Webinar - Value for Money Analysis:
Constructing the Public Sector Comparator and the Shadow Bid

Presentation: PDF
Webinar recording: Audio
Homework Assignment: Value for Money Analysis Part 1: Developing the Public Sector Comparator

P3-VALUE Webinar - January 23, 2014

Patrick DeCorla-Souza
P3 Program Manager
Office of Innovative Program Delivery

P3-Value Webinars

P3-VALUE: Suite of four integrated analytical tools and supporting documentation to help practitioners understand processes used to quantitatively evaluate P3 options

This is the third of four webinars on P3-VALUE

Course Outline

Lesson 1 Introduction to P3s and the P3 Toolkit

Lesson 2 Developing a Public Sector Comparator

Lesson 3 Developing a Shadow Bid

Lesson 4 Comparing Procurement Options

Course Summary

Course Objective

After taking this course you should be able to:

  • List the various components of the Public Sector Comparator (PSC) and Shadow Bid (SB)
  • Describe the methodologies used to estimate the PSC and Shadow Bid
  • Explain how the PSC and Shadow Bid are compared using Value for Money (VfM) analysis
  • Access the P3-VALUE tools and supporting information

Lesson 1 - Introduction to P3s and the P3 Toolkit

What is a P3?

  • Acronym: Public-private partnership (P3 or PPP)
  • Definition: Contractual agreement between a public agency and a private entity that covers more than a single phase of a project.
  • FHWA's Office of Innovative Program Delivery focuses on P3s that include financing

Common Types of P3s

Common types of P3s

Text of the graphic

  • P3
    • Greenfield
      • Design-Build-Finance
      • Design-Build-Finance-Operate-Maintain*
        • Toll Concession
        • Availability Payment Concession
    • Brownfield (primarily toll concessions)

*Focus of P3-VALUE tools

Potential Benefits and Drawbacks

Potential Benefits

  • Additional Financial Capacity
    • Accelerates project delivery
    • Conserves public sector debt capacity
  • Life-Cycle Cost Efficiencies
    • Creates incentives to manage costs over the life of the project
    • Integrates project phases creating efficiencies
  • Risk Transfer
    • Budget and cost certainty
    • Improved risk management reduces costs

Potential Drawbacks

  • Loss of flexibility of public agency
  • Complex procurement process
  • Perceived higher financial costs (due to incorporation of risk premiums into private sector returns)

FHWA's P3 Toolkit

  • The P3 Toolkit provides educational tools and guidance documents to enhance the capacity of public sector decision-makers to evaluate and implement P3s
  • Will address four key phases of P3 implementation:
  1. Legislation and policy
  2. Planning and evaluation
  3. Procurement
  4. Monitoring and oversight

P3 Evaluation

Value for Money (VfM)

  • The optimum combination of life cycle costs and quality of a good or service to meet the user's requirements
  • Generally expressed as the dollar difference or % difference between present value of costs for P3 vs. present value of costs for conventional project delivery

VfM Analysis

  • Quantitative analysis to compare the financial impacts of procurement alternatives for a project
  • Financial analysis
  • Impact on balance sheet of the procuring agency
  • Other benefits (e.g., to users) considered in qualitative assessment

Timing of VfM Analysis

Agencies typically conduct VfM analyses once they decide to undertake a project and wish to assess delivery options

Steps in VfM analysis

Text of the graphic

  • Develop PSC or; Develop shadow bid*
    • Compare PSC with shadow bid to determine option with greater VfM*
      • Release RFP if P3 option is selected and receive actual P3 bids
        • Compare PSC with actual bids to determine if VfM is achieved
          • Compare PSC with actual P3 experience throughout project's life

*Focus of this webinar

Pre-Procurement P3 Evaluation

  1. Identify potential procurement options
  2. Identify, monetize and allocate project risks (covered in September 2013 webinar)
  3. Develop public sector comparator (PSC)
  4. Develop P3 option ("shadow bid")
  5. Compare PSC to Shadow Bid
  6. Consider qualitative factors (e.g., benefits to users from accelerated project delivery)

For a more detailed discussion, see Value for Money Analysis Primer at:
http://www.fhwa.dot.gov/ipd/p3/toolkit/guidance_documents/

