FEDERAL-AID POLICY GUIDE
September 30, 1992, Transmittal 5
NS 23 CFR 650G
OPI: HNG-33
Listed are other considerations in the selection of candidates for discretionary bridge funds.
(a) Preliminary engineering is not considered an eligible item for discretionary bridge funds. States are encouraged to pay for this work from other categories.
(b) There is a reluctancy to allocate discretionary bridge funds for right-of-way expenses. Funding of right-of-way acquisition will be considered only when the State gives assurances that construction will begin on the segment involved no later than the third quarter of the next fiscal year.
(c) In evaluating new candidates as well as candidates funded in previous years, the highest priority will be given to those ready for construction in the first 3 quarters of that fiscal year.
Discretionary bridge funds are allocated for a specific phase or phases of a project as requested by the State. The funds are to be used for this phase or these phases only. If a State desires to transfer a portion of the allocated discretionary bridge funds to another phase of the project, a formal request for withdrawal and reallocation should be made through the Office of Engineering.