| Scour Technology | Bridge Hydraulics | Culvert Hydraulics | Highway Drainage | Hydrology | Environmental Hydraulics |
| FHWA > Engineering > Hydraulics > HEC 23 v2 > Design Guideline 3 Check Dams/Drop Structures |
Bridge Scour and Stream Instability Countermeasures: Experience, Selection, and Design Guidance-Third EditionDesign Guideline 3 Check Dams/Drop Structures3.1 BACKGROUNDCheck dams or channel drop structures are used downstream of highway crossings to arrest head cutting and maintain a stable streambed elevation in the vicinity of the bridge. Check dams are usually built of rock riprap, concrete, sheet piles, gabions, or treated timber piles. The material used to construct the structure depends on the availability of materials, the height of drop required, and the width of the channel. Rock riprap and timber pile construction have been most successful on channels having small drops and widths less than 100 ft (30 m). Sheet piles, gabions, and concrete structures are generally used for larger drops on channels with widths ranging up to 300 ft (100 m). Check dam location with respect to the bridge depends on the hydraulics of the bridge reach and the amount of headcutting or degradation anticipated. Check dams can initiate erosion of banks and the channel bed downstream of the structure as a result of energy dissipation and turbulence at the drop. This local scour can undermine the check dam and cause failure. The use of energy dissipators downstream of check dams can reduce the energy available to erode the channel bed and banks. In some cases it may be better to construct several consecutive drops of shorter height to minimize erosion. Concrete lined basins as discussed later may also be used. Lateral erosion of channel banks just downstream of drop structures is another adverse result of check dams and is caused by turbulence produced by energy dissipation at the drop, bank slumping from local channel bed erosion, or eddy action at the banks. Bank erosion downstream of check dams can lead to erosion of bridge approach embankments and abutment foundations if lateral bank erosion causes the formation of flow channels around the ends of check dams. The usual solution to these problems is to place riprap revetment on the streambank adjacent to the check dam. The design of riprap revetment is given in Design Guideline 4. Erosion of the streambed can also be reduced by placing rock riprap in a preformed scour hole downstream of the drop structure. A row of sheet piling with top set at or below streambed elevation can keep the riprap from moving downstream. Because of the problems associated with check dams, the design of these countermeasures requires designing the check dams to resist scour by providing for dissipation of excess energy and protection of areas of the bed and the bank which are susceptible to erosive forces. 3.2 BED SCOUR FOR VERTICAL DROP STRUCTURES3.2.1 Estimating Bed ScourThe most conservative estimate of scour downstream of channel drop structures is for vertical drops with unsubmerged flow conditions. For the purposes of design the maximum expected scour can be assumed to be equal to the scour for a vertical, unsubmerged drop, regardless of whether the drop is actually sloped or is submerged. A sketch of a typical vertical drop structure with a free overfall is shown in Figure 3.1 An equation developed by the Bureau of Reclamation (Pemberton and Lara 1984) is recommended to estimate the depth of scour downstream of a vertical drop:
where:
It should be noted that Ht is the difference in the total head from upstream to downstream. This can be computed using the energy equation for steady uniform flow:
where:
The subscripts u and d refer to up- and downstream of the channel drop, respectively. The depth of scour as estimated by the above equation is independent of the grain size of the bed material. This concept acknowledges that the bed will scour regardless of the type of material composing the bed, but the rate of scour depends on the composition of the bed. In some cases, with large or resistant material, it may take years or decades to develop the maximum scour hole. In these cases, the design life of the bridge may need to be considered when designing the check dam. The check dam must be designed structurally to withstand the forces of water and soil assuming that the scour hole is as deep as estimated using the equation above. Therefore, the designer should consult geotechnical and structural engineers so that the drop structure will be stable under the full scour condition. In some cases, a series of drops may be employed to minimize drop height and construction costs of foundations. Riprap or energy dissipation could be provided to limit depth of scour (see, for example, Peterka 1964 and FHWA 1983). 3.2.2 Check Dam Design ExampleThe following design example is based upon a comparison of scour equations presented by the USBR (Peterka and Lara 1984). Given: Channel degradation is threatening bridge foundations. Increasing the bed elevation 4.6 ft (1.4 m) will stabilize the channel at the original bed level. A drop structure will raise the channel bed and reduce upstream channel slopes, resulting in greater flow depths and reduced velocity upstream of the structure. For this example, as illustrated by Figure 3.2, the following hydraulic parameters are used:
Ht is calculated from the energy equation. Using the downstream bed as the elevation datum gives:
Using Equation (3.1), the estimated depth of scour below the downstream bed level is:
In this case, the unsupported height of the structure is (h + ds) or 12.2 ft (3.7 m). If, for structural reasons, this height is unacceptable, then either riprap to limit scour depth or a series of check dams could be constructed. It should be noted that if a series of drops are required, adequate distance between each drop must be maintained (Peterka 1964). 3.2.3 Lateral Scour Downstream of Check DamsAs was mentioned, lateral scour of the banks of a stream downstream of check dams can cause the streamflow to divert around the check dam. If this occurs, a head cut may move upstream and endanger the highway crossing. To prevent this the banks of the stream must be adequately protected using riprap or other revetments. Riprap should be sized and placed in a similar fashion as for spurs and guide banks. The designer is referred to Design Guide 4 for proper sizing, and placement of riprap on the banks. 3.3 STILLING BASINS FOR DROP STRUCTURESThis section on stilling basins for drop structures is taken from the FHWA Hydraulic Engineering Circular Number 14, "Hydraulic Design of Energy Dissipators for Culverts and Channels" (FHWA 1983). A general design for a stilling basin at the toe of a drop structure was developed by the St. Anthony Falls Hydraulic Laboratory, University of Minnesota (Donnelly and Blaisdell 1954). The basin consists of a horizontal apron with blocks and sills to dissipate energy. Tailwater also influences the amount of energy dissipated. The stilling basin length computed for the minimum tailwater level required for good performance may be inadequate at high tailwater levels. Dangerous scour of the downstream channel may occur if the nappe is supported sufficiently by high tailwater so that it lands beyond the end of the stilling basin. A method for computing the stilling basin length for all tailwater levels is presented. The design is applicable to relative heights of fall ranging from 1.0(ho/yc) to 15(ho/yc) and to crest lengths greater than 1.5yc. Here ho is the vertical distance between the crest and the stilling basin floor, and yc is the critical depth of flow at the crest (Figure 3.3). The straight drop structure is effective if the drop does not exceed 15 ft (4.6 m) and if there is sufficient tailwater. There are several elements which must be considered in the design of this stilling basin. These include the length of basin, the position and size of floor blocks, the position and height of end sill, the position of the wingwalls, and the approach channel geometry. Figure 3.3 illustrates a straight drop structure which provides protection from scour in the downstream channel. 3.3.1 Design Procedures1. Calculate the specific head in approach channel.