P3-VALUE Tools

  • Risk Assessment Tool
    • Helps identify risks, risk allocation, risk response strategies, potential cost and schedule impacts
  • Public Sector Comparator (PSC) Tool
    • Calculates risk-adjusted life-cycle costs of conventional procurement
  • Shadow Bid (SB) Tool
    • Calculates costs of P3 procurement, including payments to private partner
  • Financial Assessment Tool
    • Compares PSC and Shadow Bid costs to calculate value for money
  • P3-VALUE Tools are accessible at FHWA IPD's website:
    http://www.fhwa.dot.gov/ipd/p3/toolkit/analytical_tools/

P3-VALUE Tools flowchart

Test Your Knowledge

True or False:

P3 evaluation may be undertaken using Value for Money analysis prior to procurement as well as later during a project's life.

Questions?

Submit a question using the chat box

Lesson 2 - Developing a Public Sector Comparator

PSC Tool Overview

  • Public Sector Comparator (PSC)
    • Conventional procurement's baseline cost against which P3 option will be compared
  • Public Sector Comparator Tool (PSC Tool)
    • Estimates the risk-adjusted life-cycle costs of a project delivered by the public sector
    • Prerequisites
      • Estimates of project delivery schedule, life-cycle costs and revenues
      • Estimates of value of retained and transferable project risks
      • Basic project finance plan

Developing a PSC

  • Key assumptions:
    • Project can be completed to the same standards anticipated by P3 delivery
    • Project can be completed over the same timeframe (e.g., funding or financing issues will not delay conventional procurement)
    • Discount rate - all future cash flows are converted to "present value" terms, including:
      • Costs
      • Revenues
      • Financing (e.g., debt and equity receipts and payments)

Example of Present Value Calculation

Present Value of $10M received in Year 2 at 5% discount ratePresent Value of $10M received in year 4 at 5% discount rate

Discount Rate

  • Discount rate is a percentage by which a cash flow element in the future is reduced per year, applied exponentially
    • It is used to estimate how much money would have to be invested currently, at a rate of return equal to the discount rate, to yield the cash flow in future
    • It is also used to estimate how large an investment can be justified at a required rate of return equal to the discount rate on the basis of expected future cash flows
    • It may be used to account for uncertainty in future cash flows - one "certain" dollar is worth more than one uncertain dollar
    • A "nominal" discount rate accounts for inflation, and is applied to nominal (i.e. inflation-adjusted) future cash flows
    • A "real" discount rate is applied to future cash flows that do not incorporate inflation

Present Value

  • Present Value: A metric to determine the time-adjusted (and risk-adjusted) value of future project cash flows:
    • Net Present Value (NPV): Sum of present values of positive and negative cash flows, including the initial investment
    • Net Present Cost (NPC): For a sum that is a net cost
    • Using a high discount rate will favor lower upfront investment with higher recurring costs in the future (since the high discount rate will minimize future costs)

Effect of a High Discount Rate

  • The same annual payment ($25.6 M) appears to be much smaller with a higher discount rate

PV at 5% discount ratePV at 7.2% discount rate

Key Components of a PSC

  • Estimate the hypothetical, risk-adjusted cost of a project delivered through conventional approach:
  1. Base costs
  2. Cost impacts of risks (both transferable and retained risks)
  3. Financing costs
  4. Other project costs (e.g., procurement and oversight costs)
  5. Competitive neutrality: Adjustments for any competitive advantages and disadvantages that accrue to the public agency by virtue of its public ownership

Components of the PSC Estimate

Components of the PSC Estimate

Text of the graphic

Transferable Risks, Competitive Neutrality, Raw PSC + Financing Costs, Retained Risks = Total

1. Base Costs

Cost Item Description
Capital Costs Includes design, right-of-way purchase and construction costs.
Operations Costs Day-to-day costs of operating the project.
Maintenance Costs Routine and preventive maintenance costs (e.g., pavement overlay, replacement of lighting, and snow and ice removal).
Reconstruction & Rehabilitation Costs Costs associated with major structural replacement or upgrades, (e.g., bridge or pavement replacement).

2. Cost Impacts of Risks

Cost Item Description
Retained Risk Costs The costs of project risks that a public agency bears. If a retained risk is realized, then the public agency is responsible for the related costs of responding to that risk event.
Transferable Risk Costs Risk costs that may be transferred from the public agency to its contractor, though the public agency may still pay a risk premium through the contractor's bid price.
Shared Risk Costs The public agency and the contractor may share the burden of some risks that cannot be efficiently transferred.

