Alabama | Alaska | Arizona | Arkansas | California | Colorado | Connecticut | Delaware | District of Columbia | Eastern Dir. Fed. | Florida | Georgia | Hawaii | Idaho | Illinois | Indiana | Iowa | Kansas | Kentucky | Louisiana | Maine | Maryland | Massachusetts | Michigan | Minnesota | Mississippi | Missouri | Montana | Nebraska | Nevada | New Hampshire | New Jersey | New Mexico | New York | North Carolina | North Dakota | Ohio | Oklahoma | Oregon | Pennsylvania | Puerto Rico | Rhode Island | South Carolina | South Dakota | Tennessee | Texas | Utah | Vermont | Virginia | Washington | West Virginia | Wisconsin | Wyoming | Total
Summary Table Complete
Florida
| State | City/County | Route | Material | Type | Year | Length (feet) | Height (feet) | Cost ($/sq ft) | Barrier Cost in 2004 $ |
|---|---|---|---|---|---|---|---|---|---|
| Florida | Boca Raton | SR 808 Pnhurst-StCl | Block | I | 1982 | 1,604.00 | 12.00 | 24 | 459,022 |
| Florida | Boynton Beach | SR 9/I-95 | Concrete/Precast | I | 1997 | 2,007.00 | 20.00 | 22 | 902,992 |
| Florida | Boynton Beach | SR 9/I-95 | Concrete/Precast | I | 1998 | 4,074.00 | 12.00 | 23 | 1,130,442 |
| Florida | Brevard | I-95 | Concrete/Precast | I | 2004 | 4,599.00 | 22.00 | 28 | 2,834,866 |
| Florida | Broward | SR 818/Griffin Road | Concrete/Precast | I | 2002 | 2,850.00 | 16.00 | 23 | 1,029,333 |
| Florida | Broward | SR 869, Sawgrass Expwy. | Concrete/Precast | I | 2003 | 1,800.00 | 9.00 | 31 | 502,470 |
| Florida | Broward | SR 869, Sawgrass Expwy. | Concrete/Precast | I | 2003 | 3,000.00 | 9.00 | 31 | 847,757 |
| Florida | Broward | SR 869, Sawgrass Expwy. | Concrete/Precast | I | 2003 | 2,900.00 | 10.00 | 34 | 983,037 |
| Florida | Broward | SR 869, Sawgrass Expwy. | Concrete/Precast | I | 2003 | 7,650.00 | 12.00 | 29 | 2,683,705 |
| Florida | Broward Co | I-95 | Concrete/Precast | I | 1992 | 1,837.00 | 7.00 | 55 | 702,636 |
| Florida | Broward Co | I-95 | Concrete/Precast | I | 1992 | 9,637.00 | 16.00 | 24 | 3,684,428 |
| Florida | Broward Co | I-95 | Concrete/Precast | I | 1992 | 31,294.00 | 16.00 | 19 | 9,608,898 |
| Florida | Broward Co | I-95 | Concrete/Precast | I | 1992 | 5,199.00 | 16.00 | 24 | 1,987,873 |
| Florida | Broward Co | I-95 | Concrete/Precast | I | 1992 | 2,601.00 | 16.00 | 24 | 993,936 |
| Florida | Broward/Dade Co | I-95 | Concrete/Precast | I | 1991 | 541.00 | 13.00 | 22 | 154,671 |
| Florida | Broward/Dade Co | I-95 | Concrete/Precast | I | 1991 | 2,102.00 | 13.00 | 29 | 786,525 |
| Florida | Broward/Dade Co | I-95 | Concrete/Precast | I | 1991 | 13,018.00 | 16.00 | 26 | 5,493,067 |
| Florida | Broward/Dade Co | I-95 | Concrete/Precast | I | 1991 | 2,109.00 | 16.00 | 28 | 957,388 |
| Florida | Broward/Dade Co | I-95 | Concrete/Precast | I | 1991 | 4,825.00 | 16.00 | 27 | 2,107,534 |
| Florida | Broward/Dade Co | I-95 | Concrete/Precast | I | 1991 | 3,441.00 | 16.00 | 27 | 1,486,948 |
| Florida | Clearwater | SR 686 | Block | I | 1997 | 331.00 | 11.00 | 50 | 182,745 |
| Florida | Collier | US 41 | Concrete/Precast | I | 2004 | 790.00 | 14.00 | 25 | 276,500 |
| Florida | Daytona Beach | Nova Road 5A | Block | I | 1998 | 413.00 | 8.00 | 32 | 104,850 |
