Performance Contracting for ConstructionProject SelectionPerformance contracting is not ideal for every construction contract. However, it may hold significant advantages over traditional contracting when the following conditions are met:
One myth is that the construction project has to be large to fit under performance contracting. This is not true. This Guide can be applied to any size contract, and the work can be performed by any appropriately sized contractor. The Owner Agency should hold an initial conversation with stakeholders and then decide whether the project is suitable for performance contracting. A sample project selection process for use in this conversation is shown in Figure 2. Pros and Cons of Performance ContractingThere are a number of pros and cons of performance contracting that owner agencies need to be aware of. Pros include:
Cons include:
Outreach is needed to get both Owner Agency and contractor personnel familiar with the concept, the risks, and the rewards.
Innovation and Value EngineeringPerformance contracting is based on allowing the contractor to have flexibility in how it performs the work. This flexibility often takes the form of introducing innovative practices/technologies and/or introducing new/different approaches through the value engineering process.
For performance-contracting to be successful, the Owner Agency must cultivate an environment for innovation and remain open to new ideas, both at the proposal/bid stage, and throughout the contract. However, in the interest of public trust, the Owner Agency must ensure that the innovations/new ideas are suitable for use and will result in acceptable quality. To accomplish this, the Owner Agency should set up a formal procedure for reviewing/approving innovations and value engineering proposals. A sample procedure is provided below. Sample Procedure/Contract Language for Approval of InnovationsThe following wording is a sample of RFP wording that describes one approach to the approval of innovations. "All work performed under this contract must meet or exceed the standards contained in the Owner Agency's Standard Specifications, where applicable. Contractors are highly encouraged, however, to propose new and innovative technologies, processes, and materials that may not be encompassed within the Standard Specifications or the Standard Design Manual. These innovations must be highlighted in the Contractor's Quality Control/Quality Assurance plan and in the Contractor's Work Plan. Innovations that are standard practices in industry, or that are used by other States have a strong chance of approval. Prior to the installation or deployment of any innovation, the Contractor must request and receive the Contracting Officer's approval. To facilitate this approval, Contractors must provide assurances to the Contracting Officer's Technical Representative (COTR) that performance goals shall be achieved or exceeded. The Owner Agency may ask the Contractor to make an oral presentation on the innovation to a panel of Owner Agency employees. The Contractor shall provide the following information to the COTR regarding all proposed innovations:
|