Skip to contentU.S. Department of Transportation, Federal Highway Administration FHWA HomeFeedback
Environment

7.0 MITIGATION OF CONSTRUCTION NOISE

7.1 Introduction

This chapter provides more examples of typical mitigation techniques and options. Information provided is not to be considered all-inclusive, nor is it intended to limit the ingenuity or resourcefulness of designers, contractors, and inspectors, or create a strategy uniquely suited to the characteristics of a specific project.

Design Options
Design and Project Layout
Sequence of Operations
Alternative Construction Methods
Contract Specifications/Special Provisions
Operational Constraints
Time Periods and Duration
Specified Equipment
Noise-Related Incentives/Disincentives
Training Programs for Contractor
Mitigation at the Source
Stationary Equipment
Mobile Equipment
Selection of Equipment
Inspection/Maintenance Programs
Equipment Operation Training
Mitigation Along the Path
Natural Shielding
Temporary Shielding
Permanent Shielding
Mitigation at the Receiver
Building Envelope Improvements
Masking
Relocation of Residents
Public Involvement and Project Coordination
Critical components of the overall mitigation strategy. Should be considered during all phases of a project.

Table 7.1 Overview of mitigation options.

The level of detail in a contract required to address construction noise mitigation is dependant on the complexity of the project, the amount and type of work required, and the sensitivity of the area beyond the project boundary. Therefore, not all projects require the same amount of detail. Such detail could range anywhere from the inclusion of a standard specification requiring the contractor to be governed by local noise ordinances, to realigning the highway, providing for abatement structures, and/or relocation of residents.

The effective control of highway construction noise can be achieved in much the same manner as the control of operational traffic by considering the following techniques:

Another effective technique is the inclusion of operational conditions via contract specifications and special provisions.

Public Involvement and project coordination are also essential components of the overall mitigation strategy worthy of consideration during all phases of a project. For a more detailed discussion of this topic, refer to Chapter 8.

Most of the options presented in this chapter can be employed independently or in combination, depending on the scope of the project and the resultant effects that are desired. While reductions in noise levels will vary with the method employed, consideration of all practical and feasible options is essential during all stages of the project development from planning through design and construction to final evaluation.

7.2 Design Options

Noise impacts can occur on any project involving the construction of a highway facility. While the magnitude of the impact construction noise may have on a community may not be known early in the project development stages, measures can be implemented during the design phase that can help to reduce the anticipated noise impacts at sensitive receptors. However, design changes and modification to project layout are not always practical or feasible. Also, the magnitude of the noise reduction attained from some of these techniques is usually difficult to determine prior to and possibly even during construction.

7.2.1 Design Phases

In addressing construction noise mitigation during the design phases of a project, abatement opportunities can be considered for a variety of areas and features including those listed below:

A storage area for equipment and other goods needed for the construction project can be placed far from sensitive receptors or in land uses not affected by noise, such as highway right-of-way.

Figure 7.1 Storage area in highway right-of-way (Photo #177)

A storage area with a few supplies and construction equipment are shielded partially by a stock pile of excess fill.

Figure 7.2 Partial shielding of storage area in residential area (Photo #247)

A storage area for supplies and equipment (as noted by the crane) in a residential location that is placed far from residences and near the highway right-of-way. A temporary wooden barrier can also be seen partially shielding the storage area.

Figure 7.3 Storage area in remote location (Photo #1257)

  • Haul Roads: Haul roads can be designated in locations where the noise impacts caused by truck traffic will be reduced.

An orange sign with directional arrow posted on existing sign pole designating a street as a haul route for trucks on the Woodrow Wilson Bridge project in metro DC area.

Figure 7.4 Designated haul routes (Photo #560)

A street next to a roadway is blocked off as a construction site, thus causing congestion on the adjacent roadway. A dump truck, hoe ram, and front end loaders are on site.

Figure 7.5. Shifting of traffic to accommodate construction. (Photo #1261)

  • Existing Barriers: As early as possible in the design development process, natural and artificial barriers such as ground elevation changes, existing buildings, noise walls, and other structures can be considered for use as a noise shield during certain operations.

A construction site in the highway right-of-way uses an existing retaining wall to act as a noise barrier for a stationary grout injection activity. An historic cemetery and residences are in the background.

