Analytical Tools
Webinar - Evaluating P3 Options: An Overview
View as PDF
P3-VALUE Web-based Training Course
May 2, 2013
Today's Presenter
Patrick DeCorla-Souza
P3 Program Manager
Office of Innovative Program Delivery
P3-VALUE Webinars
- P3: Public Private Partnership
- P3-VALUE: Set of four integrated analytical
tools to help practitioners understand processes used to
quantitatively evaluate P3 options
- This is the first of four webinars on P3-VALUE
- P3 Evaluation Overview (today)
- Risk Assessment 201 (June 13)
- Value for Money Analysis (July 11)
- Financial Structuring and Assessment (August 7)
Course Outline
Lesson 1 - Introduction to P3 Evaluation
Lesson 2 - P3 Financial Evaluation
Lesson 3 - Value for Money Analysis
Lesson 4 - FHWA's P3 Toolkit and P3-VALUE
Summary
Course Objectives
After taking this course you should be able to:
- Identify the purpose of P3 evaluation
- Describe the P3 evaluation process
- Identify the limitations of P3 evaluation
- Understand the role of the P3-VALUE suite of tools
- Access the tools and supporting information
Lesson 1 - Introduction to P3 Evaluation
Project vs. Procurement Evaluation
- Project Evaluation:
- Is the project worthwhile?
- For society
- For the public sponsor
- Procurement Evaluation:
- Would P3 procurement add value relative to conventional
procurement?
- Which of several P3 options would add most value?
- Would a particular procurement option (conventional
or P3) have an impact on whether the project is worthwhile?
Procurement Evaluation at Every Step
Planning & Project Development → Procurement →
Design, Build, Operate, and Handback
P3 Evaluation at Planning Stage
Planning & Project Development
Is the project appropriate for a P3?
- Scale
- Long-term nature of service
- Complexity of risk profile
- Potential for innovation
What are the whole-life costs, and can they be reduced through
integration of design, construction and operations?
Would a P3 add value?
If so, what type of P3 is best?
Is the project worthwhile for a private entity to deliver?
How much subsidy would be required? Is it affordable?
Procurement
Does the preferred bid add value?
Does the actual P3 agreement add value?
P3 Evaluation at the Implementation Stage
Design & Construction
Has the anticipated value been realized at construction completion?
↓
Operation & Handback
Has the anticipated value been realized throughout the project's
life?
Quantitative P3 Evaluation
- Economic Efficiency Assessment:
- Considers full range of costs and benefits to
society
- May include financial elements, but some such
elements may not be included, e.g., tolls
- Employs benefit-cost analysis (BCA)
- Financial Assessment:
- Considers financial elements only, i.e., "cash
flows"
- Focuses on "costs" side; "benefits" to society
(e.g., travel time savings from accelerated project
delivery) not assessed quantitatively
- Non-financial benefits are generally left to qualitative
assessment
- Employs value-for-money (VfM) analysis and financial
models
Financial Evaluation Questions
- Is the project affordable to the public agency?
- Financial feasibility analysis
- Will P3 procurement enhance the financial position
of the public sponsor?
- Value for Money (VfM) analysis
- Is the dollar value that the private entity
offers (or is willing to accept) a good value for the viewpoint
of the public agency?
- Asset valuation (for "net revenue" projects)
- Subsidy and availability payment valuation (for
"net cost" projects)
Financial Evaluation Approach
- Focus is on costs (i.e., only the denominator in BCA)
- Considers only cash flows over the project's life
- Perspective of balance sheet of the procuring agency
- Financial elements do not cover the full range of benefits
or costs to society:
- Benefits to users and non-users (e.g., from accelerated
delivery)
- External costs and benefits
- However, non-financial elements are often covered in
qualitative assessment
Economic Efficiency Questions
- Does the project yield benefits to society that exceed
the costs to society?
- Benefit-Cost analysis (BCA)
- Generally conducted at the planning stage, i.e.,
before considering P3 option for procurement
- "Costs" are based on conventional procurement
- Will a P3 option increase net benefits to society compared
with conventional procurement?
- Benefit-Cost analysis (BCA)
- Would be conducted if answer to first question
is "Yes"
- P3 costs and benefits would be compared to conventional
procurement costs and benefits
- FHWA is conducting research to develop this approach
Benefit-Cost Analysis (BCA) Approach
- Assessment of the full range of economic costs, risks
and social benefits
- Goes beyond procuring agency's perspective
- Considers externalities and user benefits
- Key questions answered by BCA:
- Is a project a good use of society's (public)
resources?
- When should a project be undertaken?
- What is the best project design alternative?
- What is the best procurement method from
an economic perspective, i.e., considering the full
range of social costs and benefits?
Evaluating a P3 Option: Summary
| Question |
Analysis |
| What are the financial consequences of the procurement
option from the perspective of the agency's financial
position? |
Financial (VfM) |
| Which procurement method is better from society's
perspective? |
Economic (BCA)* |
* FHWA research is underway to develop this approach
P3 Evaluation Challenges
- Representing the conventional delivery option for comparison
to P3
- Identifying and pricing risk
- Allocating risk to the party best able to handle it
- Predicting traffic and revenue
- Benefits to users from accelerated project delivery
- Sensitivity of results to key assumptions (e.g., discount
rates)
Test Your Knowledge
True or False:
Financial evaluation considers the full range of costs and benefits
to society.
True or False:
Evaluation is needed at the planning stage only.
Questions?
Submit a question using the chat box
Lesson 2 - P3 Financial Evaluation
P3 Financial Evaluation Process
| 1. Preliminary Screening |
Apply high level preliminary screening criteria
to all major capital investment projects |
| 2. Detailed Evaluation |
Develop quantitative and qualitative VfM assessment
and gauge competitive interest through market sounding |
| 3. Final Decision |
Refine P3 contractual terms, revisit VfM analysis
and evaluation as cost estimates are refined |
Purpose of Transparency
Benefits to public sector:
- Offers legitimacy with facility users, elected officials
and the general public
Benefits to private sector:
- Makes process and rules of the game clear, builds confidence
in reliability of getting to decision
Maintaining Transparency
- Establish process to review P3 proposals, incorporating
transparency and public participation, e.g., VDOT process
- Be clear up-front about what type of information should
remain confidential and provide an explanation as to why
confidentiality is necessary during the proposal process.
- Temporary confidentiality could be balanced with full
disclosure of selection criteria, scoring, and agreement
terms
1. Preliminary Screening

