Skip to ContentsU.S. Department of Transportation, Federal Highway Administration FHWA Home Feedback
NHI Logo

Transportation Curriculum Coordination Council

  
 
 
FHWA > NHI > TCCC > Tutorials > Drilled Shafts

Chapter 3


Drilled Shaft Construction Methods


Contents

This Chapter contains information on the three methods of drilled shaft construction.

  • Dry Shaft
  • Wet Shaft Construction
  • Cased Shaft Construction
  • A short quiz is provided at the end of the Chapter.

Each of these methods is different and has their own potential problem areas and applicability. It is important for the Inspector to have an understanding of each of these processes to facilitate inspection of the shafts during construction.

What is a Dry Shaft

A shaft excavation that can be excavated to its designed depth without the need for slurry or casing.

he dry construction method is used at sites where the ground water level and soil and rock conditions are suitable to permit construction of the shaft in a relatively dry excavation. and where the sides and bottom of the shaft may be visually inspected by the Engineer prior to placing the concrete.  

The dry method is by far the least expensive method for drilled shaft construction. Given the choice of drilling methods, Contractors will try the dry method even in soil or rock of dubious quality.

Dry construction is generally defined by an amount of water accumulation permitted over a specified time period.

Photograph of a dry shaft

Photograph of a dry shaft.

Note that the Inspector can visually inspect the bottom of the shaft.

Dry Shaft Construction Process

The dry method consists of drilling the shaft excavation, removing accumulated water and loose material from the excavation, placing the reinforcement cage, and concreting the shaft in a relatively dry excavation.

Dry shaft construction process.  Four panes showing the shaft being drilled to the designated depth, cleanout, reinforcement cage placement, and concrete pouring

What is a Wet Shaft

Often called the "slurry-method", wet shaft construction is when a slurry or water is used to keep the hole stable for the entire depth of the shaft.

Photograph of an Inspector sounding a wet shaft with a weighted tape.

Photograph of an Inspector sounding a wet shaft with a weighted tape.

Note the slurry in the hole. The Inspector's unable to visually inspect the bottom of the shaft, as with the dry shaft seen earlier


When Used

Wet -vs- Dry

Wet Shaft Construction Process

Unlike the dry construction method, in this situation the water table may be above the shaft tip elevation or the geology consists of unstable or "caving" soils. Think of trying to dig a hole at the beach or lake near the water's edge. The hole stays open until you reach or get just below the water table or waterline. Then what happens? It collapses.

Well the same goes for drilled shafts excavated below the water table or in unstable soils. During the drilling of the hole, a slurry is introduced that "stabilizes" the sides of the hole or casing is installed and prevents the soils from collapsing into the hole.

Upon reaching the designed shaft tip elevation, the hole is cleaned, then the rebar cage placed.

Unlike the dry shaft method, the concrete is being placed "under the water" and therefore a tremie is lowered into the hole and the concrete placed through the tremie, which is carefully removed a little at a time to avoid "breaching" the concrete.

wet shaft construction process showing excavating of the hole, adding slurring, cleaning out the hole, placing the cage, and pouring concrete

Types of Wet Shaft construction

There are two types of "wet" shaft construction:

The Static Process The Circulation Process
  • Drilled down to the piezometric level
  • Slurry introduced
  • Cuttings are lifted from the hole
  • Hole is drilled
  • Slurry level maintained at the ground surface
  • Cuttings and sand, is circulated to the surface, where it is cleaned and reintroduced down the hole.

What is Slurry


What Does the Slurry Do?

Slurry is the fluid introduced into the excavation to assist in maintaining hole stability. Generally, three basic types of "slurries", Mineral, Polymer and Water, are employed in drilled shaft construction.

In some instances, though not recommended, a blended slurry, consisting of mineral and polymer slurries is employed.

What is a Cased Shaft

The casing method is often used either when shown on the plans or at sites when construction methods are inadequate to prevent hole caving or excessive deformation. In this method the casing may be either placed in a predrilled hole or advanced through the ground by twisting, driving or vibration before being cleaned out. Casings and liners play an important role in the construction of drilled shafts, and special attention must be given to their selection and use.

Casings are tubes that are relatively strong, usually made of steel, and joined, if necessary, by welding. Liners, on the other hand, are light in weight and become a permanent part of the foundation. Liners may be made of sheet metal, plastic, or pressed fibers. While their use is much less frequent than that of casings, liners can become important in some situations.

Common situations where casing is used are:

This picture shows temporary casing being inserted in a pre-drilled hole.

This picture shows temporary casing being inserted in a pre-drilled hole.


Types of Casing

Temporary Casing

Temporary casing is used to retain the sides of the borehole only long enough for the fluid concrete to be placed. The temporary casing remains in place until the concrete has been poured to a level sufficient to withstand ground and groundwater pressures. The casing is removed after the concrete is placed. Additional concrete is placed as the casing is being pulled to maintain the pressure balance. Thereafter, the fluid pressure of the concrete is assumed to provide borehole stability.

 

Permanent Casing

The use of permanent casing is implied by its name; the casing remains and becomes a permanent part of the foundation. An example of the use of permanent casing is when a drilled shaft is to be installed through water and the protruding portion of the casing is used as a form. A possible technique that has been used successfully is to set a template for positioning the drilled shaft, to set a permanent casing through the template with its top above the water and with its base set an appropriate distance below the mudline, to make the excavation with the use of drilling slurry, and to place the concrete through a tremie to the top of the casing.



This photograph shows a vibratory hammer being lowered to attached to a piece of casing for installation in the hole.

Note the casing is marked in 5 foot intervals. At the top, 1foot increments are marked to facilitate more accurate measurement as the casing nears the bottom.

This photograph shows a vibratory hammer being lowered to attached to a piece of casing for installation in the hole

Cased Shaft Construction Process

Drill- hole is advanced using slurry through the caving soils

Case- casing is then installed through the caving soils and drilling continues to desired depth

Clean- slurry and cuttings removed from the hole

Position- rebar cage is positioned in the hole

Place- concrete is placed. If temporary casing, casing slowly withdrawn as concrete level in hole rises

Cased shaft construction process

I have completed Chapter 3 and am ready to take the Quiz



<< Previous Table of Contents Next >>


FHWA