Figure 7.6 Existing retaining wall acting as noise barrier during construction (Photo #543)

7.2.2 Sequence of Operation

The sequencing and scheduling of construction operations is equally important in addressing and mitigating construction-related noise:

An aerial photo of a highway construction site that has been graded. Since noise barriers were part of the highway project, they were built first to shield nearby residences from the majority of construction activities.

Figure 7.7 Early construction of noise barriers (Photo #447)

7.2.3 Alternative Construction Methods

Alternatives to standard construction techniques may also be available and determined to be more practical and/or cost-effective in dealing with construction noise impacts and perceptions. Examples associated with several operations are discussed below.

  • Pile Driving: Pile driving may produce noise levels in excess of acceptable limits, even when feasible noise reduction methods are used. Various dampening and shielding methods discussed later can attain some reduction. However, such methods rarely reduce the noise level to an acceptable level for the sensitive receptors close to the site. As an alternative to driving piles, it is possible to use vibration or hydraulic insertion techniques. Drilled or augured holes for cast-in-place piles are another alternative that may produce noise levels significantly lower than the traditional driving method.

Instead of pile driving (an extremely noisy activity), alternative construction methods can be utilized. An auger is used to drill a hole for a cast-in-place pile.

Figure 7.8 Alternative to pile driving (Photo #509)

  • Compressors: While most compressors are powered by diesel or gasoline engines, many are contained or have baffles to help abate noise levels. Electric compressors are significantly quieter than diesel or gasoline engine powered compressors.

A diesel compressor with baffled housing is used for a project where nearby residences are present. An electric compressor is significantly quieter than a diesel or gasoline compressor.

Figure 7.9 Diesel compressor with baffled housing (Photo #69)

7.3 Contract Specifications and Special Provisions

Contract specifications and special provisions are typically produced during the design stages of project development and may be included in the project plans and contract documents. Ideally, use of these documents is considered in conjunction with other control methods to achieve an overall construction noise strategy. Examples of such specificationsref023, ref028, ref103, and ref053 are referenced in this Handbook.

7.3.1 Construction Noise Criteria Limits

When establishing suitable noise criteria limits for specifications and special provisions, they can be characterized as either being "relative" or "absolute" or a combination of both. These can be defined even further by dividing the set limits into specific time periods during the day, such as daytime, evening, and nighttime. Experience has shown that the "absolute" criteria combined with the "relative" criteria levels appears to be more realistic and tends to be self-adjusting to varying conditions, particularly when defined for the various periods of the day. An example of one such set of construction noise criteria is shown in Table 7.2.

Table 7.2 Example of Absolute and Relative Construction Noise Criteria Limits.

Lot-Line Construction Noise Criteria Limits A-weighted in dB, RMS slow
Noise Receptor Locations and Land-Uses Daytime (7 AM - 6 PM) Evening (6 PM - 10 PM) Nighttime (10 PM - 7 AM)
L10 Lmax L10 Lmax L10 Lmax
Noise-Sensitive Locations: (Residences, Institutions, Hotels, etc.) 75 or Baseline + 5 (whichever is louder) 85 90 (impact) Baseline + 5 85 Baseline + 5 > (if Baseline <70) >Baseline + 3 (if Baseline 70) 80
Commercial Areas: (Businesses, Offices, Stores, etc.) 80 or Baseline + 5 None None None None None
Industrial Areas: (Factories, Plants, etc.) 85 or Baseline + 5 None None None None None

Notes: L10 noise compliance readings are averaged over 20 minute intervals. Lmax noise compliance readings can occur instantaneously. Baseline noise conditions must be measured and established prior to construction work, commencing in accordance with the noise specification, which requires baseline noise readings over three 24-hour periods at each receptor lot-line location.

Source: Adapted from Central Artery/Tunnel Noise Specification and Table 2 in Appendix A.

As shown in Table 7.2, the noise specification's lot-line criterion is primarily a relative criterion in which construction noise levels, in general, can not exceed baseline (preconstruction) L10 noise levels by more than 5 dB at identified noise sensitive receptor locations. Lmax noise limits also apply at the lot lines and are intended to address loud impact-type noise events. In the above criteria, the following three types of receptor land uses have been suggested:

The lot-line criteria limits are more stringent for residential receptors than for commercial or industrial receptors in lieu of the more sensitive nature of residential land uses. In addition, there are different criteria limits depending on various times of day, with the most restrictive noise limits applied to the more sensitive nighttime period.

