FHWA Nebraska Division Environmental Document Review Delivery
February 10, 2010 through October 23, 2014
Number of Submittals = 2,764
Average Review Time, Calendar Days = 7.45
INFORMATION: The typical environmental submittals that are prepared/approved by NDOR and submitted to FHWA for Categorical Exclusions (CE's) are: DR 53*, Biology review, Section 106 package, and the Categorical Exclusion (CE). If a project fits the stipulations of the 2008 Programmatic Agreement between FHWA-NE and NDOR, NDOR has the authority to approve the NEPA document without FHWA approval. These are referred to as PCE's. Likewise, FHWA has also provided programmatic approval authority to NDOR for certain actions under the Endangered Species Act(ESA) and Section 106 (historic preservation). Since there is no FHWA project-level approval for the projects and actions that are covered by these programmatic agreements, that project level documentation is not recorded on this list.
BASIC NEPA STEPS FOR PROJECTS: 1) NDOR approves and submits the DR53 to FHWA; NDOR/local sign program agreements and procure consultant (for local fed-aid projects); 2) NDOR/local govt. start NEPA; 3) NDOR/local complete tech reviews (ex, wetland, bio, and cultural resource); 4)NDOR submit bio and cultural tech docs to FHWA for agency consultation, when needed; 5) NDOR/local prepare NEPA doc; 6) NDOR review/approve NEPA doc; 7) NDOR submit NEPA doc to FHWA for review/acceptance (except for PCE's)
Project Name | Subject | Control No | Project No | Date Received | Date Completed | Action Time ** | Responsible party/pending action *** |
---|---|---|---|---|---|---|---|
I-80 Kiosks | PA - revised | 00645 | ITSN-115 | 6/6/2013 | 6/10/2013 | 4 | None |
Tracy Creek Bank | Monitoring Report | 713 | STWD-1044 | 07-Mar-11 | 21-Mar-11 | 14 | FHWA sent the material to the resource agency(s) for review/concurrrence, which takes up to 4 weeks. Once all tech reviews and concurrences complete, next step is for NDOR to review/approve the NEPA doc. If not a PCE, NDOR will submit CE to FHWA |
STWD Intersection Signage Project | Bio doc | 00772 | STWD-86 | 8/9/2012 | 8/16/2012 | 7 | NDOR/address FHWA comments and resubmit |
Statewide Interesection Signage | 106 and THPO concur req | 00772 | HRRR-STWD-86 | 11/30/2012 | 12/7/2012 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
STWD Intersection Signage | Bio doc - version 2 | 00772 | STWD-86 | 4/12/2013 | 4/22/2013 | 10 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Horizontal Curved Signing Project - Phase III | Bio doc review | 00787 | STWD-90 | 8/6/2012 | 8/16/2012 | 10 | NDOR/address FHWA comments and resubmit |
Horizontal Curved Signing | 106 concur req | 00787 | HRRR-STWD-90 | 11/30/2012 | 12/7/2012 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Horizontal Curved Signage - Phase 3 | Bio doc | 00787 | STWD-90 | 3/22/2013 | 4/5/2013 | 14 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Phase III Horizontal Curve Signing | SHPO concur req - revised | 00787 | STWD-90 | 9/26/2013 | 10/3/2013 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Statewide rural traf control dev | DR 53 | 850 | STWD-108 | 16-Feb-11 | 28-Feb-11 | 12 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Statewide Guardrail D-3 and 4 | DR 53 | 00864 | STWD-111 | 8/8/2013 | 8/16/2013 | 8 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Centerline Rumble Strips | DR 53 | 865 | HSIP-STWD-112 | 31-Aug-11 | 03-Sep-11 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Statewide Centerline Rumble Strips | Bio doc version 1 | 865 | STWD-112 | 1/18/2012 | 1/25/2012 | 7 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Advanced Railroad Signing | Bio doc - version 1 | 00868 | STWD-116 | 4/16/2013 | 4/30/2013 | 14 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
NE Hwy Hist Markers | DR 53 | 00875 | STWD-119 | 7/3/2012 | 7/12/2012 | 9 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Nebr Hwy Historical Markers - Statewide | SHPO concur req | 00875 | STWD-119 | 7/13/2012 | 7/24/2012 | 11 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
STWD Hwy Historical Markers | Bio doc version 1 | 00875 | STWD-119 | 8/13/2012 | 8/20/2012 | 7 | NDOR/address FHWA comments and resubmit |
STWD Highway Historical Markers | Bio doc version 1 | 00875 | STWD-119 | 12/21/2012 | 1/8/2013 | 18 | None |
Alvo North | DR 53 | 11450 | 632-108 | 8/23/2012 | 8/29/2012 | 6 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Alvo North | SHPO and THPO concur req | 11450 | 632-108 | 8/2/2013 | 8/7/2013 | 5 | NDOR/address FHWA comments and resubmit |
Crab Orchard Southwest | DR 53 | 11473 | 7049-11 | 19-May-11 | 27-May-11 | 8 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Barneston West | SHPO concur req | 11678 | 86-106 | 28-Mar-11 | 31-Mar-11 | 3 | FHWA sent the material to the resource agency(s) for review/concurrrence, which takes up to 4 weeks. Once all tech reviews and concurrences complete, next step is for NDOR to review/approve the NEPA doc. If not a PCE, NDOR will submit CE to FHWA |
Barneston West | Bio doc version 1 | 11678 | 86-106 | 10/27/2011 | 10/28/2011 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Barneston West | CE | 11678 | 86-106 | 1/26/2012 | 2/7/2012 | 12 | NDOR/address FHWA comments and resubmit |
Barneston West | CE - revised | 11678 | 86-106 | 2/27/2012 | 3/6/2012 | 8 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Adams Northwest | DR 53 | 11776 | 7034-18 | 1/12/2012 | 1/16/2012 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Adams NW Bridge | 106 concur req | 11776 | 7034-18 | 2/27/2013 | 3/1/2013 | 2 | None |
Seward South | DR 53 | 11781 | 7080-27 | 12-Sep-11 | 16-Sep-11 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Seward South | SHPO concur req | 11781 | 7080-27 | 8/23/2012 | 8/31/2012 | 8 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Wahoo Bypass | Cat Ex proposal request | 11801 | 772-1025 | 5/8/2012 | 6/27/2012 | 50 | NDOR/address FHWA comments and resubmit |
Cordova North | T&E Consultation Memo | 12002 | 3045-5 | 12-Jul-10 | 26-Jul-10 | 14 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Beaver Cross SW | Bio doc vers 1 | 12012 | 7080-40 | 08-Oct-10 | 13-Oct-10 | 5 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Beaver Crossing SW | DR 53 | 12012 | 7080-40 | 06-Dec-10 | 14-Dec-10 | 8 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Beaver Crossing SW | SHPO concur req | 12012 | 7080-40 | 27-Jun-11 | 28-Jun-11 | 1 | FHWA sent the material to the resource agency(s) for review/concurrrence, which takes up to 4 weeks. Once all tech reviews and concurrences complete, next step is for NDOR to review/approve the NEPA doc. If not a PCE, NDOR will submit CE to FHWA |
Beaver Crossing Southwest | CE | 12012 | 7080-40 | 14-Oct-11 | 17-Oct-11 | 3 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Beaver Crossing SW | CE | 12012 | 7080-40 | 11/9/2011 | 12/7/2011 | 28 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
South & East Beltway | NDOR draft letter for review | 12153 | 3300-1 | 12/6/2011 | 1/6/2012 | 31 | NDOR/address FHWA comments and resubmit |
Crete North | DR 53 | 12222 | 1031-108 | 07-Apr-11 | 07-Apr-11 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Crete North | Bio doc vers 1 | 12222 | 1031-108 | 07-Apr-11 | 07-Apr-11 | 0 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
In Wymore | Bio doc vers 1 | 12299 | 3265-5 | 14-Dec-10 | 17-Dec-10 | 3 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
In Wymore | DR 53 | 12299 | 3265-5 | 24-Jan-11 | 31-Jan-11 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
In Wymore | 106 letter | 12299 | 3265-5 | 09-May-11 | 13-May-11 | 4 | FHWA sent the material to the resource agency(s) for review/concurrrence, which takes up to 4 weeks. Once all tech reviews and concurrences complete, next step is for NDOR to review/approve the NEPA doc. If not a PCE, NDOR will submit CE to FHWA |
In Wymore | CE | 12299 | 3265-5 | 09-Sep-11 | 13-Sep-11 | 4 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
In Wymore | Design change Memo | 12299 | 3265-5 | 6/4/2012 | 6/11/2012 | 7 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Filley North | Bio doc vers 1 | 12300 | 3285-5 | 07-Jan-11 | 07-Jan-11 | 0 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Filley North | DR 53 | 12300 | 3285-5 | 24-Jan-11 | 31-Jan-11 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Filley North, Gage Co. | SHPO concur req | 12300 | 3285-5 | 13-Jun-11 | 23-Jun-11 | 10 | FHWA sent the material to the resource agency(s) for review/concurrrence, which takes up to 4 weeks. Once all tech reviews and concurrences complete, next step is for NDOR to review/approve the NEPA doc. If not a PCE, NDOR will submit CE to FHWA |
Filley North | Cat Ex | 12300 | 3285-5 | 2/2/2012 | 2/17/2012 | 15 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
I-80 Upgrade | bio doc | 12312 | 809-872 | 20-May-10 | 21-May-10 | 1 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
-80 Upgrade Lincoln - Omaha | Reeval | 12312 | 809-872 | 20-Aug-10 | 24-Aug-10 | 4 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Mahoney Park Intrch ramps | SHPO concur req | 12312 | 809-872 | 28-Mar-11 | 31-Mar-11 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
I-80 Upgrade | Bio doc reeval | 12312 | 809-872 | 25-Mar-11 | 01-Apr-11 | 7 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Nebraska City Northwest | DR 53 | 12347 | 7066-29 | 1/12/2012 | 1/16/2012 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Nebraska City Northwest | Bio doc version 1 | 12347 | 7066-29 | 10/3/2012 | 10/30/2012 | 27 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Nebraska City NW | SHPO and THPO concur - Arch Testing Plan | 12347 | 7066-29 | 8/2/2013 | 8/12/2013 | 10 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Nebraska City NW | Revised Testing Plan | 12347 | 7066-29 | 9/12/2013 | 9/13/2013 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Rouleau St, Rulo Bridge | Reeval Memo T&E change | 12381 | 1597-106 | 05-Apr-11 | 07-Apr-11 | 2 | NDOR/address FHWA comments and resubmit |
Rouleau Street, Rulo | T&E Reeval | 12381 | 1597-105 | 13-Apr-11 | 19-Apr-11 | 6 | NDOR/address FHWA comments and resubmit |
Waverly - Greenwood | CO 22 | 12457 | 809-842 | 1/17/2012 | 1/20/2012 | 3 | None |
US-77 - 56th St Interch to Waverly Interch | Scope Change memo | 12477 | 809-850 | 8/8/2012 | 8/15/2012 | 7 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
14th St Bridge, Lincoln | SHPO concur req | 12482 | 809-855 | 21-Mar-11 | 29-Mar-11 | 8 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
14th St Bridge, Lincoln | SHPO concur req | 12482 | 809-855 | 05-Apr-11 | 07-Apr-11 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
NW 56th to US-77 South | SHPO concur req | 12489 | 809-862 | 7/17/2012 | 7/26/2012 | 9 | NDOR/address FHWA comments and resubmit |
NW 56th to US077 South I-80 | SHPO concur req - re-eval | 12489 | 809-862 | 10/25/2012 | 11/9/2012 | 15 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
NW 56th - US-77 etc | Bio doc version 1 | 12489 | 809-862 | 2/26/2013 | 3/6/2013 | 8 | NDOR/address FHWA comments and resubmit |
NW 56th to US77 South, NW 48th Br, NW 56th Br | Bio doc - version 2 | 12489 | 809-862 | 4/16/2013 | 4/22/2013 | 6 | None |
Syracuse Southeast | DR 53 | 12510 | 7066-32 | 1/12/2012 | 1/16/2012 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Syracuse SE | SHPO and THPO concur req | 12510 | 7066-32 | 6/25/2012 | 6/27/2012 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Syracuse Southeast | Bio doc version 1 | 12510 | 7066-32 | 4/10/2013 | 4/22/2013 | 12 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Dorchester SE | Bio doc vers 1 | 12519 | 7076-16 | 20-Sep-10 | 29-Sep-10 | 9 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Dorechester Southeast | SHPO concur req | 12519 | 7076-16 | 01-Nov-10 | 08-Nov-10 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Dorchester SE | DR 53 | 12519 | 7076-16 | 10-Nov-10 | 12-Nov-10 | 2 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Denton East | SHPO concur req | 12541 | 3305-9 | 07-Dec-10 | 10-Dec-10 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Denton East | Bio doc vers 1 | 12541 | 3305-9 | 10-Dec-10 | 10-Dec-10 | 0 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Denton East | CE | 12541 | 3305-9 | 22-Aug-11 | 06-Sep-11 | 15 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
In Friend | DR 53 | 12577 | 2982-1 | 14-Jul-11 | 15-Jul-11 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
In Friend | Bio doc version 1 | 12577 | 2982-1 | 11/4/2011 | 11/9/2011 | 5 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
In Friend | SHPO concur request | 12577 | 2982-1 | 11/8/2011 | 11/14/2011 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
In Friend | CE | 12577 | 2982-1 | 1/30/2012 | 2/9/2012 | 10 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Lincoln south Beltway | public notice review | 12578 | 26-120 | 5/31/2013 | 5/31/2013 | 0 | None |
Greenwood Northeast | DR 53 | 12658 | 7013-10 | 12/22/2011 | 12/23/2011 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Greenwood Northeast | SHPO concur request | 12658 | 7013-10 | 5/14/2012 | 5/25/2012 | 11 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Greenwood Northeast | THPO concur req | 12658 | 7013-10 | 6/21/2012 | 6/26/2012 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Greenwood NE | Cat Ex | 12658 | 7013-10 | 5/28/2013 | 6/5/2013 | 8 | NDOR/address FHWA comments and resubmit |
Greenwood NE | CE rev | 12658 | 7013-10 | 8/8/2013 | 8/8/2013 | 0 | NDOR/address FHWA comments and resubmit |
Greenwood Northeast | 404 Info Rev | 12658 | 7013-10 | 9/10/2013 | 9/13/2013 | 3 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Greenwood Northeast | Cat Ex responses for review | 12658 | 7013-10 | 9/27/2013 | 10/1/2013 | 4 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Verdon NW | SHPO concur req | 12666 | 7074-23 | 7/6/2012 | 7/16/2012 | 10 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Verdon Northwest | Cat Ex | 12666 | 7074-23 | 10/1/2012 | 10/12/2012 | 11 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Verdon Northwest | Cat Ex | 12666 | 7074-23 | 11/2/2012 | 11/15/2012 | 13 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Pawee City SW | DR 53 | 12677 | 7067-16 | 1/3/2012 | 1/16/2012 | 13 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Pawnee City SW | SHPO concur req | 12677 | 7067-16 | 10/22/2012 | 10/23/2012 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Pawnee SW | Cat Ex - revised | 12677 | 7067-16 | 5/14/2013 | 5/23/2013 | 9 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
N Columbia Ave, Seward | DR 53 | 12693 | 6759-2 | 27-Dec-10 | 07-Jan-11 | 11 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Columbia Ave, Seward | SHPO concur request | 12693 | 6759-2 | 12/1/2011 | 12/8/2011 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Columbia Ave, Seward | Bio doc version 1 | 12693 | 6759-2 | 1/23/2012 | 2/1/2012 | 9 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
N. Columbia Ave | Cat Ex | 12693 | 6759-2 | 6/27/2012 | 7/13/2012 | 16 | NDOR/address FHWA comments and resubmit |
