Skip to ContentsU.S. Department of Transportation, Federal Highway Administration FHWA Home Feedback
NHI Logo

Transportation Curriculum Coordination Council

  
 
FHWA > NHI > TCCC > Tutorials > Driven Piles

Begin Pile Driving

The same graphic of The Phases of the project as presented in section 5 (1. Know the Project Plans  2.  Assemble your 'tool box'  3. Contractor arrives on site  4. Equipment set-up 5. Piles arrive on site 6. Begin pile driving  7. When to stop 8. Pay). Begin pile driving is highlighted

Begin pile driving - tolerances, preformed/predrilled, jetting, pile driving record

You have verified that the Contractor's equipment matches what was submitted and approved in the Pile Installation Plan, that they have complied with Protection of Existing Structures requirements and they are now getting ready to place the first pile in position.

Tolerances

It is important that the pile be located in the proper plan position and be plumb or if battered, at the correct batter. Piles driven at the wrong locations, not plumb or at incorrect batters are a waste of everyone's time. Though not your responsibility you need to verify that tolerances are adhered to. Let's review tolerances.

It is imperative that the pile be located where it is supposed to be. If not, the remainder of the structure may not match up and that's not good. The plans provide the pile locations and the specifications provide the degree of accuracy the Contractor must meet.

How close is the pile to the planned location? The center of the pile is to be within three inches of the planned position.

Position

Schematic showing position tolerance

Ensure that the final position of the pile head at cut-off elevation is no more than 3 inches [75 mm] from the plan position indicated in the plans.If the pile is to be plumb or battered it is important that it be within a certain axial alignment as specified in.


Schematic showing axial alignment tolerances

Axial Alignment

Ensure that the axial alignment of the driven piles does not deviate by more than ¼ in/ft [20 mm/m] from the vertical or batter line indicated in the plans.

The pile cut-off elevation is specified in the plans. This is the elevation at which the designers want the top of the pile to be. In some cases, the Contractor may need to build-up the pile or cut it off to achieve the elevation. Regardless of how the pile top gets to the planned elevation, it must be within the tolerances specified in.


Schematic showing elevation tolerances

Elevation

Ensure that the final elevation of the pile head is no more than 1½ inches [38 mm] above, or more than 4 inches [100 mm] below, the elevation shown in the plans. Do not embed the pile less than 6 inches [150 mm] below the elevation shown in the plans unless a minimum penetration requirement is shown.


Predrilled and Preformed Holes

Perhaps this pile is to be driven through an embankment and predrilled holes are required or the plans call for preformed holes due to below grade conditions. One is a pay item; one isn't, so let's review Predrilled and Preformed Holes.

There are situations presented by geologic conditions or other conditions requiring the use of a predrilled hole or a preformed hole.

Notice that these terms are not interchangeable. They are totally separate and distinct terms, with a significant difference.

Predrilled holes are not paid for. Preformed holes are paid for.

Therefore, it is important that you know the difference in these two types of holes.

Predrilled Holes

Predrilled holes are either "starter holes", holes that have a maximum depth of 4 feet, or holes drilled through an embankment or compacted fill. They are also used for getting through rock material that may damage the pile during driving.

It is important to note that displacement piles, for example square concrete prestressed piles, are not to be driven through an embankment. When predrilling through an embankment, the hole is to be drilled to "natural ground" surface. This is the elevation of the existing grade prior to placement of the embankment fill. Often times this is estimated, if not specifically identified in the plans. The Contractor's estimate and the Inspector's estimate of "natural ground" should be fairly close.

Preformed Holes

These are holes determined to be necessary by the designer or engineer to penetrate a strata that would prevent the driving or jetting of the piles to the desired penetration. They serve as a penetration aid when the piles cannot be advanced with driving, jetting or a combination of these. Generally, preformed holes are identified in the project plans.

It is important to note that the Contractor cannot just preform a hole to the pile tip elevation required and stick in the pile. They must drive the pile to determine that the driving criteria has been met.

Jetting

Does the Contractor plan on jetting? Is he going to use external jets or center hole jets? There are times when jetting isn't permitted. Let's review jetting.

Jetting is simply the process of using water under pressure to erode the soil, thereby allowing for the advancement of the pile. The Engineer must approve all jetting.

Jetting is typically performed with either a center-hole jet, where a jet is inserted into a hole down the center of the pile or performed by external water jets attached outside the pile.

Note- Jetting through an embankment is not permitted.

Schematic Showing Center Hole Jet and External Jets

Pile Driving Record

The Inspector needs to set-up the Pile Driving Record Book and some information can be entered prior to driving, so let's prepare the Pile Driving Record.

Prior to the Contractor commencing pile driving, the Inspector can fill in a vast majority of the Pile Driving Record book for that pile and should make it a habit to do this before driving begins on any pile.

