Skip to contentU.S. Department of Transportation, Federal Highway Administration FHWA HomeFeedback
Environment

CMAQ ANNUAL REPORTS (FY 1999)

Page 3

Page 1 - Alabama | Alaska | Arizona | Arkansas | California | Colorado
Page 2 - Connecticut | Delaware | District of Columbia | Florida | Georgia | Hawaii | Idaho
Page 3 - Illinois | Indiana | Iowa | Kansas | Kentucky | Louisiana | Maine
Page 4 - Maryland | Massachusetts | Michigan | Minnesota | Mississippi | Missouri | Montana
Page 5 - Nebraska | Nevada | New Hampshire | New Jersey | New Mexico | New York | North Carolina | North Dakota
Page 6 - Ohio | Oklahoma | Oregon | Pennsylvania | Rhode Island
Page 7 - South Carolina | South Dakota | Tennessee | Texas | Utah
Page 8 - Vermont | Virginia | Washington | West Virginia | Wisconsin | Wyoming
Totals

STATE REPORT
SUBMIT
$ AMOUNT
APPORTION
$ AMOUNT
OBLIGATED
OBLIG %
Illinois 07/24/2001 $73,957,000 $101,147,678 136.8%
Illinois
$ PROJECT
AMOUNT
PROJECT
TYPE
PROJECT
DESCRIPTION
VOC**
(KG/DAY)
CO**
(KG/DAY)
NOX**
(KG/DAY)
PM-10**
(KG/DAY)
$57,126,000 I/M and Other TCMs I/M and Other TCMs
Enhanced Inspection and Maintenance
PR 0 0 0
$2,874,000 I/M and Other TCMs I/M and Other TCMs
Enhanced Inspection and Maintenance
PR 0 0 0
$500,000 I/M and Other TCMs I/M and Other TCMs
Clean Air Public Information Campaign and Regional Carpool Radio Advertising
QA 0 0 0
$73,171 Miscellaneous Miscellaneous
Overruns/Underruns for previously obligated projects
0 0 0 0
$72,000 Pedestrian/Bicycle Pedestrian/Bicycle
Sidewalk in Hoffman Estates - Higgins Rd from Oakton to Fairmont
1 0 0 0
$402,240 Pedestrian/Bicycle Pedestrian/Bicycle
Bikeway - Naperville DuPage River Trail from Hobson to Villa
3 0 0 0
$380,160 Pedestrian/Bicycle Pedestrian/Bicycle
Bike Rack Installation at 246 locations in Chicago
3 0 0 0
$214,221 Pedestrian/Bicycle Pedestrian/Bicycle
Bike Path Signals - Grayslake trail along Center Atkinson
4 0 0 0
$113,610 Pedestrian/Bicycle Pedestrian/Bicycle
Regional Bike trail connection from I-290 to Devon
0 0 0 0
$25,297 Pedestrian/Bicycle Pedestrian/Bicycle
Pedestrian - Sauk Trail from Kostner to Butterfield in Richton
0 0 0 0
$49,509 Pedestrian/Bicycle Pedestrian/Bicycle
Bike/Ped - New Bridge over Irving Park at Station Dr. in Wood Dale (PE I)
1 0 0 0
$2,900,000 Shared Ride Shared Ride
PACE VIP Vanpool Program
QA 0 0 0
$87,020 Traffic Flow Improvements Traffic Flow Improvements
Intersection Improvement/Consolidation Dunham at IL 25 and Stearns Rd.
