Attachment No 1

Innovative Bridge Research and Deployment Program

2007 Program Information

(March 28, 2007)

Background

The IBRC program, the predecessor of the IBRD program, was established by the Congress in the Transportation Equity Act for the 21st Century (TEA-21) (Pub. L. 105-178). This program was continued in SAFETEA-LU. However, in section 5202 of SAFETEA-LU, Congress removed two goals of the IBRC program: Goal (E), the development of cost-effective and innovative techniques to separate vehicle and pedestrian traffic from railroad traffic; and Goal (F), the development of new nondestructive bridge evaluation technologies and techniques. In addition, this section added three goals to the IBRD Program: Goal (F), the documentation and wide dissemination of objective evaluations of the performance and benefits of these innovative designs, materials, and construction methods; Goal (G), the effective transfer of resulting information and technology; and Goal (H), the development of improved methods to detect bridge scour and economical bridge foundation designs that will withstand bridge scour. The eight goals of IBRD are listed under ELIGIBILITY of this Attachment.

Funding

Funds are provided to the States under the IBRD program to pay the Federal share of the cost of projects that demonstrate innovative accelerated bridge design and construction technology, and the application of innovative material technology in the repair, rehabilitation, replacement, or new construction of bridges and other highway structures. Congress authorized $13.1 million per year from fiscal years 2005 through 2009 for the IBRD program, $4.125 million of which is designated for high performance concrete technology research and deployment. The actual amount available can vary in yearly congressional appropriations. Portion of the Funds is available for bridge projects that meet one or more of the eight program goals as listed in Section 5202 (b) of SAFETEA-LU, Public Law 109-59.

Federal Share:

In accordance with 23 U.S.C. 503(b) (5), the Secretary shall determine the Federal share of the costs for any project eligible under this program. The FHWA determines the Federal share for each project considering several factors, including the innovation parts of the project, the amount of funds requested for the project, and the available funding for the program. It is the goal to fund as many projects as possible at a 100 percent Federal share; however, because of the above considerations, some projects may be funded at a lower Federal share.

Eligibility:

Selection Criteria:

The FHWA will use the following criteria to evaluate the submitted candidates for selection:

  1. Projects that will meet one or more of the goals of the program in 23 U.S.C. Section 503(b) with a particular emphasis on safety and reducing congestion;
  2. Projects that will incorporate innovative materials and/or products that are readily available;
  3. Projects that have been funded for design and for construction or rehabilitation;
  4. Projects with designs, materials, and construction methods that have broad application;
  5. Projects that leverage Federal funds with other public or private resources, will be given preference; and
  6. Projects that are part of a large right of way improvement project.

In addition, the FHWA may consider:

  1. State priorities - For States that submit more than one project application, consideration is also given to the individual State's priorities if specified.
  2. Availability of innovative material and/or innovative material product - and projects that apply an innovative material and/or a product made of an innovative material, which is readily available for application in other projects and in other States.
  3. Expeditious completion of project in a timely manner. For large-scale projects, consideration is given to the State's total funding plan to expedite the completion of the project.
  4. Leveraging of private or other public funding - Because the annual requests for funding far exceed the available IBRD discretionary funds, commitment of other funding sources to complement the requested IBRD discretionary funding is also a consideration.

Solicitation Procedure:

Each year, a memorandum is sent from the FHWA Headquarters Office of Bridge Technology to the FHWA division offices requesting the submission of candidate projects for a given fiscal year's funding. This solicitation is also published on the IBRD Web at http://www.fhwa.dot.gov/bridge/ibrd/. The State DOTs coordinate with local and Federal agencies, universities and colleges, private sector entities, and nonprofit organizations within their respective States in order to develop viable candidate projects. The State DOTs submit the candidate applications to the FHWA division offices. After review and consultation with the DOT, the division office sends the acceptable candidate projects to the Director, Office of Bridge Technology (Attn: HIBT-1). Candidate projects for FY 2007 funding will be due in FHWA Headquarters on April 30, 2007.