N Columbia Ave, Seward | Cat Ex | 12693 | 6759-2 | 8/9/2012 | 8/14/2012 | 5 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
SW 40th St, Lincoln | Reeval | 12744 | 5267-1 | 20-Sep-10 | 29-Sep-10 | 9 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Southwest 40th Street | Reevaluation Memo | 12744 | 5267-1 | 3/20/2012 | 4/5/2012 | 16 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Brock Southwest | DR 53 | 12746 | 7064-13 | 24-Jan-11 | 31-Jan-11 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Weeping Water SE | Bio Assessment | 12764 | 7013-12 | 12-Jul-10 | 26-Jul-10 | 14 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Weeping Water SE | DR53 | 12764 | 7013(12) | 06-Dec-10 | 15-Dec-10 | 9 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Weeping Water SE | SHPO concur req | 12764 | 7013-12 | 25-Apr-11 | 25-Apr-11 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Weeping Water Southeast | CE | 12764 | 7013-12 | 10/21/2011 | 10/28/2011 | 7 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Burchard South | Bio doc vers 1 | 12773 | 87-113 | 14-Apr-11 | 19-Apr-11 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Burchard South | SHPO concur req | 12773 | 87-113 | 28-Apr-11 | 02-May-11 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Burchard South | CE | 12773 | 87-113 | 16-Sep-11 | 20-Sep-11 | 4 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Haymarket Ball Park Trail | Memo | 12781 | 55-151 | 09-Jun-10 | 09-Jun-10 | 0 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Haymarket Ballpark Trail | SHPO concur req | 12781 | 55-151 | 5/20/2013 | 5/31/2013 | 11 | NDOR/address FHWA comments and resubmit |
Haymarket Ball Park Trail | Re-Eval Memo review | 12781 | 55-151 | 7/30/2013 | 8/1/2013 | 2 | NDOR/address FHWA comments and resubmit |
Hay Market Ball Trail | Re Eval | 12781 | 55-151 | 8/6/2013 | 8/7/2013 | 1 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Syracuse Southwest | DR 53 | 12785 | 7066-43 | 1/12/2012 | 1/16/2012 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Syracuse SW | SHPO, THPO concur req | 12785 | 7066-43 | 8/14/2012 | 8/21/2012 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Sprague East | Bio doc vers 1 | 12786 | 3280-4 | 21-Sep-10 | 29-Sep-10 | 8 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Sprague East | SHPO concur req | 12786 | 3280-4 | 17-Nov-10 | 23-Nov-10 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Sprague East | DR 53 | 12786 | 3280-4 | 17-Dec-10 | 23-Dec-10 | 6 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Sprague East | CE | 12786 | 3280-4 | 22-Jul-11 | 03-Aug-11 | 12 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Sprague East | CE - vers 2 | 12786 | 3280-4 | 09-Aug-11 | 09-Aug-11 | 0 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Ithaca - Ashland | DR 53 | 12831 | 666-104 | 12-Aug-11 | 17-Aug-11 | 5 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Ithaca - Ashland | SHPO concur req | 12831 | 666-104 | 17-Aug-11 | 17-Aug-11 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Ithaca - Ashland | Bio doc version 1 | 12831 | 666-104 | 8/30/2012 | 8/31/2012 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Table Rock Southeast | SHPO concur req | 12835 | 7067-22 | 6/26/2012 | 6/28/2012 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Friend South | DR 53 | 12850 | 7076-18 | 15-Dec-10 | 17-Dec-10 | 2 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Friend South | Bio doc vers 1 | 12850 | 7076-18 | 20-Jan-11 | 31-Jan-11 | 11 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Friend South | SHPO concur req | 12850 | 7076-18 | 18-Apr-11 | 22-Apr-11 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Friend South | CE | 12850 | 7076-18 | 16-Sep-11 | 20-Sep-11 | 4 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Table Rock SE | DR 53 | 12853 | 7067-22 | 1/3/2012 | 1/16/2012 | 13 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Stella SE | DR 53 | 12855 | 7074-24 | 12/20/2011 | 12/23/2011 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Stella SE | SHPO concur req | 12855 | 7074-24 | 7/10/2012 | 7/16/2012 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Stella SE | Detour rte change proposal | 12855 | 7074-24 | 9/12/2012 | 9/17/2012 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Stella Southeast | Cat Ex | 12855 | 7074-24 | 2/20/2013 | 3/4/2013 | 12 | None |
Stella Southeast | Cat Ex - revised | 12855 | 7074-24 | 3/15/2013 | 3/22/2013 | 7 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Hickman North | DR 53 | 12859 | 3265-9 | 25-Feb-11 | 01-Mar-11 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Hickman North | SHPO concur req | 12859 | 3265-9 | 21-Mar-11 | 21-Mar-11 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Hickman North | Bio doc vers 1 | 12859 | 3265-9 | 13-May-11 | 18-May-11 | 5 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Sterling Southeast | DR 53 | 12860 | 7049-22 | 20-May-11 | 27-May-11 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Sterling Southeast | SHPO concur request | 12860 | 7049-22 | 11/3/2011 | 11/14/2011 | 11 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Sterling Southeast | Bio doc version 1 | 12860 | 7049-22 | 12/7/2011 | 12/14/2011 | 7 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Sterling Southeast | Cat Ex | 12860 | 7049-22 | 4/17/2012 | 5/8/2012 | 21 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Sterling SE Bridge, Johnson County | Congr inq - Noise Analysis | 12860 | 7049-22 | 6/29/2012 | 7/6/2012 | 7 | None |
Sterling Southeast | Cat Ex | 12860 | 7049-22 | 9/27/2012 | 10/12/2012 | 15 | NDOR/address FHWA comments and resubmit |
Malcolm Souteast | NEPA | 12864 | 7055-102 | 15-Sep-10 | 23-Sep-10 | 8 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
In Seward | Bio doc vers 1 | 12876 | 346-136 | 05-Jan-11 | 07-Jan-11 | 2 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
In Seward | SHPO concur req | 12876 | 346-136 | 24-May-11 | 27-May-11 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
In Seward | SHPO concur req for 4(f) | 12876 | 346-136 | 6/12/2012 | 6/25/2012 | 13 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
In Seward | 4(f) | 12876 | 346-136 | 8/9/2012 | 8/17/2012 | 8 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
In Seward | Cat Ex | 12876 | 346-136 | 9/7/2012 | 9/17/2012 | 10 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Jamacia trail | 4(f) exemp req | 12879 | 55-160 | 22-Apr-10 | 28-Apr-10 | 6 | NDOR/address FHWA comments and resubmit |
Jamaica North Trail | Re-eval - 3 yr lapse | 12879 | 55-160 | 9/23/2013 | 9/25/2013 | 2 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Wahoo Trail - Maple Street North | Re-eval follow-up review | 12880 | 78-26 | 6/19/2013 | 6/19/2013 | 0 | NDOR/address FHWA comments and resubmit |
Yutan Trail, Phase 1 | DR 53 | 12881 | 78-27 | 06-Oct-11 | 07-Oct-11 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Yutan Trail System - Phase 1 | Bio doc version 1 | 12881 | 78-27 | 7/17/2012 | 7/26/2012 | 9 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Yutan Trail | SHPO concur req | 12881 | 78-27 | 8/2/2012 | 8/16/2012 | 14 | NDOR/address FHWA comments and resubmit |
Yutan Trail | 4(f) Except req | 12881 | 78-27 | 9/5/2012 | 9/17/2012 | 12 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Yutan Trail | Cat Ex | 12881 | 78-27 | 8/1/2013 | 8/2/2013 | 1 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Yutan Trail | Cat Ex rev | 12881 | 78-27 | 9/23/2013 | 10/1/2013 | 8 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Blue Rvr Br, Crete | DR 53 | 12886 | 7076-22 | 06-Dec-10 | 15-Dec-10 | 9 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
13th St./Blue River Bridge, Crete | SHPO concur req | 12886 | 7076-22 | 6/15/2012 | 6/26/2012 | 11 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
In Crete - 13th Street Bridge | Cat Ex | 12886 | 7076-22 | 5/28/2013 | 6/3/2013 | 6 | NDOR/address FHWA comments and resubmit |
Utica - Goehner | DR 53 | 12907 | 808-145 | 14-Mar-11 | 15-Mar-11 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Utica - Goehner | Biio doc | 12907 | 808-145 | 3/26/2013 | 4/5/2013 | 10 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Super St, I-180 E Ramp | Bio doc vers 1 | 12928 | 5254-8 | 12-Nov-10 | 12-Nov-10 | 0 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Superior St, I-180 E Ramp Safety | DR 53 | 12928 | 5254-8 | 24-Jan-11 | 31-Jan-11 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Superior at I-180, Lincoln | SHPO concur req | 12928 | 5254-8 | 29-Mar-11 | 31-Mar-11 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Superior Street - I-180 East ramp | 4(f) exception concur request | 12928 | 5254-8 | 1/23/2012 | 2/1/2012 | 9 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Superior Street & I-80 East Ramp Safety | Cat Ex | 12928 | 5254-8 | 3/7/2012 | 3/15/2012 | 8 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Humboldt East & West | Bio Doc | 12936 | 47-105 | 26-Apr-11 | 27-Apr-11 | 1 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Humbolt East & West | SHPO concur req | 12936 | 47-105 | 19-Jul-11 | 20-Jul-11 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
4th and Corso Overlay | DR53 | 12938 | 06-Dec-10 | 14-Dec-10 | 8 | NDOR (or LPA) / Must prepare technical and NEPA documentation | |
4th Corso Overlay | Bio doc vers 1 | 12938 | 6217-3 | 24-Jan-11 | 31-Jan-11 | 7 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
4th Corso, Nebr City | Project Scope Change | 12938 | 6217-3 | 8/2/2012 | 8/9/2012 | 7 | NDOR/address FHWA comments and resubmit |
4th Corso, NE City | Change of Project Scope review | 12938 | 6217-3 | 9/20/2012 | 10/9/2012 | 19 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
N 14th St, EB On-ramp to US-6 | DR 53 | 12944 | 5227-7 | 2/24/2012 | 3/7/2012 | 12 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Lincoln Rosa Parks Way Trail | NEPA Determ | 12945 | 55-164 | 23-Aug-10 | 02-Sep-10 | 10 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Lincoln West O Historic | DR 53 | 12946 | 5266-2 | 25-Oct-10 | 26-Oct-10 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Lincoln West O Hist Hwy | Bio doc vers 1 | 12946 | 5266-2 | 23-Dec-10 | 27-Dec-10 | 4 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Lincoln West O St Hist Hwy | SHPO concur req | 12946 | 5266-2 | 05-Jan-11 | 07-Jan-11 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Lincoln West O Street | SHPO concur req | 12946 | 5266-2 | 10-Feb-11 | 16-Feb-11 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
West O, Lincoln | SHPO concur req | 12946 | 5266-2 | 22-Feb-11 | 22-Feb-11 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Lincoln West O Street | CE | 12946 | 5266-2 | 1/24/2012 | 2/6/2012 | 13 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Lincoln West O Street | Cat Ex | 12946 | 5266-2 | 2/8/2012 | 2/17/2012 | 9 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Lincoln West O Historic Hwy | SHPO Plans review | 12946 | 5266-2 | 9/7/2012 | 9/14/2012 | 7 | NDOR/address FHWA comments and resubmit |
Lincoln West O Historic Highway | SHPO concur req - plan review | 12946 | 5266-2 | 10/18/2012 | 10/23/2012 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
us6/n103 roundabout | concur req | 12953 | 66-159 | 16-Sep-10 | 01-Oct-10 | 15 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
US-6/N-103 intersection | NEPA determ 1st subm | 12953 | 66-159 | 01-Oct-10 | 04-Oct-10 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
US-6, N-103 intersection | Bio doc vers 1 | 12953 | 66-159 | 29-Oct-10 | 02-Nov-10 | 4 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
US-6/N-103 intersec impro | CE | 12953 | 66-159 | 09-Dec-10 | 16-Dec-10 | 7 | NDOR/address FHWA comments and resubmit |
US-6/N-103 intersection | NEPA determ 1st subm w Add Info | 12953 | 66-159 | 12-Jan-11 | 27-Jan-11 | 15 | NDOR/address FHWA comments and resubmit |
Jct US-6/N-103 intersect | Sum of Alt & Citizn com V-2 | 12953 | 66-159 | 01-Feb-11 | 02-Feb-11 | 1 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
US-6/N-103 inters impr | CE - revised | 12953 | 66-159 | 07-Feb-11 | 07-Feb-11 | 0 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Otoe Creek Bridge | SHPO Concur req | 12957 | 772-159 | 16-Mar-11 | 16-Mar-11 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Oak Creek Bridge | Bio doc vers 1 | 12957 | 772-159 | 16-May-11 | 18-May-11 | 2 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Otoe Creek Bridge N | CE | 12957 | 772-159 | 19-Jul-11 | 20-Jul-11 | 1 | NDOR/address FHWA comments and resubmit |
Otoe Creek Bridge N, Jct N-64 | CE subm 2 | 12957 | 772-159 | 26-Jul-11 | 01-Aug-11 | 6 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Goehner - Milford | DR 53 | 12961 | 808-147 | 03-Feb-11 | 03-Feb-11 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Goehner to Milford | Bio doc vers 1 | 12961 | 808-147 | 07-Mar-11 | 08-Mar-11 | 1 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Goehner - Milford | Reeval Scope Change | 12961 | 808-147 | 19-May-11 | 27-May-11 | 8 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Lincoln East | DR 53 | 12975 | 346-141 | 11/29/2011 | 12/5/2011 | 6 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Lincoln East | SHPO and THPO concur req | 12975 | 346-141 | 8/28/2012 | 8/31/2012 | 3 | NDOR/address FHWA comments and resubmit |
Lincoln East | SHPO/THPO concur req - revised | 12975 | 346-141 | 9/10/2012 | 9/14/2012 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Brainard East & West | DR 53 | 12980 | 926-120 | 1/22/2013 | 1/25/2013 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Mead - Utan | DR 53 | 12982 | 926-121 | 1/22/2013 | 1/25/2013 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Mead to Yutan | SHPO concur req | 12982 | 926-121 | 4/17/2013 | 4/22/2013 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Salem - Falls City | DR 53 | 12986 | 87-115 | 2/20/2013 | 2/22/2013 | 2 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
N-63 to N-50 | DR 53 | 12987 | 347-125 | 11/25/2011 | 12/5/2011 | 10 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Wilber West | Bio doc version 1 | 12990 | 416-113 | 10/25/2011 | 10/28/2011 | 3 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Auburn East | SHPO concur req | 12994 | 1366-119 | 11-Oct-11 | 13-Oct-11 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Auburn East | THPO and SHPO concur - supplemental | 12994 | 1367-126 | 8/23/2013 | 8/27/2013 | 4 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Auburn East | SHPO Suppl revised | 12994 | 1367-126 | 9/5/2013 | 9/6/2013 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Dwight to N-79 | Bio Assessment | 13018 | 666-105 | 12-Jul-10 | 23-Jul-10 | 11 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Dwight - N-79; Dwight East Bridges, N-15 - Dwight | DR-53 | 13018 | 666-105 | 7/17/2013 | 7/22/2013 | 5 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
