| New Hampshire | 07/24/2001 | $7,634,000 | $10,788,025 | 141.3% |
| $ PROJECT AMOUNT |
PROJECT TYPE |
PROJECT DESCRIPTION |
VOC** (KG/DAY) |
CO** (KG/DAY) |
NOX** (KG/DAY) |
PM-10** (KG/DAY) |
|---|---|---|---|---|---|---|
| $88,000 | I/M and Other TCMs | I/M and Other TCMs Governor's Energy Office- Construct Fuel Stations for Alternate Fuel Vehicles (94-06CM) |
1 | 0 | 0 | 0 |
| $(63,266) | Miscellaneous | Miscellaneous Improvements to sidewalk system for Nashua School District (94-25CM) |
0 | 0 | 0 | 0 |
| $(80,000) | Miscellaneous | Miscellaneous Construct 'CNG' fueling facility for City transit system to include bus storage repair servicing parts operating storage & space (96-29CM) |
0 | 0 | 0 | 0 |
| $(188,515) | Miscellaneous | Miscellaneous Bus route initiating an intracity route to serve residents students employees/ers in Rochester (94-05CM) |
0 | 0 | 0 | 0 |
| $(3,638) | Miscellaneous | Miscellaneous Optimize signals from FE Everett Turnpike to NH 122 install new controller to improve flow (1994 project) |
0 | 0 | 0 | 0 |
| $66,031 | Pedestrian/Bicycle | Pedestrian/Bicycle To provide for 2 E-W pathway corridors and combine with 2 N-S pathway corridors (96-08CM) |
1 | 0 | 1 | 0 |
| $8,000 | Pedestrian/Bicycle | Pedestrian/Bicycle Citywide bike improvements including: lockers signs striping. Facility locations include: city parking Dover rail station Dover Point Road (98-14CM) |
0 | 0 | QA | 0 |
| $28,000 | Shared Ride | Shared Ride Construct 'park and ride' approx. 90 spaces with improved access/egress; will serve: park 'n' ride shared ride Dover shuttle Coast Pulse & Bike Transfer (98-15CM) |
0 | 0 | QA | 0 |
| $88,000 | Shared Ride | Shared Ride Construct 400 space park'n'ride near B&M RR with rail platform; facility will be used for car pool vanpool & passenger rail modes (98-13CM) |
0 | 0 | QA | 0 |
| $5,513,811 | Shared Ride | Shared Ride Construct 500 Space Park-N-Ride with bus terminal on NH 101 near I-95 Exit 3. |
4 | 0 | 24 | 0 |
| $453,605 | Shared Ride | Shared Ride NH 111/ NH 121 construct new 100 space p-n-r facility with shelter. Facility to include lighting telephone service & bicycle storage lockers (96-25CM) |
0 | 0 | QA | 0 |
| $2,572,000 | Shared Ride | Shared Ride I-93 (EXIT 1) Construct 500+ space park'n'ride with bus terminal @ Rockingham Blvd (98-09CM) |
0 | 0 | QA | 0 |
| $7,867 | Shared Ride | Shared Ride Provide safety & convenience improvements to NHDOT p-n-r lot west of I-93. Includes; lighting signage shelter telephones & bike locker storage (96-24CM) |
0 | 0 | 1 | 0 |
| $(5,692) | Traffic Flow Improvements | Traffic Flow Improvements North State Street Upgrade and coordinate signals from Pleasant to Centre Street and turning lanes (94-17CM) |
0 | 0 | 0 | 0 |
| $(21,940) | Traffic Flow Improvements | Traffic Flow Improvements Intersection improvements along Mast Rd. @ Rockland Rd. & College Rd. Add center turn lane. |
1 | 11 | 0 | 0 |
| $13,600 | Traffic Flow Improvements | Traffic Flow Improvements Intersection improvement @ Back River; signalize and coordinate with adjacent signal @ Mill St to reduce severe congestion occuring during peak hours (96-10CM) |
0 | 0 | QA | 0 |
| $(25,453) | Traffic Flow Improvements | Traffic Flow Improvements Upgrading of signal systems at 8 locations. This will result in a closed loop signal system. (CMAQ Project) |
8 | 64 | 0 | 0 |
| $96,000 | Traffic Flow Improvements | Traffic Flow Improvements Signalized intersections; construct 2200' road to include 2 lanes bike lane & will be restricted to bus/transit hov pedestrians & bikes during peak hours (98-12CM) |
0 | 0 | QA | 0 |
| $74,400 | Traffic Flow Improvements | Traffic Flow Improvements Signal coordination and pedestrian crossing at 7 intersections between Greenleaf & Heritage Ave. (96-21CM) |
0 | 0 | QA | 0 |
| $55,182 | Traffic Flow Improvements | Traffic Flow Improvements NH 101A construction of roadway widenings in conjunction with signal coordination |
0 | 0 | QA | 0 |
| $40,352 | Traffic Flow Improvements | Traffic Flow Improvements Replace existing signal controller hardware with compatible state of the art equipment at 7 intersections from Merrimack River west to FEE TPK (96-28-CM) |
3 | 60 | 0 | 0 |
| $30,048 | Traffic Flow Improvements | Traffic Flow Improvements Main Street replace existing signal controller hardware with compatible state of the art equipment from Allds Street to Library Hill (96-27CM) |
2 | 28 | 3 | 0 |
| $20,000 | Transit | Traffic Flow Improvements Install closed loop coordinated signal system from Martins Ferry northerly 1.5 miles to Granite Hill/Memorial School intersection (98-20CM) |
5 | 0 | 0 | 0 |
| $1,980,034 | Transit | Transit Replace transit vehicles with mixed fleet (96-15CM) |
0 | 0 | 1 | 0 |
| $25,600 | Transit | Transit Construct rail platform and re-furbish existing infrastructure for intermodal rail terminal |
0 | 0 | QA | 0 |
| $16,000 | Transit | Transit Lincoln Street construct rail passenger station with handicapped access paved parking for 70 cars lighting |
0 | 0 | QA | 0 |
| $ AMOUNT APPORTION |
$ AMOUNT OBLIGATED |
OBLIG % | |
|---|---|---|---|
| Totals | $1,515,632,668 | $1,141,784,533 | 75.3% |