P3-SCREEN
- P3-SCREEN is a simplified P3 screening tool
to assist in preliminary screening evaluation of the suitability
of a highway project for a P3 option.
- Highlights key criteria and questions relevant to assessing
the viability of delivering a highway project using a P3
approach.
- May be used in conjunction with the development of
an Initial Financial Plan for major projects to assist
in meeting the Federal requirements under Moving Ahead
for Progress in the 21st Century (MAP-21).
Key P3 Screening Questions
- Legal Framework: Is there the necessary
legal and institutional framework in place to support a
P3 arrangement?
- Institutional Capacity: Does the agency
have the organizational capacity to deliver a P3?
- Project Characteristics: Does delivery
of the project as a P3 represent a value proposition* for
the public sector?
- Market Interest: Are there a sufficient
number of qualified bidders who are interested?
* Value = cost and schedule efficiencies, innovation, budget
certainty, accelerated delivery, etc.
2.
Detailed Financial Evaluation
- Evaluation:
- Traffic and revenue
- Cost estimates
- Risk assessment
- Comparison of P3 vs. public delivery (VfM)
- Affordability to public agency and/or to traveling
public (i.e., for tolls)
- Market outreach:
- Market analysis
- Market outreach
3. Final Decision
Review the prior evaluation before RFP release and upon receipt
of price proposals

