Skip to contentUnited States Department of Transportation - Federal Highway AdministrationSearch FHWAFeedback

Structures

PBES Innovative Projects

By Advantages : Less Disruptive for the Environment

Keaiwa Stream Bridge

LocationRoute 11 near Pahala
StateHI
Completion Date2000
Contact PersonPaul Santo P.E.
Hawaii Department of Transportation
Phone: (808) 692-7611
Email: paul_santo@exec.state.hi.us
DescriptionA record rainstorm in late 2000 caused major damage to the only route on the southeast side of the Big Island of Hawaii. The State of Hawaii Department of Transportation chose to replace the 80-foot Route 11 bridge near Pahala with a longer structure to prevent future damage from flooding. The new 7-span, 230-foot concrete bridge, using precast prestressed concrete planks with cast-in-place concrete topping, was in operation within seven months.
PhotoPhoto of construction on Keaiwa Stream Bridge. Click image for larger view
Prefabricated ElementsDecks
Other Keywords4-foot-wide by 11-inch-thick precast prestressed concrete deck planks,precast deck panels with topping slab, precast pretensioned partial-depth deck panels
AdvantagesMinimized traffic disruption by reducing construction time and limiting lane closures.; Minimized environmental disruption because deck topping did not require shoring or falsework in the streambed, and minimized traffic disruption because precast planks were fabricated during pier construction.
Photo CreditsHawaii Department of Transportation

Linn Cove Viaduct

LocationGrandfather Mountain on the Blue Ridge Parkway, milepost 304.6
StateNC
Completion Date1983
Contact PersonGary S. Jakovich
Federal Highway Administration
Phone: (703) 404-6236
Email: gary.jakovich@fhwa.dot.gov
DescriptionThe Linn Cove Viaduct is 1,243 feet long and contains 153 superstructure segments, each weighing 50 tons, along with 40 substructure segments weighing up to 45 tons. The road is at an elevation of 4,100 feet and was designed as an S-shape to wind around the scenic mountains. To avoid placement of heavy equipment in a sensitive environment, the bridge was built in one direction from the south abutment to the north almost entirely from the top down. The only exceptions to the top down method were construction of the initial span on falsework and construction of a temporary timber bridge that enabled the micropile foundation drilling machine to prepare several of the foundation sites ahead of the superstructure erection.
PhotoLinn Cove Viaduct. Click on image for larger view
Prefabricated ElementsTotal prefab bridges
Other KeywordsElevated roadway,speed of construction
AdvantagesMinimized environmental disruption. Precasting each segment of the bridge allowed construction workers to assemble the bridge with little impact to the most environmentally sensitive section of Grandfather Mountain. This bridge also proved that a design could be environmentally sensitive in addition to being utilitarian and economical.
Related Document 1Linn Cove Viaduct Details: Plan and Elevation, Sub-footing and Footing Layout, Temporary Support, Typical Segment, Construction Notes (PDF, 3.2 mb)
HTML Version:
Photo CreditsHugh Morton of Eugene Figg, Jr.

Pelican Creek Bridge

LocationChichagof Island
StateAK
Completion Date1992
Contact PersonMike Higgs, P.E.,
Alaska Department of Transportation and Public Facilities,
(907) 465-8896
Description

This bridge has precast decked double-tee girders with precast caps and steel piles. It is one bridge 178 ft. long and 18 ft. wide with 3 spans.

A small fishing community on Chicagof Island in southeast Alaska needed a new bridge quickly after buying a fire truck that was too heavy for their old timber bridge. Construction requirements included staying out of the sensitive creek bed and completing work within a short time defined by the Department of Fish and Game. The Alaska Department of Transportation & Public Facilities chose a totally prefabricated bridge with all material, including rock for the approach fill, barged to the work site. The contractor floated in barges at high tide and anchored them in the creek. Crews drove steel piles from barges, drove a large wheeled crane onto the barges, and then used the crane to install first caps and then decked double-tee girders, post-tensioning the diaphragms. No heavy equipment was lodged in the creek bed. All construction completed in approximately 5 weeks in 1992.

Alaska DOT regularly uses decked bulb-tee girder bridges consisting of precast, prestressed girders cast with an integral deck to form a "T" shaped beam. The maximum span length is 145 ft. The superstructures are often installed in 1-2 days for a typical highway bridge. Prefabrication provided ADOT with a new bridge with a longer service life and lower maintenance costs, and it facilitated safe construction in a sensitive environment. Total prefabrication improved constructibility for Trucano Construction crews and reduced labor costs. Residents of the island got a new bridge quickly constructed and strong enough to support their civic vehicles.