3. Financing Costs

Cost Item Description
Financing Costs Costs associated with the interest charged on debt, as well as other costs (e.g., arrangement fees, commitment fees, and "swap" credit premiums).

4. Other Project Costs (Examples)

Cost Item Description
Procurement Costs Transaction costs incurred by the public agency throughout the procurement process for preparing and advertising a bid, receiving and reviewing proposals, etc.
Monitoring & Oversight Costs Costs inherent to the public agency as it performs its project oversight and monitoring activities (e.g., conducting site inspections or preparing Federal-aid reports).
Right-of-way Costs Costs associated with land acquisition and right-of-way entitlements. May be included in Base Costs (capital costs).

5. Competitive Neutrality Adjustments (Examples)

Cost Item Description
Federal corporate tax "Opportunity cost" of Federal corporate taxes that would be paid under a P3. Consideration depends on the procuring agency's viewpoint
State corporate tax "Opportunity cost" of State corporate taxes that would be paid under a P3. Consideration depends on the procuring agency's viewpoint
Self-insurance Cost For example, tort liability limits under public operation favor the public sector
Costs associated with transparency, accountability and public scrutiny For example, a public agency may incur higher costs for public involvement with a P3 procurement; on the other hand, greater public involvement may be required in the operations phase with traditional delivery, especially in toll rate setting.

Test Your Knowledge

True or False:

Using a high discount rate to get the present value of a stream of future cash flows will result in a lower present value.

Illustration of PSC Estimation

  • We will use hypothetical project data to illustrate how a PSC may be estimated.
  • We will first show how the data may be used with a very simple model
    • To illustrate each step of the process
    • Using simple assumptions
  • We will then show results produced by P3-VALUE focusing on:
    • How the results differ from our simple calculations
    • Why the results differ

Hypothetical PSC Cost Data

  • Design-Bid-Build (or Design-Build)
  • Base design/construction costs of $30M in Year 1 and $70M in year 2 - P3-VALUE expects these cost in nominal dollars
  • $10 million (real dollars) per year O&M costs over 28 years
  • Risk cost estimates for design-build phase:
    • 10% probability (P10) that they will be at or below $10 M
    • 70% probability (P70) that they will be at or below $20 M
    • 90% probability (P90) that they will be at or below $30 M
  • Risk cost estimates for operations phase:
    • 10% probability (P10) that they will be at or below $1 M
    • 70% probability (P70) that they will be at or below $2 M
    • 90% probability (P90) that they will be at or below $3 M
  • Other project costs are assumed to be zero for simplicity

Hypothetical PSC Assumptions

  • Financing:
    • Bond financing for 100% of construction costs, at 5% interest and 30-year maturity
    • Bond issuance costs of 2% of borrowed amount are financed as part of the debt
    • For simplicity, no reserves are required, but reserve requirements (for debt service and O&M) are normally required to be financed
  • Inflation = 3% annually
  • Discount rate = 5%
    • This rate is the same as the public sector borrowing rate
    • It assumes that all project risks are accounted for in the cash flows, including:
      • Risks that would be transferred to contractors
      • Risks that would be retained by the public agency for each phase, as well as "systematic" risks, project coordination risks, and long-term performance risks

Base PSC Capital Costs

  • While nominal costs are $100 M, the present value of those costs are only $92.1M

PSC Design-Build Costs

Base PSC Operations Costs

PSC Operations Costs

PSC DB Phase Risk Costs (at P70)

PSC Design Build Risk Costs

PSC Operations Risk Costs (at P70)

PSC Operations Risk Costs

PSC Net Financing Costs (at P70)

PSC Net Financing Costs chart

Note: Financing for reserve funds is not included - they can greatly increase costs

PSC Estimates - Bond vs. Draw

Note: The amount invested does NOT include debt service and O&M reserves that would also normally be financed up front. For the bond scenario, any interest received on bond proceeds is ignored.

