in routine maintenance activities, which are
not Federal-aid eligible.
7.1.3
Here, ODOT
anticipates that a long-term general warranty will be a
critical part of any Implementation Agreement in order to
ensure quality in design and construction of the project. Due
to the unique nature of proposed approach to projects, the
FHWA agrees that ODOT may use long-term warranties in
Implementation Agreements. FHWA further acknowledges that
such warranties could be a significant factor in determining
whether ODOT is getting the best value for the project and
that, under certain circumstances, it may not be practicable
to separate the costs of routine maintenance associated with
a warranty from preventive maintenance. FHWA will participate
in the costs of such a warranty, including the associated
maintenance costs that cannot be segregated from the
underlying warranty costs, provided that FHWA concurs that
such warranty is primarily focused on non-routine maintenance
activities of the highway and is a factor in providing the
best value to ODOT for the project.
7.1.4
The foregoing
shall not preclude ODOT from entering into any agreement
involving performance of routine maintenance services that
will not be federally-funded,
7.2 Deviation from standard
Form FHWA 1273
-Technical
adjustment to update Form FHWA 1273 for conformity with current
law.
7.2.1 ODOT may modify Form
FHWA 1273 to provide that contractor performance requirements do
not apply as provided in 23 C.F.R. 635.1
7.2.2 The purpose of Form FHWA
1273 is to ensure that all contractors to a aid project comply
with Federal requirements. One of the provisions in Form FHWA
1273 requires prime contractors to perform at least 30 percent
of the work of a contract with its own forces. However, the
design-build rule modified this requirement making it not
applicable to design build contracts. Form FHWA 1273 has not
been modified to provide for this change.
7.2.3 The FHWA will allow ODOT to use a modified Form FHWA 1273, as described in Section 7.2.1, in Implementation Agreements for the projects. This deviation is a technical change that is designed to bring Form FHWA 1273 into
conformity with current Federal requirements. Thus, the purpose of Form FHWA 1273 will continue to be met with this change.
SECTION
8.
EXPERIMENTAL
FEATURES: VALUE ENGINEERING
8.1 Deviation from 23 C.F.R. 627.1,627.3, & 627.5 -Value engineering for the
OIPP Initiative.
8.1.1
ODOT may deviate from the FHWA's value engineering requirement under 23 C.F.R. 627.1,627.3, & 627.5 by undertaking value engineering only for projects constructed with Title 23 funds where the total Implementation Agreement price is expected to exceed $25 million and Title 23 funds are expected to exceed 30 percent of the Implementation Agreement price.
8.1.2
The purpose
of this provision is to help eliminate unnecessary and
costly elements of a project and, when a project is
constructed in a series of segments, to ensure that
features of other segments are looked at for potential
cost savings in other affected segments.
8.1.3
Due to the
extent of private funds that are expected to be invested
in the OIPP Initiative, it is expected that the Developer
will have an incentive to value engineer, or perform other
cost savings analyses. Thus, the purpose described
in
Section 8.1.2 will be satisfied by
only requiring Federal value engineering to apply where
the total Implementation Agreement price is expected to
exceed $25 million and Title 23 funds are expected to
exceed 30 percent of the Implementation Agreement price.
Nothing in this Section shall be interpreted as
discouraging ODOT from requiring value engineering
provisions in Implementation Agreements, and any such
provisions could be included in the discretion of ODOT,
depending upon the nature of the project and any proposed
Implementation Agreements.
SECTION 9.
EVALUATION CRITERIA
9.1 General
The purpose of
this Section is to describe the evaluation criteria that ODOT
shall use in evaluating the Predevelopment Agreement procurement
and development process in connection with the reports to be
provided under Section
10.
9.2 Time Savings
ODOT shall:
- Compare the actual schedule for delivery of projects with the estimated schedule based on a traditional procurement process;
- Evaluate the effect of the Predevelopment Agreement process on delivery of the projects; and
- Attempt to quantifl the value of early completion.
Innovation
in Project Development
ODOT shall analyze the type and nature of facilities developed through Predevelopment Agreement and the procurement approaches described in Section 4 and compare those facilities with ODOT's other projects. ODOT shall also analyze the benefits of issuing an RFP prior to the completion of the NEPA process and allowing project development work to proceed while the environmental process is still being carried out.
Innovation
in Public-Private Partnership Selection
ODOT shall analyze the process used to select the Developer and report on how well that process facilitated competition in the selection of development proposals, how well that process produced a sufficient pool of qualified competitors, how well that process enabled ODOT to select a developer offering the best value, how well that process enabled ODOT to achieve the best value, how the process was perceived in the industry, and how the process was perceived by the unsuccessful competitors.
Innovation
in Design and Construction
ODOT shall analyze
innovative design and construction ideas and concepts used by
the Developer team, which evolve as a byproduct of the
Predevelopment Agreement process.
9.6
Quality
and Warranty
ODOT shall
analyze the ultimate quality of the work and the strength of
any warranties provided for delivered projects.