N-64 to Schuyler | DR 53 | 13019 | 152-122 | 14-Mar-11 | 15-Mar-11 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Brock NW | DR 53 | 13024 | 7064-19 | 12-Jul-11 | 19-Jul-11 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Brock Northwest | Bio doc version 1 | 13024 | 7064-19 | 11/4/2011 | 11/10/2011 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Brock NW | SHPO concur req | 13024 | 7064-19 | 7/9/2012 | 7/16/2012 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Ulysses Spur | DR 53 | 13029 | S12C-105 | 12/7/2011 | 12/15/2011 | 8 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Preston North & South | DR 53 | 13031 | 3615-8 | 29-Aug-11 | 06-Sep-11 | 8 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Preston North & South | SHPO concur request | 13031 | 3615-8 | 1/30/2012 | 2/3/2012 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Preston North & South | 106 Tribal Coord | 13031 | 3615-8 | 1/30/2012 | 2/3/2012 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Preston North and South | CE | 13031 | 3615-8 | 3/29/2012 | 4/23/2012 | 25 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
N-112 - Beatrice | DR 53 | 13034 | 771-130 | 11/15/2011 | 11/23/2011 | 8 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
N-112 - Beatrice | SHPO concur req | 13034 | 771-130 | 7/9/2012 | 7/16/2012 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
N-112 to Beatrice | Cat Ex | 13034 | 771-130 | 10/9/2012 | 10/26/2012 | 17 | NDOR/address FHWA comments and resubmit |
N-112 - Beatrice | Cat Ex - 2nd submittal | 13034 | 771-130 | 2/21/2013 | 3/5/2013 | 12 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Sterling East | DR 53 | 13045 | 417-102 | 11/15/2011 | 11/17/2011 | 2 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Sterling East | SHPO concur request | 13045 | 417-102 | 5/18/2012 | 5/25/2012 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Sterling East | SHPO Supplemental | 13045 | 417-102 | 7/1/2013 | 7/8/2013 | 7 | NDOR/address FHWA comments and resubmit |
Sterling East | Rev 106 Sterling East | 13045 | 417-102 | 7/12/2013 | 7/12/2013 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
US-77 to Platte River | SHPO concur req | 13052 | 646-105 | 4/17/2013 | 4/22/2013 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Nebr. City Steinhart Park Trl | DR 53 | 13055 | 66-34 | 13-Oct-10 | 13-Oct-10 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Steinhart Park Trail | Bio Doc vers 1 | 13055 | 66-34 | 20-Dec-10 | 27-Dec-10 | 7 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Steinhart Park Trail Phase II | SHPO Concur req | 13055 | 66-34 | 16-Mar-11 | 16-Mar-11 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Steinhart Park Trail Phase II | SHPO concur request | 13055 | 66-34 | 5/23/2012 | 6/8/2012 | 16 | NDOR/address FHWA comments and resubmit |
Steinhart Trail Phs II | SHPO concur req | 13055 | 66-34 | 7/11/2012 | 7/24/2012 | 13 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Steinhart Park Trail Phase II | SHPO rev; NPS coordination | 13055 | 66-34 | 8/6/2012 | 8/16/2012 | 10 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Steinhart Park Trail Phase II | 4(f) determination | 13055 | 66-34 | 3/25/2013 | 4/2/2013 | 8 | NDOR/address FHWA comments and resubmit |
Steinhart Park Trail Phase II | 4(f) | 13055 | 66-34 | 4/25/2013 | 5/13/2013 | 18 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Steinhart Park Trail Phase II | Section 4(f) | 13055 | 66-34 | 8/30/2013 | 9/5/2013 | 6 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Beatrice Homestead Trail | NEPA det form | 13059 | 34-38 | 15-Sep-10 | 23-Sep-10 | 8 | NDOR to address FHWA comments and resubmit |
Beatrice Homestead Trl | NEPA Determ form | 13059 | 34-38 | 27-Sep-10 | 01-Oct-10 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Seward West Trail | SHPO concur req | 13060 | 80-32 | 4/5/2012 | 4/25/2012 | 20 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
In Auburn | SHPO concur req | 13062 | 1367-123 | 24-May-11 | 27-May-11 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Wyuka Stables Restoration | Bio doc vers 1 | 13063 | 55-170 | 04-Aug-11 | 05-Aug-11 | 1 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Wyuka Stable Restoration | SHPO concur req | 13063 | 55-170 | 13-Sep-11 | 16-Sep-11 | 3 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Wyuka Stable Restoration | SHPO concur request | 13063 | 55-170 | 10/24/2011 | 11/14/2011 | 21 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Wyuka Stable Restoration | Wyuka MOA | 13063 | 55-170 | 12/21/2011 | 1/17/2012 | 27 | NDOR/address FHWA comments and resubmit |
Wyuka Stables Renovation | Cat Ex | 13063 | 55-170 | 4/10/2012 | 4/27/2012 | 17 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Wyuka Stables | Cat Ex - revised | 13063 | 55-170 | 6/12/2012 | 6/14/2012 | 2 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Wyuka Stables | SHPO concur req | 13063 | 55-170 | 8/15/2012 | 8/21/2012 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Wyuka Stables Renovation | SHPO final plan review | 13063 | 55-170 | 3/27/2013 | 4/5/2013 | 9 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Cavett Connector Trail | DR 53 | 13079 | 55-172 | 10-Jun-11 | 16-Jun-11 | 6 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Lincoln Cavett Connector Trail | SHPO concur req | 13079 | 55-172 | 6/11/2012 | 6/26/2012 | 15 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Lincoln Cavett Connector Trail | 4(f) excep req | 13079 | 55-172 | 8/28/2012 | 8/31/2012 | 3 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Lincoln Cavett Connector Trail | Cat Ex | 13079 | 55-172 | 2/8/2013 | 2/27/2013 | 19 | NDOR/address FHWA comments and resubmit |
Lincoln Cavett Connector Trail | Cat Ex revised | 13079 | 55-172 | 5/17/2013 | 5/31/2013 | 14 | NDOR/address FHWA comments and resubmit |
Lincoln Cavett Connector Trail | De minimis review | 13079 | 55-172 | 7/30/2013 | 8/1/2013 | 2 | NDOR/address FHWA comments and resubmit |
Cavett Trail | Section 4(f) - Public Meeting minutes | 13079 | 55-172 | 9/5/2013 | 9/11/2013 | 6 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Beatrice Main St Signage | DR 53 | 13080 | 34-39 | 23-Nov-10 | 24-Nov-10 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Bio doc vers 1 | Beatrice Main Histor Byway Sign | 13080 | 34-39 | 28-Feb-11 | 01-Mar-11 | 1 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Beatrice Main St Hist Byway Sign | SHPO concur req | 13080 | 34-39 | 25-Mar-11 | 31-Mar-11 | 6 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Beatrice Main St Hist Byway Sign | SHPO concur req | 13080 | 34-39 | 18-Apr-11 | 21-Apr-11 | 3 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Beatrice Main Street Historic Byway Signage | 106 Concur | 13080 | 34-39 | 26-Apr-11 | 27-Apr-11 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Kansas Line - W Jct N-8 | DR 53 | 13083 | 1121-103 | 11/15/2011 | 11/17/2011 | 2 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Kansas Line - W. Jct. N-8 | Cat Ex | 13083 | 1121-103 | 8/16/2012 | 8/20/2012 | 4 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Furnas St - Silver St, Ashland | DR 53 | 13084 | 666-107 | 11/28/2011 | 12/5/2011 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Furnas St - Silver St, Ashland | SHPO concur req | 13084 | 666-107 | 7/2/2012 | 7/13/2012 | 11 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Furnas - Silver In Ashland | SHPO concur req - revised | 13084 | 666-107 | 9/30/2013 | 10/8/2013 | 8 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Beatrice Wide Resurf. | DR 53 | 13086 | 6108-1 | 06-Dec-10 | 15-Dec-10 | 9 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Beatrice Citywide resurf | DR 53 | 13086 | 6108-1 | 18-Jan-11 | 31-Jan-11 | 13 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Beatrice City Wide Resurfacing | Bio doc vers 1 | 13086 | 6108-1 | 10/27/2011 | 10/28/2011 | 1 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Beatrice City Wide Resurfacing | SHPO concur request | 13086 | 6108-1 | 11/30/2011 | 11/30/2011 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
N-15 west | bio doc | 13087 | 86(114) | 16-Sep-10 | 23-Sep-10 | 7 | NDOR/address FHWA comments and resubmit |
S. Jct. N-15 West | Bio doc | 13087 | 86-114 | 17-Sep-10 | 23-Sep-10 | 6 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
BNSF/Middle Creek | SHPO Concur Req | 13089 | 772-161 | 11-Jul-11 | 11-Jul-11 | 0 | NDOR/address FHWA comments and resubmit |
BNSF-Middle Creek, Lincoln | Bio doc version 1 | 13089 | 772-161 | 2/3/2012 | 2/17/2012 | 14 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
BNSF/Middle Creek, Lincoln | 106 supplemental consult | 13089 | 772-161 | 12/20/2012 | 12/26/2012 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
BNSF-Middle Creek, Lincoln | Bio doc scope change memo | 13089 | 772-161 | 2/28/2013 | 3/6/2013 | 6 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
BNSF - Middle Creek, Lincoln | Bio doc version 2 | 13089 | 772-161 | 4/29/2013 | 5/14/2013 | 15 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
BNSF-Middle Creek, Lincoln | SHPO - 2nd Supplemental | 13089 | 772-161 | 6/4/2013 | 6/5/2013 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
BNSF/Middle Creek, Lincoln | Cat Ex | 13089 | 772-161 | 6/18/2013 | 6/24/2013 | 6 | NDOR/address FHWA comments and resubmit |
BNSF-Middle Creek, Lincoln | Cat Ex - revised | 13089 | 772-161 | 7/18/2013 | 7/23/2013 | 5 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
US-6/SW 40th Street | SHPO Concur Req | 13093 | 66-161 | 12-Jan-11 | 31-Jan-11 | 19 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
US-6, W. 40th St., Lincoln | Bio doc version 1 | 13093 | 66-161 | 10/1/2012 | 10/24/2012 | 23 | NDOR/address FHWA comments and resubmit |
US-6/W. 40th Street, Lincoln | Bio doc - version 2 | 13093 | 66-161 | 1/14/2013 | 1/17/2013 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
US-6 to SW 40th | Cat Ex | 13093 | 66-161 | 6/13/2013 | 6/26/2013 | 13 | NDOR/address FHWA comments and resubmit |
US-6 40th Street | Cat Ex - revised | 13093 | 66-161 | 7/31/2013 | 8/1/2013 | 1 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Nemaha - E. Jct. US-136 | DR 53 | 13094 | 671-117 | 12/15/2011 | 12/20/2011 | 5 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Nemaha - E. Jct. US-136 | SHPO & THPO concur req | 13094 | 671-117 | 3/11/2013 | 3/13/2013 | 2 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
W. Jct. US-136 - Peru Spur | DR 53 | 13095 | 671-118 | 4/5/2012 | 4/26/2012 | 21 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
W Jct US-136 - Peru Spur | SHPO and THPO concur req | 13095 | 671-118 | 3/6/2013 | 3/6/2013 | 0 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Lincoln Citywide Durable | Bio doc version 1 | 13096 | 5239-8 | 16-Jun-10 | 21-Jun-10 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
OA 50 Challenge proj | Bio doc version 1 | 13097 | 5221-3 | 18-Jun-10 | 21-Jun-10 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Seward North | DR 53 | 13099 | 152-121 | 18-Apr-11 | 21-Apr-11 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Goehner West | Bio doc vers 1 | 13107 | 808-149 | 02-Nov-10 | 02-Nov-10 | 0 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Milford to Airpark | DR 53 | 13108 | 808-515 | 04-Apr-11 | 11-Apr-11 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Milford - Air Park | Bio doc vers 1 | 13108 | 808-515 | 08-Apr-11 | 12-Apr-11 | 4 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Goehner - Air Park | DR 53 | 13110 | 808-150 | 11/2/2012 | 11/15/2012 | 13 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
27th St Interchange Lincoln | DR 53 | 13111 | 809-74 | 2/8/2013 | 2/11/2013 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Airpark W-Jct, US-77 Lincoln | PCA | 13113 | 809-58 | 02-Feb-11 | 02-Feb-11 | 0 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Airpark W, Jct US-77 | Bio doc vers 1 | 13113 | 809-58 | 01-Mar-11 | 02-Mar-11 | 1 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
I-80 to Cornhusker | DR 53 | 13116 | 1809-1 | 6/7/2013 | 6/10/2013 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Nebraska City North | DR 53 | 13123 | 752-171 | 28-Jul-11 | 03-Aug-11 | 6 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Nebraska City North | Bio doc version 1 | 13123 | 752-171 | 8/28/2012 | 8/31/2012 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Nebraska City North | 106 and THPO concur req | 13123 | 752-171 | 11/28/2012 | 12/3/2012 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Nebraska City North | Cat Ex | 13123 | 752-171 | 3/5/2013 | 3/6/2013 | 1 | NDOR/address FHWA comments and resubmit |
Nebraska City North | Cat Ex - revised | 13123 | 752-171 | 3/18/2013 | 3/27/2013 | 9 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Beatrice Museum and 2nd St Historical Preservation | DR-53 | 13127 | 6105-6 | 15-Sep-10 | 22-Sep-10 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
2nd St-Court to Ella, Beatrice | SHPO concur req | 13127 | 6105-6 | 26-Aug-11 | 14-Sep-11 | 19 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
2nd St, Court to Ella, Beatrice | Bio doc version 1 | 13127 | 6105-6 | 10/31/2011 | 11/2/2011 | 2 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Court to Ella, Beatrice | 4(f) | 13127 | 6105-6 | 2/1/2012 | 2/14/2012 | 13 | NDOR/address FHWA comments and resubmit |
2nd St, Court - Ella | 4(f) exception comments | 13127 | 6105-6 | 2/29/2012 | 3/8/2012 | 8 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
2nd Street, Court - Ella | Cat Ex | 13127 | 6105-6 | 6/27/2012 | 7/2/2012 | 5 | NDOR/address FHWA comments and resubmit |
Beatrice Museum - 2nd St, Court - Ella | SHPO re-consult | 13127 | 6105-6 | 8/30/2012 | 8/31/2012 | 1 | NDOR/address FHWA comments and resubmit |
Beatrice Museum - 2nd to Court | SHPO concur req - revised | 13127 | 6105-6 | 9/20/2012 | 10/11/2012 | 21 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Beatrice Museum - 2nd St, Court to Ella | Cat Ex | 13127 | 6105-6 | 8/20/2013 | 8/22/2013 | 2 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Alvo - I-80 | Bio doc vers 1 | 13131 | 632-115 | 28-Sep-10 | 01-Oct-10 | 3 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Hickman Road Trl Connect | DR 53 | 13134 | 55-174 | 18-Jan-11 | 31-Jan-11 | 13 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Hickman Road Trail | SHPO concur req | 13134 | 55-174 | 8/15/2012 | 8/20/2012 | 5 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Hickman Road Trail Connection | 106 concur req | 13134 | 55-174 | 11/21/2012 | 12/3/2012 | 12 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Seward East Bridges | DR 53 | 13136 | 808-153 | 06-Jul-11 | 11-Jul-11 | 5 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Anti-Icing System Installation projects | Bio Doc - Batched Anti-Icing System Install | 13136 | 808-153 | 5/7/2013 | 5/14/2013 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Seward East Bridges - Seward County | SHPO re-consult | 13136 | 808-153 | 6/28/2013 | 7/3/2013 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Seward East Bridges | bio Scope Change Memo | 13136 | 808-153 | 7/2/2013 | 7/3/2013 | 1 | NDOR/address FHWA comments and resubmit |
Seward East Bridges | Rev Bio, | 13136 | 808-153 | 7/16/2013 | 7/16/2013 | 0 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Seward Bridges Deicing | CE rev | 13136 | 808-153 | 8/9/2013 | 8/14/2013 | 5 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
