| Scour Technology | Bridge Hydraulics | Culvert Hydraulics | Highway Drainage | Hydrology | Environmental Hydraulics |
| FHWA > Engineering > Hydraulics > HEC 14 > Chapter 1 |
Hydraulic Design of Energy Dissipators for Culverts and Channels
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| Chapter | Dissipator Type | Froude Number7 (Fr) | Allowable Debris1 | Tailwater (TW) | ||
|---|---|---|---|---|---|---|
| Silt/Sand | Boulders | Floating | ||||
| 4 | Flow transitions | na | H | H | H | Desirable |
| 5 | Scour hole | na | H | H | H | Desirable |
| 6 | Hydraulic jump | > 1 | H | H | H | Required |
| 7 | Tumbling flow2 | > 1 | M | L | L | Not needed |
| 7 | Increased resistance3 | na | M | L | L | Not needed |
| 7 | USBR Type IX baffled apron | < 1 | M | L | L | Not needed |
| 7 | Broken-back culvert | > 1 | M | L | L | Desirable |
| 7 | Outlet weir | 2 to 7 | M | L | M | Not needed |
| 7 | Outlet drop/weir | 3.5 to 6 | M | L | M | Not needed |
| 8 | USBR Type III stilling basin | 4.5 to 17 | M | L | M | Required |
| 8 | USBR Type IV stilling basin | 2.5 to 4.5 | M | L | M | Required |
| 8 | SAF stilling basin | 1.7 to 17 | M | L | M | Required |
| 9 | CSU rigid boundary basin | < 3 | M | L | M | Not needed |
| 9 | Contra Costa basin | < 3 | H | M | M | < 0.5D |
| 9 | Hook basin | 1.8 to 3 | H | M | M | Not needed |
| 9 | USBR Type VI impact basin4 | na | M | L | L | Desirable |
| 10 | Riprap basin | < 3 | H | H | H | Not needed |
| 10 | Riprap apron8 | na | H | H | H | Not needed |
| 11 | Straight drop structure5 | < 1 | H | L | M | Required |
| 11 | Box inlet drop structure6 | < 1 | H | L | M | Required |
| 12 | USACE stilling well | na | M | L | N | Desirable |
The energy dissipator design procedure, illustrated in Figure 1.1, shows the recommended design steps. The designer should apply the following design procedure to one drainage channel/culvert and its associated structure at a time.
Step 1. Identify and Collect Design Data.
Energy dissipators should be considered part of a larger design system that includes a culvert or a chute, channel protection requirements (both upstream and downstream), and may include a debris control structure. Much of the input data will be available to the energy dissipator design phase from previous design efforts.
Figure 1.1. Energy Dissipator Design Procedure

Step 2. Evaluate Velocities.
Compute culvert or chute exit velocity, Vo, and compare with downstream channel velocity, Vn. (See Chapter 3.) If the exit velocity and flow depth approximates the natural flow condition in the downstream channel, the culvert design is acceptable. If the velocity is moderately higher, the designer can evaluate reducing velocity within the barrel or chute (see Chapter 3) or reducing the velocity with a scour hole (step 3). Another option is to modify the culvert or chute (channel) design such that the outlet conditions are mitigated. If the velocity is substantially higher and/or the scour hole from step 3 is unacceptable, the designer should evaluate energy dissipators (step 4). Definition of the terms "approximately equal," "moderately higher," and "substantially higher" is relative to site-specific concerns such as sensitivity of the site and the consequences of failure. However, as rough guidelines that should be re-evaluated on a site-specific basis, the ranges of less than 10 percent, between 10 and 30 percent, and greater than 30 percent, respectively, may be used.
Step 3. Evaluate Outlet Scour Hole.
Compute the outlet scour hole dimensions using the procedures in Chapter 5. If the size of the scour hole is acceptable, the designer should document the size of the expected scour hole for maintenance and note the monitoring requirements. If the size of the scour hole is excessive, the designer should evaluate energy dissipators (step 4).
Step 4. Design Alternative Energy Dissipators.
Compare the design data identified in step 1 to the attributes of the various energy dissipators in Table 1.1. Design one or more of the energy dissipators that substantially satisfy the design criteria. The dissipators fall into two general groups based on Fr:
Debris, tailwater channel conditions, site conditions, and cost must also be considered in selecting alternative designs.