As covered earlier, much of the requested information is already known, either from the plans, the Pile Installation Plan, the Driving Criteria Letter or the Authorized Lengths Letter. However, following are two extremely helpful items that can be entered prior to driving commencing and will make your job so much easier.

Minimum Tip Target (MT) - MT, This is the specified Minimum Tip Elevation Target. If a Minimum Tip is specified, this is the elevation the tip of the pile must achieve before driving can be stopped, unless approved by the Engineer. This is an elevation that you can mark ahead of time. To have to constantly be calculating where the pile tip is in relation to Minimum Tip Elevation can be a hassle. By making a mark ahead, the Inspector has one less thing to worry about. So, what is it and how does the Inspector calculate it?

Stop for Set-Check (CO) - CO, The "Stop for Set-Check" mark is also a mark the Inspector can make ahead of time. During the heat of battle, to have to constantly be calculating where Cutoff is in relation to the amount of pile remaining can just be another thing to worry about. Remember, the specification states we should stop driving, if the pile is within 12" of the Cutoff elevation and the required resistance has not been achieved, for a 15 minute Set-Check. This interruption in driving will allow us to perform a set-check to see if the pile gains capacity. By making a mark ahead, the Inspector eliminates one more thing to worry about. So, what is it and how does the Inspector calculate it?

Minimum Tip Target is a mark in the Pile Log Book, prior to driving, that assists the Inspector in easily identifying when the pile tip has reached "Minimum Tip".

Illustration of vertical pile.  Shows pile, template, and reference point against a scale with known reference point elevation and minimum tip elevation

Calculation


For Vertical Pile

MT = Reference Elev. - Min. Tip Elev.

EXAMPLE 1:

Assume Reference Elevation = +10.00 ft.
Assume Specified Min. Tip Elev. = -53.00 ft.

Therefore; +10.00 - (-53.00) (Remember- A plus minus a minus equals a plus
+10.00 + 53.00 (So our equation looks like this now)
= 63.00 feet

Therefore at the 63-foot mark in the logbook you would make your MT mark and when the 63 foot mark on the pile reaches the reference point you have reached Minimum Tip.


Illustration of battered pile.  Shows pile, template, and reference point against a scale with known reference point elevation and a specified pile cutoff elevation
For Battered Pile

MT = (Ref. Elev. - Min. Tip Elev.)/Correction Factor

Assume Reference Elevation = +80.00 ft.
Assume Specified Min. Tip Elev. = +20.00 ft.
Assume batter is 10:3

Therefore;

(+80.00 - +20.00)/.958
60/.958
= 62.63 feet

Therefore at the 62-foot mark in the logbook you would make your MT mark.

  Batter Ratio (V:H)     Correction Factor (R)  
12:1 0.997
10:1 0.995
12:2 (6:1) 0.986
10:2 (5:1) 0.981
12:3 (4:1) 0.971
10:3 0.958
12:4 (3:1) 0.949
10:4 (5:2) 0.928
12:5 0.923


"Stop for Set-Check Target" is a mark in the Pile Log Book, prior to driving, that assists the Inspector in easily identifying when the specified pile "Cutoff Elevation" is within 2 feet of the elevation. We suggest 2 feet prior to cutoff for this mark, even though the specification states 12". A little extra time is the Inspector's friend.

Calculation


For Vertical Pile
Illustration of vertical pile.  Shows pile, template, and reference point against a scale with known reference point elevation and a specified pile cutoff elevation

CO = Pile Length - 2' - (Cut-off Elev. - Ref. Elev.)

EXAMPLE 1:
Assume pile length (L) is 90 ft.
Assume Cut-off Elev. = + 12.00 ft.
Assume Reference Elevation = +10.00 ft.

Therefore;
90'- 2' - (+12.00 - +10.00)- Remember, always do the function in brackets first
90'- 2' - (2)88' - 2' = 86'
= 86.00 feet

Therefore at the 86 foot mark in the logbook you would make your CO mark and as the 86 foot mark on the pile reaches the reference point, you will know you are at that critical Set-Check decision making point.


Illustration of battered pile.  Shows pile, template, and reference point against a scale with known reference point elevation and a specified pile cutoff elevation

Calculation


For Battered Pile

CO = Pile Length - 2' - [(Cut-off Elev. - Ref. Elev.)/Corr. Factor]

(See correction factors in above table)

EXAMPLE 1:
Assume pile length (L) is 90 ft.
Assume Cut-off Elev. = + 12.00 ft.
Assume Reference Elevation = +10.00 ft.
Assume batter is 10:3

Therefore;
90'- 2' - [(+12.00 - +10.00)/.958] t
90'- 2' - [2/.958]
90'-2'- 2.08
88-2.08 = 85.9'
= 85.92 feet

Therefore at the 85.9 foot mark in the logbook you would make your CO mark and watch for the 85.9 pile mark passing reference point.

