MAJOR CONTRACT CHANGE ORDER REQUIREMENTS
- Change Scope of Work (ex. Additional lanes, design exceptions, etc.) especially
those which effect previous environmental NEPA clearance
- Any contract change order that costs $200,000 or greater
- Any contract change order that increases the cost of anticipated supplemental
work listed in the detailed estimate by $200,000 or more
- Once the $200,000 threshold is reached, each supplemental contract change
order must obtain FHWA prior approval
- Any change in the following:
- Specifications (with the exception of "Lane Requirements and Hours of Work"
charts)
- Method of payment
- Method of materials processing
- Type or quality of materials to be furnished (with the exception of minor
building materials), such as changing the individual aggregate base to a asphalt
concrete material
- Proprietary material for which specific or blanket approval has not been
previously given
- Environmental requirements
- environmental mitigation (if available, see Mitigation Monitoring Reporting Record)
- permit conditions
- agreements with Federal Resource Agencies (examples: revising, sound walls
- height, length & location, adding auxiliary lanes, disturbing a 106 historical
site, etc.)
- Introduction of new social, environmental or economic issues that need to
be addressed under applicable federal laws
- Changes to, or requiring of, mandatory disposal or borrow sites - Public Interest
Finding (PIF) and/or NEPA clearance may be needed
- Project limits expanding beyond the limits set in the environmental document
- Any revision due to a Cost Reduction Incentive Proposal (CRIP)
- Any form of payment (not just a CCO) to a contractor resulting from a claim,
Board of Review, Exception to Project Record Final Estimate (PRFE), District Director
Determination, or Arbitration
- Experimental Work Plan
- Supplemental CCOs to all of the above
- Any changes that result in a contract time extension of 20 or more working
days. Additionally, if time is extended by more than 20% of the original contract
working days, then that change and each subsequent contract change order to extend
time
- Waivers to the "Buy America" requirements
FHWA Home |
Feedback
United States Department of Transportation - Federal Highway Administration