| Florida | Fort Lauderdale | I-95 | Concrete/Precast | I | 1994 | 3,277.00 | 8.00 | 17 | 447,924 |
| Florida | Fort Lauderdale | I-95 | Concrete/Precast | I | 1994 | 653.00 | 8.00 | 13 | 69,621 |
| Florida | Fort Lauderdale | I-95 | Concrete/Precast | I | 1994 | 535.00 | 8.00 | 15 | 64,349 |
| Florida | Fort Lauderdale | I-95 | Concrete/Precast | I | 1994 | 4,238.00 | 16.00 | 20 | 1,380,344 |
| Florida | Fort Lauderdale | I-95 | Concrete/Precast | I | 1994 | 1,610.00 | 17.00 | 21 | 564,211 |
| Florida | Fort Lauderdale | I-95 | Concrete/Precast | I | 1994 | 531.00 | 17.00 | 20 | 179,083 |
| Florida | Fort Lauderdale | I-95 | Concrete/Precast | I | 1994 | 5,002.00 | 18.00 | 20 | 1,810,276 |
| Florida | Fort Lauderdale | I-95 | Concrete/Precast | I | 1994 | 3,336.00 | 18.00 | 20 | 1,185,835 |
| Florida | Fort Lauderdale | I-95 | Concrete/Precast | I | 1994 | 1,132.00 | 20.00 | 20 | 443,524 |
| Florida | Fort Lauderdale | I-95 | Concrete/Precast | I | 1994 | 410.00 | 21.00 | 17 | 147,309 |
| Florida | Fort Lauderdale | I-95 | Concrete/Precast | I | 1995 | 1,571.00 | 8.00 | 18 | 221,039 |
| Florida | Fort Lauderdale | I-95 | Concrete/Precast | I | 1995 | 8,662.00 | 12.00 | 16 | 1,713,908 |
| Florida | Fort Lauderdale | I-95 | Concrete/Precast | I | 1995 | 210.00 | 17.00 | 219 | 783,302 |
| Florida | Fort Lauderdale | SR-60 | Comb/Concrete/Block | I | 1993 | 1,102.00 | 10.00 | 18 | 193,066 |
| Florida | Hillsborough | SR 589/Suncoast Pkwy | Concrete/Precast | T | 2001 | 8,175.00 | 9.00 | 17 | 1,272,310 |
| Florida | Hillsborough Co near Tampa | I-75 SR60-Columbs | Berm Only | S | 1983 | 1,345.00 | 8.00 | 9 | 93,181 |
| Florida | Jacksonville | I-295 | Concrete/Precast | I | 1998 | 5,802.00 | 17.00 | 27 | 2,654,484 |
| Florida | Jacksonville | I-95 | Concrete/Precast | I | 1998 | 16,400.00 | 20.00 | 13 | 4,380,142 |
| Florida | Lantana | SR 9/I-95 | Concrete/Precast | I | 1997 | 4,248.00 | 20.00 | 21 | 1,823,126 |
| Florida | Miami | I-195/SR 112 | Concrete/Unspecified | I | 1996 | 692.00 | 10.00 | 41 | 284,250 |
| Florida | Miami | Miami Tr | Concrete/Unspecified | I | 1994 | 230.00 | 9.00 | 32 | 66,350 |
| Florida | Miami | Miami Tr | Concrete/Unspecified | I | 1994 | 380.00 | 9.00 | 32 | 109,623 |
| Florida | Miami | Miami Tr | Concrete/Unspecified | I | 1995 | 643.00 | 9.00 | 126 | 727,501 |
| Florida | Miami | SR 821 | Concrete/Precast | I | 1998 | 10,109.00 | 7.00 | 27 | 1,909,738 |
| Florida | Miami | US 41/SR 90/SW 8th St | Concrete/Unspecified | I | 1997 | 564.00 | 10.00 | 31 | 176,547 |
| Florida | Miami/Dade | Tallahassee Road | Concrete/Unspecified | C | 2000 | 1,095.00 | 11.00 | 45 | 541,177 |
| Florida | Miami/Dade | Tamiami Tl Plz/FTP No | Concrete/Precast | T | 2001 | 5,310.00 | 13.00 | 16 | 1,086,716 |