Step 5. Select Energy Dissipator.
Compare the design alternatives and select the dissipator that has the best combination of cost and velocity reduction. Each situation is unique and the exercise of engineering judgment will always be necessary. The designer should document the alternatives considered.
The energy dissipator design procedure is best illustrated by applying it and the material presented in the energy dissipator design chapters to a series of design problems. These examples are intended to provide an overview of the design process. Pertinent chapters should be consulted for design details. The two design examples illustrate the process for cases where the Froude number is greater than 3 with a defined channel (tailwater) and less than 3 without a defined channel (no tailwater), respectively.
Design Example: RCB (Fr > 3) with Defined Downstream Channel (SI)
Evaluate the outlet velocity from a 3048 mm x 1829 mm RCB and determine the need for an energy dissipator.
Solution
Step 1. Identify Design Data.
RCB, D = 1.829 m, B = 3.048 m, L = 91.44 m, n = 0.012
So = 6.5%, Q = 11.8 m3/s, TW = 0.579 m, inlet control
Elevation of outlet invert = 30.48 m
yo = 0.457 m, Vo = 8.473 m/s, Fro = 4
The standard outlet with 45° wingwalls is an abrupt expansion. Since the culvert is in inlet control, the flow at the end of the apron will be supercritical: y = yo = 0.457 m and V = Vo = 8.473 m/s
Q = 11.8 m3/s, So = 6.5%, trapezoidal, 1:2 (V:H), b = 3.048 m, n = 0.03
yn = 0.579 m, Vn = 4.846 m/s
Graded gravel bed with no boulders, little floating debris
Scour hole should be contained within channel Ws = Ls = 3.048 m and should be no deeper than 1.524 m. This allowable estimate can be obtained by observing scour holes in the vicinity.
The channel, culvert, and related structures are evaluated for stability considering potential erosion, as well as buoyancy, shear, and other forces on the structure. If the channel, culvert, and related structures are assessed as unstable, the depth of degradation or height of aggradation that will occur over the design life of the structure should be estimated. In this case, the channel appears to be stable. No long-term degradation or head cutting was observed in the field.
Step 2. Evaluate Velocities.
Since Vo = 8.473 m/s is much larger than Vn = 4.846 m/s, increasing culvert n is not practical. Determine if a scour hole is acceptable (Step 3) or design an energy dissipator (Step 4).
Step 3. Evaluate Outlet Scour Hole.
hs, Ws, Ls, Vs from Chapter 5. If these values exceed allowable values in step 1, protection is required. ye = 0.835 m, hs = 2.530 m, Ws = 15.850 m, Ls = 21.640 m, Vs = 737 m3 Scour appears to be a problem and consideration should be given to reducing the Vo = 8.473 m/s to the 4.846 m/s in the channel.
Step 4. Design Alternative Energy Dissipators.
The following dissipators were determined from Table 1.1 by comparing the limitations shown against the site conditions. Since Fr > 3, tumbling flow, increased resistance, as well as, USBR Type IV, SAF stilling basin, and USBR Type VI streambed level dissipators will be designed. The outlet weir and outlet drop/weir were also assessed, but were not feasible without increasing the size of the culvert. Furthermore, a broken-back culvert was not considered and the culvert is too large for a riprap apron.
Step 5. Select Energy Dissipator.
The dissipator selected should be governed by comparing the efficiency, cost, natural channel compatibility, and anticipated scour for all the alternatives.
In this example, all the structures highlighted fit the channel, meet the velocity criteria, and produce significant energy losses. However, the costs of the USBR Type VI are lower than the other dissipators, so becomes the dissipator of choice.
Design Example: RCB (Fr > 3) with Defined Downstream Channel (CU)
Evaluate the outlet velocity from a 10 ft x 6 ft reinforced concrete box (RCB) culvert and determine the need for an energy dissipator.
