USDOT Federal Highway Administration USDOT Home | FHWA Home | Feedback
Skip to main content

Project Profiles

Northwest Corridor Project
Location Atlanta, Georgia
Project Borrower / Sponsor Georgia Department of Transportation (GDOT)
Program Areas P3Revenue - Road Pricing Revenue
Mode Highway
Description

The Northwest Corridor project, formerly known as West by Northwest Corridor project, extends along 29.7 miles of I-75 and I-575 and includes the following components:

  • The extension of managed lanes from the current end of the HOV lanes along I-75 at Akers Mill Road south of I-285
  • Two reversible tolled managed lanes to the west of the existing general purpose lanes along I-75 between I-285 north and I-575
  • One reversible tolled managed lane in the median along I-75 between I-575 and Hickory Grove Road and along I-575 to Sixes Road

The design-builder will be responsible for design and construction of the road, including tolling ITS, signage, and integration of components, and will also be required to finance 10–20 percent of the cost of the project.

GDOT will be responsible for managing the procurement process and overseeing the design and construction of the facility. GDOT will also be responsible for the long-term operation and maintenance of the highway. Georgia State Road and Toll Authority (SRTA) will be responsible for the tolling operations, tolling gantries and equipment and for communicating with customers about tolls.

Cost $950 million (estimated)
Funding Sources

State motor fuel taxes - $300 million

TIFIA (LOI accepted) - $270 million

GDOT work program funds - $200 million

DBF partner gap financing - $80–160 million (to be repaid by the state)

Project Delivery/Contract Method DBF (design-build-finance)
Private Partner To be awarded
Project Advisors/Consultants

PRAG, Ernst & Young – financial advisors

Greenberg Traurig, Nossaman – legal advisors

HNTB – technical advisor

Aon – insurance advisor

Stantec – Investment Grade traffic and revenue advisor

Lenders TBD
Duration/Status

The project was previously going to be procured as a DBFOM concession but the state canceled the procurement in December 2011 and has since pursued a DBF approach.

Three shortlisted candidates remain in the bidding for the DBF contract:

  • C.W. Matthews Contracting Co., Inc., and the Michael Baker Corp. 
  • Georgia Transportation Partners (Bechtel Infrastructure Corp., Kiewit Infrastructure South Co., Dewberry and Davis, LLC, STV Inc.) 
  • Northwest Express Road Builders (Archer Western Contractors, The Hubbard Group, Parsons Corp.)

The Request for Proposals (RFP) was issued in December 2012 and proposals are due June 2013. 

Construction is estimated to start summer 2014 and be complete spring 2018.

Financial Status Not yet financed; in procurement
Innovations  
Related Links/Articles GDOT Northwest Corridor Website
Contacts John D. Hancock, P.E.
Assistant State Innovative Program Delivery Engineer
GDOT Office of Innovative Program Delivery
(404) 631-1315
georgiaP3nwc@dot.ga.gov