BOND DRAW
Discount rate = 5% Cost ($M) Discount rate = 5% Cost ($M)
Base DB costs 100.0 Base DB costs 92.1
DB Risks 20.0 DB Risks 18.4
Total investment 120.0 Total investment 110.5
       
Base O&M costs 206.3 Base O&M costs 206.3
O&M risk costs 41.3 O&M risk costs 41.3
Total O&M costs 247.6 Total O&M costs 247.6
Financing costs 2.4 Financing costs 2.4
Total cost 370.0 Total cost 360.5

PSC Results with "Draw" Option

  • Results for P70 scenario are shown in the middle column
Nominal Discount Rate Results - Risk Adjusted Payments ($)
5.00% PV of Payments with P10 Risk Adjustment PV of Payments with P70 Risk Adjustment PV of Payments with P90 Risk Adjustment
Payment Item      
Design and Construction After Subsidy # - - -
Construction Phase Transferable Risks # - - -
Construction Phase Retained Risks # - - -
Operations 101,692,152 101,692,152 101,692,152
Routine Maintenance 101,692,152 101,692,152 101,692,152
Periodic Maintenance - - -
Operations Phase Transferable Risks 20,338,430 40,676,861 61,015,291
Operations Phase Retained Risks - - -
Other Project Costs (ROW etc) - - -
PSC Adjustments - - -
Principal Debt Payments 41,890,908 45,768,288 49,645,668
Interest & Fee Payments 61,154,273 67,250,245 73,346,216
Total Payments $326,767,915 $357,079,697 $387,391,476
Toll and Other Revenue (290,082,714) (290,082,714) (290,082,714)
Total Payments After Toll and Other Revenue $36,685,201 $66,996,983 $97,308,765

Comparison of Estimates - "Draw"

  • With P3-VALUE, a six-month payment schedule is used instead of a one-year schedule; also the amount invested includes any reserves that must be financed up front.
SIMPLE MODEL P3-VALUE
Discount rate = 5% Cost ($M) Discount rate = 5% Cost ($M)
Base DB costs 92.1 Principal 45.8
DB Risks 18.4 Interest & Fee 67.2
Total investment 110.5 Total investment 113.0
   
Base O&M costs 206.3 Base O&M costs 203.4
O&M risk costs 41.3 O&M risk costs 40.7
Total O&M costs 247.6 Total O&M costs 244.1
Financing costs 2.0 Financing cost (incl. above)
Total cost 360.1 Total cost 357.1

PSC Results with "Bond" Option

Nominal Discount Rate Results - Risk Adjusted Payments ($)
5.00% PV of Payments with P10 Risk Adjustment PV of Payments with P70 Risk Adjustment PV of Payments with P90 Risk Adjustment
Payment Item      
Design and Construction After Subsidy # - - -
Construction Phase Transferable Risks # - - -
Construction Phase Retained Risks # - - -
Operations 101,692,152 101,692,152 101,692,152
Routine Maintenance 101,692,152 101,692,152 101,692,152
Periodic Maintenance - - -
Operations Phase Transferable Risks 20,338,430 40,676,861 61,015,291
Operations Phase Retained Risks - - -
Other Project Costs (ROW etc) - - -
PSC Adjustments - - -
Principal Debt Payments 58,070,133 67,909,258 77,748,384
Interest & Fee Payments 84,433,428 99,155,313 113,877,199
Total Payments $366,266,294 $411,125,736 $456,025,177
Toll and Other Revenue (290,082,714) (290,082,714) (290,082,714)
Total Payments After Toll and Other Revenue $76,143,580 $121,043,021 $165,942,463

Comparison of Estimates - "Bond"

  • With P3-VALUE, total investment amount includes debt service and O&M reserves - it is assumed they must be financed up front (e.g., for payments to be made before toll revenue kicks in)
SIMPLE MODEL P3-VALUE
Discount rate = 5% Cost ($M) Discount rate = 5% Cost ($M)
Base DB costs 100.0 Principal 67,9
DB Risks 20.0 Interest & Fee 99.1
Total investment 120.0 Total investment 167.0
   
Base O&M costs 206.3 Base O&M costs 203.4
O&M risk costs 41.3 O&M risk costs 40.7
Total O&M costs 247.6 Total O&M costs 244.1
Financing costs 2.4 Financing cost (incl. above)
Total cost 370.0 Total cost 411.1

Illustrative Project Revenues

  • Base revenue estimate:
    • Average Annual Daily Traffic (AADT) in Year 3 = 21,600 vehicles, no growth over project life
    • Average toll rate = $2.00 in Year 0 dollars (increases with inflation)
    • Year 3 Revenue = 21,600 X 365 days X $2.19 = $17.2 M
  • Adjustment for "revenue leakage," i.e., uncollected tolls (5% reduction):
    • Year 3 = $17.2 M - $0.8 M = $16.4 M
  • Ramp-up period (Years 3 and 4):
    • Year 3 = 67% reduction = $16.4 M - $11.0 M = $5.4 M

