| Location | Charlotte, North Carolina |
| Project Borrower / Sponsor | North Carolina Department of Transportation (NCDOT) |
| Program Areas |
|
| Mode | Highway |
| Description |
This project involves the construction of a new 5.1-mile, eight-lane section of interstate from west of NC 115 (Old Statesville Rd.) to west of I-85 north of Charlotte. This is the last segment of the I-485 Outer Belt around Charlotte and will connect I-77 to I-85. Related but separate projects in the completion of the I-485 Outer Loop include the widening of six miles of I-85 from four to eight lanes and the upgrade of the interchange between I-485 and I-85. |
| Cost | $139.5 million |
| Funding Sources | GARVEE bonds, State Transportation Trust Fund disbursements, contractor financing to be repaid by future General Assembly appropriations based on an availability payment schedule conveyed in the contract. |
| Project Delivery/Contract Method | DBF (design-build-finance) |
| Private Partner | Blythe Construction Inc./Wilbur Smith Associates (now CDM Smith) |
| Project Advisors/Consultants | Not available |
| Lenders | None |
| Duration/Status |
Construction began summer 2011 Expected construction completion December 2014 |
| Financial Status | Under this DBF contract, the design-builder is completing construction over 4.5 years and has agreed to an “extended payment schedule” of 5.5 years. |
| Innovations | North Carolina’s first DBF project estimated to accelerate project delivery by five years. |
| Related Links/Articles | |
| Contacts | Jen Thompson NCDOT Division 10 2327 Tipton Drive Charlotte, NC 28206 (704) 347-6618 |