27th & Leighton Viad. | DR 53 | 13137 | 5231-13 | 11-Nov-10 | 12-Nov-10 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
27th & Leighton Viad Rehab | Bio doc vers 1 | 13137 | 5231-13 | 17-Oct-11 | 18-Oct-11 | 1 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
27th & Leighton Viaduct Rehabilitation | SHPO concur request | 13137 | 5231-13 | 12/7/2011 | 12/9/2011 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Lincoln Citywd resurf. | DR 53 | 13138 | 5228-4 | 11-Nov-10 | 12-Nov-10 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Lincoln Citywide Resurfacing | SHPO concur request | 13138 | 5228-4 | 1/6/2012 | 1/17/2012 | 11 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Lincoln City Street Resurfacing | Bio doc version 1 | 13138 | 5228-4 | 2/22/2012 | 3/8/2012 | 15 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Lincoln Citywide Resurfacing | Cat Ex | 13138 | 5228-4 | 6/7/2012 | 6/12/2012 | 5 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Lincoln Citywide Resurfacing | Cat Ex - version 2 | 13138 | 5228-4 | 8/3/2012 | 8/3/2012 | 0 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Lincoln Citywide Resurfacing | SHPO supplemental concur req | 13138 | 5228-4 | 5/8/2013 | 5/8/2013 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Lincoln Microsurfacing | DR 53 | 13139 | 5249-7 | 09-Nov-10 | 12-Nov-10 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Lincoln Streets Microsurf | Bio doc vers 1 | 13139 | 5249-7 | 05-Jan-11 | 06-Jan-11 | 1 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Lincoln Downtown Resurf | DR 53 | 13140 | 5230-2 | 04-Nov-10 | 08-Nov-10 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Lincoln Dwntwn Str Resurf | Bio doc vers 1 | 13140 | 5230-2 | 05-Jan-11 | 06-Jan-11 | 1 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
56th, Shadow Pines - Old Cheney | NEPA memo | 13141 | 5241-5 | 25-Mar-11 | 28-Mar-11 | 3 | NDOR/address FHWA comments and resubmit |
South 56th, Shadow Pines to Old Cheney | SHPO concur request | 13141 | 5241-5 | 5/4/2012 | 5/9/2012 | 5 | NDOR/address FHWA comments and resubmit |
South 56th, Shadow Pines to Old Cheney | SHPO concur req - revised | 13141 | 5241-5 | 6/28/2012 | 7/2/2012 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
S. 56th - Old Cheney to Shadow Pines Drive | Noise Study comments | 13141 | 5241-5 | 11/20/2012 | 12/26/2012 | 36 | NDOR/address FHWA comments and resubmit |
56th St, Shadow Pines to Old Cheney | 4(f) Exception | 13141 | 5241-5 | 1/10/2013 | 1/14/2013 | 4 | None |
S 56th - Shadow Pines to Old Cheney | EA - Re-eval | 13141 | 5241-5 | 5/20/2013 | 6/12/2013 | 23 | NDOR/address FHWA comments and resubmit |
56th St, Shadow Pines to Old Cheney | EA Re-eval | 13141 | 5241-5 | 8/13/2013 | 8/19/2013 | 6 | NDOR/address FHWA comments and resubmit |
56th Old Cheney to Shadow Pines | EA Re-Eval rev | 13141 | 5241-5 | 8/23/2013 | 9/4/2013 | 12 | NDOR/prepare for public outreach (if document is a DEA, the outreach is a hearing) |
Pleasant Dale N and S | DR-53 | 13142 | 1032-103 | 7/18/2013 | 7/23/2013 | 5 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Wahoo Northwest | DR 53 | 13143 | 78-30 | 09-Jun-11 | 16-Jun-11 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Brock N Brdg Repair | DR 53 | 13145 | ER 3675-7 | 27-Dec-10 | 06-Jan-11 | 10 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
NE Butler Co Brg Repair | DR 53 | 13146 | ER 3020-1 | 27-Dec-10 | 06-Jan-11 | 10 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
S. Coddington Ave. W. Van Dorn St. | DR 53 | 13147 | 5205-1 | 12-Jan-11 | 27-Jan-11 | 15 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
S. Coddington Ave/Van Dorn | Public Involve memo | 13147 | 5205-1 | 9/11/2012 | 9/17/2012 | 6 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
South Coddington/West Van Dorn Intersection | 106 concur req | 13147 | 5205-1 | 1/28/2013 | 1/31/2013 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
South Coddington - West Van Dorn, Lincoln | Section 4(f) Temporary Occupancy | 13147 | 5205-1 | 8/14/2013 | 8/19/2013 | 5 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Coddington and Van Dorn - Bison Park | Section 4(f) - revised | 13147 | 5205-1 | 8/23/2013 | 8/29/2013 | 6 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
CCTV and Snapshot Cameras | Batched CCTV and Snapshot Cameras - Version 2 | 13148 | ITSN-11 | 4/29/2013 | 5/1/2013 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Statewide Cameras | SHPO and THPO concur req - revised | 13148 | ITSN-11 | 7/16/2013 | 7/22/2013 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Diller/Odell Elem Sch SRTS | DR 53 | 13153 | 48-24 | 09-Jun-11 | 16-Jun-11 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
3 Sites in Otoe County | DR 53 | 13154 | ER 3680-7 | 30-Sep-11 | 30-Sep-11 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
N-66 - Mahoney Interchange | DR 53 | 13155 | 667-117 | 9/6/2012 | 9/17/2012 | 11 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Mahoney Interchange, Phs 2 | SHPO and THPO concur req | 13155 | 667-117 | 12/14/2012 | 12/26/2012 | 12 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
4th Corso Viad, NE City | DR 53 | 13159 | 6217-4 | 09-Jun-11 | 16-Jun-11 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
4th Corso Viaduct | SHPO and THPO concur request | 13159 | 6217-4 | 6/3/2013 | 6/10/2013 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
4th Corso Viaduct | Rev 106 | 13159 | 6217-4 | 7/12/2013 | 7/22/2013 | 10 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
4th Corso Viaduct - Nebraska City | Bio doc V1 | 13159 | 6217-4 | 8/13/2013 | 8/19/2013 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Seward West Trail | DR 53 | 13160 | 80-32 | 18-Jan-11 | 31-Jan-11 | 13 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Karol Kay Blvd Extension | DR 53 | 13161 | 6763-1 | 11/30/2011 | 12/5/2011 | 5 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
N-2, 56th - 84th | Bio Doc V1 | 13164 | 26-122 | 21-Jul-11 | 29-Jul-11 | 8 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
N-2, 56th - 84th, Lincoln | DR 53 | 13164 | 26-122 | 03-Aug-11 | 05-Aug-11 | 2 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
North Jct N-15 West | DR 53 | 13166 | 416-114 | 05-May-11 | 11-May-11 | 6 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
North Jct N-15 West | Bio Doc V1 | 13166 | 416-114 | 21-Jul-11 | 29-Jul-11 | 8 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
N-4 to Wilber | DR 53 | 13168 | 1031-110 | 30-Aug-11 | 06-Sep-11 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
N-4 - Wilber | Bio doc vers 1 | 13168 | 1031-110 | 11/18/2011 | 11/23/2011 | 5 | NDOR/address FHWA comments and resubmit |
N-4 - Wilber | Bio doc vers 2 | 13168 | 1031-110 | 12/2/2011 | 12/6/2011 | 4 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Cornhusker - S Jct US-34 | DR 53 | 13173 | 1809-2 | 11/15/2011 | 11/23/2011 | 8 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Prague South | DR 53 | 13175 | 78-31 | 18-Jul-11 | 20-Jul-11 | 2 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Crete Elem BOLTAGE Prgm | DR 53 | 13176 | 76-47 | 02-Sep-11 | 08-Sep-11 | 6 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Blue River Bridge Beaver Crossing | DR 53 | 13182 | L80E-113 | 5/3/2013 | 5/20/2013 | 17 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Lets All Pedal to Prescott, Lincoln | DR 53 | 13187 | 55-176 | 10/18/2011 | 10/28/2011 | 10 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Turkey Creek Bridge South of Steinauer | DR-53 | 13188 | 47-107 | 6/17/2013 | 6/17/2013 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Salt Creek Bridge, Lincoln | DR 53 | 13194 | L55X-103 | 2/9/2012 | 2/17/2012 | 8 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Salt Creek Bridge, Lincoln | SHPO concur request | 13194 | L55X-103 | 4/25/2012 | 4/27/2012 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Bruno Spur Bridges | DR 53 | 13197 | S12B-106 | 8/2/2012 | 8/16/2012 | 14 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Bruno Spur Bridges | SHPO concur req | 13197 | S12B-106 | 8/22/2012 | 8/31/2012 | 9 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Water Park to Hannibal Park Trail, Beatrice | DR 53 | 13212 | 34-42 | 3/8/2012 | 4/5/2012 | 28 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Beatrice Water Park to Hannibal Park Trail | SHPO concur req | 13212 | 34-42 | 7/12/2012 | 7/24/2012 | 12 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Hannibal Trail | SHPO supp concur request | 13212 | 34-42 | 6/19/2013 | 6/21/2013 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Lincoln Stonebridge Trail | DR 53 | 13213 | 55-177 | 3/26/2012 | 4/6/2012 | 11 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Tecumseh Historic Square | DR 53 | 13214 | 49-46 | 3/29/2012 | 4/6/2012 | 8 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Lincoln - N-370 Rumble Strips | DR 53 | 13217 | 809-72 | 9/7/2012 | 9/17/2012 | 10 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
27th St - Pflug Road Rumble Strips | Bio doc | 13217 | 809-72 | 8/21/2013 | 8/27/2013 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Filley - Crab Orchard | DR 53 | 13219 | 1366-123 | 3/14/2013 | 3/19/2013 | 5 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Swan Creek Bridge, South of Western | DR 53 | 13221 | 151-116 | 7/27/2012 | 8/14/2012 | 18 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
W. Jct. N-92, David City | DR 53 | 13222 | 152-123 | 8/14/2012 | 8/20/2012 | 6 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
66th St and Fremont St | DR 53 | 13227 | 5253-1 | 9/4/2012 | 9/13/2012 | 9 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
DMS Replacement | Batched DR-53 | 13231 | ITSN-31 | 8/22/2013 | 8/29/2013 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
10th and Salt Creek Bridge | DR 53 | 13233 | 5215-3 | 12/19/2012 | 12/26/2012 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
70th St - Van Dorn to Eastborough | DR 53 | 13243 | 5247-13 | 5/9/2013 | 5/13/2013 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Rumble Strips | DR-53 | 13248 | HSIP-D1-105 | 6/20/2013 | 6/24/2013 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Seward Trail | DR 53 | 13255 | 80-33 | 8/6/2012 | 8/16/2012 | 10 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
North Platte - Maxwell Bridges | 106 concur req | 16157 | 804-144 | 3/4/2013 | 3/6/2013 | 2 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
N-36 North, Omaha | Bio doc vers 1 | 21791 | 1333-102 | 14-Jan-11 | 31-Jan-11 | 17 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
US-75, Plattsmouth - Bellevue | re-eval ESA | 21849 | 752-155 | 28-May-10 | 01-Jun-10 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
US-75, Plattsmouth to Bellevue | Re-evaluation | 21849 | 752-155 | 21-Jul-10 | 23-Jul-10 | 2 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
US 275 Stockyards | DR 53 | 21853 | 2757-180 | 17-Oct-11 | 18-Oct-11 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
US-275/Stockyards, Omaha | SHPO concur request | 21853 | 2757-180 | 1/11/2012 | 1/17/2012 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
US-275/Stockyards, Omaha | Bio doc version 1 | 21853 | 2757-180 | 1/13/2012 | 1/17/2012 | 4 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
US 275 Omaha Stock Yards | Hazmat review | 21853 | 2757-180 | 7/5/2012 | 7/11/2012 | 6 | NDOR/address FHWA comments and resubmit |
US-275, Omaha Stock Yards | Hazmat memo review | 21853 | 2757-180 | 7/16/2012 | 7/18/2012 | 2 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
US-275/Omaha Stockyards | HazMat Review - update | 21853 | 2757-180 | 8/2/2012 | 8/7/2012 | 5 | NDOR/address FHWA comments and resubmit |
US-275/Stockyards, Omaha | Cat Ex | 21853 | 2757-180 | 8/8/2012 | 8/13/2012 | 5 | NDOR/address FHWA comments and resubmit |
US-275/Stockyards, Omaha | Cat Ex - revised | 21853 | 2757-180 | 8/21/2012 | 8/22/2012 | 1 | NDOR/address FHWA comments and resubmit |
US-275/Stockyards, Omaha | Cat Ex - revised | 21853 | 2757-180 | 8/23/2012 | 8/23/2012 | 0 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Elkhorn North | DR 53 | 21911 | 312-110 | 6/15/2012 | 6/26/2012 | 11 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Elkhorn North | SHPO and THPO concur req | 21911 | 312-110 | 6/26/2012 | 6/27/2012 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Bell St Viad, Fremont | Reeval Form | 21953 | 5625-2 | 23-Sep-10 | 01-Oct-10 | 8 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Blair West | DR 53 | 22026 | 7089-23 | 15-Dec-10 | 17-Dec-10 | 2 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Blair West | Bio doc vers 1 | 22026 | 7089-23 | 15-Apr-11 | 21-Apr-11 | 6 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Blair West | SHPO concur req | 22026 | 7089-23 | 25-Apr-11 | 25-Apr-11 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Blair West | CE | 22026 | 7089-23 | 19-Aug-11 | 03-Sep-11 | 15 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Hooper North | DR 53 | 22052 | 3495-3 | 23-Sep-11 | 26-Sep-11 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Hooper North | SHPO concur request | 22052 | 3495-2 | 1/26/2012 | 2/3/2012 | 8 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Hooper North | Bio doc version 1 | 22052 | 3495-3 | 2/15/2012 | 2/17/2012 | 2 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Hooper North | CE 1st review | 22052 | 3495(3) | 5/18/2012 | 6/1/2012 | 14 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Hooper North | Reeval and 4(f) | 22052 | 3495-2 | 5/8/2013 | 5/8/2013 | 0 | None |
Blair Bypass | P/N Chapter | 22075 | 89(17) | 27-Jun-11 | 29-Jun-11 | 2 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Blair Bypass | Bio doc version 1 | 22075 | 89-17 | 4/12/2012 | 4/23/2012 | 11 | NDOR/address FHWA comments and resubmit |
Blair Bypass | SHPO concur request | 22075 | 89-17 | 4/12/2012 | 5/7/2012 | 25 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Blair Bypass | Bio doc - version 2 | 22075 | 89-17 | 6/7/2012 | 6/12/2012 | 5 | NDOR/address FHWA comments and resubmit |
Blair Bypass | SHPO THPO concur req revised | 22075 | 89-17 | 6/22/2012 | 6/25/2012 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Blair Bypass | Bio doc - version 3 | 22075 | 89-17 | 6/25/2012 | 7/2/2012 | 7 | NDOR/address FHWA comments and resubmit |
Blair Bypass | Bio doc - version 4 | 22075 | 89-17 | 7/3/2012 | 7/13/2012 | 10 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Blair Bypass | draft EIS | 22075 | 89-17 | 6/29/2012 | 7/27/2012 | 28 | None |
Blair Bypass | 106 Non-Conur Resp Req | 22075 | 89-17 | 8/15/2012 | 8/15/2012 | 0 | None |
Fremont West | Bio doc vers 1 | 22097 | 3460-4 | 01-Dec-10 | 10-Dec-10 | 9 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Fremont West | DR 53 | 22097 | 3460-4 | 15-Dec-10 | 17-Dec-10 | 2 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Westbound I-80 Expansion | SHPO Concur | 22143 | 809-897 | 13-Sep-10 | 13-Sep-10 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Westbound I-80 expansion | SHPO concur req | 22143 | 809-897 | 20-Sep-11 | 26-Sep-11 | 6 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
