U.S. Department of Transportation
Federal Highway Administration
1200 New Jersey Avenue, SE
Washington, DC 20590
202-366-4000
California Division
Change Scope of Work (ex. Additional lanes, design exceptions, etc.) especially those which effect previous environmental NEPA clearance
Any contract change order that costs $200,000 or greater
Any contract change order that increases the cost of anticipated supplemental work listed in the detailed estimate by $200,000 or more
Once the $200,000 threshold is reached, each supplemental contract change order must obtain FHWA prior approval
Any change in the following:
Introduction of new social, environmental or economic issues that need to be addressed under applicable federal laws
Changes to, or requiring of, mandatory disposal or borrow sites – Public Interest Finding (PIF) and/or NEPA clearance may be needed
Project limits expanding beyond the limits set in the environmental document
Any revision due to a Cost Reduction Incentive Proposal (CRIP)
Any form of payment (not just a CCO) to a contractor resulting from a claim, Board of Review, Exception to Project Record Final Estimate (PRFE), District Director Determination, or Arbitration
Experimental Work Plan
Supplemental CCOs to all of the above
Any changes that result in a contract time extension of 20 or more working days. Additionally, if time is extended by more than 20% of the original contract working days, then that change and each subsequent contract change order to extend time
Waivers to the "Buy America" requirements