|
The purpose of this guidance is to provide a common understanding among the US Department of
Transportation (USDOT), State Transportation Departments and local transit operators, and Federal
resource agencies regarding options for using Federal transportation funding under Title 23 to fund Federal
resource agency coordination for Federal-aid transportation projects. It was developed cooperatively by the
Federal Highway Administration, Federal Transit Administration, Environmental Protection Agency, Fish and
Wildlife Service, Army Corps of Engineers, and the Advisory Council on Historic Preservation, to provide
USDOT, Federal resource agencies, State DOT’s, and local transit authorities with the tools needed to
develop mutually beneficial agreements to meet the environmental streamlining goals of TEA-21.
The environmental provisions of the Transportation Equity Act for the 21st Century (TEA-21), reflect Congress’
concern about delays, unnecessary duplication of effort, and added costs often associated with the current
process for reviewing and approving transportation projects. The objective of Section 1309 of TEA-21,
Environmental Streamlining, is to focus efforts on better and earlier coordination among Federal, state, and
local agencies. In implementing Section 1309, the emphasis of environmental streamlining should be to:
As a result of TEA-21, Federal transportation funding has increased by 40% without a corresponding increase in Federal resource agency staff. This substantial increase in projects highlights the need for measures to improve the way project development and environmental review processes are executed. The expectation of more intensive involvement by Federal resource agencies risks burdening their already-strained budgets and personnel resources, and could result in costly delays in complying with Federal environmental statues and executive orders. The DOT has been asking Federal resource agencies for more involvement in spite of these limitations. For streamlining to be effective, resource agencies will need additional funds and continuing involvement. The additional funds under TEA-21 will supplement, not replace, existing federal budgets for work on transportation projects.
Federal resource agencies’ efforts to improve streamlining have been underway for some time. The FHWA,
EPA, FWS, ACOE, and NOAA developed the guidance Applying the Section 404 Permit Process to Federal-
Aid Highway Projects (the "Red Book") in1988 to identify methods to improve coordination
before and during the processing of Section 404 permits. It emphasized increased effort in scoping, training,
public involvement, and other programmatic and project-specific approaches, and provided the basis for
numerous interagency agreements for streamlining environmental processes. In a 1994 report prepared on
the integrated NEPA/ 404 process, the Government Accounting Office (GAO) acknowledged that the length of
time needed to complete the NEPA and 404 permitting process was a major impetus, and emphasized that
the objectives of the process were to avoid duplication of effort and late-process revisiting of issues.
Although the report focused on the time and cost savings that could be realized through the an integrated
process, it identified that "resource constraints could limit success of the integrated process", and
pointed out that the integrated processes require agencies to spend more resources than under traditional
processes. The GAO Report also recommended that time cost and delay be tracked to establish a baseline
of how long a "typical" project would take to go through the process. The projects conducted
using additional resource agency staff under these agreements could provide useful information as part of
an effort to demonstrate time and cost savings of the streamlined environmental process.
In 1997, the FHWA Office of Program Quality Coordination prepared the report Interagency Coordination
with Federal Agencies during the FHWA Project Planning and NEPA Processes. The report focused on
FHWA’s role as the lead Federal agency, and identified activities that have been most effective in
overcoming obstacles to achieving interagency coordination, obtaining the involvement and commitment
from other Federal agencies, and providing leadership in project decisionmaking. Emphasis was placed on
facilitating scoping, resolving conflict, and assuring quality project decisions.
We expect that funding additional Federal resource agency staff can result in a joint benefit that earlier efforts
such as the Red Book and Interagency Coordination report have identified, but whose benefits were unale to
be fully achieved. Additional Federal resource agency staff will be better able to assist the State DOT’s and
applicants efficiently reach better and faster transportation solutions earlier and at less cost, as well as
enabling better environmental decisions in the project plans.
A. Transportation Equity Act for the 21st Century (TEA-21)
The Fish and Wildlife Coordination Act authorizes the Secretary of the Interior "to accept donations of land and contributions of funds in furtherance of the purposes of this Act." (Sec. 1) Further, it states:
C. Intergovernmental Personnel Act of 1970 (5 CFR 334)
Assignments may be made up to 2 years (may be extended), and conditions are laid out regarding total length of mobility assignments, continuation of service agreements, certifications, and necessary agreements between the agencies.
