
Location |
Washington, DC |
Project Sponsor / Borrower |
District Department of Transportation (DDOT) |
Program Areas |
|
Mode |
Bridge |
Description |
The Eleventh Street Bridge Project is replacing the existing twin bridges that carry I-295 over the Anacostia River in the southeast quadrant of the District. Three new bridges are being constructed and improvements being made to the interchanges at both ends, including adding missing movements to and from the north onto the Anacostia Freeway (I-295/DC 295). The two-phase project will:
Phase 1 includes the three bridges and most of the amenities described above. Phase 2 will further improve the connection between the Southeast-Southwest Freeway and Virginia Ave. SE with the new outbound 11th Street Freeway Bridge. |
Cost |
Phase 1 project cost: $309.2 million
Phase 2 project cost: $90 million |
Funding Sources |
Phase 1: Federal funds:
Local funds:
|
Project Delivery / Contract Method |
Design-Build |
Private Partner |
Design-builder: Skanska/Facchina |
Project Advisors / Consultants |
Phoenix Capital Partners, LLP - Financial Advisor |
Lenders |
Bondholders |
Duration / Status |
Phase 1 construction began December 2009; expected completion summer 2013 Phase 2 construction to start late 2012; expected completion late 2015 |
Financial Status |
Closed |
Innovations |
|
Related Links / Articles |
DDOT Project Website |
Contacts |
Bryon Johnston |
