ACTT Workshop: New York
Tappan Zee Bridge Deck Replacement

[Archived] Appendix B (continued): Skill Set Recording Forms

Construction/Innovative Contracting

Construction/Innovative Contracting Team
Facilitator:Anthony P. Kirby
Jay W. Wagner
Michael Schwartz
Butch Marcelle
William Moreau
Mary Lou Masko
Michael M. Sprinkel
Herbert W. Litts
James Tynan
Timothy LaCoss
Robert Davies
Peter M. Melewski
Lawrence J. O'Connor
Gerald Yakowenko
Charles Johnson
Idea (Short Name) Idea (Detailed Description) Implementation Details (Barriers, Skill Set Coordination, etc.)
Pre-purchase materials.
  • Deck materials especially.
  • Saves contractor mark-up, shifts responsibility. Lock in price on steel and concrete. Saves time and shows the public that things are being done efficiently.
Use staging areas.
  • Barge is possible from upstate if the contractor elects.

Increase length of spans to 100 feet.
  • Trucking is problematic.

Use lightweight materials

Ship in pieces and assemble at staging area.
  • You still have to get it across the street.
  • Need cranes.
Get as much assembled off-site, including the barrier.

Consider water option.
  • Productive work during the day without lane closures.
  • Reach factor is a negative; low water is an issue. Some Coast Guard concerns.
Consider eight-lane Bailey bridge 150 feet long.
  • Above the work zone.
  • Set-up and moving would require closures. Only works on causeway.
Construct temporary outrigger bridges.
  • Snake in the road. 250 feet of muck before bedrock.
Use incentives and disincentives.
  • Incentives work if variables are minimized.
  • Fines if not out of the road are necessary: $1,000 per minute per lane after 6:00 AM.
Use A plus B bidding.
  • Again, variables must be minimized.
  • Contractors know how to work the system to their advantage. Don't want to restrict variables too much.
Consider design-build (D-B).
  • Design-bid-build (D-B-B) vs. D-B.
  • NYS law prohibits.
Consider construction manager (CM) "at risk."

Pre-qualify contractors.
  • Precast okay with contractors?

Consider best value.

Use A plus B plus C bidding.

Use alternative bidding.

Consider technical proposals.

Reuse decks.
  • Leverages savings.

Bailey bridge the whole thing until new bridge on top.
  • Punch throughs are the problem.
  • FDR project.
Replace the causeway.
  • $500 million.
Use two-inch-thick grid panels.
  • Mill off 2-inch wearing course.

Construct Bailey bridges off to the side.
  • Eliminates six- to eight-hour work limitation.
Consider a long-term temporary structure.
  • Saves a lot of money for the users.
Is post-tensioning a given?

Is match casting necessary?

Consider streamlining the contracting process.

Consider shop drawing process innovations.

Use an issue resolution model.

Consider partnering.