Process Review of State Highway Construction & Materials Project Staffing
Laboratory and Project Visit Review Guidelines
(For: Central Laboratory, District Laboratory, and Individual Project Visits)
Word Version (67 kb) | PDF Version (66 kb)
| Review Date: | |
| Review Location: | |
| Personnel Met With: | |
| Project/Contract Number: | |
| Project Location: | |
| Contract Amount: | |
| Project Work/Materials type(s) | Total Value of Work | Percentage of Total Contract |
| Earthwork | | |
| Drainage & Water Systems | | |
| Subbase & Base Courses | | |
| Curbs & Pavements (HMA) | | |
| Highway Safety Appurtenances | | |
Roadside Items (Fence, Walls, Landscape) | | |
| Traffic Control Devices | | |
| Reinforced Portland Cement Concrete | | |
| Prestressed Concrete Beams | | |
| Piles & Sheeting | | |
| Structural Steel & Metal Products | | |
| Structures Waterproofing Systems | | |
Earth Retaining Systems (Revetment, MSE Walls) | | |
Number & Qualifications of Staff in Laboratories and on Individual Projects
- Number of construction and materials personnel currently assigned to Project
(List each Position):
Are all Project Records (Diary, IDRs, Materials Test Reports, Ledger, etc.) completed daily and maintained up to date?
Do Project Personnel feel that additional construction & materials staff are needed on this Project to ensure adequate contract administration and inspection?
For each person assigned to Project:
| Position Title | |
| Grade | |
| Project Job Duties | |
Assigned Full-time or Part time (What %) | |
| Number of Other Projects to which Currently Assigned | |
| Number of Hours/Day on this Project | |
| Number of Days/Week on this Project | |
| Level of Formal Education | |
| Number of Years Experience in Construction Inspection & Testing | |
Current Formal Qualifications Held (i.e. NETTCP, Other) | |
| Training (State, NHI, Other) Relevant to Work on this Project | |
| Number of Years Employed by state | |
| How was Person Hired by state | |
| Position Held Prior to Current Position | |
|