|
|
| FHWA > HfL > Projects > Maryland Demonstration Project > Economic Analysis |
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
As-built |
Baseline | ||
|---|---|---|---|
| Prestressed Slab Bridge | Costs | Steel Beam Bridge | Costs |
| Prestressed slabs | 264,000 | Structural steel | 220,000 |
| Superstructure concrete | 84,000 | Superstructure concrete (8" desk) | 115,000 |
| Metal railing | 32,000 | Superstructure reinforcing steel | 24,000 |
| Shear studs | 5,000 | ||
| Metal railing | 32,000 | ||
| Total Superstructure Costs | 380,000 | 396,000 | |
Notes:
|
|||
The MDSHA Office of Bridge Design provided comparative estimated construction costs for various construction alternatives considered in the MD 28 MOT Alternatives Analysis study. These numbers were used to capture the expected difference in total roadway and structural construction costs based on the number of phases of construction dictated by MOT alternative. Table 5 summarizes these comparative costs between the as-built and baseline MOT alternatives, with the as-built scenario providing an expected cost savings of $310,000 over the baseline scenario.
| MOT Alternative | Total Structural & Roadway Cost |
|---|---|
| Full closure with detour | 1,240,000 |
| One lane, two-way traffic (temporary signal) | 1,550,000 |
| Notes: Information in this table is referenced directly from "MD 28 over Washington Run: Maintenance of Traffic Alternative Analysis", Sabra, Wang & Associates, Inc., dated April 2007. | |
It is assumed that the combined effect of cost savings for both utilizing prefabricated bridge elements and constructing the bridge within a full roadway closure will result in a total cost savings of roadway and bridge construction of approximately $326,000.
The MD 28 MOT Alternatives Analysis study included a detailed economic analysis section, with calculations and comparative analysis performed to quantify delay, fuel consumption, and safety costs as user costs. This analysis was conducted on behalf of MDSHA and submitted for consideration, based upon valid assumptions and analysis inputs (i.e. accident rates, unit costs) deemed appropriate for the State of Maryland. Therefore, the user costs determined by Sabra, Wang & Associates have been reviewed, summarized, and included in our analysis as follows.
Delay and Fuel Costs
Total delay and fuel costs for the traveling public were determined for the MD 28 project based on the following assumptions:
Table 6 summarizes the delay and fuel cost calculations between the as-built and baseline scenarios. As is expected in the case of a full detour, the as-built scenario more than doubles the delay and user costs of the baseline scenario, increasing user costs by $475,650.
| Item | As-built | Baseline |
|---|---|---|
| Individual Delay (hours per vehicle) | 0.167 | 0.0167 |
| Individual Delay Cost ($12.10 x individual delay) | 2.02 | 0.20 |
| Peak Hour Delay Cost (500 veh. x ind. delay cost) | 1,010 | 100 |
| Fuel Consumption (7.5 miles / 20 miles per gallon) | 0.375 | 0 |
| Individual Fuel Cost ($2.75 x fuel consumption) | 1.03 | 0.00 |
| Peak Hour Fuel Cost (500 veh. x ind. fuel cost) | 515 | 0 |
| Peak Hour Delay & Fuel Cost | 1,525 | 100 |
| Daily Delay & Fuel Cost (peak hour delay & fuel cost / 8%) | 19,063 | 1,250 |
| Total Days (Project Duration x [5 workdays / 7 days]) | 46 | 321 |
| Total Delay & Fuel Cost (daily delay & fuel cost x total days) | 876,900 | 401,250 |
Notes: |
||
Safety Costs
In their study, Sabra, Wang & Associates performed a comparative safety analysis between methods, based on a one-mile project length on and adjacent to the MD 28 bridge, considering the various MOT methods and the following analysis inputs based on MDSHA accident data available for a two-lane, two-way, rural non-divided highway:
The standard rate of accidents for a typical section of highway with no construction work is calculated as:
Rate = (7.42 x 6,000 veh/day x 1 mile x 30 days/month) / 1,000,000 = 1.33 per month.
It was presumed that the presence of a maintained work zone throughout the project site will nearly double the incident rate, resulting in an expected additional one accident per month at a minimum. Therefore, the determined safety cost for the baseline scenario is calculated as:
Baseline cost = (1 accident per month x $150,000 x 15 months) = $2,250,000
In the as-built scenario with a full roadway closure, there will be no accidents within the project limits; however, the increase of detour traffic throughout the immediate area will have an effective increase on accidents, particularly at intersections in the immediate area. Sabra, Wang & Associates reported an expected increase in accident rates, based on MDSHA crash data, of 3 accidents per month for the detour route. Therefore, the determined safety cost for the as-built scenario is calculated as:
As-built cost = (3 accidents per month x $150,000 x 2 months) = $900,000
The expected cost savings in safety user costs from employing the full roadway closure and constructing the bridge utilizing PBES construction methodologies is the cost differential between the baseline and as-built costs calculated above, or $1,350,000.
Construction costs for the MD 28 project would have likely placed traditional delivery and construction methods (baseline) at $326,000 more than the as-built case. Moreover, utilizing a full roadway closure increase delay and fuel costs by $475,650, but realized in additional cost savings of $1,350,000 in safety user costs. Sabra, Wang & Associates also reported a difference in estimated work zone cost of $426,500 for the baseline scenario and $137,000 for the as-built scenario, resulting in an additional planned cost savings of $289,500.
Therefore, the estimated total savings from using the innovative HfL project delivery approach are approximately $1.49 million for the MD 28 project alone, with a baseline total cost of $4.63 million. It is expected that a detailed analysis with as-built data for the MD 450 project would yield similar results. In other words, the innovative approach to these projects had an approximate 32 percent cost benefit over traditional methods.
Mary Huie
Highways for LIFE
202-366-3039
mary.huie@dot.gov