Best PracticesEnvironmental Commitments - Woodrow Wilson Bridge ProjectReturn to listingIssue or Need Identified/Addressed:Large construction projects reputedly give little care or attention to environmental sensitivity. From the planning of this 12-lane Interstate 95 drawbridge with four adjacent major interchanges, through design and during its first six years of construction, an ongoing key to the continuing success has been its environmental management group. Strategy or Best Practice:Throughout the planning phase, both the public and regulators warned of substantial environmental degradation stemming from construction. After all, the massive project would be built in the Potomac River, its tributaries and fragile wetlands along its corridor. To address these legitimate concerns, the Project's public sponsors (Federal Highway Administration, Virginia Department of Transportation, Maryland State Highway Administration, and District of Columbia Department of Transportation) called on the general engineering consultant to assemble an Environmental Management Group (EMG). EMG includes three integrated teams:
Results:The EMG has provided continuity, initiative and flexibility. We know of no other mega-project environmental effort integrated to this degree.
The flexible EMG model holds major promise for achieving positive environmental outcomes on virtually any infrastructure project – from the largest mega-project to projects of much smaller scale. Environmental Challenge Stewardship Approach to Project DevelopmentReturn to listingProblem or Issue Addressed:SHA's often run into difficulty processing environmental documents for significant highway projects. In Maryland, SHA had developed two Draft EIS's for the $2.4 billion Inter County Connector (ICC) project in 1982 and in 1997, resulting in so much controversy that the project stalled. Resource agency and environmental groups opposition to the project had been formidable. A Final EIS was never issued. Meanwhile development in the immediate project area that had been planned in anticipation of the project continued, and congestion of discontinuous east-west roadways in the project area became intolerable. Idea/Best Practice:In order to move this critical project forward Maryland State Highway Administration (MSHA) and the FHWA-MD Division adopted an environmental stewardship approach. This approach emphasized consultation, community involvement, avoidance (where possible), and mitigation (including engineering solutions). The new project development process involved:
Results:The end result of the taking a fresh and proactive, environmentally sensitive approach to a controversial project in an area of sensitively perceived environmental impacts, is the issuance of a Final EIS within 31.5 months after the Notice of Intent, and is on track for issuance of a ROD within 35 months of the Notice of Intent. Environmental Stewardship Approach to Project DevelopmentReturn to listingProblem or Issue Addressed:SHA had developed two previous Draft EIS's for the Inter County Connector (ICC) project in 1982 and in 1997, which resulting in so much controversy that the project stalled. Resource agency opposition to the project had been formidable. A Final EIS was never issued. Meanwhile development in the immediate project area that had been planned in anticipation of the project continued, and congestion of discontinuous east-west roadways in the project area became intolerable. Idea/Best Practice:Maryland State Highway Administration (MSHA) and the FHWA-MD Division adopted an environmental stewardship approach to restarting the project study. The new project development process involved: A proactive interagency involvement process that relied on professionally facilitated, regularly scheduled coordination meetings with resource agencies at the working level and the management level;
Results:The end result of the taking a fresh and proactive, environmentally sensitive approach to a controversial project in an area of sensitively perceived environmental impacts, is the issuance of a Final EIS within 31.5 months after the Notice of Intent, and is on track for issuance of a ROD within 35 months of the Notice of Intent. Environmental Stewardship Approach to Intercounty Connector (ICC)Return to listingProblem or Issue Addressed:SHA's often run into difficulty processing environmental documents for significant highway projects. In Maryland, SHA had developed two Draft EIS's for the $2.4 billion Inter County Connector (ICC) project in 1982 and in 1997, resulting in so much controversy that the project stalled. Resource agency opposition to the project had been formidable. A Final EIS was never issued. Meanwhile development in the immediate project area that had been planned in anticipation of the project continued, and congestion of discontinuous east-west roadways in the project area became intolerable. Idea/Best Practice:In order to move this critical project forward Maryland State Highway Administration (MSHA) and the FHWA-MD Division adopted an environmental stewardship approach. This approach emphasized consultation, community involvement, avoidance (where possible), and mitigation (including engineering solutions). The new project development process involved:
Results:The end result of taking a fresh and proactive, environmentally sensitive approach to a controversial project in an area of sensitively perceived environmental impacts, is the issuance of a Final EIS within 31.5 months after the Notice of Intent, and issuance of a ROD within 35 months of the Notice of Intent.
|
| About Us | Office Roster | Program Areas | Electronic Documents | Best Practices | Major Projects | Visitor Info | Useful Links |