The candidate project applications are reviewed and evaluated by a selection panel composed of representatives from the FHWA Office of Bridge Technology and the FHWA Office of Infrastructure R&D, and an allocation plan is prepared for presentation of the candidate projects to the Federal Highway Administrator, for the final selection of projects for funding.

Submission Requirements:

State DOTs submit applications for funding under this program. A prescribed format for a project submission is provided in the format of a project application form, and the following information should be included to properly evaluate the candidate projects. Those applications that do not include this information will be considered incomplete and will be rejected.

Application Guidance:

Decision Process for Funding:

Projects are to be screened for eligibility first by the FHWA division office and then evaluated by the Headquarters IBRD selection panel. Another consideration is:

The State must commit to building the projects for which IBRD funds are awarded. The IBRD funds will be de-obligated if the funds cannot be expended as intended. (Note: For FY 2005 (IBRC), the maximum funds provided for each acceptable application were $400,000 For FY 2006 (IBRD), the amount will be $250,000. Funds for FY2007 have yet to be determined.)

State Department of Transportation's Responsibilities:

FHWA Division Office Responsibilities:

FHWA Headquarters Program Office Responsibilities:

FHWA Headquarters Program Office Contact:

Chien-Tan Chang
Senior Bridge Engineer - Planning and Coordination
Office of Bridge Technology (HIBT-1)
Email: chien-tan.chang@dot.gov
Phone: (202) 366-6749 Fax: (202) 366-3077

Attachment No. 2

2007 Application for Innovative Bridge Research and Deployment Program

State

State's Priority Ranking: # of

Project type (new construction, replacement, rehabilitation, or repair)

NBI structure number

County

Structure Name and/or Identifying Description (e.g., Number/Name of Route on the Bridge and Feature Crossed)

Structure description (e.g., bridge type, number of spans, length, width, material)

Innovative designs, materials and construction methods (describe the designs, materials, and/or construction methods, how they are used and how the project meets one or more of the program goals). Each application (proposal) shall include and address the following items:

  1. Project Name:
  2. Project classification/technology: such as, SCC, ABC, Geotechnology, Hydraulics/Scour etc.
  3. Project Summary:
  4. Project Description:
    1. Describe designs, materials and construction methods;
    2. Describe how it is used and how the projects meet one or more of the program goals including a statement on safety and congestion benefits (also please see the cover memorandum for details); and
    3. Technical merits (technical details, quality of innovation, technically sound, cost effective, likelihood of having a lasting impact on the State, and likelihood of having a national lasting impact.) Note: Please limit the narrative (proposal) on this section to 2 pages.

Schedule for start of work (month/year):

Cost Estimates:

Total project cost: P

Cost of "innovative material" portion of the construction A

Preliminary engineering cost, if requested B

Cost of innovative material performance evaluation (e.g., for a 2-year post-construction period) C

PE costs + construction costs + evaluation costs = (A + B + C) T

Total Federal Program Funds Requested $

State Department of Transportation Contact Person

Name:
Title:
Agency:
Ph:
Fax:
E-mail:

Local Agency Contact Person (if applicable):

Name:
Title:
Agency:
Ph:
Fax:
E-mail:

FHWA Division Office Contact Person:

Name:
Title:
Agency:
Ph:
Fax:
E-mail:

Attachment No. 3

Innovative Bridge Research and Deployment Program

Electronic Data Submission Requirements (Division Office Use Only)

The Division Office is requested to input the following basic application data to the IBRD database via the FHWA Web site. Separate instructions will be provided at a later date for submitting the information directly via the Web site. Those applications that do not include these items will be considered incomplete and returned for additional data.

Also include 2007 APPLICATION FOR INNOVATIVE BRIDGE RESEARCH AND DEPLOYMENT PROGRAM in attachment No. 2.

FHWA Headquarters Program Office Contact:

Chien-Tan Chang
Senior Bridge Engineer - Planning and Coordination
Office of Bridge Technology (HIBT-1)
Email: chien-tan.chang@dot.gov
Phone: (202) 366-6749 Fax: (202) 366-3077

FHWA Home | Infrastructure Home | Bridge Home | Feedback