Test Your Knowledge
True or False:
Value for Money analysis may be used to make a decision on whether
to use a P3.
Questions?
Submit a question using the chat box.
Lesson 3 - Value for Money Analysis
Definitions
- Value for Money (VfM)
- The optimum combination of life cycle costs and
quality of a good or service to meet the user's requirements
- Generally expressed as the dollar difference or
% difference between present value of costs for P3
vs. present value of costs for conventional project
delivery
- VfM Analysis
- Quantitative analysis to compare the financial
impacts of procurement alternatives for a project
- Financial analysis
- Impact on balance sheet of the procuring agency
- Other benefits (e.g., to users) considered in
qualitative assessment
- Public Sector Comparator
- Conventional procurement's baseline cost against
which P3 option will be compared
- Shadow Bid
- Cost of P3 option
- Includes estimated payments to private partner
as well as other costs incurred by public sponsor
Timing
- Agencies typically conduct VfM analyses once they decide
to undertake a project and wish to assess delivery options
| Develop PSC |
→ |
Compare PSC with shadow bid to determine
option with greater VfM |
→ |
Release RFP if P3 option is selected
and receive actual P3 bids |
→ |
Compare PSC with actual bids to determine
option with greater VfM |
→ |
Compare PSC with actual P3 experience
throughout project's life |
| Develop Shadow Bid |
→ |
Purpose of Value for Money Analysis
- Identify project suitability for P3 delivery
- Quantify risks and determine value of private
risk premium
- Answer the question: "Will P3 procurement provide greater
value compared with conventional procurement?"
- Inform selection and negotiation process for a P3 project.
- Evaluate implemented P3 projects
VfM Analytical Process
- Identify potential procurement options
- Identify, monetize and allocate project risks
- Develop public sector comparator (PSC)
- Develop P3 option ("shadow bid")
- Compare public sector comparator to P3 option
- Consider qualitative factors (e.g., benefits to users
from accelerated project delivery)
1. Identify Procurement Options
- Conventional procurement options:
- Design-Bid-Build
- Design-Build
- Design-Build-Finance
- Other (e.g., Contract manager at risk)
- Common P3 procurement options:
- Design-Build-Finance-Operate-Maintain (DBFOM)
with toll concession
- Design-Build-Finance-Operate-Maintain (DBFOM)
with availability payments
- Design-Build-Finance-Operate-Maintain (DBFOM)
with shadow tolls
- Other possibilities:
- DBFO - South Bay Expressway, CA (original)
- DBFM - Goethals Bridge, NYC
2. Risk Assessment and Allocation
- Risk identification
- All phases - design, construction, operation
- Risk quantification
- Probability of occurrence
- Range of cost and schedule impacts
- Aggregate risk valuation
- Formula-based
- Monte-Carlo simulation
- Risk allocation
- Transferrable to private sector
- Retained by public sector
3. Develop Public Sector Comparator
- Estimate the hypothetical, risk-adjusted cost of a
project delivered through conventional approach:
- Base costs (including financing)
- Cost impacts of risks
- Procurement and oversight costs
- Competitive neutrality adjustments
- Assumes project can be completed to the same standards
anticipated by P3 delivery
- Assumes same time frame, i.e., funding or financing
issues will not delay conventional procurement
4. Develop a Shadow Bid
- Estimate the total costs to the public agency
for delivering the same project as
a P3
- Components include:
- P3 contract payment: Amount that
would be demanded by private sector to deliver the
project based on its costs and desired rate of return
- Retained risks: Value of risks
retained by the public sector in P3 delivery structure
- Other project costs: Costs incurred
by the public agency to facilitate project delivery
and oversight
5. Compare PSC with Shadow Bid

6. Qualitative Assessment
- Key consideration - Non-financial benefits, e.g., user
benefits from accelerated project delivery
- Other considerations include:
- Viability: Ability to formulate
a sound contract
- Performance: Opportunity for
innovation
- Achievability: Public agency's
capabilities and those of the private sector
Hypothetical Illustration
- Not real project data - only to illustrate process
- P3 options: (1) Availability payment (2) Toll
- Illustrative assumptions:
- P3 options reduce life-cycle costs by 5 percent
- Risks transferred to P3 concessionaire are managed
at 25 percent lower cost
- P3 concessionaire may increase toll revenue by
5 percent for toll concession
- Future cash flows discounted using public sector
borrowing rate
1. Estimate Initial Cost to Agency
P3 costs may appear higher despite lower life cycle costs
2. Add Retained Risks & Other Costs
Retained risk in PSC may make it more costly than P3