Revenue Calculations

  Avg. annual daily traffic Average toll rate Leakage Ramp-up reduction Revenue ($M)
Year 0   $2.00      
Year 3 21,600 $2.19 5% 67% $5.4
Year 4 21,600 $2.25 5% 33% $11.3
Year 5 21,600 $2.32 5% 0% $17.4
Year 30 21,600 $4.44 5% 0% $36.4
Total (nominal) 41.3       $686.2
NPV*         $295
P3-VALUE NPV est.         $290

Note: Revenues are discounted at the same rate as costs. Since revenue estimates are riskier than cost estimates, a higher discount rate may be warranted to reflect the higher risk. P3-VALUE's estimate is lower due to six-month cash flow periods.

Test Your Knowledge

True or False:

If the discount rate is equal to the interest rate on the debt, the present value of a stream of debt service payments discounted to the year the loan is made will be equal to the amount borrowed.

Questions?

Submit a question using the chat box

Lesson 3 - Developing a Shadow Bid

Shadow Bid Tool Overview

  • Shadow Bid
    • Cost of P3 option
    • Includes estimated payments to private partner as well as other costs incurred by public sponsor
  • Shadow Bid Tool
    • Estimates the risk-adjusted, life-cycle costs of a project delivered by the private sector
      • Prerequisites
        • Estimates of project delivery schedule, life-cycle costs and revenues
        • Estimates of value of retained and transferable project risks
        • Basic project finance plan

Developing a Shadow Bid

  • Estimate the total costs to the public agency for delivering the same project as a P3 (instead of conventional delivery)
  • Components include:
    • P3 contract payment: Amount that would be required by private sector to deliver the project based on its costs and desired rate of return
    • Retained risks: Value of risks retained by the public sector in P3 delivery structure
    • Other project costs: Costs incurred by the public agency to facilitate project delivery and oversight
  • Note: the term "shadow bid" as used in Value for Money analysis includes both the estimated private bid cost as well as additional public costs

Estimating the P3 Contract Method

  • Payments to Private Partner cover:
  1. Base life-cycle costs borne by private partner
    • Capital Costs (Design and Construction)
    • Annual Operations and Maintenance Costs
    • Periodic Maintenance Costs (Reconstruction and Rehabilitation)
  2. Costs of transferred risks
  3. Financing costs:
    • Interest on debt
    • Equity returns, including consideration of taxes to be paid by concessionaire

1. Base Life-Cycle Costs of Private Partner

Costs may be reduced (relative to PSC) due to:

  • Cost Efficiency
    • Lower design-build costs
    • Lower O&M costs
  • Schedule Efficiency
    • Faster design and construction

2. Costs of Transferred Risks

  • Includes risks transferred to subcontractors, as well as risks borne by the concessionaire
    Risk Contingency Reduction

3. P3 Financing Costs

P3 financing costs incorporate risk premiums for:

  • Identified project risks that are not transferred to subcontractors (and so are not included in the cash flows)
  • Unidentified project risks that are transferred
  • Market risks ("systematic" risks)
    • Inflation
    • Economy
    • Interest rates (e.g., when short-term loans have to be refinanced)

P3 financing costs may be higher (relative to PSC) due to incorporation of project risk premiums that may not be incorporated in PSC financing costs or PSC operational cash flows

Hypothetical Shadow Bid Costs

  • DBFOM with "availability payments" made by public agency over a 30-year concession term, contingent on meeting performance standards; toll revenue is allocated to the public agency
  • 10% DB cost reduction relative to PSC
  • 5% O&M cost reduction relative to PSC
  • Risk management efficiency
    • 50% of design-build phase risk costs are transferred
    • 100% of operations phase risk costs are transferred
    • 25% lower risk costs for all transferred risks

Hypothetical Shadow Bid Assumptions

  • Financing costs
    • Project funded 80% by bank debt and 20% by equity
    • Average debt interest rate is 6% (vs. 5% for PSC)
    • Required after-tax return on equity is 12% ("hurdle" rate)
    • For simplicity, we assume no reserves are required; reserve requirements (for debt service and O&M) are normally required to be financed
    • For simplicity, there is no consideration of taxes paid by concessionaire, since after-tax equity return is used
  • Inflation = 3% annually
  • Discount rate = 5%
    • This rate is the same as the public sector borrowing rate
    • It assumes that all project risks are accounted for in the operational cash flows through contingencies, and through risk premiums in financing costs