PhotoOld and new Pelican Creek Bridge on Chicagof Island, Alaska. Click for larger version of image Substructure of new Pelican Creek Bridge on Chicagof Island, Alaska. Click for larger version of image New Pelican Creek Bridge on Chicagof Island, Alaska. Click for larger version of image Construction of new Pelican Creek Bridge on Chicagof Island, Alaska. Click for larger version of image Construction of new Pelican Creek Bridge on Chicagof Island, Alaska. Click for larger version of image
Prefabricated ElementsTotal prefab bridges
Other Keywordstotally prefabricated bridges
AdvantagesMinimized environmental disruption, constructibility
Contract ElementsSuperstructure Detail Sheet
Photo CreditsAlaska Department of Transportation and Public Facilities

Reedy Creek Bridge

LocationMain entrance to Walt Disney World's Animal Kingdom theme park in Orlando, FL
StateFL
Completion Date1997
Contact PersonJames S. Guarre P.E.
Phone: (206) 431-2300
Email: guarre@abam.com
DescriptionThe bridge over Reedy Creek in Osceola Parkway serves as the main entrance to Walt Disney World's Animal Kingdom. Owned by a private entity, it was designed to Florida Department of Transportation (FDOT) standards and bid as a conventional contract. The winning contractor and engineer reworked the initial design using precast concrete components on the same alignment. Design constraints included the following: the bridge had to be a low-profile structure certifiable by FDOT; it had to be constructed entirely from the top with no impact to the creek bed below; design and construction had to yield a low-maintenance structure; and certain utility lines had to be carried at the center of the alignment between the two bridges. The 1,000-ft. long bridge consisted of five structures, each 200 ft. long with expansion joints at ends and at abutments. The eastbound and westbound bridges were separated by 14 ft, which carried the utility lines on suspended steel framing. Each 200-ft. structure had five 40-ft. spans designed as a continuous structure. Precast components included pile caps and deck panels. All the pile caps were of the same cross section, made in different lengths as needed, and simply reinforced and set on a slope to provide the transverse grade. Most of the deck panels were haunched panels--thicker at the ends. The haunched panels were prestressed with strands designed to provide eccentricity in the middle region while coming close to the neutral axis at the ends. Remaining panels were prismatic, with some of them having width varying from one end to the other, and all were simply reinforced. The shallow precast pile caps supporting the precast deck panels resulted in a total depth just under 5 ft. with the deck itself only 2 ft. 5 in. deep. Except for touch-up painting of the steel piles, all work was completed from the top with no activity on the creek bed below.
PhotoReedy Creek Bridge
Prefabricated ElementsTotal prefab bridges
AdvantagesMinimized environmental impact, minimized environmental disruption
Photo CreditsBERGER/ABAM Engineers, Inc.

Route 57 over Wolf River

LocationFayette County
StateTN
Completion Date1999
Contact PersonEdward P. Wasserman P.E.
Tennessee Department of Transportation
Phone: (615) 741-3351
Email: Ed.Wasserman@state.tn.us
DescriptionThe Wolf River Bridge in Fayette County, Tennessee, crosses sensitive wetlands and carries the only east-west route through its geographic region. For the 20-span replacement bridge, the Tennessee Department of Transportation chose staged construction, maintaining one lane of traffic with timed signals. TDOT designers selected precast prestressed beams to facilitate speedy construction and allowed optional stay-in-place precast prestressed concrete deck forms. TDOT and the contractor developed details for precasting bent caps in two pieces to suit staged construction. Construction of the 1,408-foot long, 46-foot wide bridge was completed in eleven months without putting any equipment in the surrounding wetlands.
PhotoRoute 57 over Wolf River
Prefabricated ElementsBent caps; decks
Other KeywordsPrecast bent caps; precast prestressed concrete stay-in-place deck forms; precast prestressed I beams; steel pipe piles,precast deck panels with topping slab,precast prestressed I-beams,precast pretensioned partial-depth deck panels
AdvantagesMinimized environmental disruption by eliminating the need to place equipment in surrounding wetlands, and minimized traffic disruption of an important east-west corridor.
Contract Elements"A" plus "B" format was used. The "A" portions of the bids reflected prices for construction items. The "B" portion required the contractor to identify the number of calendar days needed to complete construction, which was then multiplied by a pre-determined price per day established by the owner.
Photo CreditsTennessee Department of Transportation

Events

More Information

Contact

Reggie Holt
Office of Bridge Technology
202-366-4596
E-mail Reggie

 
 
This page last modified on 05/12/08
 

FHWA
United States Department of Transportation - Federal Highway Administration