Office of Planning, Environment, & Realty (HEP)
Planning • Environment • Real Estate
| STATE | REPORT SUBMIT |
$ AMOUNT APPORTION |
$ AMOUNT OBLIGATED |
OBLIG % |
|---|---|---|---|---|
| Mississippi | * 07/24/2001 | $7,255,000 | $4,285,571 | 59.1% |
| $ PROJECT AMOUNT |
PROJECT TYPE |
PROJECT DESCRIPTION |
VOC** (KG/DAY) |
CO** (KG/DAY) |
NOX** (KG/DAY) |
PM-10** (KG/DAY) |
|---|---|---|---|---|---|---|
| $(469,686) | Miscellaneous | Miscellaneous Deobligations from previously approved projects |
0 | 0 | 0 | 0 |
| $2,993,240 | STP/CMAQ | STP/CMAQ Construction of Clinton Parkway between US 80 and Northside Drive |
0 | 0 | 0 | 0 |
| $200,000 | STP/CMAQ | STP/CMAQ P.E. for four lanes |
0 | 0 | 0 | 0 |
| $800,000 | STP/CMAQ | STP/CMAQ P.E. from Hernando to Tennessee State Line |
0 | 0 | 0 | 0 |
| $762,017 | STP/CMAQ | STP/CMAQ Bypass |
0 | 0 | 0 | 0 |
| $ AMOUNT APPORTION |
$ AMOUNT OBLIGATED |
OBLIG % | |
|---|---|---|---|
| Totals | $1,515,632,668 | $1,141,784,533 | 75.3% |