ACTT Workshop: Minnesota
June 14-16, 2004, Minneapolis, Minnesota
[Archived] Chapter 4: Next Steps
Mn/DOT's action for each of the recommendations is shown in Chapter 3. Several recommendations will be evaluated for use on this project during the final design. Policy level evaluations will also be performed and implemented on this project if possible. The following summarizes Mn/DOT's actions:
Skill Set |
Number of Goals |
Goals Not Addressed |
Number of Recommend- ations |
Normally Do / Will Do |
Will Evaluate |
Will Consider |
Will Consider Policy Change |
Requires More Funding or Resources |
Unable / Not Ready to Pursue |
R/W and Utilities | 6 | 2 | 23 | 14 | 1 | 4 | 3 | 0 | 1 |
Structures | 7 | 3 | 21 | 7 | 9 | 1 | 0 | 3 | 1 |
Construction | 10 | 2 | 14 | 2 | 8 | 4 | 0 | 0 | 0 |
Innovative Contracting | 4 | 0 | 15 | 5 | 5 | 3 | 0 | 1 | 1 |
Geotechnical Materials | 5 | 1 | 19 | 10 | 5 | 4 | 0 | 0 | 0 |
Traffic / ITS / Safety / PR | 6 | 1 | 18 | 7 | 3 | 4 | 1 | 3 | 0 |
Environment | 5 | 0 | 38 | 27 | 0 | 2 | 3 | 3 | 3 |
Totals | 43 | 9 | 148 | 72 | 31 | 22 | 7 | 9 | 7 |