| Florida | Miami/Dade | Tamiami Tl Plz/FTP So | Concrete/Precast | T | 2001 | 4,779.00 | 11.00 | 15 | 788,031 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 695.00 | 14.00 | 57 | 552,215 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 95.00 | 14.00 | 65 | 86,392 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 70.00 | 14.00 | 15 | 14,330 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 590.00 | 14.00 | 65 | 536,539 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 588.00 | 14.00 | 65 | 534,720 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 1,586.00 | 14.00 | 57 | 1,260,163 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 781.00 | 14.00 | 57 | 620,547 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 410.00 | 14.00 | 56 | 323,627 |
| Florida | Miami-Dade | I-95 | Concrete/Precast | I | 2002 | 960.00 | 14.00 | 40 | 530,883 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 731.00 | 15.00 | 53 | 580,819 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 583.00 | 15.00 | 53 | 463,225 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 594.00 | 15.00 | 53 | 471,965 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 1,278.00 | 15.00 | 53 | 1,015,440 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 313.00 | 15.00 | 55 | 260,132 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 85.00 | 16.00 | 57 | 77,298 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 424.00 | 16.00 | 55 | 370,088 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 983.00 | 16.00 | 50 | 781,047 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 1,040.00 | 16.00 | 55 | 907,765 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 514.00 | 16.00 | 57 | 467,426 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 360.00 | 16.00 | 57 | 327,380 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 556.00 | 16.00 | 55 | 485,305 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 595.00 | 16.00 | 55 | 519,346 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 203.00 | 16.00 | 50 | 161,294 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 1,848.00 | 16.00 | 50 | 1,468,336 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 145.00 | 16.00 | 57 | 131,861 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 480.00 | 16.00 | 55 | 418,968 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 29.00 | 17.00 | 54 | 26,524 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 480.00 | 17.00 | 47 | 381,386 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 280.00 | 17.00 | 53 | 254,628 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 57.00 | 17.00 | 53 | 51,835 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 138.00 | 17.00 | 54 | 126,215 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 450.00 | 17.00 | 53 | 409,225 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 111.00 | 17.00 | 47 | 88,196 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 675.00 | 17.00 | 47 | 536,324 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 183.00 | 17.00 | 47 | 145,403 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 540.00 | 18.00 | 53 | 516,437 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 784.00 | 18.00 | 44 | 622,930 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 400.00 | 18.00 | 51 | 363,756 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 569.00 | 18.00 | 44 | 452,101 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 260.00 | 18.00 | 51 | 236,441 |
