Texas

STATE REPORT
SUBMIT
$ AMOUNT
APPORTION
$ AMOUNT
OBLIGATED
OBLIG %
Texas07/24/2001$97,492,000$60,576,43762.1%
$ PROJECT
AMOUNT
PROJECT
TYPE
PROJECT
DESCRIPTION
VOC**
(KG/DAY)
CO**
(KG/DAY)
NOX**
(KG/DAY)
PM-10**
(KG/DAY)
$2,344,956 Demand ManagementDemand Management
CM 99(017) HOV Lanes
5 0 8 0
$460,000 Demand ManagementDemand Management
CM 2000(005) Construction ADDTL. Track
0 0 QA 0
$440,000 Demand ManagementPublic-Private Partnerships
CM 99(316) FY99 Clean Air Action Program
4 0 8 0
$239,000 Demand ManagementDemand Management
CM 99(467) FY99 REG. Commute ALTERN Program
115 0 280 0
$188,000 Demand ManagementPublic-Private Partnerships
CM 2000(077) TRVL Demand MGMT PRG-TX CL Air COAL
1 0 2 0
$3,091,885 MiscellaneousMiscellaneous
Obligations to Previously Approved Projects
0 0 0 0
$28,000 Pedestrian/BicyclePedestrian/Bicycle
CM 99(197) Hike/Bike Tr in Herman PK PHILL.
0 0 2 0
$3,800,000 Pedestrian/BicyclePedestrian/Bicycle
CM 94(017) CONST. Pedestrian/Transit Way
0 0 0 0
$359,000 Shared RideShared Ride
CM 2000(078) TRVL Demand MGMT PRG-Vanpool Support
74 478 118 0
$750,000 Shared RideShared Ride
CM 2000-(141) Subsidized Vanpool Prog.-VEH. Acquisition
0 0 QA 0
$883,200 Shared RideShared Ride
CM 99(474) FY99 Regional Vanpool Program
102 0 249 0
$2,850,000 Shared RideShared Ride
CM 99(476) FY99 New Shuttle SVC/VIS TRANS FR P
0 0 0 0
$280,000 Traffic Flow ImprovementsTraffic Flow Improvements
CM 108(147) Const TRN-ARND Ramp & FRTG Rd
2 18 0 0
$1,773,191 Traffic Flow ImprovementsTraffic Flow Improvements
CM94(075) Commun Sys of/off Sys TRF MGMT
95 767 97 0
$530,121 Traffic Flow ImprovementsTraffic Flow Improvements
CM97(059) Install On-Sys. TRF. Signals
29 233 35 0
$520,000 Traffic Flow ImprovementsTraffic Flow Improvements
CM 99(636) Utility Adjustment
6 54 1 0
$83,021 Traffic Flow ImprovementsTraffic Flow Improvements
CM98(137) Intersection Improvement
1 9 2 0
$2,485,326 Traffic Flow ImprovementsTraffic Flow Improvements
CM98(451) Gr. STRUC. BASE & PVMT.
2 12 4 0
$6,342 Traffic Flow ImprovementsTraffic Flow Improvements
CM 99(172) Row Acq. Utility Adj. & Reloc. Asst.
1 10 2 0
$435,500 Traffic Flow ImprovementsTraffic Flow Improvements
CM 99(354) Install of Traffic Signal
5 35 11 0
$69,873 Traffic Flow ImprovementsTraffic Flow Improvements
CM 98(249) Intersection Improvements
1 4 1 0
$552,400 Traffic Flow ImprovementsTraffic Flow Improvements
CM 99(544) & (679) Intersection Improvements
2 16 3 0
$348,000 Traffic Flow ImprovementsTraffic Flow Improvements
CM 99(459) ROW Acquisition & RELOC Assistance
2 15 4 0
$20,000 Traffic Flow ImprovementsTraffic Flow Improvements
CM 99(214) PE
4 35 7 0
$450,000 Traffic Flow ImprovementsTraffic Flow Improvements
CM 96(749) Traffic Surveillance
0 0 QA 0
$302,900 Traffic Flow ImprovementsTraffic Flow Improvements
CM 99(232) & (633) Install Closed LP Signal SYS.-OFF/SYS.