2 0 0 0
$2,104,153 Traffic Flow Improvements Traffic Flow Improvements
Bottleneck Elimination - US 20 @ Shales V illa St West Bluff City Blvd Elgin (Construction)
QA 0 0 0
$376,000 Traffic Flow Improvements Traffic Flow Improvements
Intersection Improvement - McHenry County Highway Dept - Main @ Cary (Construction)
2 0 0 0
$202,643 Traffic Flow Improvements Traffic Flow Improvements
Intersection Improvement - Oakton Rd at Knox in Skokie
3 0 0 0
$1,389,000 Traffic Flow Improvements Traffic Flow Improvements
Intersection Improvement - US 14 at Main St in Crystal Lake
14 0 0 0
$118,149 Traffic Flow Improvements Traffic Flow Improvements
Intersection Improvement - Wilson at IL 134 PE
10 0 0 0
$55,435 Traffic Flow Improvements Traffic Flow Improvements
Signal Interconnect - Delany from US 41 to Sunset Av. PE
3 0 0 0
$50,800 Traffic Flow Improvements Traffic Flow Improvements
Intersection Improvement - Washington St and FAU2552
1 0 0 0
$338,270 Traffic Flow Improvements Traffic Flow Improvements
Signal Interconnect - 12 locations in/near north Side of Chicago
30 0 0 0
$152,000 Transit Transit
River Forest station on Union Pacific West Line - Renovation
0 0 0 0
$620,000 Transit Transit
CTA New Employee New Resident Corporate Relocation University Pass Programs
216 0 0 0
$11,624,000 Transit Transit
Metra Commuter parking at 17 stations
210 0 0 0
$19,300,000 Transit Transit
CTA Station Renovation at 4 Stations
115 0 0 0
STATE REPORT
SUBMIT
$ AMOUNT
APPORTION
$ AMOUNT
OBLIGATED
OBLIG %
Indiana 07/24/2001 $17,429,000 $12,115,430 69.5%
Indiana
$ PROJECT
AMOUNT
PROJECT
TYPE
PROJECT
DESCRIPTION
VOC**
(KG/DAY)
CO**
(KG/DAY)
NOX**
(KG/DAY)
PM-10**
(KG/DAY)
$3,880 Demand Management Demand Management
Ozone Awareness (Vanderburgh)
15 102 21 0
$8,000 Demand Management Demand Management
Ozone Awareness (Vanderburgh)
15 102 21 0
$100,000 Demand Management Demand Management
Ozone Awareness (Marion)
19 105 20 0
$155,246 I/M and Other TCMs I/M and Other TCMs
Effectiveness of the Borman Expressway ITS Program (Lake and Porter)
28 244 5 0
$61,670 I/M and Other TCMs I/M and Other TCMs
Urban Transportation Planning (Vanderburgh)
0 1 0 0
$100,000 I/M and Other TCMs I/M and Other TCMs
Urban Transportation Planning (St Joseph)
0 1 0 0
$93,600 I/M and Other TCMs I/M and Other TCMs
Metropolitan Planning (Lake andPorter)
0 1 0 0
$270,000 I/M and Other TCMs I/M and Other TCMs
Urban Transportation Planning (Vanderburgh)
0 1 0 0
$66,674 I/M and Other TCMs I/M and Other TCMs
Urban Transportation Planning (Vanderburgh)
0 1 0 0
$(8,775,252) Miscellaneous Miscellaneous
Deobligations from Previously Authorized Project
0 0 0 0
$169,469 Miscellaneous Miscellaneous
Obligations to Previously Approved Projects
0 0 0 0
$9,167,321 Traffic Flow Improvements Traffic Flow Improvements
I 80 & Borman Expressway from Illinois state Line to Porter County & ATMS
45 251 1 0
$793,043 Traffic Flow Improvements Traffic Flow Improvements
Regional Center Signal System (Marion)
548 4470 167 0
$3,688,004 Traffic Flow Improvements Traffic Flow Improvements