3. Adjust for Competitive Neutrality
P3-Availability may have best VfM if toll revenue is same

4. Final Agency Cost Estimates
P3-Toll may have best VfM if it generates higher toll revenues

VfM Analysis Limitations
- Analytical process to assess costs and risks is resource
intensive and may require outside expertise
- Analysis results are entirely dependent on the assumptions,
especially regarding risk transfer
- Choice of discount rate can skew the results - extreme
care is needed to ensure risk costs are not double-counted
in the discount rate
- Does not answer the question: "Can the government agency
afford the costs of delivering a project as a P3?"
- Does not quantitatively assess non-financial costs
and benefits of a project (e.g., benefits of project acceleration)
Test Your Knowledge
True or False:
The PSC assumes that the project can be delivered and operated
to the same quality as the P3 option.
True or False:
If the Shadow Bid is lower than the PSC, then the project is
affordable.
True or False:
Highway user benefits are included in the cash flows estimated
for VfM analysis.
Questions?
Submit a question using the chat box
Lesson 4 - FHWA's P3 Toolkit and P3-VALUE
FHWA's P3 Toolkit
- P3 Toolkit provides educational tools and guidance
documents to enhance the capacity of public sector decision-makers
to analyze procurement options
- Will address four key phases of P3 implementation:
- Legislation and policy
- Planning and evaluation
- Procurement
- Monitoring and oversight
1. Legislation and Policy
2. Evaluation
Resources include:
- Orientation Guide
- Primers
- Evaluation Guidebooks
- P3-SCREEN: P3 Screening Tool
- P3-VALUE: A suite of educational tools and accompanying
user guides
3. Procurement
- Model contracts - under development
- Best Practices Guidebook - under development
4. Oversight and Monitoring
- Best Practices Guidebook - under development
What is P3-VALUE?
- A set of integrated analytical tools to help practitioners
understand processes used to quantitatively evaluate procurement
options
- Educates users so they can understand assumptions and
results of analyses performed by experts
- Major component of FHWA's P3 Toolkit
P3-VALUE Tools
- Risk Assessment Tool
- Identifies risks, risk allocation, mitigation
strategies, potential cost and schedule impacts
- Public Sector Comparator (PSC) Tool
- Calculates risk-adjusted life cycle costs of conventional
procurement
- Shadow Bid Tool
- Calculates costs of P3 procurement, including
payments to private partner
- Financial Assessment Tool
- Compares PSC and Shadow Bid costs to calculate
value for money
P3-VALUE Structure

P3-VALUE Limitations
- P3-VALUE is for educational purposes only and is not
intended to guide decisions on actual projects
- Costs are based on user assumptions about the probability
and consequences of risks
- No assessment of the non-financial benefits from accelerated
project delivery
- Provide only a rudimentary measure of potential differences
in financing costs
- Not applicable for brownfield or asset monetization
P3s (i.e., P3s for existing revenue generating facilities)
Test Your Knowledge
True or False :
FHWA's P3 Toolkit will provide tools to cover four phases of
P3 implementation.
True or False:
P3-VALUE should not be used to evaluate actual projects.
True or False:
P3-VALUE can provide estimates of non-financial benefits such
as user benefits due to accelerated project delivery.
Questions
Submit a question using the chat box
Course Summary
Course Recap
Lesson 1 - Overview of P3 Evaluation
Lesson 2 - P3 Financial Evaluation
Lesson 3 - Value for Money Analysis
Lesson 4 - P3 Toolkit and P3-VALUE
Summary
Resources
IPD Website:
http://www.fhwa.dot.gov/ipd/
P3 Website:
http://www.fhwa.dot.gov/ipd/p3/
FHWA Value for Money Primer:
http://www.fhwa.dot.gov/ipd/p3/toolkit/guidance_documents/index.htm
FHWA Financial Assessment Primer:
http://www.fhwa.dot.gov/ipd/p3/toolkit/guidance_documents/index.htm
FHWA Economic Analysis Primer:
http://www.fhwa.dot.gov/infrastructure/asstmgmt/primer05.cfm
P3-VALUE Website:
http://www.fhwa.dot.gov/ipd/p3/toolkit/analytical_tools/index.htm
Upcoming P3-VALUE Training
June 13: Project Risk Assessment 201
July 11: Public Sector Comparator/Shadow Bid 201
August 7: P3 Financial Assessment 201
To register, please visit
http://www.nhi.fhwa.dot.gov/resources/webconference/eventcalendar.aspx
Contact Information
Patrick DeCorla-Souza
P3 Program Manager
Office of Innovative Program Delivery
Federal Highway Administration
(202) 366-4076
Patrick.DeCorla-Souza@dot.gov
Thay N. Bishop, CPA, CTP
Senior Program Advisor/Capacity Builder
Office of Innovative Program Delivery
Federal Highway Administration
(404) 562-3695
Thay.Bishop@dot.gov
Questions?
Submit a question using the chat box