Strategies for Developing a Plan of Action
Box 1: Scour Assessment (Item 113) shows the structure is scour critical? Box 2: Is the foundation material highly erodible? Box 3: Have scour countermeasures been installed? Box 4 Bent/Pier soundings during high water events. Box 5: Is there evidence of on-site localized scour? Box 6: Maintenance personnel check during high water events Box 7: The bridge has a history of drift accumulation Box 8: Maintenance personnel check during high water events Box 1 to Box 2 Box 2 to Box 3, if N to Box 5 Box 3 to Box 4, if N to Box 5 Box 5 if Y to Box 6, if N to Box 7 Box 7 if Y to Box 6, if N to Box 8 |
Related FeaturesContact:Dave Henderson Cynthia Nurmi Joe Krolak |
|
Updated: 04/07/2011
|