I 80 & Borman Expressway from Illinois state Line to Porter County & ATMS
44 254 8 0
$4,082,304 Transit Transit
FTA Transfer
QA 0 0 0
$60,871 Transit Transit
2 13 Free Fare - 3 Year (Lake)
2 13 2 0
$320,000 Transit Transit
Urban Transportation Planning (Marion)
0 1 0 0
$150,000 Transit Transit
Public Education Program (Clark and Floyd)
32 235 45 0
$480,000 Transit Transit
Urban Transportation Planning (Clark and Floyd)
53 1 0 0
$320,600 Transit Transit
Buses for Chicago Connector (Lake)
10 22 7 0
$800,000 Transit Transit
Passenger Shelter/Signs (Marion)
2 9 1 0
STATE REPORT
SUBMIT
$ AMOUNT
APPORTION
$ AMOUNT
OBLIGATED
OBLIG %
Iowa * 07/24/2001 $6,941,000 $4,837,318 69.7%
Iowa
$ PROJECT
AMOUNT
PROJECT
TYPE
PROJECT
DESCRIPTION
VOC**
(KG/DAY)
CO**
(KG/DAY)
NOX**
(KG/DAY)
PM-10**
(KG/DAY)
$4,837,318 STP/CMAQ STP/CMAQ
149-1 (50) --2C-54 (Paving) 61-4 (53) --19-70 (Grading) 18-6 (55) --19-34 (Bridge) 218-9 (81) --19-34 (Grading)
0 0 0 0
STATE REPORT
SUBMIT
$ AMOUNT
APPORTION
$ AMOUNT
OBLIGATED
OBLIG %
Kansas 07/24/2001 $6,697,000 $5,886,992 87.9%
Kansas
$ PROJECT
AMOUNT
PROJECT
TYPE
PROJECT
DESCRIPTION
VOC**
(KG/DAY)
CO**
(KG/DAY)
NOX**
(KG/DAY)
PM-10**
(KG/DAY)
$580,432 I/M and Other TCMs I/M and Other TCMs
Kansas City and Wichita Metro Area (FY2000) Motorist Assist
QA 0 0 0
$571,468 I/M and Other TCMs I/M and Other TCMs
Kansas City and Wichita Metro Area Motorist Assist
QA 0 0 0
$60,000 I/M and Other TCMs I/M and Other TCMs
Kansas City Metro Area Study
QA 0 0 0
$(54,308) Miscellaneous Miscellaneous
Deobligations From Previously Approved Projects
0 0 0 0
$2,401,600 STP/CMAQ STP/CMAQ
Wichita: Central: I-235 to West Street Grading/Surfacing
0 0 0 0
$1,084,800 STP/CMAQ STP/CMAQ
Wichita: 29th Street North Oliver to Woodlawn Grading/Surfacing
0 0 0 0
$516,000 Traffic Flow Improvements Traffic Flow Improvements
Overland Park: 95th and Metcalf Interchange
11 0 0 0
$420,000 Traffic Flow Improvements Traffic Flow Improvements
Overland Park: 119th/Switzer and 119th/Quivira Interchange
12 0 0 0
$72,000 Traffic Flow Improvements Traffic Flow Improvements
Overland Park: 119th Street and Grant/Hayes Traffic Signal
13 0 2 0
$65,000 Traffic Flow Improvements Traffic Flow Improvements
Overland Park: 112th and Nall Traffic Signal
13 0 2 0
$20,000 Traffic Flow Improvements Traffic Flow Improvements
Kansas City: Kansas Int. Speedway I-70 & I-435 Study
QA 0 0 0
$30,000 Traffic Flow Improvements Traffic Flow Improvements
Overland Park: Citywide Study
QA 0 0 0
$120,000 Traffic Flow Improvements Traffic Flow Improvements
Overland Park: Metcalf 119th and 135th ITS
QA 0 0 0
STATE REPORT
SUBMIT
$ AMOUNT
APPORTION
$ AMOUNT
OBLIGATED
OBLIG %
Kentucky 07/24/2001 $12,070,000 $7,379,332 61.1%
Kentucky
$ PROJECT
AMOUNT
PROJECT
TYPE
PROJECT
DESCRIPTION
VOC**
(KG/DAY)
CO**
(KG/DAY)
NOX**
(KG/DAY)
PM-10**
(KG/DAY)
$1,108,144 Demand Management Demand Management
TRIMARC - Interstate Traffic Management Program
38 274 0 0
$116,000 Demand Management Demand Management