Solution
Step 1. Identify Design Data:
RCB, D = 6 ft, B = 10 ft, L = 300 ft, n = 0.012
So = 6.5%, Q = 417 ft3/s, TW = 1.9 ft, inlet control
Elevation of outlet invert = 100 ft
yo = 1.5 ft, Vo = 27.8 ft/s, Fro = 4
The standard outlet with 45° wingwalls is an abrupt expansion. Since the culvert is in inlet control, the flow at the end of the apron will be supercritical: y = yo = 1.5 ft and V = Vo = 27.8 ft/s
Q = 417 ft3/s., So = 6.5%, trapezoidal, 1:2 (V:H), b = 10 ft, n = 0.03
yn = 1.9 ft, Vn = 15.9 ft/s
Graded gravel bed with no boulders, little floating debris
Scour hole should be contained within channel Ws = Ls = 10 ft and should be no deeper than 5 ft. This allowable estimate can be obtained by observing scour holes in the vicinity.
The channel, culvert, and related structures are evaluated for stability considering potential erosion, as well as buoyancy, shear, and other forces on the structure. If the channel, culvert, and related structures are assessed as unstable, the depth of degradation or height of aggradation that will occur over the design life of the structure should be estimated. In this case, the channel appears to be stable. No long-term degradation or head cutting was observed in the field.
Step 2. Evaluate Velocities.
Since Vo = 27.8 ft/s is much larger than Vn = 15.9 ft/s, increasing culvert n is not practical. Determine if a scour hole is acceptable (step 3) or design an energy dissipator (step 4).
Step 3. Evaluate Outlet Scour Hole.
hs, Ws, Ls, Vs from Chapter 5. If these values exceed allowable values in step 1, protection is required.
ye = 2.74 ft, hs = 8.3 ft, Ws = 52 ft, Ls = 71 ft, Vs = 963 ft3
Scour appears to be a problem and consideration should be given to reducing the Vo = 27.8 ft/s to the 15.9 ft/s in the channel.
Step 4. Design Alternative Energy Dissipators.
The following dissipators were determined from Table 1.1 by comparing the limitations shown against the site conditions. Since Fr > 3, tumbling flow, increased resistance, as well as the USBR Type IV, SAF stilling basin, and USBR Type VI streambed level dissipators will be designed. The outlet weir and outlet drop/weir were also assessed, but were not feasible without increasing the size of the culvert. Furthermore, a broken-back culvert was not considered and the culvert is too large for a riprap apron.
Step 5. Select Energy Dissipator.
The dissipator selected should be governed by comparing the efficiency, cost, natural channel compatibility, and anticipated scour for all the alternatives.
In this example, all the structures highlighted fit the channel, meet the velocity criteria, and produce significant energy losses. However, the costs of the USBR Type VI are lower than the other dissipators, so becomes the dissipator of choice.
Design Example: RCB (Fr < 3) with Undefined Downstream Channel (SI)
Evaluate the outlet velocity from a 3048 mm x 1829 mm reinforced concrete box (RCB) and determine the need for an energy dissipator.
Solution
Step 1. Identify Design Data.
RCB, D = 1.524 m, B = 1.524 m, L = 64.922 m, n = 0.012
So = 3.0%, Q = 5.66 m3/s, TW = 0.0 m, inlet control
Elevation of outlet invert = 30.480 m
yo = 0.655 m, Vo = 5.791 m/s, Fro = 2.3
The standard Outlet with 90° headwall is an abrupt expansion. Since the culvert is in inlet control, the flow at the end of the apron will be supercritical: y = yo = 0.655 m and V = Vo = 5.791 m/s
The downstream channel is undefined. The water will spread and decrease in depth as it leaves the culvert making tailwater essentially zero. The channel is graded sand with no boulders and has moderate to high amounts of floating debris.
A scour basin not more than 0.914 meters deep is allowable at this site. Allowable outlet velocity should be about 3 m/s.
The channel, culvert, and related structures are evaluated for stability considering potential erosion, as well as buoyancy, shear, and other forces on the structure. If the channel, culvert, and related structures are assessed as unstable, the depth of degradation or height of aggradation that will occur over the design life of the structure should be estimated. In this case, the channel appears to be stable. No long-term degradation or head cutting was observed in the field.
Step 2. Evaluate Velocities.
Since Vo = 5.791 m/s is much larger than Vallow = 3.0 m/s, increasing culvert n is not practical. Determine if a scour hole is acceptable (step 3) or design an energy dissipator (step 4).
Step 3. Evaluate Outlet Scour Hole.
hs, Ws, Ls, Vs from Chapter 5. If these values exceed allowable values in step 1, protection is required.
ye = 0.707 m, hs = 1.707 m, WS = 9.449 m, LS = 14.935 m, VS = 62 m3
Since 1.707 m is greater than the 0.914 m allowable, an energy dissipator will be necessary.
