|
Printable version (.pdf, 23 kb)
FHWA FOS PS&E Checklist
updated 8/3/06
Area Engineer
_____________________________signature |
Team Leader (last)
_______ initial |
Technical Programs: Primary responsibility for structure and hydraulics review
_______ initial if
assistance provided |
Safety and Traffic Ops :
Assist AE in reviewing signing/staging plans for compliance with MUTCD
_______ initial if assistance provided |
Planning: Assist AE in filling out the planning section
_______ initial if
assistance provided |
ADA/DA (conditional authorizations or major projects
only) |
Project Information
Federal Aid Project Number: |
County |
Region |
Project Description: |
Funding:
| |
Yes |
No |
NA |
Does project description
agree with authorization request? |
|
|
|
What is the funding
code(s)? ________________________________________
Is funding compatible to
regulations & Federal Aid ratio correct? |
|
|
|
Is the cost estimate
acceptable? |
|
|
|
Is this project valued at
more than $ 100M as defined in the environmental document? If so, the ADA/DA
must be advised prior to authorization. |
|
|
|
If answer to question above
is "Yes", has a financial plan been submitted and has it been
determined to be adequate by HFO, HPP and HFA Team Leaders? |
|
|
|
Is the project is an
advanced construction project? If so, notify HFO and HPP team leaders. |
|
|
|
Planning:
If the Area Engineer needs assistance in completing this
section, he/she should consult with the appropriate Planner
|
Yes |
No |
NA |
Is project and construction
phase of work in the existing STIP for current FY? |
|
|
|
Is the project scope
consistent with the S/TIP project scope/description? |
|
|
|
Rural STIP No.________
OR TIP Area ___________ TIP No. _______
Programmed S/TIP Amount for
Phase: _____________________
Amount of funds requested:
_______________________
Is the authorization amount
above the programmed STIP amount? If yes, the HPP and HFO TL must be
notified. |
|
|
|
If the project includes
changes to Interstate Access, are these changes consistent with the IJS/IMS?
Are all crossroad improvements let simultaneously or prior to the Interchange
project so that we avoid new interchanges to nowhere. |
|
|
|
Once project is authorized,
did you update the STIP Tracking sheet at G:\USERS\SHARED FILES\TN Key
Business Process STIP 06-08 tracking.xls? |
|
|
|
Structures
| |
Yes |
No |
NA |
Has coordination with FEMA
been accomplished? |
|
|
|
If the project contains
structures, has the Division Office Structural Engineer reviewed the plans
and have their concerns been addressed? |
|
|
|
Right of Way (ROW) and Utilities
| |
Yes |
No |
NA |
Has all of the ROW been
obtained and cleared? ____If No, consult with ROW Specialist and HFO Team
leader.
If yes, Date ROW
Certificate Approved (attach copy)____________ |
|
|
|
If answer to above is
"No," do special provisions contain:
- Restrictions to the contractor?
- An estimate as to when the ROW will be cleared?
Team Leader must be
consulted if ROW is not clear. |
|
|
|
Does the project require use of or adjustment to railroad
facilities?
If yes, is there a signed agreement between the
railroad/SHA, and does the proposal include liability insurance requirements? |
|
|
|
Is the project located within two miles of an airport?
If yes, has FAA/FHWA coordination been completed?
__________ |
|
|
|
Will utilities be affected by this project? If yes, have
all utility agreements been signed and completed? Team Leader must be
consulted if utilities are not clear. |
|
|
|
| |
|
|
|
|
Environment
| |
Yes |
No |
NA |
Is the project in a
Non-attainment Area?
If yes, is a hot spot
analysis needed? Is analysis included (in environmental document or with
PS&E package) if needed? |
|
|
|
Is an approved environmental document or clearance on file?
What type? ______________
Date of approval: ___________ |
|
|
|
Has an environmental
re-evaluation been approved within a reasonable timeframe (about six months)? |
|
|
|
Have measures been included
in PS&E to ensure that environmental conditions and commitments are
satisfied? |
|
|
|
Is a 404 permit required?
If yes,
- Are mitigation or enhancement requirements
of permit incorporated into the PS&E? _______________
- Is the permit date valid?
________________
|
|
|
|
Is a US Coast Guard permit required? If so, is it
valid? |
|
|
|
Plans
| |
Yes |
No |
NA |
Have comments on
Construction Field Review been adequately resolved? If the CFR was not
attended by FHWA as per requirements of other office procedures, a full
review of geometric design and operations is required, see Team Leader. |
|
|
|
If necessary, has
justification for Additional Access (Interstate) been approved by the HFO
Team Leader? |
|
|
|
Are there any Design
Exceptions for the 13 controlling criteria? If so, have they been approved by
HFO Team Leader? |
|
|
|
If over $ 25 M, has a Value
Engineering Study been performed?
If not, see HFO Team Leader. |
|
|
|
Is the Pavement Design
appropriate, i.e. is pavement type (HMA versus PCC) appropriate and does
pavement design meet AASHTO criteria)? |
|
|
|
Are the staging and traffic
control plans workable and consistent with the MUTCD? (get assistance from
HSO section) |
|
|
|
Are signing and pavement
markings consistent with MUTCD?
(get assistance from HSO
section) |
|
|
|
For split funds projects,
are funding limits shown on plans? |
|
|
|
Have major pay items been
checked against construction plans to identify questionable items? |
|
|
|
Have major pay items been
crosschecked against summary of quantities, and engineer's estimate? |
|
|
|
Do all safety appurtenances
meet NCHRP 350 criteria and are they placed in accordance with the current
"Roadside Design Guide"? (get assistance from HSO section) |
|
|
|
Are ADA requirements met? In particular, check standards
and plans for curb ramps, see AE responsible for ADA if you have questions. |
|
|
|
Are there any unresolved items/issues? Explain. |
|
|
|
Engineer's Estimate
| |
Yes |
No |
NA |
Does the estimate include a
pay item for all work included in the plans? |
|
|
|
Does the estimate
appropriately represent the scope and requirements of the PS&E? |
|
|
|
What is the estimate for
CEI? _________% of construction cost
Is this reasonable
(typically about 10 %) |
|
|
|
Specifications
| |
Yes |
No |
NA |
Does the proposal include
Form FHWA-1273 Required contract provisions? (23 CFR 633) |
|
|
|
Does the proposal include any Proprietary items? Check
specially for:
Traffic Striping and Sign Sheeting
and any other potential items |
|
|
|
Does the proposal include an incentive/disincentive
clause?
Has the incentive/disincentive been specifically
calculated for this project? _________________________________
1. Have the calculations been
previously submitted for our review and approval?
_____________________________ |
|
|
|
Are there training requirements? If yes,
1. Are training special provisions
included? |
|
|
|
Are DBE special provisions
included, including non-discrimination clause and EEO checksheet? |
|
|
|
Does the proposal include all of the latest applicable
standard special provisions that would apply? |
|
|
|
Have you reviewed the determination of contract time, and
is it satisfactory? (TDOT has agreed to involve FHWA on SP 108 B)
Contract time: _________________________
Completion Date: _______________________ |
|
|
|
What is # calendar days divided by cost of contract in
millions? ____ Is this number less than 40? (if not, see HFO Team Leader) |
|
|
|
What are the allowable working hours/hours for lane
closures? ________________________
_________________________Are these acceptable and have
adequate measures been taken to analyze delays? |
|
|
|
Upon review of this
PS&E,
I recommend authorizing
the project: |
_______________________________ |
| |
Signature |
| |
|
Upon review of this
PS&E,
I do not recommend
authorizing the project: |
_______________________________ |
| |
Signature |
|