ARTIMIS-Interstate Traffic Management Program
36 279 0 0
$12,000 Demand Management Demand Management
ARTIMIS-Interstate Traffic Management Program
36 279 0 0
$104,000 Demand Management Demand Management
TANK-Experimental Pilot Project
QA QA QA 0
$208,072 Demand Management Demand Management
ARTIMIS-Interstate Traffic Management Program
36 279 0 0
$325,928 Demand Management Demand Management
ARTIMIS-Interstate Traffic Management Prog:operations
36 279 0 0
$164,450 I/M and Other TCMs I/M and Other TCMs
LEX - Oxone Projects
157 755 63 0
$120,000 I/M and Other TCMs I/M and Other TCMs
APCD-Kentucky Ozone Prevention Coalition
QA QA QA 0
$40,000 I/M and Other TCMs I/M and Other TCMs
APCD-KCFC
0 0 QA 0
$260,000 I/M and Other TCMs I/M and Other TCMs
LEX - Ozone Coalition (3 years)
QA QA QA 0
$35,000 I/M and Other TCMs I/M and Other TCMs
LEX - City-Incident Management
QA QA QA 0
$(7,833) Miscellaneous Miscellaneous
Old Project Phase - Closeout
0 0 0 0
$(123,608) Miscellaneous Miscellaneous
Old Project Phase - Closeout
0 0 0 0
$40,230 Miscellaneous Miscellaneous
Old Project Phase - Closeout
0 0 0 0
$(324) Miscellaneous Miscellaneous
Deobligations from Previously Approved Projects
0 0 0 0
$(57,836) Miscellaneous Miscellaneous
Old Project Phase - Closeout
0 0 0 0
$(2,041) Miscellaneous Miscellaneous
Old Project Phase - Closeout
0 0 0 0
$(7,502) Miscellaneous Miscellaneous
Old Project Phase - Closeout-LEX-Upgrade Corporate Drive Intersection at Harrodsburg Rd
0 0 0 0
$(5,009) Miscellaneous Miscellaneous
Old Project Phase - Closeout
0 0 0 0
$(55,587) Shared Ride Traffic Flow Improvements
Construct park and ride lot at US 27 at KY 10
4 22 4 0
$36,800 Shared Ride Traffic Flow Improvements
TANK-Park and ride Lot Development
QA QA QA 0
$14,135 Traffic Flow Improvements Traffic Flow Improvements
ASH-KY 168/29th Street Intersection Realignment
1 6 0 0
$1,464,761 Traffic Flow Improvements Traffic Flow Improvements
OKI-Left Turn Lane on Dixie Highway at Turkeyfoot Rd
6 61 1 0
$16,000 Traffic Flow Improvements Traffic Flow Improvements
OKI-Left Turn Lane on Dixie Highway at Turkeyfoot Rd
6 61 1 0
$(146,414) Traffic Flow Improvements Traffic Flow Improvements
OKI-Left Turn Lane on Dixie Highway at Sleepy Hollow Rd
6 61 1 0
$180,000 Traffic Flow Improvements Traffic Flow Improvements
OKI-Left Turn Lane on Dixie Highway at Turkeyfoot Rd
6 61 1 0
$(15,554) Traffic Flow Improvements Traffic Flow Improvements
Florence-Upgrade of traffic signal system: 4 locations
52 0 16 0
$(8,704) Traffic Flow Improvements Traffic Flow Improvements
ASH-Upgrade signal systems on US 23 and US 60
21 0 6 0
$400,000 Traffic Flow Improvements Traffic Flow Improvements
LEX - Computer Upgrade
QA QA QA 0
$(76,976) Traffic Flow Improvements Traffic Flow Improvements
LOU - Signal systems on KY 61(Preston HWY) and KY 1065(Outer Loop)
42 0 13 0
$1,280,000 Transit Transit
TARC - New and Restructured transit service
313 2507 379 0
$652,000 Transit Transit
TARC - Transportation Tomorrow-Phase II Study for Rapid Transit Corridor.