WB I-80 Expansion | SHPO concur req | 22143 | 809-897 | 26-Sep-11 | 26-Sep-11 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
I-80, Omaha | DR 53 | 22150 | 809-901 | 19-Apr-11 | 26-Apr-11 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
#NAME? | DR 53 | 22162 | 6809-910 | 27-Jul-11 | 03-Aug-11 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
I-680 NB Lanes | SHPO concur req | 22162 | 6809-910 | 15-Sep-11 | 16-Sep-11 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Missouri Rvr Bridge Approach, Bellevue | CO 1 | 22176 | 347-118 | 11/16/2012 | 11/19/2012 | 3 | None |
Fremont viaducts | Draft EA | 22177 | 5616-1 | 04-Jan-11 | 28-Jan-11 | 24 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
23rd Street Viaduct, Fremont | SHPO concur req | 22177 | 5616-1 | 6/18/2012 | 7/13/2012 | 25 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
23rd St Viaduct | SHPO concur req | 22177 | 5616-1 | 8/15/2012 | 8/30/2012 | 15 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
23rd St Viaduct | SHPO concur req | 22177 | 5616-1 | 9/13/2012 | 9/17/2012 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
23rd St Viaduct | 4(f) Net Benefit memo | 22177 | 5616-1 | 9/12/2012 | 10/10/2012 | 28 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
23rd Street Viaduct | Net Benefits | 22177 | 5616-1 | 12/21/2012 | 1/11/2013 | 21 | NDOR/address FHWA comments and resubmit |
23rd St Viaduct | 4(f) review - revised | 22177 | 5616-1 | 7/24/2013 | 8/8/2013 | 15 | NDOR/address FHWA comments and resubmit |
Ruff Road to Millard | DR 53 | 22201 | 809-63 | 27-Jul-11 | 03-Aug-11 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Ruff Road - Millard | Bio doc version 1 | 22201 | 809-63 | 12/29/2011 | 1/3/2012 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
144th St West Dodge, Omaha | ERRATA FONSI Approval Req | 22202 | 5001-15 | 21-Dec-10 | 21-Dec-10 | 0 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
144th W Dodge to Eagle Run | ERRATA doc | 22202 | 5001-15 | 22-Dec-10 | 11-Jan-11 | 20 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
144th, et al, Omaha | 404 b 1 analysis | 22202 | 5001-15 | 10-Feb-11 | 15-Feb-11 | 5 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
144th & Blondo, Omaha | Errata | 22202 | 5001-15 | 03-Mar-11 | 08-Mar-11 | 5 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
144th & Blondo | Errata Doc - final | 22202 | 5001-15 | 09-Mar-11 | 09-Mar-11 | 0 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
144th & Blondo | Wetland Mit memo | 22202 | 5001-15 | 13-Oct-11 | 17-Oct-11 | 4 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Bennington South | DR 53 | 22221 | 3805-4 | 16-Jun-11 | 23-Jun-11 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Bennington South | SHPO concur request | 22221 | 3805-4 | 12/1/2011 | 12/8/2011 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
WDCT - Valley to YMCA, Ph 1 | DR 53 | 22227 | 28-87 | 09-Jun-11 | 10-Jun-11 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Western Douglas County Trail | Sect 4(f) Eval | 22227 | 28-87 | 6/6/2012 | 6/14/2012 | 8 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Western Douglas County Trail | Cat Ex | 22227 | 28-87 | 5/14/2013 | 5/22/2013 | 8 | NDOR/address FHWA comments and resubmit |
156th St Improvements | Purpose and Need review | 22233 | 3805-5 | 8/6/2012 | 8/16/2012 | 10 | None |
N 96th St. Bridge | DR 53 | 22235 | 7028-47 | 3/28/2012 | 4/6/2012 | 9 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
North 96th St Bridge Replacement | SHPO & THPO concur req | 22235 | 7028-47 | 9/11/2012 | 9/14/2012 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
N 96th St Bridge | 4(f) | 22235 | 7028-47 | 4/23/2013 | 5/1/2013 | 8 | NDOR/address FHWA comments and resubmit |
96th St Bridge De Minimis | Public outreach review | 22235 | 7028-47 | 7/29/2013 | 8/2/2013 | 4 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
North 96th St Bridge Replacement | Public Outreach review | 22235 | 7028-47 | 9/11/2013 | 9/12/2013 | 1 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
144th - Pierce Pl to Burke St | Bio doc vers 1 | 22236 | 5011-8 | 01-Feb-11 | 02-Feb-11 | 1 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Pierce Plaza - Burke St | SHPO concur req | 22236 | 5011-8 | 21-Mar-11 | 21-Mar-11 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
114th St, Pierce Plaza to Burke St. | two 4(f) except requests | 22236 | 5011-8 | 16-Jun-11 | 23-Jun-11 | 7 | NDOR/address FHWA comments and resubmit |
Pierce Plaza to Burke Street | 4f exception request | 22236 | 5011-8 | 11-Jul-11 | 20-Jul-11 | 9 | NDOR/address FHWA comments and resubmit |
114th Street | Documents comments | 22236 | 5011-8 | 3/4/2013 | 3/4/2013 | 0 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
114th Street, Burke - Pacific | SHPO and THPO concur request | 22236 | 5011-8 | 5/29/2013 | 6/4/2013 | 6 | NDOR/address FHWA comments and resubmit |
114th St, Burke - Pacific | SHPO and THPO concur req | 22236 | 5011-8 | 7/16/2013 | 7/22/2013 | 6 | NDOR/address FHWA comments and resubmit |
114th St, Burke to Pacific | SHPO and THPO concur req - revised | 22236 | 5011-8 | 7/23/2013 | 7/24/2013 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
108th, Madison to Q | NEPA Action Memo | 22237 | 5011-9 | 10-Nov-10 | 12-Nov-10 | 2 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
108th, Madison - Q | 4(f) and NEPA action | 22237 | 5011-9 | 29-Dec-10 | 10-Jan-11 | 12 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
108th, Madison - Q, Omaha | 4(f) and CE Memo req | 22237 | 5011-9 | 22-Feb-11 | 01-Mar-11 | 7 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Missouri River Trail | letter to ACHP with MOA | 22252 | 28(89) | 16-Aug-10 | 19-Aug-10 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Mo River Trail phs 2 | Data revovery plan | 22252 | 28-89 | 19-Aug-10 | 26-Aug-10 | 7 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Missouri River Trail Phase 2 | NEPA CE | 22252 | 28-89 | 25-Aug-10 | 27-Aug-10 | 2 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Missouri Rvr Trl, Phase 2 | Section 106 doc | 22252 | 28-89 | 26-Oct-10 | 27-Oct-10 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Fremont - Winslow | DR 53 | 22256 | 773-130 | 06-Apr-11 | 12-Apr-11 | 6 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Frermont - Winslow | Bio doc version one | 22256 | 773-130 | 12/19/2011 | 12/22/2011 | 3 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Bennington SE | Bio doc vers 1 | 22258 | 3806-1 | 20-Sep-10 | 29-Sep-10 | 9 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Fort Street - Missouori River | DR 53 | 22264 | 6809-29 | 11/22/2011 | 11/28/2011 | 6 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Fort Street - Missouri River | SHPO concur request | 22264 | 6809-29 | 2/9/2012 | 2/14/2012 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Fort St - Missouri River | THPO concur req | 22264 | 6809-29 | 9/20/2012 | 10/11/2012 | 21 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Fremont South Bridge | Temp Occ Monnich Letter | 22265 | 773-128 | 11-Mar-10 | 11-Mar-10 | 0 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Fremont Bridge | 1st draft DEA | 22265 | 773-128 | 09-Mar-10 | 16-Mar-10 | 7 | NDOR/address FHWA comments and resubmit |
Freemont South Bridge | Eff Determ Pkg v2 | 22265 | 773-128 | 25-Mar-10 | 25-Mar-10 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Fremont South | additl info; bio memo | 22265 | 24-Apr-10 | 01-May-10 | 7 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, | |
Fremont Bridge | FEA-Errata, DEA | 22265 | 773-128 | 20-Jul-10 | 21-Jul-10 | 1 | NDOR/address FHWA comments and resubmit |
Fremont South Bridge | FEA/Errata - FONSI Rec | 22265 | 773-128 | 27-Jul-10 | 11-Aug-10 | 15 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Fremont South Bridge | Final EA Approval | 22265 | 773-128 | 30-Jul-10 | 11-Aug-10 | 12 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Fremont South Bridge | CO 13 | 22265 | 773-128 | 11/29/2012 | 12/3/2012 | 4 | None |
Rumsey Station SRTS | Bio doc vers 1 | 22270 | 77-53 | 23-Nov-10 | 23-Nov-10 | 0 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Rumsey Station SRTS | DR 53 | 22270 | 77-53 | 23-Nov-10 | 24-Nov-10 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Papillion-Rumsey Sta School | SHPO concur req | 22270 | 77-53 | 07-Dec-10 | 10-Dec-10 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
36th Street Improvements | P&N review | 22276 | 5061-5 | 01-Apr-11 | 04-Apr-11 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
36th ST Bellevue | NEPA Merge concurrence point 2 package | 22276 | 5061(5) | 5/2/2012 | 5/10/2012 | 8 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
36th Street Reconstruction, Bellevue | Alternatives Addendum following merge process | 22276 | 5061-5 | 3/25/2013 | 4/10/2013 | 16 | None |
36th St Improvements | SHPO concur request | 22276 | 3773-1 | 6/11/2013 | 6/12/2013 | 1 | NDOR/address FHWA comments and resubmit |
36th Street Improvements | 106 Rev Testing Plan Review | 22276 | 5061-5 | 7/8/2013 | 7/9/2013 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
120th St, Stonegate to Roanoke | Bio doc vers 1 | 22277 | 5009-3 | 19-Nov-10 | 24-Nov-10 | 5 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Stonegate Dr to Roanoke Blvd | SHPO concur req | 22277 | 5009-3 | 07-Dec-10 | 10-Dec-10 | 3 | NDOR/address FHWA comments and resubmit |
Stonegate Dr -Roanoke | SHPO concur req | 22277 | 5099-3 | 14-Dec-10 | 17-Dec-10 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
120th, Stonegate to Roanoke | Purp & Need | 22277 | 5009-3 | 28-Dec-10 | 04-Jan-11 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
120th St - Stonegate - Roanoke | 6(f) 106 concur req | 22277 | 5009-3 | 7/24/2013 | 7/31/2013 | 7 | NDOR/address FHWA comments and resubmit |
Inters Sorensen Prk & N Frwy | DR 53 | 22278 | 5114-6 | 15-Dec-10 | 17-Dec-10 | 2 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Intersect Sorensen Parkwy & N Freeway | Bio doc vers 1 | 22278 | 5114-6 | 26-May-11 | 27-May-11 | 1 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Intersection of Sorensen Parkway and North Freeway | SHPO Concur Req | 22278 | 5114-6 | 22-Jul-11 | 26-Jul-11 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Sorensen Parkway & North Freeway | CE | 22278 | 5114-6 | 11/29/2011 | 12/5/2011 | 6 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
42nd & Q | Purpose & Need | 22279 | 5057-9 | 18-Oct-10 | 20-Oct-10 | 2 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
42nd & Q, Omaha | Purp and Need | 22279 | 5058-9 | 22-Oct-10 | 26-Oct-10 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
42nd & Q Brdg & Intersec | Bio doc vers 1 | 22279 | 5057-9 | 01-Feb-11 | 02-Feb-11 | 1 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
42nd & Q, Omaha | SHPO concur req | 22279 | 5057-9 | 19-May-11 | 27-May-11 | 8 | NDOR/address FHWA comments and resubmit |
42nd & Q, Omaha | SHPO concur req | 22279 | 5057-9 | 18-Jul-11 | 20-Jul-11 | 2 | NDOR/address FHWA comments and resubmit |
42nd & Q | SHPO Concur Req V3 | 22279 | 5057-9 | 21-Jul-11 | 22-Jul-11 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
42nd & Q Intersection, Omaha | Section 4(f) | 22279 | 5057-9 | 02-Sep-11 | 15-Sep-11 | 13 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
42nd and Q | SHPO effects concurrence letter | 22279 | 5057-9 | 12/20/2011 | 12/21/2011 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
42nd & Q, Omaha | draft EA Chapter 1-3 Final | 22279 | 5057-9 | 12/30/2011 | 1/11/2012 | 12 | NDOR/address FHWA comments and resubmit |
42nd & Q, Omaha | draft EA | 22279 | 5057-9 | 3/14/2012 | 3/28/2012 | 14 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
42nd & Q Bridge Replacement | Hazmat coord letters | 22279 | 5057-9 | 4/17/2012 | 4/19/2012 | 2 | NDOR/address FHWA comments and resubmit |
42nd & Q Bridge Replacement | HazMat memos review request | 22279 | 5057-9 | 4/26/2012 | 4/26/2012 | 0 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
42nd & Q | draft EA Revisions | 22279 | 5057-9 | 7/9/2012 | 7/23/2012 | 14 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
42nd & Q | DEA - revised | 22279 | 5057-9 | 8/7/2012 | 8/16/2012 | 9 | NDOR/address FHWA comments and resubmit |
42nd & Q Bridge Replace & Intersect improvements | Errata Doc | 22279 | 5057-9 | 11/1/2012 | 11/14/2012 | 13 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
42nd and Q | Errata - draft | 22279 | 5057-9 | 12/19/2012 | 12/21/2012 | 2 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Dodge/Douglas S-Curve | Purpose and Need memo | 22282 | 67-179 | 12/21/2012 | 1/8/2013 | 18 | None |
Dodge-Douglas Street S-Curve Historic Structures Report | draft SHPO standing structures report | 22282 | 67-179 | 5/1/2013 | 5/3/2013 | 2 | NDOR/address FHWA comments and resubmit |
Dodge-Douglas St - S-Curve | SHPO concur - version 1 | 22282 | 67-179 | 5/2/2013 | 5/3/2013 | 1 | NDOR/address FHWA comments and resubmit |
Dodge Street S Curve Area Connectivity Study | APE final draft | 22282 | 67-179 | 8/20/2013 | 9/11/2013 | 22 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Dodge Street S Curve Connectivity | EJ Memo - draft | 22282 | 67-179 | 9/18/2013 | 9/24/2013 | 6 | None |
Intersec 132 & W Giles Rd | DR 53 | 22283 | 5005-1 | 11-Nov-10 | 12-Nov-10 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
132nd & Giles Road | SHPO & THPO concur req | 22283 | 5005-1 | 9/24/2012 | 10/11/2012 | 17 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
132nd & West Giles Rd, Omaha | Bio doc version 1 | 22283 | 5005-1 | 10/9/2012 | 10/30/2012 | 21 | NDOR/address FHWA comments and resubmit |
132nd and W. Giles Road | Bio doc - version 2 | 22283 | 5005-1 | 10/31/2012 | 11/9/2012 | 9 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
132nd and West Giles Rd | Cat Ex | 22283 | 5005-1 | 6/19/2013 | 6/24/2013 | 5 | NDOR/address FHWA comments and resubmit |
132nd and West Giles Road | Cat Ex - V2 | 22283 | 5005-1 | 9/5/2013 | 9/6/2013 | 1 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
F St. Bridge | DR 53 | 22284 | 5028-4 | 3/27/2012 | 4/6/2012 | 10 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
F Street Bridge | 4(f) except request | 22284 | 5028-4 | 12/31/2012 | 1/8/2013 | 8 | NDOR/address FHWA comments and resubmit |
F St Bridge | 4(f) except determ | 22284 | 5028-4 | 1/29/2013 | 2/22/2013 | 24 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
F Street Bridge | SHPO and THPO concur req | 22284 | 5028-4 | 2/25/2013 | 3/4/2013 | 7 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Washington St Reconstr | Bio doc vers 1 | 22290 | 5023-14 | 05-Apr-11 | 07-Apr-11 | 2 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Washington St, Papillion | SHPO concur req | 22290 | 5023-14 | 05-Apr-11 | 07-Apr-11 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Washington St, Caphard to Cedardale Rd | CE Form concurrent review | 22290 | 5023-14 | 31-May-11 | 06-Jun-11 | 6 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Washington St. | CE v2 | 22290 | 5023-14 | 20-Jun-11 | 23-Jun-11 | 3 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Washington St, Capehard to Cedardale Rd | CE - Version 3 | 22290 | 5023-14 | 27-Jun-11 | 28-Jun-11 | 1 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Bennington Papio Creek Bridge and Trail | DR 53 | 22307 | 28-90 | 23-Sep-11 | 26-Sep-11 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Bennington Papio Creek Bridge and Trail | 106 and THPO concur req | 22307 | 28-90 | 12/18/2012 | 12/26/2012 | 8 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Bennington Papio Trail | 4(f) Exception | 22307 | 28-90 | 2/19/2013 | 2/28/2013 | 9 | NDOR/address FHWA comments and resubmit |
