FEDERAL-AID POLICY GUIDE
September 30, 1992, Transmittal 5
NS 23 CFR 650C
OPI: HNG-33
(1) Each State has a system to record recommendations included in the Bridge Inspection report and document actions taken to address the recommendations, and
(2) Each division office establishes a procedure to provide for spot checking the State's follow-up actions in response to recommendations included in the inspection report.
(1) Bridges with recommendations for immediate work on fracture critical members;
(2) Bridges with recommendations for immediate correction of scour or hydraulic problems;
(3) Bridges with condition ratings of 3 or less for the superstructure or substructure or appraisal ratings of 3 or less for waterway adequacy; and
(4) Bridges with recommendations for immediate work to prevent substantial reduction in the safe load capacity.
The FHWA has taken several actions to strengthen the National Bridge Inspection Standards (23 CFR 650, subpart C). All States are to take appropriate action to ensure that underwater bridge inspection programs areunderway. As part of the underwater program, bridge owners should establish a scour evaluation program to evaluate the adequacy of existing bridges to resist damage from scour. The essential elements of the scour program are:
(a) A screening process to identify those bridges that are most likely to be vulnerable to damage from scour and which should receive early attention.
(b) Engineering evaluations of existing bridges toetermine which bridges are scour critical; reporting the results of these evaluations in Item 113 of the FHWA Bridge Recording and Coding Guide.
(c) A plan of action for monitoring and providing countermeasures as appropriate for scour critical bridges.
(1) A 3-week course would be required for persons without a civil engineering degree and with less than 5 years bridge inspection experience.
(2) A 2-week course would be sufficient for civil engineering graduates or for those with more than 5 years bridge inspection experience.
(1) correction of NBIS deficiencies, or
(2) submission, for approval by the FHWA, of an aggressive, short-term plan to correct NBIS deficiencies.
(1) after 90 days from the date of notification are not complying with the NBIS frequency and load posting requirements and do not have a satisfactory plan for correcting the deficiencies, or
(2) are not carrying out the plan to correct NBIS deficiencies satisfactorily and on schedule.
In fulfilling the inspection requirements of the National Bridge Inspection Standards (23 CFR 650, subpart C), the FHWA gives guidance regarding the inspection of bridge piers and fendering systems. Each FHWA field office is requested to evaluate and emphasize the State inspection proceduresfor bridges over navigable waters. The evaluation should assure that the State inspection continues to include an assessment and evaluation of bridge piers and fendering systems for structural integrity.