The noise barrier system, including the posts, panels, and foundation, must be designed and installed to withstand local wind loads as determined by the reference wind specifications for each unique installation, in conjunction with the soil design parameters along the centerline of the wall. Regardless whether the noise barrier system is to be prefabricated or fabricated on site, the manufacturer/contractor should be required to provide advance notice of the date that the fabrication of the noise barrier components is expected to commence. This is to provide sufficient opportunity for the responsible organization to observe and, possibly, take samples for quality control and quality assurance testing.
This section discusses a variety of installation-related processes including
11.1 Site Grading and Preparation
Earth grading and/or paving at the base of the noise barrier panels and posts should be such that
the bottom panels are effectively buried to avoid any gaps. The earth and/or pavement should be
sloped away from the installation to prevent the washout of soil at the base of the noise barrier.
All graded earth should be sufficiently compacted in accordance with ASTM D1557. ref.67 This is to reduce or eliminate settling of the surrounding earth and possibly creating gaps at the base of the wall between the panels and the ground line.
Changes in vertical alignment, or the ground line, should occur at the posts, or the posts should be installed where these changes occur.
11.2 Foundation Requirements.
The site-specific type, depth, size, and shape of the
foundations should be determined in accordance with the governing codes based on the
determined soil design parameters along the alignment of the noise barrier installation. The topic
of footings was discussed previously in Section 8.4.1 and
Section 8.4.2
11.3 Quality Assurances
All materials delivered to the construction site should be checked to assure that they meet all the
stipulated requirements. This is typically done in three ways:
11.3.1 Visual Examination.
A visual examination of all components should be done at the
plant and at the site before, during, and after installation. Specifically, components should be
visually inspected for:
11.3.2 Proof of Certification.
In some cases, the quality of a product may be inspected by
another approving or certifying responsible organization, or a self-governing industrial
association. A certificate may be provided from the manufacturer of that particular component,
certifying that the product had been manufactured to a specific standard and that the materials
used are of a certain quality. This type of quality assurance certification is typical for most steel
products where the certificate is issued by the mill, usually certifying the grade of the metal and
some physical and chemical properties. These certificates should be made available at the time of
supply.
11.3.3 Testing Methods.
There are two types of physical testing that can be done on any
product: (1) destructive; and (2) non-destructive. Nondestructive testing
allows the product to
be evaluated without destroying its properties or appearance. If this type of testing cannot
provide the necessary degree of accuracy or adequate information, some form of destructive
testing may be required. There are varying degrees of destructive testing, ranging from total
destruction of the product to minor cosmetic damage, which may be either too small to see or
easily repairable.
11.3.4 Sampling.
Samples for additional testing should only be provided when products are
delivered to the site, which are ready for installation and have passed both the visual inspection
and the proof of certification requirements.
11.4 Handling and Storage of Materials on
Site
Handling and storage of noise barrier components on site should be according to the
manufacturer's specifications.
11.5 Barrier Assembly and Construction
This section discusses the considerations associated with barrier assembly and construction,
including construction tolerances, sealants, fasteners, and other related processes.
11.5.1 Construction Tolerances
To ensure proper fitting of components and an acceptable overall appearance, the noise barrier
should be constructed to the height and horizontal and vertical alignment within specified
tolerances. Regardless of the aesthetic treatment and changes in elevation to accommodate
vertical and horizontal alignment shifts, the minimum specified height of the noise barrier should
be maintained at all times.
11.5.2 Grout, Caulking, and Sealants.
Any gaps or cracks in the installed noise barrier
system should be filled with an acceptable filler materials (i.e. grout, caulking, backer rods, or
sealant). When this type of material is recommended, it is important that all surfaces be clean,
dry, and free of loose material before applying the filler material. In some cases, it may be
necessary to use a flashing to cover larger gaps or to redirect water away from the noise barrier
wall. In all cases, it is critical to ensure that light cannot be seen through any part of the noise
barrier system and that the filler material or flashing
does not trap water inside the wall
components or near the base and foundation of the wall.
11.5.3 Anchors, Fasteners, and Lifting
Inserts.
Anchors, fasteners, and lifting inserts should be either made of a non-corroding metal or have a
corrosion resistant coating applied after
fabrication, but before installation.
11.5.4 Field Welds.
Factory-applied coatings, such as paints, stains, or galvanizing, are
considered to be far superior to field-applied methods. Therefore, any field operation that would
require recoating the component surfaces, such as welding of metal components, should be kept
to an absolute minimum to maintain the integrity and durability of the original coating. If field
welds are necessary, the weld and its surrounding area should be cleaned and painted with an
acceptable organic zinc-rich paint matching the color of the surrounding surfaces.
11.5.5 Coatings.
If painted, stained, or galvanized surfaces become abraded during shipping,
storage, or installation, those surfaces should be cleaned and re-coated with an organic zinc-rich
paint that matches the color of the surrounding surfaces.
![]() |
![]() |
| Figure 238. Intallation
considerations photo #2406 |
Figure 239. Intallation
considerations photo #2327 |
11.6.1 Temporary Noise Walls and
Berms.
Both stationary and mobile noise sources may
be shielded by placing either a noise berm or wall between the source and the receiver. Such a
berm, if needed for only a relatively short period of time, may be constructed of virtually any
construction material, with minimum stabilization (as per soil erosion requirements) provided.
Noise wall enclosures can be constructed of material such as construction grade plywood or sheet
metal. They may be built in sections which can be easily transported to the location needed,
assembled, disassembled after use, and moved for use at a new location. It may be possible to
create a construction noise barrier by temporarily supporting noise panels which will ultimately
become part of a permanent noise barrier system.
|
Installations considerations for all noise barriers. | ||||
| Item# | Main Topic | Sub-Topic | Consideration | See Also Section |
| 11-1 | Site Grading & Preparation | . | All graded earth should be compacted to reduce or eliminate settling of the surrounding earth and possibly creating gaps at the base of the wall between the panels and the ground line. | 11.1 |
| 11-2 | Quality Assurances | Testing Methods | Non-destructive testing is the preferred method; however, it may not always be the most accurate, or possible, for the determination and verification of some properties. | 11.3 |
| 11-3 | Construction Tolerances | . | Regardless of the aesthetic treatment and changes in elevation to accommodate alignment shifts, the minimum specified height of the noise barrier should be maintained at all times. | 11.5.1 |
| 11-4 | Installation Materials & Processes | Grout, Caulking, and Sealants | It is critical to ensure that light cannot be seen through any part of the noise barrier system and that the filler material or flashing does not trap water inside the wall components or near the base and foundation of the wall. | 11.5.2 |
| Coatings | If painted, stained or galvanized surfaces become abraded during shipping, storage, etc., those surfaces should be cleaned and re-coated. | 11.5.5 | ||