Options/ Mechanisms
Examples of the use of the IPA:
TEA-21 section 1309(e) states that federal agency reimbursement money should be available to help meet
review "time limits" if such time limits are less than the "customary time for such review". Cooperative
interagency agreements already in place, such as those for Section 404/ NEPA, serve the environmental
streamlining goals of TEA-21 and should be considered to meet the requirements of section 1309(e).
The DOT Field Offices should encourage and proactively pursue State Transportation Department’s or
transit operators’ use of the funds under this provision. However, the decision to participate remains with the
State DOT’s or transit operators, who are encouraged to take a flexible approach to the concept of funding
Federal resource agency positions.
Concept of Good Investment
As a normal practice, the FHWA encourages appropriate Federal resource agencies to participate in the
project development process, become cooperating agencies, perform routine analyses, conduct studies
(if appropriate), and/or prepare a portion of the environmental documentation. However, Federal resource
agencies cannot substantially increase their involvement in planning, scoping, and alternatives development
without additional resources. This up-front investment , if well-planned and executed in a timely manner, will
result in lower overall project costs and reduced time periods, producing a win-win situation.
State DOT’s, transit operators, and Federal resource agencies should address the question of whether to
fund a whole position vs. funding an existing position’s time to a project (or series of projects). Funding levels
that do not result in increased staffing levels for the Federal resource agencies are generally not going to
achieve the environmental streamlining goal. Funding agreements shall be in compliance with Federal
contracting and finance laws and procedures.
Considerations for Interagency Agreements
The USDOT and the Federal resource agencies urge applicants for Title 23 funding (State DOT’s and transit operators) to actively pursue agreements with them to improve interagency coordination, more effectively address environmental concerns, and reduce costly delays in the environmental review process. In addition to the need for predictable, expedient time frames within which resource agencies conduct their roles in the process, there is also a need for increased, meaningful activity from the Federal resource agencies. The advantage of more intensive Federal resource agency involvement is that agencies’ input is more useful in project decisionmaking the earlier it comes in the process. The timeliness and quality of the projects is improved, and environmental issues can more easily be resolved.
Section 1309(e) of the Act states:
B. The Fish and Wildlife Act of 1956 (16 U.S.C. 742f(a)(4)), and the Fish and Wildlife Coordination Act (16 U.S.C. 661 et. seq.)
(e) Assistance to Affected Federal Agencies --
(1) The Secretary may approve a request by a State or recipient to provide funds for a highway . . .
or for a mass transit project made available . . .to the State for the project . . . to affected Federal agencies to
provide the resources necessary to meet any time limits established under this section.
(2) Such requests . . . shall be approved only for the additional amounts . . . necessary to meet the time limits
for environmental review; and if such time limits are less than the customary time necessary for such review.
The Fish and Wildlife Act of 1956 authorizes FWS to use another agency’s funds to assist its efforts for the
". . . development, advancement, conservation and protection of the fisheries resources [and] of wildlife
resources through research, acquisition of refuge lands, development of existing facilities, and other means.
" (Sec. 7(a)(4) and (5)). The law suggests that the "Secretary [of the Interior] may request and
secure the advice or assistance of any department or agency of the Government in carrying out the
provisions of this Act, and any such department or agency which furnishes advice or assistance to the
Secretary may expend its own funds for such purposes, with or without reimbursement from the Secretary as
may be agreed upon between the Secretary and the department or agency." (Sec. 6(c))
"In the case of construction by a Federal agency, that agency is authorized to transfer to the USFWS, out of appropriations or other funds made available for investigations, engineering, or construction, such funds as may be necessary to conduct all or part of the investigations required to carry out the purposes of this section."
The Intergovernmental Personnel Act of 1970 authorized the temporary assignment of employees between Federal agencies and State, local, and Indian tribal governments, institutions of higher learning and other eligible organizations. It provides for additional flexibility for augmenting the staffing available to Federal resource agencies to carry out their missions.
Examples of the use of the Fish and Wildlife Act of 1956/ Fish & Wildlife Coordination Act:
An agreement between the State and a Federal agency should:
In addition to the funding efforts described in this guidance, FHWA Division Offices should continue to work with SHA’s and Federal resource agencies to explore ways to collectively “work smarter” through informal cooperative and programmatic approaches. Also, the use of other media techniques (e.g., videoconferencing) can improve the efficiency, effectiveness, and economy of interagency coordination and is encouraged.
Attachment 1: Federal Aid Financing for Highways and Transit
Attachment 2: Sample Agreements
Attachment 3: FHWA and FTA Field Environmental Contacts
Attachment 4: EPA, FWS, [others] Field Contacts