where:
2. Calculate critical depth.
3. Calculate the minimum height for tailwater surface above the floor of the basin.
4. Calculate the vertical distance of tailwater below the crest. This will generally be a negative value since the crest is used as a reference point.
where:
5. Determine the location of the stilling basin floor relative to the crest.
6. Determine the minimum length of the stilling basin, LB, using:
where: L1 is the distance from the headwall to the point where the surface of the upper nappe strikes the stilling basin floor. This is given by:
where:
or L1 can be found graphically from Figure 3.4 L2 is the distance from the point at which the surface of the upper nappe strikes the stilling basin floor to the upstream face of the floor blocks, Figure 3.3. This distance can be determined by:
L3 is the distance between the upstream face of the floor blocks and the end of the stilling basin. This distance can be determined from:
The geometry of the undisturbed flow should be taken into consideration in the design of a straight drop stilling basin. If the overfall crest length is less than the width of the approach channel, it is important that a transition be properly designed by shaping the approach channel to reduce the effect of end contractions. Otherwise the contraction at the ends of the spillway notch may be so pronounced that the jet will land beyond the stilling-basin and the concentration of high velocities at the center of the outlet may cause additional scour in the downstream channel. 3.3.2 Stilling Basin Design ExampleUsing the same problem as was used to estimate scour at the check dam (Section 3.2.2), establish the size of a stilling basin. Given: Channel degradation is threatening bridge foundations. Increasing the bed elevation 4.6 ft (1.4 m) will stabilize the channel at the original bed level. A drop structure will raise the channel bed and reduce upstream channel slopes, resulting in greater flow depths and reduced velocity upstream of the structure. For this example, as illustrated by Figure 3.2, the following hydraulic parameters are used:
Find: Dimensions for the stilling basin as shown in Figure 3.3. Solution: Step 1. Calculate the Specific Head in Approach Channel Step 2. Calculate Critical Depth Step 3. Calculate the Minimum Height for Tailwater Surface Above the Floor of the BasinStep 4. Calculate the Vertical Distance of Tailwater Below the CrestThis will generally be a negative value since the crest is used as a reference point. h2 = -(h - yo) = -(4.6 - 9.5) = +4.9 ft (+1.5 m) where:
Step 5. Determine the Location of the Stilling Basin Floor Relative to the Crest
Step 6. Determine the Minimum Length of the Stilling Basin where: L1 is the distance from the headwall to the point where the surface of the upper nappe strikes the stilling basin floor. This is given by: where: Then, L1 = (19.7 + 67.9) / 2 = 43.8 ft (13.38 m) L2 is the distance from the point at which the surface of the upper nappe strikes the stilling basin floor to the upstream face of the floor blocks, Figure 3.3. This distance can be determined by:
L3 is the distance between the upstream face of the floor blocks and the end of the stilling basin. This distance can be determined from: L3 > 1.75 yc = 1.75 (7.3) = 12.8 ft (3.9 m) Step 7. Proportion the Floor Blocks
Step 8. Calculate the End Sill Height
Step 9. Longitudinal SillsIf used, should pass through, not between, the floor blocks. These sills are for structural purposes and are neither beneficial nor harmful hydraulically. Step 10. Calculate the Sidewall Height Above the Tailwater Level
Step 11. WingwallsShould be located at an angle of 45° with the outlet centerline and have a top slope of 1 to 1. Step 12. Modify the Approach Channel
Step 13. Aeration of the NappeNo special provision of aeration of the space beneath the nappe is required if the approach channel geometry is as recommended in Step 12. 3.4 REFERENCESDonnelly, C.A., and Blaisdell, F.W., 1954, "Straight Drop Spillway Stilling Basin," University of Minnesota, St. Anthony Falls Hydraulic Laboratory, Technical Paper 15, Series B, November. Federal Highway Administration, 1983, "Hydraulic Design of Energy Dissipators for Culverts and Channels," Hydraulic Engineering Circular Number 14, U.S. Department of Transportation, Washington, D.C. Pemberton, E.L. and Lara, J.M., 1984, "Computing Degradation and Local Scour," Technical Guidelines for Bureau of Reclamation, Engineering Research Center, Denver, CO, January. Peterka, A.J., 1964, "Hydraulic Design of Stilling Basins and Energy Dissipators," Engineering Monograph No. 25, Bureau of Reclamation, Division of Research, Denver, CO. |
Contact:Larry Arneson Joe Krolak |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Updated: 09/20/2011 |