| Florida | Miami-Dade | I-95 | Concrete/Precast | I | 2002 | 1,700.00 | 18.00 | 36 | 1,094,792 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 281.00 | 18.00 | 44 | 223,269 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 663.00 | 18.00 | 44 | 526,789 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 476.00 | 18.00 | 44 | 378,208 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 596.00 | 18.00 | 44 | 473,554 |
| Florida | Miami-Dade | I-95 | Concrete/Precast | I | 2002 | 1,800.00 | 18.00 | 36 | 1,161,325 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 549.00 | 18.00 | 44 | 436,210 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 605.00 | 18.00 | 44 | 480,705 |
| Florida | Miami-Dade | I-95 | Concrete/Precast | I | 2002 | 1,320.00 | 18.00 | 36 | 849,271 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 439.00 | 18.00 | 44 | 348,809 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 485.00 | 18.00 | 44 | 385,359 |
| Florida | Miami-Dade | I-95 | Concrete/Precast | I | 2002 | 1,020.00 | 18.00 | 36 | 660,502 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 482.00 | 18.00 | 44 | 382,975 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 587.00 | 18.00 | 44 | 466,403 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 750.00 | 18.00 | 44 | 595,915 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 892.00 | 19.00 | 42 | 708,742 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 739.00 | 19.00 | 42 | 587,175 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 752.00 | 19.00 | 42 | 597,505 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 435.00 | 19.00 | 53 | 434,183 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 83.00 | 19.00 | 42 | 65,948 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 499.00 | 19.00 | 42 | 396,482 |
| Florida | Miami-Dade | I-95 | Concrete/Precast | I | 2002 | 580.00 | 19.00 | 36 | 393,219 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 84.00 | 19.00 | 48 | 76,389 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 290.00 | 19.00 | 42 | 230,420 |
| Florida | Miami-Dade | I-95 | Concrete/Precast | I | 2002 | 1,200.00 | 19.00 | 36 | 811,976 |
| Florida | Miami-Dade | I-95 | Concrete/Precast | I | 2002 | 840.00 | 19.00 | 36 | 569,164 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 540.00 | 19.00 | 42 | 429,059 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 730.00 | 19.00 | 53 | 728,630 |
| Florida | Miami-Dade | I-95 | Concrete/Precast | I | 2002 | 900.00 | 19.00 | 35 | 604,197 |
| Florida | Miami-Dade | I-95 | Concrete/Precast | I | 2002 | 440.00 | 19.00 | 36 | 297,036 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 530.00 | 19.00 | 42 | 421,113 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 30.00 | 19.00 | 42 | 23,836 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 624.00 | 19.00 | 48 | 567,458 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 477.00 | 19.00 | 48 | 433,778 |
| Florida | Miami-Dade | I-95 | Concrete/Precast | I | 2002 | 940.00 | 20.00 | 35 | 649,675 |