Splicing of Piles

In some instances, the authorized pile length may not be long enough. In those instances, the Contractor needs to splice on additional length, so let's review Splicing of Piles.

There are several situations which would necessitate the splicing of piles to achieve additional length, such as:

In the event splicing is needed, ask yourself these questions:

Concrete Splices

Once the type of splice is determined, the following items should be checked to ensure that the splice is properly performed:

On the Casted Splice Sections
  1. Check to ensure that the splice has the FDOT stamp from the inspector at the casting yard and not damaged during shipment.
  2. Check to ensure that the dowels are the proper length and that the proper number of dowels are present.
  3. Check to ensure the splice is the proper length. A minimum splice length of 10 ft. should be specified in the pile splice from the District Construction Office.
  4. Prior to splicing, ensure that the dowels and concrete are clean and dry. The epoxy will not properly bond if grease or water is present.
On Cut-Off Pile Section Used As Splice (Prestressed Concrete)
  1. Check to ensure that the pile cut-off section has no visible cracks and that the pile head is square and clean.
  2. Check to ensure that the Contractor drills the dowel hole in the proper location, on the correct end, and to the proper depth. Typically, these holes are 2 inches deeper than the dowels.
  3. Check to ensure that the dowels are properly placed and epoxied. Dowels should be clean and dry.
  4. The epoxy in the dowel holes of this section must be set before splicing onto the pile to be spliced.
On The Pile To Be Spliced
  1. Check to ensure that the pile has no visible cracks and that the pile head is square and clean.
  2. Check to ensure that the Contractor drills the dowel hole in the proper location, on the correct end, and to the proper depth. Typically, these holes are 2 inches deeper then the dowels.
  3. A wood form is typically constructed around the pile to hold the epoxy.
  4. Ensure that both the holes and the pile top are cleaned out, free of dust and dry.
Epoxy
  1. Ask the Contractor to provide copies of the epoxy manufacturer's specifications and mixing instructions and ensure they are followed. Pay particular attention to temperature and time restrictions.
  2. Check to ensure that enough epoxy is placed in the holes. Epoxy should overflow the holes to fill the ½ inch gap between pile and splice section after placement.
  3. Check for expiration dates on the epoxy
During Splicing
  1. Once the spliced section is in place, check to ensure the splice section is aligned with the in-place pile section and that it is not moved while the epoxy sets. Set times should be stated in the manufacturer's instructions. Once the set times for the epoxy have been met (check to ensure it is set) the pile may be driven.

Spliced prestressed concrete piles are highly susceptible to damage from high tension stresses due to the lack of prestressing in the splice. The Inspector should pay particular attention to the splicing operation and the driving of the spliced pile. Alignment is probably the major cause of failure of spliced piles. Incorrect use of the epoxy procedure is the second leading cause of splice failure. Also remember that spliced piles cannot withstand the same tension stresses as an unspliced pile. Therefore, driving in high tension needs to be avoided if at all possible. If any cracking appears, the driving operation should be stopped and the Engineer notified.


The Specification uses a variety of terms, interchangeably, to describe these splices- Extension, Build-Up and Splice. These terms are based upon the length of the "splice". To keep this simple, remember:

Build-up- less than 2 feet below cutoff with dowels drilled in place. Concrete and steel are placed as part of the cap.

Splice- less than 21 feet as a nondriven or nondrivable.

Splice- greater than 21 feet must be made as a drivable splice.

Therefore- A Buildup is anything 2 feet or less in length, everything else is a splice.

Steel Splices

Splices are use to bring piles driven below the pile cut-off elevation to the proper elevation. For steel piles, a length of pile is welded on as shown in the plans. This is a relatively simple process. As a pile driving inspector, you are responsible for ensuring the following.

  1. Check to ensure that the piece being used for the splice is of the same grade and size steel as the pile being spliced.
  2. Check to ensure that the splice length is the same as the lengths specified in splice letter provided to the District Construction Engineer. The Contractor can choose to provide a longer splice, however, this is done at no cost to the State. Also, the District Geotechnical Engineer's office must be notified if a longer length is used so that the proper driving criteria can be provided.
  3. The Contractor will place a beveled edge on the ends of the pile which will be spliced together. This is done using a grinder and the inspector should ensure that the ends are smooth and clean so that a proper weld can be place.
  4. Steel plates are then placed on either side of the web for a H-pile or sleeves for a pipe pile using tack welds. These are used to hold the piles in place during welding and provides a backing plate to weld against. The Inspector should check that these are placed as detailed in the plans.
  5. The two sections are then fully butt-welded together. The Inspector should ensure that the two pieces are plumb and the weld is properly placed.
  6. Is splice done as shown on plans?
  7. Is the welder qualified for this type of welding procedure?


<< Previous Table of Contents Next >>


FHWA