Bennington Papio Trail | revised Section 4(f) | 22307 | 28-90 | 3/7/2013 | 3/8/2013 | 1 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Bennington Papio Creek Bridge and Trail | Cat Ex | 22307 | 28-90 | 5/3/2013 | 5/14/2013 | 11 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Papillion Midland Creek Trl | SHPO concur req | 22309 | 77-55 | 02-Sep-11 | 06-Sep-11 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Papillion Midland Creek Trail | Bio Doc | 22309 | 77-55 | 30-Sep-11 | 30-Sep-11 | 0 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Papillion Midland Trail | 4(f) exemption request | 22309 | 77-55 | 11/15/2011 | 11/15/2011 | 0 | NDOR/address FHWA comments and resubmit |
Papillion Midland Creek Trail | CE | 22309 | 77-55 | 1/6/2012 | 1/16/2012 | 10 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Springfield Trail Project | 4(f) PA Memo | 22310 | 77-56 | 23-Aug-10 | 08-Sep-10 | 16 | NDOR/address FHWA comments and resubmit |
Springfied Trail | 4(f) #2 | 22310 | 77(56) | 13-Sep-10 | 23-Sep-10 | 10 | NDOR/address FHWA comments and resubmit |
Springfield Trail | 4-f Memo | 22310 | 77-56 | 04-Oct-10 | 12-Oct-10 | 8 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Springfield Trail Phase III | SHPO concur request | 22310 | 77-56 | 04-Nov-10 | 08-Nov-10 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Springfield Trl - Phase III | Bio doc vers 1 | 22310 | 77-56 | 18-Nov-10 | 23-Nov-10 | 5 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Springfield Trl Phs 3 | DR 53 | 22310 | 77-56 | 15-Dec-10 | 17-Dec-10 | 2 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Springfield Trail, Ph 3 | Reeval Memo | 22310 | 77-56 | 05-May-11 | 11-May-11 | 6 | NDOR/address FHWA comments and resubmit |
Springfield Trail | 106 reeval | 22310 | 77-56 | 09-May-11 | 13-May-11 | 4 | NDOR/address FHWA comments and resubmit |
Springfield Trail | 106 Concur Letter | 22310 | 77-56 | 20-May-11 | 27-May-11 | 7 | NDOR/address FHWA comments and resubmit |
Springfield Trl, Phase 3 | SHPO concur req | 22310 | 77-56 | 30-Jun-11 | 01-Jul-11 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Springfield Trail | 4(f) reeval memo | 22310 | 77-56 | 13-Sep-11 | 16-Sep-11 | 3 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
City of Springfield | CE | 22310 | 77-56 | 12/19/2011 | 12/23/2011 | 4 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
City of Springfield | CE - 2nd | 22310 | 77-56 | 1/12/2012 | 1/16/2012 | 4 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
4th Ave: 16th-Hillcrest | DR 53 | 22313 | 6404-1 | 01-Oct-10 | 04-Oct-10 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
In Plattsmouth | 106 Concur Req | 22313 | 6404-1 | 4/2/2012 | 4/25/2012 | 23 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
In Plattsmouth | 4(f) exception | 22313 | 6404-1 | 7/26/2012 | 8/14/2012 | 19 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
4th Ave, 16th - Hillcrest, Plattsmouth | Cat Ex | 22313 | 6404-1 | 11/28/2012 | 12/5/2012 | 7 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Omaha McMillan Magnet Middle School - infras. | DR 53 | 22321 | 28-93 | 19-Aug-11 | 03-Sep-11 | 15 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Q St Bridge repl, Omaha | DR 53 | 22325 | 5026-11 | 18-Jan-11 | 31-Jan-11 | 13 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Q St Br repla, 26 - 27th, Omaha | DR 53 | 22325 | 5026-11 | 02-Feb-11 | 02-Feb-11 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Q St Bridge, 26th - 27th | Bio doc vers 1 | 22325 | 5026-11 | 07-Oct-11 | 07-Oct-11 | 0 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Q Street Bridge Replacement | SHPO THPO concur req | 22325 | 5026-11 | 8/9/2012 | 8/16/2012 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
26th and Q St Bridge, Omaha | Cat Ex | 22325 | 5026-11 | 8/14/2013 | 8/29/2013 | 15 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Inters N-133 & N-64 | Bio doc vers 1 | 22336 | 1332-112 | 22-Sep-10 | 01-Oct-10 | 9 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Intersec N-133 & N-64 | DR 53 | 22336 | 1332-112 | 11-Feb-11 | 16-Feb-11 | 5 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Intersection N-133 (90th & Maple) | Variance approval | 22336 | 1332-112 | 11/9/2011 | 11/10/2011 | 1 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Colfax-Dodge Co Line East | DR 53 | 22338 | 306-134 | 25-Oct-10 | 26-Oct-10 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Fort Calhoun SW - 2 sites | DR 53 | 22341 | 89-25 | 16-Feb-11 | 22-Feb-11 | 6 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Fort Calhoun SW | SHPO concur request | 22341 | 89-25 | 10/28/2011 | 10/28/2011 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Fort Calhoun Southwest - 2 sites | Bio doc version 1 | 22341 | 89-25 | 12/29/2011 | 1/3/2012 | 5 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Ft. Calhoun SW | Cat Ex | 22341 | 89-25 | 3/16/2012 | 4/20/2012 | 35 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
10th St Brdg, Omaha | SHPO concur req | 22352 | 5103-14 | 14-Dec-10 | 17-Dec-10 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
10th St Bridge, Omaha | DR 53 | 22353 | 5013-4 | 10-Nov-10 | 12-Nov-10 | 2 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
10th St. Brdg Widen | Bio doc vers 1 | 22353 | 5103-14 | 30-Dec-10 | 06-Jan-11 | 7 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
10th St. Brg. Widening | 4(f) concur req review | 22353 | 5013-14 | 16-Mar-11 | 16-Mar-11 | 0 | NDOR/address FHWA comments and resubmit |
10th St Brg Wide, Omaha | SHPO concur req | 22353 | 5103-14 | 23-Mar-11 | 24-Mar-11 | 1 | NDOR/address FHWA comments and resubmit |
10th St Bridge, Omaha | 4(f) DeMin Form | 22353 | 5103-14 | 06-May-11 | 06-May-11 | 0 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
10th St Bridge, Omaha | CE | 22353 | 5103-14 | 13-May-11 | 18-May-11 | 5 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
58th Street, Omaha | NEPA Determination Form | 22363 | 5086-1 | 02-Aug-10 | 20-Aug-10 | 18 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Intersec 58th & NW Radial Hwy, Omaha | CE | 22363 | 5086-1 | 06-Apr-11 | 07-Apr-11 | 1 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Kennedy and Cornhusker Exit Ramps | DR 53 | 22366 | 5006-4 | 12/29/2011 | 1/4/2012 | 6 | NDOR/address FHWA comments and resubmit |
Kennedy and Cornhusker Exit Ramps | DR 53 | 22366 | 5006-4 | 1/4/2012 | 1/16/2012 | 12 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Kennedy Freeway and Cornhusker Road | SHPO concur request | 22366 | 5006-4 | 3/7/2012 | 3/15/2012 | 8 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
US-275 East | Bio doc vers 1 | 22368 | 917-108 | 22-Feb-11 | 24-Feb-11 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
US-275 East | SHPO concur req | 22368 | 917-108 | 28-Apr-11 | 02-May-11 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
US-275 East | CE | 22368 | 917-108 | 02-Jun-11 | 10-Jun-11 | 8 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
US-275 East | Scope change memo | 22368 | 917-108 | 5/31/2012 | 6/1/2012 | 1 | None |
Inters F/16th & Spring Lake Dr | Bio doc vers 1 | 22371 | 5089-1 | 14-Dec-10 | 17-Dec-10 | 3 | NDOR/address FHWA comments and resubmit |
F/16th & Spring Lake Dr | DR 53 | 22371 | 5089-1 | 28-Dec-10 | 07-Jan-11 | 10 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Intersec of F & 16th | SHPO Concur Req | 22371 | 5089-1 | 22-Jul-11 | 26-Jul-11 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Intersection of F/16th St and Spring Lake Drive | 4(f) determ | 22371 | 5089-1 | 7/26/2012 | 8/14/2012 | 19 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Spring Lake and F/16th Street, Omaha | Cat Ex | 22371 | 5089-1 | 12/12/2012 | 12/21/2012 | 9 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
102nd & Maple Improv. | DR 53 | 22372 | 5015-1 | 29-Dec-10 | 18-Jan-11 | 20 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
102nd & Maple, Omaha | SHPO concur req | 22372 | 5015-1 | 15-Apr-11 | 21-Apr-11 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
102nd & Maple Improv, Omaha | Bio doc vers 1 | 22372 | 5015-1 | 19-Apr-11 | 21-Apr-11 | 2 | NDOR/address FHWA comments and resubmit |
102nd & Maple, Omaha | Bio doc vers 2 | 22372 | 5015-1 | 22-Apr-11 | 25-Apr-11 | 3 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
156Th St - Pepperwood Dr | P&N | 22376 | 5127-1 | 30-Sep-11 | 13-Oct-11 | 13 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
156th St, West Dodge - Corby, Phase 2 | Bio doc version 1 | 22376 | 5127-1 | 1/10/2012 | 1/16/2012 | 6 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
156th St, Pepperwood Dr to Corby Street | SHPO concur request | 22376 | 5127-1 | 3/8/2012 | 3/15/2012 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
156th St. Pepperwood Dr. to Corby St. | Noise Study | 22376 | 5127-1 | 1/3/2013 | 1/11/2013 | 8 | None |
144th St - Dodge to Corby | Time Extension FONSI | 22376 | 5001-15 | 8/22/2013 | 8/29/2013 | 7 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
108th, L to M, Omaha | Bio doc vers 1 | 22378 | 5011-12 | 22-Sep-10 | 29-Sep-10 | 7 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
108th, L-M, Omaha | DR 53 | 22378 | 5011-12 | 28-Dec-10 | 18-Jan-11 | 21 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
108th, from L to M, Omaha | SHPO concur req | 22378 | 5011-12 | 25-Jul-11 | 26-Jul-11 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
108th, from L to M, Omaha | Bio reintiation | 22378 | 5011-12 | 02-Sep-11 | 15-Sep-11 | 13 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
108th Street, from L to M | CE | 22378 | 5011-12 | 1/23/2012 | 2/3/2012 | 11 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Traf Signals 15th & Farnam | Bio doc vers 1 | 22379 | 5097-1 | 29-Oct-10 | 02-Nov-10 | 4 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
15th & Farnam, Omaha | SHPO concur req | 22379 | 5097-1 | 21-Apr-11 | 25-Apr-11 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
52nd & NW Radial Traf Sigs, Medians, curb ramps | DR 53 | 22380 | 5049-3 | 16-Jun-11 | 23-Jun-11 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
52nd & NW Radial | Bio Doc V1 | 22380 | 5049-3 | 22-Jul-11 | 29-Jul-11 | 7 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
52nd and NW Radial | SHPO concur request | 22380 | 5049-3 | 11/10/2011 | 11/14/2011 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Trfc Sigs - 42nd & Dodge | DR 53 | 22381 | 5057-11 | 17-Dec-10 | 23-Dec-10 | 6 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Traf Sigs 42nd & Dodge | Bio doc vers 1 | 22381 | 5057-11 | 03-Jan-11 | 06-Jan-11 | 3 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Traf Sigs - 42nd & Dodge | SHPO concur | 22381 | 5057-11 | 27-Dec-10 | 07-Jan-11 | 11 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Traf Sigs - 13th & Harney, etc | SHPO concur | 22383 | 5121-2 | 27-Dec-10 | 07-Jan-11 | 11 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Traf Sigs 13th & Harney | Bio doc vers 1 | 22383 | 5121-2 | 03-Jan-11 | 07-Jan-11 | 4 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Traf sigs, various Omaha | DR 53 | 22383 | 5121-2 | 22-Feb-11 | 22-Feb-11 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Westbrook SRTS | DR 53 | 22410 | 28-96 | 8/30/2012 | 8/31/2012 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Valley DC West School Sidewalk | DR 53 | 22411 | 28-97 | 10/24/2011 | 10/28/2011 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
32nd Ave | DR 53 | 22414 | 28-99 | 14-Dec-10 | 17-Dec-10 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
32nd St Streetscape & Bike Trail | revised DR53 | 22414 | 28-99 | 23-Sep-11 | 07-Oct-11 | 14 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Fremont Johnson Rd Trail | DR 53 | 22427 | 27-55 | 08-Apr-11 | 12-Apr-11 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Johnson Rd Trail - Military Ave to 20th St. | Bio doc vers 1 | 22427 | 27-55 | 17-Oct-11 | 18-Oct-11 | 1 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Johnson Road Trail | SHPO concur request | 22427 | 27-55 | 11/30/2011 | 12/6/2011 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Fremont Johnson Road Trail | 106 concur req | 22427 | 27-55 | 4/3/2013 | 4/17/2013 | 14 | NDOR/address FHWA comments and resubmit |
Fremont Johnson Rd Trail | SHPO concur req | 22427 | 27-55 | 4/30/2013 | 5/2/2013 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Fremont Johnson Rd Trails | Variance Request | 22427 | 27-55 | 6/27/2013 | 7/1/2013 | 4 | NDOR/address FHWA comments and resubmit |
Scribner Ped Trail | DR 53 | 22428 | 27-56 | 02-Sep-11 | 14-Sep-11 | 12 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Scribner Ped Trail | DR 53 | 22428 | 27-56 | 13-Oct-11 | 17-Oct-11 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
84th & L Improvement | DR 53 | 22429 | 5023-16 | 29-Dec-10 | 11-Jan-11 | 13 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
84th & L, Omaha | SHPO concur req | 22429 | 5023-16 | 15-Apr-11 | 21-Apr-11 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
84th & L Improv, Omaha | Bio doc vers 1 | 22429 | 5023-16 | 19-Apr-11 | 21-Apr-11 | 2 | NDOR/address FHWA comments and resubmit |
84th & L, Omaha | Bio doc vers 2 | 22429 | 5023-16 | 22-Apr-11 | 25-Apr-11 | 3 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
US-77, 5th-10th, Fremont | DR 53 | 22434 | 773-129 | 14-Jul-11 | 19-Jul-11 | 5 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
US-77 5th - 10th, Fremont | SHPO Concur req | 22434 | 773-129 | 10/18/2011 | 10/28/2011 | 10 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
US-77, 5th - 10th in Fremont | SHPO supp concur req | 22434 | 773-129 | 6/27/2013 | 7/3/2013 | 6 | None |
Fremont | SHPO and 4F Concur Rev | 22434 | 773-129 | 7/30/2013 | 7/31/2013 | 1 | NDOR/address FHWA comments and resubmit |
Omaha Traf Signals Pkg 4 | DR 53 | 22435 | 5091-4 | 17-Dec-10 | 23-Dec-10 | 6 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Traf Sigs pkg 4 | Bio doc vers 1 | 22435 | 5091-4 | 30-Dec-10 | 06-Jan-11 | 7 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Traf Sigs - pkg 4 | SHPO concur | 22435 | 5091-4 | 27-Dec-10 | 07-Jan-11 | 11 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Traff signals various | SHPO concur req | 22436 | 5089-3 | 07-Dec-10 | 10-Dec-10 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Traf Sigs - pkg 5 | Bio doc vers 1 | 22436 | 5089-3 | 30-Dec-10 | 06-Jan-11 | 7 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Traf Signls various - Pkg 6 | DR 53 | 22437 | 5083-6 | 17-Dec-10 | 23-Dec-10 | 6 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Traf Sigs - pkg 6 | Bio doc vers 1 | 22437 | 5083-6 | 30-Dec-10 | 06-Jan-11 | 7 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Traf Sigs - pkg 6 | SHPO concur | 22437 | 5083-6 | 27-Dec-10 | 07-Jan-11 | 11 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Adapt Trfc Control Sys 32nd St. | DR 53 | 22438 | 5003-10 | 17-Dec-10 | 23-Dec-10 | 6 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