0 0 QA 0
$400,000 Transit Transit
Demand Management TANK-Clean Air Fare
1343 8101 513 0
$259,200 Transit Transit
Demand Management TANK-Southbank Shuttle Expansion
50 290 18 0
$150,000 Transit Transit
TARC-Electronic Trottle Modulation Devices
0 3467 0 0
$500,000 Transit Transit
TARC-Ozone Buster Fares
875 5936 1390 0
STATE REPORT
SUBMIT
$ AMOUNT
APPORTION
$ AMOUNT
OBLIGATED
OBLIG %
Louisiana 07/24/2001 $7,735,000 $5,306,587 68.6%
Louisiana
$ PROJECT
AMOUNT
PROJECT
TYPE
PROJECT
DESCRIPTION
VOC**
(KG/DAY)
CO**
(KG/DAY)
NOX**
(KG/DAY)
PM-10**
(KG/DAY)
$(428,020) Miscellaneous Miscellaneous
Traffic Signal project
QA 0 0 0
$637,518 Traffic Flow Improvements Traffic Flow Improvements
Motorist Assistance Patrol for interstate construction project
QA 0 0 0
$134,640 Traffic Flow Improvements Traffic Flow Improvements
Intersection Improvement project
QA 0 0 0
$2,767,544 Traffic Flow Improvements Traffic Flow Improvements
Advanced Traffic Management Center
68 0 174 0
$714,906 Traffic Flow Improvements Traffic Flow Improvements
Interstate Motorist Assistance Patrol
1 0 1 0
$1,480,000 Transit Transit
FTA Transfer for expansion of bus system for City of Baton Rouge
50 0 3 0
STATE REPORT
SUBMIT
$ AMOUNT
APPORTION
$ AMOUNT
OBLIGATED
OBLIG %
Maine 07/24/2001 $7,437,000 $13,543,519 182.1%
Maine
$ PROJECT
AMOUNT
PROJECT
TYPE
PROJECT
DESCRIPTION
VOC**
(KG/DAY)
CO**
(KG/DAY)
NOX**
(KG/DAY)
PM-10**
(KG/DAY)
$150,000 Demand Management Demand Management
Traffic Demand Management. (A TDM Program to oversee the Implementation of rideshare vanpool transit and ped/bike opportunities in the Capital Area Region.)
162 0 261 0
$80,000 Demand Management Demand Management
Mount Desert Island League of Towns - TDM Measures (Project elements include: purchase eight-20 passenger buses to provide seasonal transportation build a loading area and queing area for buses serving cruise ships and provide linkage between bicycle tr
27 0 21 0
$80,280 I/M and Other TCMs I/M and Other TCMs
GPCOG Educational Outreach Program (This program will provide Cumberland County schoolchildren with both theoretical information and practical experience with alternative modes of transportation including mass transit bicycling walking and rideshare.
34 0 55 0
$1,130,000 I/M and Other TCMs I/M and Other TCMs
Portland New Crane for Harbor (Replaces existing crane at the Portland Harbor. Has an extended reach and increased speed capacity)
1 0 13 0
$23,776 I/M and Other TCMs I/M and Other TCMs
GPCOG Educational Outreach Program (This program expands the outreach program to all of Cumberland County)
4 0 7 0
$(670,357) Miscellaneous Miscellaneous
Deobligation From Previously Approved Projects
0 0 0 0
$24,030 Pedestrian/Bicycle Pedestrian/Bicycle
Lewiston Central Ave/Campus Bicycle Loop (This project establishes a bicycle route along Central Ave Hogan Rd. and College Ave.)