Base SB Capital Investment Costs

  • Nominal costs are $90M (10% reduction relative to PSC), and the present value of those costs are only $82.9M

SB Design-Build Costs

Base SB Operations Costs

SB Operations Costs

SB Transferred Risk Costs (at P70)

  • Nominal costs of DB risks are $7.5 M (25% reduction for the transferred $10M which is 50% of total $20M in risks); the present value of those risk costs is $6.9 M

SB Risk Costs

SB Financing Costs (at P70)

SB Net Financing Costs

Summary of Shadow Bid Estimate

Comparison of PV of SB with P3-VALUE Results

SIMPLE MODEL P3-VALUE
Discount rate = 5% Cost ($M) Discount rate = 5% Cost ($M)
Base DB costs 82.9    
DB Risks 6.9    
Total investment 89.8    
Financing cost 32.9    
Base O&M costs 196.0    
O&M risk costs 31.0    
Total O&M costs 227.0    
Total concessionaire cost 349.7 Availability payments 351.6
Retained risks 9.2 Retained risks 8.9
Total cost 358.9 Total cost 360.5

Shadow Bid Costs (from P3-VALUE)

Note: P70 estimates are in the middle column

Value for Money Analysis Results
Manual Input Risk Adjusted Payments ($)
5.00% PV of Payments with P10 Risk Adjustment PV of Payments with P70 Risk Adjustment PV of Payments with P90 Risk Adjustment
Payment Item
Availability Payments

$329,228,341

$351,564,296 $374,172,641
Construction Phase Retained Risks $4,434,779 $8,869,557 $13,304,336
Operations Phase Retained Risks $  - $  - -
Other Project Costs (For Agency) $  - $  - -
Total Payments Before Toll Revenue $333,663,120 $360,433,853 $387,476,976
Toll and Other Revenue $  (290,082,714) $ (290,082,714) $ (290,082,714)
Total Payments After Toll Revenue $43,580,406 $70,351,139 $97,394,262

Availability Payment Calculation (P70)

  • PV of concessionaire's costs:
    • Total = $349.7 M, in year 0
      = $385.5 M, in year 2
  • Uniform availability payment over 28 years*:
    • Similar to mortgage payment, with $385.5 M "borrowed" and an "interest" rate of 5%**
      = $25.9M

*Annual availability payments are made by public agency over a 28-year operating period (i.e., 30-year term less 2-year design-build phase), contingent on meeting performance standards

*The PV of total concessionaire costs (i.e., $349.7M) includes the costs for financing with debt and equity, so the 5% discount rate is appropriate in this case

P3-VALUE Availability Payment Results

  • With P3-VALUE, the availability payment is inflated over the term of the concession, rather than being uniform throughout - that is why the first year availability payment is lower than we calculated with our simple model

Payment totals

Test Your Knowledge

Multiple answer:

Which of the following are included in the calculation of payments to a concessionaire:

  • Base life-cycle costs estimated for the concessionaire
  • Costs of risks transferred to the concessionaire
  • Cost of risks retained by the public sector

Questions?

Submit a question using the chat box

Lesson 4 - Comparing Procurement Options

Comparing PSC to Shadow Bid

Comparing PSC and Shadow Bid

Comparison of PSC and SB: Simple Model

  • Retained risks on the PSC side are zero because they are included in the PSC total investment
  • Financing cost includes risk premiums due to some transferred risks that are not accounted for in the PSC
  PSC (Draw) Shadow Bid
Simple Model Cost ($M) Cost ($M)
Total investment 110.5 89.8
Total O&M costs 247.6 227.0
Financing costs 2.4 32.9
Retained Risks - 9.2
Total cost 360.5 358.9

Concessionaire's Financing Cost

  • Cost of financing reflects costs to arrange for the financing, corporate taxes to be paid by concessionaire, and project risks
  • Financing is backed only by project revenues (tolls or availability payments) which are riskier than public financing backed by broader revenue sources
  • Higher weighted average cost of capital (interest rates and returns on equity) reflect the project risk premium for those risks not transferred to subcontractors:
    • Systematic risks;
    • Project coordination risks; and
    • Long-term performance risks
  • But these risks are also not accounted for in the PSC