| Florida | Miami-Dade | I-95 | Concrete/Precast | I | 2002 | 860.00 | 20.00 | 34 | 592,942 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 200.00 | 20.00 | 40 | 158,911 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 300.00 | 20.00 | 45 | 272,816 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 200.00 | 20.00 | 40 | 158,911 |
| Florida | Miami-Dade | I-95 | Concrete/Precast | I | 2002 | 260.00 | 20.00 | 35 | 180,919 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 614.00 | 21.00 | 43 | 558,364 |
| Florida | Miami-Dade | I-95 | Concrete/Unspecified | I | 2002 | 790.00 | 21.00 | 38 | 627,698 |
| Florida | Miami-Dade | I-95 | Concrete/Precast | I | 2002 | 2,180.00 | 22.00 | 33 | 1,595,312 |
| Florida | Miami-Dade | I-95 | Concrete/Precast | I | 2002 | 1,420.00 | 22.00 | 33 | 1,046,459 |
| Florida | N Miami Beach | I-95 | Concrete/Precast | I | 1988 | 1,916.00 | 13.00 | 19 | 473,213 |
| Florida | N Miami Beach | I-95 | Concrete/Precast | I | 1988 | 5,658.00 | 15.00 | 20 | 1,701,114 |
| Florida | N Miami Beach | I-95 | Concrete/Precast | I | 1988 | 3,998.00 | 16.00 | 21 | 1,318,020 |
| Florida | New Port Richey | SR 54 | Block | I | 1998 | 1,210.00 | 12.00 | 31 | 445,386 |
| Florida | Orlando | SR-40 | Concrete/Unspecified | I | 1995 | 216.00 | 9.00 | 111 | 216,137 |
| Florida | Palm Beach | Andrews Ave | Concrete/Precast | I | 2004 | 1,875.00 | 16.00 | 23 | 702,000 |
| Florida | Palm Beach | I-95 | Concrete/Precast | I | 2002 | 1,383.00 | 22.00 | 20 | 615,712 |
| Florida | Palm Beach | I-95 | Concrete/Precast | I | 2003 | 1,485.00 | 21.00 | 23 | 707,478 |
| Florida | Palm Beach | I-95 | Concrete/Precast | I | 2003 | 2,102.00 | 21.00 | 22 | 991,773 |
| Florida | Palm Beach | I-95 | Concrete/Precast | I | 2003 | 1,008.00 | 22.00 | 37 | 826,279 |
| Florida | Palm Beach | I-95 | Concrete/Precast | I | 2003 | 2,058.00 | 22.00 | 29 | 1,310,390 |
| Florida | Palm Beach | I-95 | Concrete/Precast | I | 2003 | 2,160.00 | 22.00 | 29 | 1,375,337 |
| Florida | Palm Beach | I-95 | Concrete/Precast | I | 2003 | 1,610.00 | 22.00 | 29 | 1,025,136 |
| Florida | Palm Beach | I-95 | Concrete/Precast | I | 2003 | 2,422.00 | 22.00 | 37 | 1,985,367 |
| Florida | Palm Beach | I-95 | Concrete/Precast | I | 2003 | 1,239.00 | 22.00 | 37 | 1,015,636 |
| Florida | Palm Beach | I-95 | Concrete/Precast | I | 2003 | 2,120.00 | 22.00 | 37 | 1,737,810 |
| Florida | Palm Beach | I-95 | Concrete/Precast | I | 2004 | 1,904.00 | 8.00 | 26 | 399,840 |
| Florida | Palm Beach | I-95 | Concrete/Precast | I | 2004 | 2,440.00 | 17.00 | 31 | 1,301,564 |
| Florida | Palm Beach | I-95 | Concrete/Precast | I | 2004 | 1,730.00 | 18.00 | 28 | 858,234 |
| Florida | Palm Beach | I-95 | Concrete/Precast | I | 2004 | 2,070.00 | 21.00 | 31 | 1,334,415 |
| Florida | Palm Beach | I-95 | Concrete/Precast | I | 2004 | 1,675.00 | 21.00 | 30 | 1,065,341 |
| Florida | Palm Beach | I-95 | Concrete/Precast | I | 2004 | 1,260.00 | 22.00 | 26 | 733,022 |
| Florida | Palm Beach | I-95/SR 9 #18 (shldr) | Concrete/Precast | I | 2001 | 350.00 | 8.00 | 19 | 51,950 |
| Florida | Palm Beach | SR 80/I-95 NB ramp | Concrete/Precast | I | 2004 | 571.00 | 8.00 | 48 | 217,500 |
| Florida | Palm Beach | SR 91, Fl.Turnpike Mailine | Concrete/Precast | I | 2003 | 5,640.00 | 19.00 | 35 | 3,718,254 |