1 10 2 0
$182,201 Traffic Flow ImprovementsTraffic Flow Improvements
CM 99(683 & 684 & 685) Acquisition Relocation & Utilities
71 566 125 0
$48,000 Traffic Flow ImprovementsTraffic Flow Improvements
CM 99(378)& (415) Traffic Signal Progression
3 19 5 0
$145,348 Traffic Flow ImprovementsTraffic Flow Improvements
CM 99(331) Install of Fiber Optic Cable
0 0 QA 0
$949,763 Traffic Flow ImprovementsTraffic Flow Improvements
CM 99(713) ITS Priority Corridor work order #15
0 0 QA 0
$88,000 Traffic Flow ImprovementsTraffic Flow Improvements
CM 99(242) Downtown Circulation Study
1 0 0 0
$262,532 Traffic Flow ImprovementsTraffic Flow Improvements
CM 99(156) Upgrade TP Actuated Signals
1 0 0 0
$2,320,000 Traffic Flow ImprovementsTraffic Flow Improvements
CM 99(155) Widen to 8 and 10 Lanes w/HOV and FRT RDS
4 0 8 0
$993,353 Traffic Flow ImprovementsTraffic Flow Improvements
CM 99(110) Install CTMS
20 0 5 0
$7,533,569 Traffic Flow ImprovementsTraffic Flow Improvements
CM 98(492) CONST NB SH146-WB SP330 Ramp N-SH14
0 0 1 0
$301,615 Traffic Flow ImprovementsTraffic Flow Improvements
CM 98(354) Add Right Turn Lanes
1 0 0 0
$700,000 Traffic Flow ImprovementsTraffic Flow Improvements
CM 96(659) Add left turn Lanes @ FRTG Roads
2 0 1 0
$1,216,430 Traffic Flow ImprovementsTraffic Flow Improvements
CM 98(425) Add Turning Lanes @ Intersection
1 0 0 0
$1,467,683 Traffic Flow ImprovementsTraffic Flow Improvements
CM 99(364) Improve Intersection and Replace BRID
1 0 0 0
$835,817 Traffic Flow ImprovementsTraffic Flow Improvements
CM 99(018) Add U-Turns
1 0 0 0
$224,079 Traffic Flow ImprovementsTraffic Flow Improvements
CM 99(007) Arterial Traffic MGMT System
1 0 0 0
$188,000 Traffic Flow ImprovementsTraffic Flow Improvements
CM 2000(077) Travel Demand MGMT PRG-TX CL Air Coal
0 0 QA 0
$4,282 Traffic Flow ImprovementsTraffic Flow Improvements
CM 99(173) ROW Acquisition utility ADJ and Relo Asst.
1 9 0 0
$134,023 Traffic Flow ImprovementsTraffic Flow Improvements
CM 97(059) Traffic Signal Upgrade
0 0 QA 0
$400,000 Traffic Flow ImprovementsTraffic Flow Improvements
CM 2000(101) Motorist Assistance Program
0 0 QA 0
$110,743 Traffic Flow ImprovementsTraffic Flow Improvements
CM 99(170)& (171) Row Acq. Utility Adj. & Reloc. Asst.
11 89 20 0
$724,284 Traffic Flow ImprovementsTraffic Flow Improvements
CM98(355) Intersection Improvement
2 12 3 0
$14,000,000 TransitExperimental Pilot Projects
CM 99(627) Rail TRAN Rail Project
55 383 95 0
$96,000 TransitExperimental Pilot Projects
CM 2000(109) PURCH. 2 Buses for E l Paso Co Transit
5 29 4 0
$1,200,000 TransitTransit
CM 99(475) CEN A/C Units-MULT Buses for Metro
18 0 36 0
$480,000 TransitTransit
CM 99(432) FY99 add Buses FR RSH Forest PRK/RI
0 0 1 0
$400,000 TransitExperimental Pilot Projects
CM 96(141) Electric Bus DEMO. Project
5 0 9 0
$160,000 TransitTransit
CM 98 (333) PHI PE GALV. Island Rail Trolley Ex
0 0 QA 0
$720,000 TransitExperimental Pilot Projects
CM 99(324) Rubber Tire Trolley OPER. (Tx90-454)
8 68 7 0
$1,000,000 TransitExperimental Pilot Projects
CM 2000(142) Transit Fleet ALTERN Fuels Prg.
8 57 11 0
$400,000 TransitExperimental Pilot Projects
CM 99(132) CONST Transit Mall FY99 (T309B)
0 0 QA 0
  $ AMOUNT
APPORTION
$ AMOUNT
OBLIGATED
OBLIG %
Totals $1,515,632,668$1,141,784,53375.3%
Updated: 07/06/2011