132nd St. Adaptive Traffic Control System | Bio Doc V1 | 22438 | 5003-10 | 22-Jul-11 | 29-Jul-11 | 7 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Military Avenue Resurfacing | DR 53 | 22439 | 5610-5 | 14-Feb-11 | 16-Feb-11 | 2 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Military Ave-Broad to Bell, Fremont | Bio doc vers 1 | 22439 | 5610-5 | 17-Oct-11 | 18-Oct-11 | 1 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Military Ave, Broad to Bell, Fremont | SHPO concur request | 22439 | 5610-5 | 10/26/2011 | 10/28/2011 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Military Ave. Broad-Bell | 106 Concur Req (Resubmission) | 22439 | 5610-5 | 3/28/2012 | 4/25/2012 | 28 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
I-480 & US-75 intrchnge | Bio doc vers 1 | 22441 | 4809-102 | 04-Nov-10 | 08-Nov-10 | 4 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Resurfacing, WB W. Center Rd 114 - 120, Omaha | Env Re-Eval Memo | 22446 | 5038-17 | 05-Oct-11 | 07-Oct-11 | 2 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Ft Calhoun - Blair | DR 53 | 22447 | 753-116 | 4/9/2012 | 4/27/2012 | 18 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Ft Calhoun to Blair | SHPO concur req | 22447 | 753-116 | 5/17/2013 | 5/31/2013 | 14 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Scribner North | DR 53 | 22448 | 2756-141 | 10/27/2011 | 10/28/2011 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Scribner North | Bio doc version 1 | 22448 | 2756-141 | 1/3/2012 | 1/3/2012 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Scribner North | SHPO concur request | 22448 | 2756-141 | 2/16/2012 | 2/17/2012 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Adapt Trafc Contr 144th St | DR 53 | 22449 | 5001-17 | 20-Dec-10 | 23-Dec-10 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Adapt Traf Contr Syst | Bio doc vers 1 | 22449 | 5001-17 | 04-Jan-11 | 06-Jan-11 | 2 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Adaptive Traf Control Sys - 144th St. | SHPO concur req | 22449 | 5001-17 | 11-Oct-11 | 12-Oct-11 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
108th Decatur to N Brdg Rd, Omaha | DR 53 | 22450 | 5011-14 | 13-Oct-10 | 26-Oct-10 | 13 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Blair West | DR 53 | 22454 | 917-109 | 4/16/2012 | 4/23/2012 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Blair West | 106 concur req | 22454 | 917-109 | 11/16/2012 | 11/19/2012 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Louisville - Springfield | DR 53 | 22456 | 502-134 | 10/4/2012 | 10/26/2012 | 22 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Louisville - Springfield | SHPO and THPO concur request | 22456 | 502-134 | 4/16/2013 | 4/22/2013 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Cedar Creek Spur | DR 53 | 22457 | S13H-104 | 11/7/2011 | 11/14/2011 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Cedar Creek Spur | SHPO concur request | 22457 | S13H-104 | 1/31/2012 | 2/3/2012 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Cedar Creek Spur | Cat Ex | 22457 | S13H-104 | 5/3/2013 | 5/14/2013 | 11 | NDOR/address FHWA comments and resubmit |
Cedar Creek Spur | Cat Ex - revised | 22457 | S13H-104 | 5/17/2013 | 5/31/2013 | 14 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
N-1 to Plattsmouth | DR 53 | 22458 | 347-128 | 27-Jul-11 | 03-Aug-11 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Plattsmouth North | DR 53 | 22459 | 752-169 | 13-Jun-11 | 16-Jun-11 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
30th & McKinley, Omaha | SHPO concur req | 22461 | 752-170 | 04-Apr-11 | 07-Apr-11 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
30th&McKinley, Omaha | Bio doc vers 1 | 22461 | 752-170 | 15-Apr-11 | 19-Apr-11 | 4 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Waterloo South | DR 53 | 22463 | 2757-193 | 4/16/2012 | 4/23/2012 | 7 | None |
Waterloo South | SHPO and THPO concur req | 22463 | 2757-193 | 7/5/2012 | 7/13/2012 | 8 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
84th St Interchange | Bio doc vers 1 | 22465 | 809-34 | 09-Jun-11 | 10-Jun-11 | 1 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Manley East | DR-53 | 22467 | 17-106 | 5/17/2013 | 5/31/2013 | 14 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
OA 50 Challenge | Bio doc version 1 | 22468 | 3795-5 | 24-Jun-10 | 02-Jul-10 | 8 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Traf sigs, various Omaha | DR 53 | 22475 | 5099-1 | 22-Feb-11 | 22-Feb-11 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Traf sigs various, Omaha | Bio doc vers 1 | 22475 | 5099-1 | 24-Mar-11 | 29-Mar-11 | 5 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Traf sigs Omaha vari locates | SHPO concur req | 22475 | 5099-1 | 19-May-11 | 19-May-11 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Traf Ops & Sigs timing study | DR 53 | 22476 | 28-101 | 22-Feb-11 | 22-Feb-11 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Papillion Walnut Creek Connector Trail | DR-53 | 22477 | 77-59 | 15-Sep-10 | 23-Sep-10 | 8 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Walnut Creek Connector Trail | SHPO and THPO concur req | 22477 | 77-59 | 2/25/2013 | 3/4/2013 | 7 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
96th St. Resurfacing | DR 53 | 22478 | 5017-4 | 19-Jan-11 | 31-Jan-11 | 12 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
96th, Portal-Harrison | Bio doc vers 1 | 22478 | 5017-4 | 05-Apr-11 | 07-Apr-11 | 2 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
69th - 93rd on Dodge | DR 53 | 22482 | 67-180 | 19-Jan-11 | 31-Jan-11 | 12 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Dodge St Traf Contr System | Bio doc vers 1 | 22482 | 67-180 | 22-Mar-11 | 23-Mar-11 | 1 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Dodge St 69th - 93rd | SHPO concur req | 22482 | 67-180 | 25-Apr-11 | 25-Apr-11 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Mud Crk Culvert - Plattsmouth | DR 53 | 22483 | ER 3720-1 | 20-Dec-10 | 27-Dec-10 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Bellevue signals | DR 53 | 22484 | 5109-8 | 24-Jan-11 | 31-Jan-11 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Bellevue Signals | Bio doc vers 1 | 22484 | 5109-8 | 05-Apr-11 | 07-Apr-11 | 2 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Giles Road Signal Coord. | DR 53 | 22485 | 5129-1 | 29-Jul-11 | 03-Aug-11 | 5 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
D2 Overhead DMS | Bio doc | 22487 | ITSN-16 | 9/3/2013 | 9/4/2013 | 1 | None |
Overhead DMS | DR-53 | 22489 | ITSN-33 | 8/21/2013 | 8/22/2013 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Metro Omaha Bicycle Safety Education | DR 53 | 22492 | 28-111 | 4/13/2012 | 4/23/2012 | 10 | None |
Winslow East | DR 53 | 22493 | ER 3860-1 | 23-Sep-11 | 23-Sep-11 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
North Bend Northwest | DR 53 | 22495 | ER 3465-5 | 23-Sep-11 | 23-Sep-11 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Omaha Concrete Panel Replacement | DR 53 | 22498 | 5001-18 | 22-Apr-11 | 26-Apr-11 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Omaha Major Str concrete panel repair | DR 53 | 22499 | 5026-14 | 22-Apr-11 | 26-Apr-11 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Omaha concrete panel replace | DR 53 | 22500 | 5009-4 | 22-Apr-11 | 26-Apr-11 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Traf sigs St Marys & Park Ave | DR 53 | 22501 | 5-46-3 | 04-Mar-11 | 08-Mar-11 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Traf sigs St Marys & Park Ave | Bio doc vers 1 | 22501 | 5046-3 | 15-Mar-11 | 15-Mar-11 | 0 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Traf sigs Inters St Marys Ave & Park Ave | SHPO concur req | 22501 | 5046-3 | 15-Apr-11 | 19-Apr-11 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
1st St Ext, Luther to Johnson, Fremont | DR 53 | 22503 | 27-62 | 09-Jun-11 | 16-Jun-11 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
1st St, Luther Rd to Johnson Rd, Fremont | DR-53 stipulations review | 22503 | 27-62 | 4/30/2013 | 5/2/2013 | 2 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
1st Street, Luther to Johnson | SHPO concur req | 22503 | 27-62 | 8/13/2013 | 8/19/2013 | 6 | NDOR/address FHWA comments and resubmit |
Concrete Panel Repair | DR 53 and 530 | 22505 | 5044-6 | 5/16/2012 | 5/25/2012 | 9 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
24th Street Road Diet, Omaha | DR 53 | 22506 | 5083-7 | 4/12/2012 | 4/23/2012 | 11 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Jackson & Blain Impr, Blair | DR 53 | 22507 | 6462-1 | 09-Jun-11 | 16-Jun-11 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Jackson St, 3rd to River Rd, Blair | Bio doc version 1 | 22507 | 6462-1 | 1/9/2013 | 1/11/2013 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Jackson and Blaine St Improvements | 106 concur req | 22507 | 6462-1 | 2/28/2013 | 3/4/2013 | 4 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Jackson and Blaine Sts Improvements | Cat Ex | 22507 | 6462-1 | 8/7/2013 | 8/16/2013 | 9 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Jackson and Blaine Street Improvements | Cat Ex - revised | 22507 | 6462-1 | 9/4/2013 | 9/5/2013 | 1 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Platteview Road Corridor Study | DR 53 | 22511 | 3770-4 | 12-Sep-11 | 12-Sep-11 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Traf signals, Omaha | DR 53 | 22519 | 5103-15 | 14-Jul-11 | 20-Jul-11 | 6 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Traffic Signals at Various Locations-Omaha | Bio Doc Vers 1 | 22519 | 5103-15 | 11/23/2011 | 11/28/2011 | 5 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Traffic Signals at Various Locations, Omaha | SHPO concur request | 22519 | 5103-15 | 12/1/2011 | 12/8/2011 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Arlington SRTS project | DR 53 | 22523 | 89-29 | 19-Aug-11 | 03-Sep-11 | 15 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Arlington SRTS | SHPO concur req | 22523 | 89-29 | 9/18/2012 | 10/11/2012 | 23 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Bancroft - Dewey, Omaha | DR 53 | 22525 | 4809-103 | 3/8/2012 | 4/5/2012 | 28 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
I-80/680 Interch Q to L CD Roads, Omaha (WB) | DR 53 | 22526 | 809-65 | 8/2/2012 | 8/15/2012 | 13 | None |
L St - 50th St, Omaha | DR 53 | 22527 | 809-66 | 3/8/2012 | 4/5/2012 | 28 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Jct N-31 and N-36 | DR 53 | 22530 | 312-111 | 8/9/2013 | 8/16/2013 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
US-75 West in Bellevue | DR 53 | 22534 | 3707-126 | 11/2/2012 | 11/15/2012 | 13 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Fort Crook Road Striping | DR 53 | 22535 | 5145-3 | 1/13/2012 | 1/17/2012 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Major Street Resurfacing, Omaha | DR 53 | 22536 | 5103-16 | 2/13/2012 | 2/17/2012 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Cedar Creek Spur | ThPO concur request | 22547 | S13H-104 | 1/10/2013 | 1/22/2013 | 12 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Blair Culvert | T&E Update Memo | 22548 | 6462-2 | 2/28/2013 | 3/4/2013 | 4 | None |
Blair Connector Trails | DR 53 | 22549 | 889-30 | 4/18/2012 | 4/23/2012 | 5 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Blair Connector Trails | Bio doc version 1 | 22549 | 89-30 | 12/14/2012 | 1/7/2013 | 24 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Blair Connector Trails | 106 concur req | 22549 | 89-30 | 3/6/2013 | 3/7/2013 | 1 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Traffic Signals at Various Locations | DR 53 | 22554 | 5071-1 | 9/26/2012 | 10/11/2012 | 15 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Traffic Signals at Various Locations | SHPO & THPO concur req | 22554 | 5071-1 | 1/22/2013 | 1/28/2013 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
66th St, Harrison - Giles | DR-53 | 22570 | 5043-1 | 11/30/2012 | 12/12/2012 | 12 | NDOR/address FHWA comments and resubmit |
North Downtown Riverfront Connector Bridge | DR-53 | 22571 | 28-114 | 12/28/2012 | 1/3/2013 | 6 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
S. Jct. US-77 - N-91 at Nickerson | DR 53 | 22576 | 773-133 | 9/3/2013 | 9/4/2013 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Omaha ATMS Central System Software | DR-53 | 22591 | 28-116 | 9/24/2013 | 9/30/2013 | 6 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Schuyler to Fremont | purpose and need | 31090 | 305(120) | 09-May-11 | 27-May-11 | 18 | NDOR/address FHWA comments and resubmit |
US-30, Schuyler - Fremont | Coord Plan | 31091 | 305-120 | 27-Apr-11 | 27-May-11 | 30 | NDOR/address FHWA comments and resubmit |
Primrose East | Bio doc version 1 | 31192 | 6-Jun | 12/8/2011 | 12/14/2011 | 6 | NDOR/address FHWA comments and resubmit |
Stanton North | DR 53 | 31208 | 7084-7 | 1/3/2012 | 1/16/2012 | 13 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Stanton North | SHPO concur req | 31208 | 7084-7 | 7/9/2012 | 7/13/2012 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Craig Northeast | NEPA determ form | 31226 | 3875-2 | 20-Sep-10 | 29-Sep-10 | 9 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Craig Northeast | SHPO concur req | 31226 | 3875-2 | 22-Sep-10 | 29-Sep-10 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Craig Northeast | CE | 31226 | 3875-2 | 11/10/2011 | 11/14/2011 | 4 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Norfolk West | Class 2 Update (CE) | 31417 | 2755-137 | 10-Jun-10 | 17-Jun-10 | 7 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Norfolk - 3 projects | SHPO concur req | 31442 | 353-105 | 27-Sep-11 | 27-Sep-11 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Hartington SE | Bio doc vers 1 | 31502 | 7014-31 | 18-Nov-10 | 24-Nov-10 | 6 | NDOR/address FHWA comments and resubmit |
Hartington Southeast | DR 53 | 31502 | 7014-31 | 06-Dec-10 | 16-Dec-10 | 10 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Hartington SE | SHPO letter | 31502 | 7014-31 | 16-Mar-11 | 16-Mar-11 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Hartington SE | CE Form | 31502 | 7014-31 | 24-May-11 | 01-Jun-11 | 8 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Walthill East | 106, THPO, BIA concur request | 31511 | 947-105 | 11/21/2012 | 12/3/2012 | 12 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Walthill East | Bio doc - BIA | 31511 | 947-105 | 9/11/2013 | 9/11/2013 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Albion to N-45 | DR 53 | 31517 | 915-114 | 4/4/2013 | 4/5/2013 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Petersburg | DR 53 | 31535 | 7638-1 | 22-Feb-11 | 22-Feb-11 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Petersburg Northeast | SHPO Concur Req | 31535 | 2532-1 | 11-Jul-11 | 13-Jul-11 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Petersburg Northeast | Bio Doc Vers 1 | 31535 | 2532-1 | 11/23/2011 | 12/1/2011 | 8 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Petersburg Northeast | Cat Ex | 31535 | 2532-1 | 2/1/2012 | 2/14/2012 | 13 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Stanton Southeast | DR 53 | 31597 | 7084-10 | 06-Dec-10 | 15-Dec-10 | 9 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Stanton SE | Bio doc vers 1 | 31597 | 7084-10 | 05-Apr-11 | 07-Apr-11 | 2 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Stanton SE | SHPO concur req | 31597 | 7084-10 | 27-Apr-11 | 06-May-11 | 9 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Stanton SE | Cat Ex | 31597 | 7084-10 | 6/11/2012 | 6/14/2012 | 3 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