Step 4. Design Alternative Energy Dissipators.
The following dissipators were determined from Table 1.1 by comparing the limitations shown against the site conditions. For comparison purposes all the Fr < 3 dissipators will be designed (even those that cannot handle a moderate amount of debris). Dissipators meeting the Froude number requirement, but not designed are as follows (reason for exclusion in parentheses): SAF stilling basin (requires tailwater), Contra Costa basin (no defined channel); Broken-back culvert (mild site slope); outlet weir (infeasible without increasing culvert size); and riprap apron (culvert too large).
Step 5. Select Energy Dissipator.
The dissipator selected should be governed by comparing the efficiency, cost, natural channel compatibility, and anticipated scour for all the alternatives.
Right-of-way (ROW), debris, and dissipator cost are all constraints at this site. ROW is expensive making the longer dissipators more costly. Debris will affect the operation of the impact basin and may be a problem with the CSU roughness elements and tumbling flow designs. In the final analysis, the riprap basin was selected based on cost and anticipated maintenance.
Design Example: RCB (Fr < 3) with undefined Downstream Channel (CU)
Evaluate the outlet velocity from a 5 ft by 5 ft reinforced concrete box (RCB) and determine the need for an energy dissipator.
Solution
Step 1. Identify Design Data.
RCB, D = 5 ft, B = 5 ft, L = 213 ft, n = 0.012
So = 3.0%, Q = 200 ft3/s, TW = 0.0 ft, inlet control
Elevation of outlet invert = 100 ft
yo = 2.15 ft, Vo = 19 ft/s, Fro = 2.3
The standard Outlet with 90° headwall is an abrupt expansion. Since the culvert is in inlet control, the flow at the end of the apron will be supercritical: y = yo = 2.15 ft and V = Vo = 19 ft/s
The downstream channel is undefined. The water will spread and decrease in depth as it leaves the culvert making tailwater essentially zero. The channel is graded sand with no boulders and has moderate to high amounts of floating debris.
A scour basin not more than 0.914 meters deep is allowable at this site. Allowable outlet velocity should be about 10 ft/s.
The channel, culvert, and related structures are evaluated for stability considering potential erosion, as well as buoyancy, shear, and other forces on the structure. If the channel, culvert, and related structures are assessed as unstable, the depth of degradation or height of aggradation that will occur over the design life of the structure should be estimated. In this case, the channel appears to be stable. No long-term degradation or head cutting was observed in the field.
Step 2. Evaluate Velocities.
Since Vo = 19 ft/s is much larger than Vallow = 10 ft/s, increasing culvert n is not practical. Determine if a scour hole is acceptable (step 3) or design an energy dissipator (step 4).
Step 3. Evaluate Outlet Scour Hole.
hs, Ws, Ls, Vs from Chapter 5. If these values exceed allowable values in step 1, protection is required.
ye = 2.32 ft, hs = 5.6 ft, WS = 32 ft, LS = 49 ft, VS = 81 yd3
Since 5.6 ft is greater than the 3.0 ft allowable, an energy dissipator will be necessary.
Step 4. Design Alternative Energy Dissipators.
The following dissipators were determined from Table 1.1 by comparing the limitations shown against the site conditions. For comparison purposes all the Fr < 3 dissipators will be designed (even those that cannot handle a moderate amount of debris). Dissipators meeting the Froude number requirement, but not designed are as follows (reason for exclusion in parentheses): SAF stilling basin (requires tailwater), Contra Costa basin (no defined channel); Broken-back culvert (mild site slope); outlet weir (infeasible without increasing culvert size); and riprap apron (culvert too large).
Step 5. Select Energy Dissipator.
The dissipator selected should be governed by comparing the efficiency, cost, natural channel compatibility, and anticipated scour for all the alternatives.
Right-of-way (ROW), debris, and dissipator cost are all constraints at this site. ROW is expensive making the longer dissipators more costly. Debris will affect the operation of the impact basin and may be a problem with the CSU roughness elements and tumbling flow designs. In the final analysis, the riprap basin was selected based on cost and anticipated maintenance.
| << Previous | Contents | Next >> |
Cynthia Nurmi
Resource Center (Atlanta)
404-562-3908
cynthia.nurmi@dot.gov