| Florida | Palm Beach Co | I-95 | Concrete/Precast | I | 1992 | 1,876.00 | 10.00 | 29 | 549,690 |
| Florida | Palm Beach Co | I-95 | Concrete/Precast | I | 1992 | 2,749.00 | 13.00 | 22 | 777,662 |
| Florida | Palm Beach Co | I-95 | Concrete/Precast | I | 1992 | 1,519.00 | 13.00 | 19 | 377,186 |
| Florida | Palm Beach Co | I-95 | Concrete/Precast | I | 1992 | 722.00 | 13.00 | 36 | 342,220 |
| Florida | Palm Beach Co | I-95 | Concrete/Precast | I | 1992 | 1,929.00 | 13.00 | 21 | 519,964 |
| Florida | Palm Beach Co | I-95 | Concrete/Precast | I | 1992 | 2,575.00 | 16.00 | 18 | 723,535 |
| Florida | Palm Beach Co | I-95 | Concrete/Precast | I | 1992 | 2,831.00 | 16.00 | 21 | 961,285 |
| Florida | Palm Beach Co | I-95 | Concrete/Precast | I | 1992 | 4,398.00 | 16.00 | 20 | 1,389,409 |
| Florida | Palm Beach Co | I-95 | Concrete/Precast | I | 1992 | 3,710.00 | 16.00 | 21 | 1,229,642 |
| Florida | Palm Beach Co | I-95 | Concrete/Precast | I | 1992 | 1,151.00 | 16.00 | 19 | 346,084 |
| Florida | Palm Beach Co | I-95 | Concrete/Precast | I | 1992 | 5,205.00 | 16.00 | 19 | 1,575,980 |
| Florida | Palm Beach Co | I-95 | Concrete/Precast | I | 1992 | 4,133.00 | 16.00 | 20 | 1,294,717 |
| Florida | Palm Beach Co | I-95 | Concrete/Precast | I | 1992 | 1,089.00 | 16.00 | 19 | 328,082 |
| Florida | Palm Beach Co | I-95 | Concrete/Precast | I | 1992 | 2,575.00 | 16.00 | 20 | 807,982 |
| Florida | Palm Beach Co | I-95 (SR 9) #16 | Concrete/Precast | I | 1998 | 975.00 | 8.00 | 13 | 97,750 |
| Florida | Palm Beach Co | I-95 (SR 9) #19 | Concrete/Precast | I | 2001 | 1,480.00 | 22.00 | 14 | 444,399 |
| Florida | Palm Beach Co | I-95 (SR 9) #20 | Concrete/Precast | I | 2001 | 2,340.00 | 22.00 | 14 | 702,631 |
| Florida | Palm Beach Co | I-95 (SR 9) #24 | Concrete/Precast | I | 1999 | 2,060.00 | 22.00 | 23 | 1,027,009 |
| Florida | Palm Beach Co | I-95 (SR 9) #25 | Concrete/Precast | I | 1999 | 2,040.00 | 22.00 | 26 | 1,169,345 |
| Florida | Palm Beach Co | I-95 (SR 9) #26 | Concrete/Precast | I | 1999 | 2,580.00 | 22.00 | 21 | 1,173,472 |
| Florida | Palm Beach Co | I-95 (SR 9) #27 | Concrete/Precast | I | 1999 | 2,280.00 | 22.00 | 23 | 1,136,689 |
| Florida | Palm Beach Co | I-95 (SR 9) #6 | Concrete/Precast | I | 1998 | 4,380.00 | 13.00 | 23 | 1,316,306 |
| Florida | Palm Beach Co | I-95 (SR 9) #7 | Concrete/Precast | I | 2001 | 1,020.00 | 22.00 | 24 | 535,981 |
| Florida | Palm Beach Co | I-95 (SR 9) #8 | Concrete/Precast | I | 1996 | 2,020.00 | 20.00 | 26 | 1,038,154 |
| Florida | Palm Beach Co | I-95 (SR 9) #9 | Concrete/Precast | I | 1998 | 4,350.00 | 19.00 | 24 | 2,011,215 |
| Florida | Palm Beach Co | I-95/SR 9 #17 (R/W) | Concrete/Precast | I | 1998 | 980.00 | 22.00 | 24 | 525,538 |
| Florida | Palm Beach Co | I-95/SR 9 #17 (shldr) | Concrete/Precast | I | 1998 | 677.00 | 8.00 | 18 | 95,550 |
| Florida | Palm Beach Co | I-95/SR 9 #18 (R/W) | Concrete/Precast | I | 2001 | 1,500.00 | 18.00 | 19 | 500,947 |
| Florida | Palm Beach Co | SR 7- Boca Greens | Concrete/Precast | I | 2001 | 560.00 | 19.00 | 20 | 209,262 |
| Florida | Palm Beach Gardens | SR 9/I-95 | Concrete/Precast | I | 1998 | 2,276.00 | 22.00 | 22 | 1,116,936 |