0 0 0 0
$358,400 Pedestrian/Bicycle Pedestrian/Bicycle
Auburn Turner Street Bicycle Loop (This project establishes a bicycle route in the Turner SV Central Maine Technical College area)
0 0 0 0
$4,400 Pedestrian/Bicycle Pedestrian/Bicycle
Gray Bicycle/Pedestrian Facility (This project provides a safe accessible and convenient network of pedestrian facilities in the village and bicycle racks at key locations)
4 0 4 0
$77,120 Pedestrian/Bicycle Pedestrian/Bicycle
Topeham Bicycle and Pedesrian Facility (This facility will link community and neighborhood activity centers and the regional network)
5 0 7 0
$299,777 Pedestrian/Bicycle Pedestrian/Bicycle
Standish Bicycle/Pedestrian Facility (Construction of a pedestrian/bicycle facility along Whites Bridge Road)
6 0 6 0
$43,581 Pedestrian/Bicycle Pedestrian/Bicycle
Brunswick Bicycle/Pedestrian Facility (This project constructs a bicycle and pedestrian corridor in Brunswick that will include bike lane markings signage and bike racks as needed.)
16 0 28 0
$800 Shared Ride Shared Ride
Bowdoinham - Park and Ride Improvements (Install lighting as a park and ride improvement as part of PIN 6935.00)
0 0 1 0
$150,525 Shared Ride Shared Ride
Freeport Park and Ride
5 0 1 0
$5,183 Shared Ride Shared Ride
South Berwick Park and Ride
2 0 5 0
$14,155 Shared Ride Shared Ride
Southbay Park and Ride
1 0 1 0
$100,000 Shared Ride Shared Ride
Bar Harbor - Park and Ride Expansion (This park and ride lot is an extension of the Hancock Point lot. It will serve commuters traveling to the ferry at Hancock Point or commuters traveling to Ellsworth.)
6 0 6 0
$11,426 Traffic Flow Improvements Traffic Flow Improvements
Portland Waterfront Intermodal Connector (Preliminary engineering for a tunnel to eliminate heavy vehicles from local streets and shorten truck route)
0 0 1 0
$24,564 Traffic Flow Improvements Traffic Flow Improvements
South Portland Signal Project
16 0 8 0
$43,873 Traffic Flow Improvements Traffic Flow Improvements
Traffic Calming Phase I (Experimental) (This project uses CMAQ funds to implement temporary and permanent traffic calming measures along Stevens Avenue in Portland.)
0 0 2 0
$322,407 Traffic Flow Improvements Traffic Flow Improvements
Mechanic Falls - Transportation Center (Develop a Publicly owned off-street Transportation Center to encourage use of Park and Ride facilities sidewalks for pedestrians and bicycle travel and offer a bus stop for WMTS)
0 0 1 0
$138,738 Traffic Flow Improvements Traffic Flow Improvements
Ogunquil Traffic and Parking Plan (This project is designed to specifically reduce congestion during the peak summer tourist season. Elements of this project include: new and improved parking areas bike racks sidewalk improvements and conversion of po
10 0 7 0
$71,143 Traffic Flow Improvements Traffic Flow Improvements
Scarborough Signal Project (The 3 projects listed above are signalized intersection improvement projects. Typical improvements include replacement of defective traffic signal hardware upgrades of traffic signal control equipment signal timing adjustmen
9 0 4 0
$11,638 Traffic Flow Improvements Traffic Flow Improvements
Gray Signal Project
3 0 1 0
$500,000 Transit Transit
Portland Amtrak Passenger Facility
9 0 -20 0
$800,000 Transit Transit
Additional AMTRAK subsidy (Additional funding for the Boston-Portland-Rockland Passenger Rail)
62 0 4 0
$741,487 Transit Transit
(CMAQ funds will be used to extend Amtrak service from Portland to Brunswick. Also funds will be used to upgrade Rockland Branch rail line for passenger rail service including a new park and ride lot in Brunswick for train travelers.)
QA 0 0 0
$9,000,000 Transit Transit
Rail upgrade Portland to Brunswick as part ot the AMTRAK expansion (Emissions credits are part of the overall AMTRAK program)
PR 0 PR 0
$6,573 Transit Transit
MDOT - Strategic Passenger Transportation Plan (The Strategic Passenger Transportation Plan is expected to work with private transportation providers to create transportation centers and corridors that will support vacations that are not reliant on privat
434 0 274 0


FHWA Home | HEP Home | Feedback
FHWA