As shown in Table 7.3, contract specifications can also contain an absolute noise criterion which can be applied to generic classes of heavy equipment to limit their noise emissions. Equipment-specific A-weighted Lmax noise limits, in dBA, evaluated at a reference distance of 50 feet, are defined in the noise specification. Thus, contract specifications could contain two types of noise criteria limits (relative lot-line limits and absolute equipment emissions limits), defining compliance requirements for the contractor. Consequently, if measured or anticipated construction noise levels exceed the allowable noise criteria limits, noise mitigation measures may be warranted during similar work activities.

Table 7.3 Example of Possible Construction Equipment Noise Emission Criteria Limits.

Equipment Description Lmax Noise Limit at 50 ft,
dB, slow
Equipment Description Lmax Noise Limit at 50 ft, dB, slow
All other equipment > 5 HP 85 Gradall 85
Auger Drill Rig 85 Grader 85
Backhoe 80 Horizontal Boring Hydraulic Jack 80
Bar Bender 80 Hydra Break Ram 90
Blasting 94 Impact Pile Driver (diesel or drop) 95
Boring Jack Power Unit 80 Insitu Soil Sampling Rig 84
Chain Saw 85 Jackhammer 85
Clam Shovel 93 Mounted Impact Hammer (hoe ram) 90
Compactor (ground) 80 Paver 85
Compressor (air) 80 Pickup Truck 55
Concrete Batch Plant 83 Pneumatic Tools 85
Concrete Mixer Truck 85 Pumps 77
Concrete Pump 82 Rock Drill 85
Concrete Saw 90 Scraper 85
Crane (mobile or stationary) 85 Slurry Plant 78
Dozer 85 Slurry Trenching Machine 82
Dump Truck 84 Soil Mix Drill Rig 80
Excavator 85 Tractor 84
Flat Bed Truck 84 Vacuum Street Sweeper 80
Front End Loader 80 Vibratory Concrete Mixer 80
Generator (25 KVA or less) 70 Vibratory Pile Driver 95
Generator (more than 25 KVA) 82 Welder 73

Source: Adapted from Central Artery/Tunnel Noise Specification

7.3.2 Time Periods and Duration

Time constraints and use of equipment regulations can be effective in reducing the impacts caused during sensitive time periods. In addition, operating noisy equipment only when necessary and switching off such equipment when not in use can minimize noise impacts.

A crane is placing a span of bridge onto two abutments on a nighttime bridge project.

Figure 7.10 Nighttime bridge construction (Photo #661)

A nighttime demolition of an existing concrete bridge span has a loader, bulldozer, and several water sprayers to minimize dust.

Figure 7.11 Nighttime demolition operation (Photo #1049)

7.3.3 Specified Equipment

Another effective noise mitigation technique involves use of the quietest practical type of equipment. To avoid confusion and misinterpretations, such types should be specified in the contract specifications and special provisions.

7.3.4 Noise Related Incentives/Disincentives

Another technique worthy of consideration involves the inclusion of incentives and/or disincentives in the contract specifications to encourage contractors to participate in the mitigation program and to make the contractors more accountable for impacts.

7.3.5 Training Programs for Contractors

It may be appropriate to require contractors to participate in training programs related to project-specific noise requirements, specifications, and/or equipment operations. Such training may be provided by agency or project management personnel, outside consultants, and/or equipment manufacturers or suppliers. For example, project personnel (or consultants assigned to the project) may train the contractor in the measurement of construction-related noise levels that may be required to meet the contract specifications.

The contractor may also receive onsite training related to noise-specific issues and noise-critical areas and sites adjacent to the project. Equipment manufacturers and/or suppliers may be available to provide training to the contractor on the proper use of the noise abatement features of specific pieces of construction equipment. Any training requirements that are envisioned to be required would typically be described or referenced within the contract's specifications and special provisions.

Page Top | < Previous | Contents | Next >


FHWA Home | HEP Home | Feedback
FHWA