Adjusted Comparison of PSC and SB

  • Project risk costs not accounted for in the PSC estimate may be calculated as a "virtual risk premium"
  • The virtual risk premium may be approximated as the difference between financing costs of the PSC and the SB
  PSC Shadow Bid
Simple Model Cost ($M) Cost ($M)
Total investment 110.5 89.8
Total O&M costs 247.6 227.0
Financing costs 2.4 32.9
Retained Risks - 9.2
Virtual risk premium 30.5  
Total cost 391.0 358.9

Qualitative Assessment

  • Key qualitative considerations related to project goals:
    • User benefits from accelerated project delivery
    • Safety
    • Service quality
    • Reliability
  • P3 contract-related considerations include:
    • Viability: Ability to formulate a sound contract
    • Performance: Opportunity for innovation
    • Achievability: Public agency's capabilities and those of the private sector
    • Flexibility: Ability of the public agency to coordinate regional network policies

VfM Analysis Limitations

  • Analytical process to assess costs and risks is resource-intensive and may require outside expertise
  • Analysis results are entirely dependent on the assumptions, especially regarding risk transfer
  • Choice of discount rate can skew the results - extreme care is needed to ensure risk costs are not double-counted in the discount rate
  • Does not answer the question: "Can the government agency afford the costs of delivering a project as a P3?"
  • Does not quantitatively assess non-financial costs and benefits of a project (e.g., benefits of project acceleration)

Course Summary

Lesson 1 Introduction to P3s, Value for Money and the P3 Toolkit

Lesson 2 Developing a Public Sector Comparator

Lesson 3 Developing a Shadow Bid

Lesson 4 Comparing Procurement Options

Summary

Homework Assignment

  • Run a Value for Money analysis using the P3-VALUE tools with the hypothetical project data presented in this webinar:
    • Availability payment concession
    • Toll concession
  • Technical assistance options:

Resources

IPD's P3 Website:
http://www.fhwa.dot.gov/ipd/p3/

P3-VALUE Website:
http://www.fhwa.dot.gov/ipd/p3/toolkit/analytical_tools/

FHWA Value for Money Assessment Primer:
http://www.fhwa.dot.gov/ipd/pdfs/p3/p3_value_for_money_primer_122612.pdf

FHWA Value for Money Analysis Fact Sheet:
http://www.fhwa.dot.gov/ipd/pdfs/p3/factsheet_03_vfm.pdf

P3-VALUE PSC and Shadow Bid Tools:
http://www.fhwa.dot.gov/ipd/p3/toolkit/analytical_tools/

P3-VALUE PSC Tool User Manual:
http://www.fhwa.dot.gov/ipd/pdfs/p3/p3_value_psc_manual_v1.pdf

P3-VALUE Shadow Bid Tool User Manual:
http://www.fhwa.dot.gov/ipd/pdfs/p3/p3_value_shadowbid_manual_v1.pdf

I-595 Corridor Value for Money Analysis:
http://www.transportation-finance.org/pdf/funding_financing/financing/i595_vfm_0609.pdf

Presidio Parkway Value for Money Analysis:
http://www.presidioparkway.org/project_docs/files/presidio_prkwy_prjct_bsnss_case.pdf

Sea-to-Sky Highway Value for Money Analysis:
http://www.presidioparkway.org/project_docs/files/presidio_prkwy_prjct_bsnss_case.pdf

Upcoming P3-VALUE Training

  • Feb. 21: Office Hours: Value for Money Homework Assignment Review
  • Mar. 13: P3 Financial Assessment 201
  • Apr. 18: Office Hours: Financial Assessment Homework Assignment Review

To register for the March 13 webinar, please visit http://www.nhi.fhwa.dot.gov/resources/webconference/eventcalendar.aspx

Contact Information

Patrick DeCorla-Souza
P3 Program Manager
Office of Innovative Program Delivery

Federal Highway Administration
(202) 366-4076
Patrick.DeCorla-Souza@dot.gov

Thay N. Bishop, CPA, CTP
Senior Program Advisor/Capacity Builder
Office of Innovative Program Delivery Federal Highway Administration

(404) 562-3695
Thay.Bishop@dot.gov

Questions?

Submit a question using the chat box