| STATE | REPORT SUBMIT |
$ AMOUNT APPORTION |
$ AMOUNT OBLIGATED |
OBLIG % |
|---|---|---|---|---|
| Maine | 07/24/2001 | $7,437,000 | $13,543,519 | 182.1% |
| $ PROJECT AMOUNT |
PROJECT TYPE |
PROJECT DESCRIPTION |
VOC** (KG/DAY) |
CO** (KG/DAY) |
NOX** (KG/DAY) |
PM-10** (KG/DAY) |
|---|---|---|---|---|---|---|
| $150,000 | Demand Management | Demand Management Traffic Demand Management. (A TDM Program to oversee the Implementation of rideshare vanpool transit and ped/bike opportunities in the Capital Area Region.) |
162 | 0 | 261 | 0 |
| $80,000 | Demand Management | Demand Management Mount Desert Island League of Towns - TDM Measures (Project elements include: purchase eight-20 passenger buses to provide seasonal transportation build a loading area and queing area for buses serving cruise ships and provide linkage between bicycle tr |
27 | 0 | 21 | 0 |
| $80,280 | I/M and Other TCMs | I/M and Other TCMs GPCOG Educational Outreach Program (This program will provide Cumberland County schoolchildren with both theoretical information and practical experience with alternative modes of transportation including mass transit bicycling walking and rideshare. |
34 | 0 | 55 | 0 |
| $1,130,000 | I/M and Other TCMs | I/M and Other TCMs Portland New Crane for Harbor (Replaces existing crane at the Portland Harbor. Has an extended reach and increased speed capacity) |
1 | 0 | 13 | 0 |
| $23,776 | I/M and Other TCMs | I/M and Other TCMs GPCOG Educational Outreach Program (This program expands the outreach program to all of Cumberland County) |
4 | 0 | 7 | 0 |
| $(670,357) | Miscellaneous | Miscellaneous Deobligation From Previously Approved Projects |
0 | 0 | 0 | 0 |
| $24,030 | Pedestrian/Bicycle | Pedestrian/Bicycle Lewiston Central Ave/Campus Bicycle Loop (This project establishes a bicycle route along Central Ave Hogan Rd. and College Ave.) |
0 | 0 | 0 | 0 |
| $358,400 | Pedestrian/Bicycle | Pedestrian/Bicycle Auburn Turner Street Bicycle Loop (This project establishes a bicycle route in the Turner SV Central Maine Technical College area) |
0 | 0 | 0 | 0 |
| $4,400 | Pedestrian/Bicycle | Pedestrian/Bicycle Gray Bicycle/Pedestrian Facility (This project provides a safe accessible and convenient network of pedestrian facilities in the village and bicycle racks at key locations) |
4 | 0 | 4 | 0 |
| $77,120 | Pedestrian/Bicycle | Pedestrian/Bicycle Topeham Bicycle and Pedesrian Facility (This facility will link community and neighborhood activity centers and the regional network) |
5 | 0 | 7 | 0 |
| $299,777 | Pedestrian/Bicycle | Pedestrian/Bicycle Standish Bicycle/Pedestrian Facility (Construction of a pedestrian/bicycle facility along Whites Bridge Road) |
6 | 0 | 6 | 0 |
| $43,581 | Pedestrian/Bicycle | Pedestrian/Bicycle Brunswick Bicycle/Pedestrian Facility (This project constructs a bicycle and pedestrian corridor in Brunswick that will include bike lane markings signage and bike racks as needed.) |
16 | 0 | 28 | 0 |
| $800 | Shared Ride | Shared Ride Bowdoinham - Park and Ride Improvements (Install lighting as a park and ride improvement as part of PIN 6935.00) |
0 | 0 | 1 | 0 |
| $150,525 | Shared Ride | Shared Ride Freeport Park and Ride |
5 | 0 | 1 | 0 |
| $5,183 | Shared Ride | Shared Ride South Berwick Park and Ride |
2 | 0 | 5 | 0 |
| $14,155 | Shared Ride | Shared Ride Southbay Park and Ride |
1 | 0 | 1 | 0 |
| $100,000 | Shared Ride | Shared Ride Bar Harbor - Park and Ride Expansion (This park and ride lot is an extension of the Hancock Point lot. It will serve commuters traveling to the ferry at Hancock Point or commuters traveling to Ellsworth.) |
6 | 0 | 6 | 0 |
| $11,426 | Traffic Flow Improvements | Traffic Flow Improvements Portland Waterfront Intermodal Connector (Preliminary engineering for a tunnel to eliminate heavy vehicles from local streets and shorten truck route) |
0 | 0 | 1 | 0 |
| $24,564 | Traffic Flow Improvements | Traffic Flow Improvements South Portland Signal Project |
16 | 0 | 8 | 0 |
| $43,873 | Traffic Flow Improvements | Traffic Flow Improvements Traffic Calming Phase I (Experimental) (This project uses CMAQ funds to implement temporary and permanent traffic calming measures along Stevens Avenue in Portland.) |
0 | 0 | 2 | 0 |
| $322,407 | Traffic Flow Improvements | Traffic Flow Improvements Mechanic Falls - Transportation Center (Develop a Publicly owned off-street Transportation Center to encourage use of Park and Ride facilities sidewalks for pedestrians and bicycle travel and offer a bus stop for WMTS) |
0 | 0 | 1 | 0 |
| $138,738 | Traffic Flow Improvements | Traffic Flow Improvements Ogunquil Traffic and Parking Plan (This project is designed to specifically reduce congestion during the peak summer tourist season. Elements of this project include: new and improved parking areas bike racks sidewalk improvements and conversion of po |
10 | 0 | 7 | 0 |
| $71,143 | Traffic Flow Improvements | Traffic Flow Improvements Scarborough Signal Project (The 3 projects listed above are signalized intersection improvement projects. Typical improvements include replacement of defective traffic signal hardware upgrades of traffic signal control equipment signal timing adjustmen |
9 | 0 | 4 | 0 |
| $11,638 | Traffic Flow Improvements | Traffic Flow Improvements Gray Signal Project |
3 | 0 | 1 | 0 |
| $500,000 | Transit | Transit Portland Amtrak Passenger Facility |
9 | 0 | -20 | 0 |
| $800,000 | Transit | Transit Additional AMTRAK subsidy (Additional funding for the Boston-Portland-Rockland Passenger Rail) |
62 | 0 | 4 | 0 |
| $741,487 | Transit | Transit (CMAQ funds will be used to extend Amtrak service from Portland to Brunswick. Also funds will be used to upgrade Rockland Branch rail line for passenger rail service including a new park and ride lot in Brunswick for train travelers.) |
QA | 0 | 0 | 0 |
| $9,000,000 | Transit | Transit Rail upgrade Portland to Brunswick as part ot the AMTRAK expansion (Emissions credits are part of the overall AMTRAK program) |
PR | 0 | PR | 0 |
| $6,573 | Transit | Transit MDOT - Strategic Passenger Transportation Plan (The Strategic Passenger Transportation Plan is expected to work with private transportation providers to create transportation centers and corridors that will support vacations that are not reliant on privat |
434 | 0 | 274 | 0 |
| $ AMOUNT APPORTION |
$ AMOUNT OBLIGATED |
OBLIG % | |
|---|---|---|---|
| Totals | $1,515,632,668 | $1,141,784,533 | 75.3% |