Are all the bases covered? | Yes | No | Not Applicable | Comments |
Has an effective project manager been selected? | ||||
Have all project tasks been identified? | ||||
Have all project tasks been defined enough so they are understood by the performing organization? | ||||
Does the performing organization agree the task budget is sufficient? | ||||
Has a project schedule been developed, reviewed, and agreed to by all parties? | ||||
Does the performing organization agree the project schedule is sufficient? | ||||
Have the necessary documents to support procurement of a contracted effort been prepared [the Request for Qualifications and/or Proposal]? | ||||
Are the Project Plan and any supporting plans documented? |