| Florida | Palm Beach Gardens | SR 9/I-95 | Concrete/Precast | I | 1998 | 2,558.00 | 22.00 | 23 | 1,301,973 |
| Florida | Pinellas | SR 586 Palm Harbor | Comb/Block/Brick | I | 2000 | 1,171.00 | 7.00 | 37 | 305,079 |
| Florida | Polk | I-4 | Concrete/Precast | I | 2003 | 3,280.00 | 16.00 | 17 | 881,692 |
| Florida | Polk | I-4 | Concrete/Precast | I | 2003 | 5,556.00 | 16.00 | 17 | 1,493,499 |
| Florida | Polk | I-4 | Concrete/Precast | I | 2003 | 2,440.00 | 22.00 | 16 | 880,317 |
| Florida | Riviera Beach | SR 9/I-95 | Concrete/Precast | I | 1998 | 1,837.00 | 20.00 | 23 | 850,721 |
| Florida | Riviera Beach | SR 9/I-95 | Concrete/Precast | I | 1998 | 1,978.00 | 22.00 | 22 | 970,566 |
| Florida | Sarasota | Business US 41 | Concrete/Unspecified | I | 2004 | 425.00 | 10.00 | 45 | 189,574 |
| Florida | Sarasota | Business US 41 | Concrete/Unspecified | I | 2004 | 571.00 | 12.00 | 35 | 236,989 |
| Florida | Sarasota | Business US 41 | Concrete/Unspecified | I | 2004 | 450.00 | 12.00 | 35 | 187,114 |
| Florida | Sarasota | Business US 41 | Concrete/Unspecified | I | 2004 | 186.00 | 14.00 | 45 | 118,153 |
| Florida | Sarasota | SR 72 | Block | I | 1998 | 830.00 | 10.00 | 37 | 306,639 |
| Florida | Seminole | I-4 | Concrete/Precast | I | 2003 | 4,722.00 | 22.00 | 30 | 3,081,829 |
| Florida | Seminole | SR 414/Maitland Blvd | Concrete/Precast | I | 2001 | 5,842.00 | 14.00 | 26 | 2,153,725 |
| Florida | St. Petersburg | I-175 16th-9thS | Concrete/Unspecified | I | 1978 | 1,778.00 | 10.00 | 25 | 446,131 |
| Florida | St. Petersburg | I-175 9th-4thS | Concrete/Unspecified | I | 1980 | 1,489.00 | 8.00 | 22 | 258,950 |
| Florida | St. Petersburg | I-275 37th-41stS | Concrete/Precast | I | 1984 | 1,332.00 | 8.00 | 29 | 308,808 |
| Florida | St. Petersburg | I-275 5thAv-28thS | Concrete/Unspecified | I | 1980 | 1,929.00 | 8.00 | 23 | 355,622 |
| Florida | St. Petersburg | I-275 Temporary | Metal/Unspecified | I | 1985 | 318.00 | 9.00 | 25 | 71,145 |
| Florida | St. Petersburg | I-375 16th-9thN | Concrete/Unspecified | I | 1977 | 1,204.00 | 8.00 | 39 | 379,137 |
| Florida | St. Petersburg | I-375 9th-6thN | Concrete/Unspecified | I | 1979 | 948.00 | 7.00 | 4 | 25,491 |
| Florida | St. Petersburg | I-375 9th-6thN | Concrete/Unspecified | I | 1979 | 574.00 | 8.00 | 23 | 104,288 |
| Florida | St. Petersburg | I-l75 9th-4thS | Block | I | 1980 | 902.00 | 8.00 | 3 | 20,968 |
| Florida | Sumter | SR 44 at Wildwood | Concrete/Precast | I | 2000 | 1,290.00 | 9.00 | 51 | 593,462 |
| Florida | Tampa | I-75 | Concrete/Precast | I | 1996 | 1,079.00 | 7.00 | 44 | 328,839 |
| Florida | Tampa | SR-580 | Concrete/Unspecified | I | 1995 | 1,250.00 | 8.00 | 37 | 369,348 |
| Florida | Vero Beach | SR 60 | Block | II | 1992 | 1,102.00 | 10.00 | 18 | 199,128 |
| Florida | Volusia | I-4 | Concrete/Precast | I | 2004 | 4,980.00 | 18.00 | 33 | 2,948,000 |
| Florida | West Palm Beach | SR 9/I-95 | Concrete/Unspecified | I | 1998 | 1,319.00 | 8.00 | 12 | 126,440 |
| Florida | West Palm Beach | SR 9/I-95 | Concrete/Unspecified | I | 1998 | 974.00 | 22.00 | 32 | 681,355 |
| Subtotal | 424,702.00 | 175,906,017.00 |