9.7
Responsiveness
to
Local
Concerns
ODOT shall
evaluate the success of the process used in responding to
local concerns as well as coordinating with, and responding to concerns
of, Metropolitan Planning Organizations.
9.8
Price
Reasonableness
ODOT shall
review the price reasonableness process described above, and
evaluate whether the process is cost effective and in the
public interest. The evaluation shall look at whether the
FHWA and ODOT are, in fact, getting the best value in terms
of cost, quality, and timeliness of the work as well as the
continued operations and maintenance of the project.
SECTION
10.
REPORTING
REQUIREMENTS
Initial Report and Updates
ODOT shall
submit an initial report within 120 days after the execution
of the Predevelopment Agreement, and will include a
preliminary analysis of the Predevelopment Agreement
procurement. This report shall:
- describe the process used to select the Developer team;
- identify any reaction by the industry to use of the Predevelopment Agreement concept;
- document major innovations contained in the proposals received; and
- discuss any major problems or issues that have occurred and how they were resolved.
ODOT shall also
submit periodic updates to the initial report as appropriate
during the period prior to issuance of NEPA approval,
describing the progress of the environmental analysis as well
as the developer's activities relating to the project(s).
Interim
Reports
10.2.1
ODOT will prepare
an interim report after the occurrence of a significant
development relating to federally-funded projects. A significant
development includes:
- completion of
the NEPA process for the project;
- execution of an
Implementation Agreement that contemplates use of Title 23
funding for the project; and
- completion of
construction of each federally-funded project.
10.2.2
Each interim
report shall describe:
-
the progress
of the development of each project as of the date of the
interim report;
-
any major
problems encountered and how ODOT has addressed each of
the problems;
- how any significant changes in the project resulting fiom the NEPA analysis and other permitting processes have been addressed in the Predevelopment Agreement;
-
an
evaluation of the price reasonableness process used and
whether there have been any problems determining price
reasonableness and how those problems have been addressed;
and
-
how the time
and cost needed to complete the initial development as of
the date of the interim report compares to past experience
under design-bid-build procurement procedures.
Project Acceptance Report
A project acceptance
report will be submitted within 180 days following
determination that the construction of any federally-funded
project is complete. This report will be prepared by an
independent consultant engaged by ODOT and shall:
-
provide an
overall evaluation of the procurement and development
processes;
-
provide an
overall evaluation of the NEPA and right-of-way
acquisition process for the project;
-
provide an
overall evaluation of the price reasonableness process and
how that process contributed to obtaining the best value
in terms of cost, quality, and timeliness;
-
evaluate the
completed project against the factors described in
Section
9;
-
describe
lessons learned, pitfalls to avoid, and suggestions for
improvements on future innovative procurements and
approaches to NEPA reviews;
-
provide an
explanation of contract complications encountered and
claims made during construction;
-
indicate and
evaluate innovations in design or construction;
-
emphasize
and focus upon the quality and timeliness and how they
were affected by the OIPP Initiative;
- describe the extent to which the SEP-15 program contributed to the success of the OIPP Initiative;
- provide an evaluation of the Experimental Features used and the extent to which those features contributed to the OIPP Initiative's success; and
-
recommend
any statutory or regulatory changes.
Post-Acceptance Reports
A
post-acceptance report will be submitted for each
federally-funded project at the end of the first two years of
any long-term operations and maintenance or concession term,
and at intervals thereafter as deemed appropriate by ODOT.
This report will:
- evaluate the
overall quality and performance of the projects;
- identify and evaluate warranties and document complications encountered
during the period;
- identify any cost- or time-intensive maintenance items and evaluate the
manner and effectiveness of their resolution;
- evaluate the overall safety and operation of the projects;
- evaluate design requirements in the completed facilities and document any
design adjustments that could improve quality; and
- evaluate the private sector's responsiveness.
SECTION
11. MISCELLANEOUS PROVISIONS
11.1
Amendments
11.1.1 This EDA may be amended
at any time by written agreement of the parties.
Amendments to this EDA may include, but are not limited
to, the addition or deletion of Experimental Features,
modification of performance measures, and modification of
reporting requirements. The FHWA Oregon Division
Administrator shall have the authority to amend this EDA
for the FHWA, subject to the concurrence of the FHWA
facilitator.
11.1.2 The parties anticipate
that this EDA will be modified over time as the projects
mature. ODOT may reopen this EDA and seek modifications
thereof at any time, including upon completion of
negotiations with a Proposer concerning a Predevelopment Agreement
or Implementation Agreement.
11.2
Original
Copies
This EDA shall
be prepared in duplicate original copies so that each
signatory has an original copy.
IN
WITNESS THEREOF, the parties hereto have caused this EDA
to be duly executed in duplicate as of the day and year first written
above.
J. Richard Capka
Acting Administrator
Federal Highway Administration
Douglas J. Tindall
Deputy Director for Highways
Oregon Department of Transportation |