Arrow Maine Demonstration Project: Reconstruction of Lamson and Boom Birch Bridges

<<Previous Contents  

Maine Demonstration Project: Reconstruction of Lamson and Boom Birch Bridges

APPENDIX C - SHOWCASE AGENDA

August 13, 2007

8:00 a.m.

  • Call to Order, Introductions Devin Anderson, Maine DOT (10 min.)
  • Welcome David Cole, Commissioner, Maine DOT (10 min.)
  • Maine's Bridges for Tomorrow Jonathan McDade, Federal Highway Administration, Maine Division Administrator (10 min.) Description of Projects: A discussion of issues in the areas of environment, geotechnical, emergency responders, and corrosion protection (60 min.)
    • Boom Birch Bridge, Old Town, Maine Robert Bulger, Maine DOT
    • Lamson Bridge, Addison, Maine Robert Ellena, Maine DOT
    • Geotechnical Considerations Laura Krusinski, Maine DOT
  • Highways for LIFE Program Overview Gary Hoffman, Applied Research Assoc. (15 min.)

Break (15 min.)

10:00 a.m.

  • Prefabricated Bridges – National Perspective Mary Lou Ralls (30 min.)
  • Decision on Full-Road Closure Catherine Small, Maine DOT (20 min.)
  • Contractor Perspective on Contract Requirements Wyman & Simpson (20 min.)
  • Open Q & A (Devin Anderson – Moderator) (20 min.)

Lunch (11:30 – 12:30)

12:30 p.m.

Travel to Boom Birch Site

  • Observe erection of prefabricated elements (30 minutes)
  • Q & A of Field Staff

1:00 p.m.

Return to Conference Center

  • Review of Things Learned and Wrap Up Devin Anderson – Moderator (20 min)
<<Previous Contents  

More Information

Events

Contact

Mary Huie
Highways for LIFE
202-366-3039
mary.huie@dot.gov

This page last modified on 04/04/11
 

FHWA
United States Department of Transportation - Federal Highway Administration