West Point SE | DR 53 | 31665 | 7020-19 | 5/24/2013 | 5/31/2013 | 7 | NDOR/address FHWA comments and resubmit |
West Point SE | DR-53 review | 31665 | 7020-19 | 7/31/2013 | 7/31/2013 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
N-12 Niobrara E&W | Alt Carried Frwd EIS | 31674 | 125-1011 | 20-Sep-10 | 18-Oct-10 | 28 | NDOR/address FHWA comments and resubmit |
Richland NW | DR 53 | 31702 | 7019-10 | 16-Dec-10 | 23-Dec-10 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Richland NW | SHPO concur req | 31702 | 7019-10 | 22-Mar-11 | 29-Mar-11 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Richland Southwest | Bio doc vers 1 | 31702 | 7019-10 | 21-Apr-11 | 27-Apr-11 | 6 | NDOR/address FHWA comments and resubmit |
Richland NW | Bio doc vers 2 | 31702 | 7019-10 | 27-Apr-11 | 02-May-11 | 5 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Richland Northwest | CE | 31702 | 7019-10 | 28-Jul-11 | 03-Aug-11 | 6 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Concord East | DR 53 | 31723 | 3130-5 | 15-Dec-10 | 17-Dec-10 | 2 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Concord East | SHPO Concur Req | 31723 | 3130-5 | 30-Sep-11 | 30-Sep-11 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Concord East | Bio doc version 1 | 31723 | 3130-5 | 10/27/2011 | 10/28/2011 | 1 | NDOR/address FHWA comments and resubmit |
Concord East | Bio doc version 1 | 31723 | 3130-5 | 10/31/2011 | 11/2/2011 | 2 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Fordyce West | DR 53 | 31761 | 7014-34 | 06-Dec-10 | 15-Dec-10 | 9 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Fordyce West | SHPO concur req | 31761 | 7014-34 | 8/7/2012 | 8/16/2012 | 9 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Wayne trail | 4(f) exemption req | 31777 | 90-4 | 22-Apr-10 | 28-Apr-10 | 6 | NDOR/address FHWA comments and resubmit |
Wayne Trail Phase 2 | SHPO concur req | 31777 | 90-4 | 7/29/2013 | 7/30/2013 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
E Jct N-9 to Dakota City | Bio Assessment | 31784 | 354-120 | 09-Aug-10 | 18-Aug-10 | 9 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Laurel Northeast | SHPO Letter | 31786 | 206-108 | 12-Aug-10 | 16-Aug-10 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Laurel Northeast | NEPA Determ | 31786 | 206-108 | 20-Aug-10 | 30-Aug-10 | 10 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Laurel Northeast | Bio doc | 31786 | 206-108 | 13-Sep-10 | 23-Sep-10 | 10 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Laurel Northeast | NEPA CE | 31786 | 206-108 | 29-Oct-10 | 08-Nov-10 | 10 | NDOR/address FHWA comments and resubmit |
Laurel NE | Revised CE | 31786 | 206-108 | 08-Nov-10 | 08-Nov-10 | 0 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
West Bow and Norwegian Bow Bridges | NEPA Determ | 31788 | 814-115 | 18-Aug-10 | 03-Sep-10 | 16 | NDOR to address FHWA comments and resubmit |
West Bow & Norw Bow Brdgs | NEPA Determ 2nd submittal | 31788 | 814-115 | 27-Sep-10 | 29-Sep-10 | 2 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
West Bow Norw. Bow Crk bridges | 106 consult SHPO concur | 31788 | 814-115 | 20-Oct-10 | 22-Oct-10 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
West Bow and Norw Bow Crk brgs | CE | 31788 | 814-115 | 03-Dec-10 | 14-Dec-10 | 11 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Tilden South and In Tilden and Battle Creek North | Cat Ex - batched | 31808 | 453-107 | 3/19/2013 | 3/27/2013 | 8 | NDOR/address FHWA comments and resubmit |
Tilden South and In Tilden and Battle Creek North | Cat Ex - 2nd submittal | 31808 | 453-107 | 6/28/2013 | 7/8/2013 | 10 | NDOR/address FHWA comments and resubmit |
Tilden South and In Tilden and Battle Creek North | Cat Ex -V3 with 4(f) Exception | 31808 | 453-107 | 7/26/2013 | 7/30/2013 | 4 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Petersburg - Elgin | SHPO concur request | 31809 | 143-112 | 5/15/2012 | 5/25/2012 | 10 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Petersburg - Elgin | Cat Ex | 31809 | 143-112 | 12/6/2012 | 12/12/2012 | 6 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Jackson West | DR-53 | 31817 | 207-115 | 9/10/2013 | 9/11/2013 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Verdigre North | DR-53 | 31821 | 7054-19 | 4/2/2012 | 4/26/2012 | 24 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Bloomfield West | T&E Memo | 31822 | 7054-20 | 12-May-10 | 27-May-10 | 15 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Bloomfield West | SHPO concur req | 31822 | 7054-20 | 21-Mar-11 | 29-Mar-11 | 8 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Bloomfield West | DR 53 | 31822 | 7054-20 | 22-Mar-11 | 29-Mar-11 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Bloomfield West | CE | 31822 | 7054-20 | 01-Aug-11 | 04-Aug-11 | 3 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Bloomfield West | Wetlands determination | 31822 | 7054-20 | 7/25/2012 | 8/15/2012 | 21 | None |
Foster Northwest & Southeast | DR 53 | 31825 | 134-110 | 7/10/2012 | 7/13/2012 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Foster Northwest and Southeast | SHPO concur req | 31825 | 134-110 | 9/11/2013 | 9/12/2013 | 1 | NDOR/address FHWA comments and resubmit |
Albion-Petersburg | SHPO Concur Req | 31826 | 143-114 | 12-Jul-11 | 13-Jul-11 | 1 | NDOR/address FHWA comments and resubmit |
Albion to Petersburg | SHPO Concur Req R2 | 31826 | 143-114 | 22-Jul-11 | 27-Jul-11 | 5 | NDOR/address FHWA comments and resubmit |
Albion - Petersburg | CE | 31826 | 143-114 | 12/5/2011 | 12/9/2011 | 4 | NDOR/address FHWA comments and resubmit |
Albion - Petersburg | CE - revised | 31826 | 143-114 | 1/30/2012 | 2/7/2012 | 8 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
E. Jct N-45 to Madison | DR 53 | 31829 | 325-107 | 02-Aug-11 | 05-Aug-11 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
E Jct N-45 to Madison | SHPO concur request | 31829 | 325-107 | 2/14/2012 | 2/17/2012 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
E Jct N-45 to Madison | Bio doc Re-eval - Scope Change | 31829 | 325-107 | 8/26/2013 | 8/28/2013 | 2 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
E Jct N-45 to Madison; In Madison | 4(f) de minimis revised | 31829 | 325-107 | 9/20/2013 | 9/23/2013 | 3 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Albion Wwest | DR 53 | 31833 | 915-118 | 28-Sep-10 | 04-Oct-10 | 6 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Albion West | SHPO concur request | 31833 | 915-118 | 3/14/2012 | 3/15/2012 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Albion West | Cat Ex | 31833 | 915-118 | 8/1/2012 | 8/15/2012 | 14 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Norfok 25th St widening | Bio doc vers 1 | 31875 | 6001-1 | 01-Mar-11 | 02-Mar-11 | 1 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Norfolk 25th St. | Reeval | 31875 | 6001-1 | 16-Mar-11 | 17-Mar-11 | 1 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Norfolk 25th St. | Reeval memo | 31875 | 6001-1 | 29-Mar-11 | 31-Mar-11 | 2 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
25th St, Norfolk | Reeval Memo | 31875 | 6001-1 | 01-Apr-11 | 01-Apr-11 | 0 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
25th St. - Norfolk | Fence relocation | 31875 | 6001-1 | 10/26/2012 | 11/15/2012 | 20 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Martinsburg NE | DR 53 | 31880 | 7026-20 | 22-Mar-11 | 29-Mar-11 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Martinsburg NE | SHPO concur req | 31880 | 7026-20 | 6/25/2012 | 6/27/2012 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Martinburg NE | Section 106 re-eval information | 31880 | 7026-20 | 3/7/2013 | 3/7/2013 | 0 | None |
Martinsburg NE | SHPO Re-eval | 31880 | 7026-20 | 5/21/2013 | 5/31/2013 | 10 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Martinsburg NE | CE rev | 31880 | 7026-20 | 8/22/2013 | 8/22/2013 | 0 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Martinsburg NE | Cat Ex | 31880 | 7026-20 | 8/20/2013 | 8/22/2013 | 2 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Creighton - Center | DR 53 | 31884 | 135-101 | 4/25/2013 | 5/1/2013 | 6 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Creighton to Center | SHPO concur req | 31884 | 135-101 | 6/24/2013 | 6/26/2013 | 2 | NDOR/address FHWA comments and resubmit |
Creighton to Center | Arch Testing Plan | 31884 | 135-101 | 8/1/2013 | 8/2/2013 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Union Crk to N-57 | Bio doc vers 1 | 31887 | 326-111 | 09-Nov-10 | 12-Nov-10 | 3 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Stanton South | DR 53 | 31889 | 573-107 | 11/7/2011 | 11/14/2011 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Stanton South | SHPO concur request | 31889 | 573-107 | 5/18/2012 | 5/25/2012 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Stanton South | Bio doc version 1 | 31889 | 573-107 | 7/10/2012 | 7/16/2012 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Stanton South | Cat Ex | 31889 | 573-107 | 9/28/2012 | 10/24/2012 | 26 | NDOR/address FHWA comments and resubmit |
Stanton South | Cat Ex - 2nd submittal | 31889 | 573-107 | 1/15/2013 | 1/25/2013 | 10 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Hartington Trail | DR 53 | 31891 | 846-106 | 9/6/2012 | 9/17/2012 | 11 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Hartington West | 106 concur req | 31891 | 846-106 | 12/21/2012 | 12/26/2012 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Wayne Bridges | SHPO Concur Req | 31893 | 154-118 | 29-Sep-11 | 30-Sep-11 | 1 | NDOR/address FHWA comments and resubmit |
N-32 - Pilger | Bio doc vers 1 | 31894 | 153-113 | 28-Oct-10 | 03-Nov-10 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
N-32 to Pilger, Stanton Co | SHPO concur req | 31894 | 153-113 | 06-Jan-11 | 07-Jan-11 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
In Tilden and Battle Creek North | Bio doc vers 1 | 31897 | 453-110 | 21-Dec-10 | 27-Dec-10 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
In Tilden and Battle Creek North | 4(f) Exception | 31897 | 453-110 | 6/28/2013 | 7/8/2013 | 10 | NDOR/address FHWA comments and resubmit |
Fordyce East & West | DR 53 | 31912 | 126-116 | 11-Oct-11 | 13-Oct-11 | 2 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Fordyce East and West | Cat Ex - revised | 31912 | 126-116 | 4/25/2013 | 5/13/2013 | 18 | NDOR/address FHWA comments and resubmit |
Fordyce East and West | Cat Ex - V3 | 31912 | 126-116 | 6/7/2013 | 6/19/2013 | 12 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
N-13 to Osmond | DR 53 | 31917 | 1214-111 | 12-Jul-11 | 19-Jul-11 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
N-13 to Osmond | SHPO concur request | 31917 | 1214-111 | 5/17/2012 | 6/4/2012 | 18 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Santee Spur | DR 53 | 31918 | S54D-103 | 01-Aug-11 | 04-Aug-11 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Santee Spur | SHPO concur request | 31918 | S54D-103 | 11/15/2011 | 11/22/2011 | 7 | NDOR/address FHWA comments and resubmit |
Santee Spur | SHPO concur - revised | 31918 | S54D-103 | 12/6/2011 | 12/8/2011 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Santee Spur | Bio doc version 1 | 31918 | S54D-103 | 12/30/2011 | 1/3/2012 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Santee Spur | Tribal SHPO concur request | 31918 | S54D-103 | 1/10/2012 | 1/10/2012 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
W. Jct N-15 to Newcastle | DR 53 | 31919 | 126-115 | 13-Jun-11 | 16-Jun-11 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
W. Jct. N-15 to Newcastle | 106 concur req | 31919 | 126-115 | 11/29/2012 | 12/7/2012 | 8 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Wayne West | DR 53 | 31920 | 354-121 | 2/16/2012 | 2/17/2012 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Wayne West | 106 concur req | 31920 | 354-121 | 11/26/2012 | 12/3/2012 | 7 | NDOR/address FHWA comments and resubmit |
Wayne West | 106 concur req - revised | 31920 | 354-121 | 12/5/2012 | 12/7/2012 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
St Edward to Albion | DR 53 | 31921 | 393-105 | 9/26/2012 | 10/12/2012 | 16 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Columbus projects | Bio doc vers 1 | 31924 | 6065-2 | 28-Sep-10 | 01-Oct-10 | 3 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Columbus projects | SHPO Concur req | 31924 | 6065-5 | 29-Sep-10 | 01-Oct-10 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Columbus Viaducts | HazMat Section review | 31924 | 6061-8 | 06-Dec-10 | 06-Dec-10 | 0 | NDOR/address FHWA comments and resubmit |
Columbus viaducts | DEA | 31924 | 6065-5 | 04-Apr-11 | 05-Apr-11 | 1 | NDOR/prepare for public outreach (if document is a DEA, the outreach is a hearing) |
UPRR/3rd Ave. & UPRR/12th & 18th Ave., Columbus | Public Meeting Materials | 31924 | 6065-5 | 20-Apr-11 | 25-Apr-11 | 5 | NDOR/address FHWA comments and resubmit |
Columbus Viaducts | Final EA | 31924 | 6065-5 | 20-Jun-11 | 21-Jun-11 | 1 | NDOR/address FHWA comments and resubmit |
Columbus Viaducts | partial submittal FEA#2 | 31924 | 6065(5) | 01-Jul-11 | 01-Jul-11 | 0 | NDOR/address FHWA comments and resubmit |
Columbus Viaducts | FEA, version 3 | 31924 | 6065-5 | 08-Jul-11 | 08-Jul-11 | 0 | NDOR/address FHWA comments and resubmit |
N-57 to Wisner | Bio doc version 1 | 31938 | 2756-140 | 11/22/2011 | 11/25/2011 | 3 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
N-57 to Wisner | SHPO concur request | 31938 | 2756-140 | 2/8/2012 | 2/17/2012 | 9 | NDOR/address FHWA comments and resubmit |
N-57 to Wisner | 106 Concur Req (2nd Submittal) | 31938 | 2756-140 | 3/28/2012 | 4/25/2012 | 28 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
N-57 to Wisner | Cat Ex | 31938 | 2756-140 | 6/12/2012 | 6/21/2012 | 9 | NDOR/address FHWA comments and resubmit |
N-57 to Wisner | Cat Ex - 2nd submittal | 31938 | 2756-140 | 7/16/2012 | 7/23/2012 | 7 | NDOR/address FHWA comments and resubmit |
N-57 - Wisner | Cat Ex - 3rd submittal | 31938 | 2756-140 | 8/7/2012 | 8/9/2012 | 2 | NDOR/address FHWA comments and resubmit |
N57 to Wisner | Cat Ex v4 | 31938 | 2756-140 | 8/14/2012 | 8/14/2012 | 0 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Rogers East & West | DR 53 | 31942 | 306-132 | 25-Oct-10 | 26-Oct-10 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
In Madison & East | DR 53 | 31950 | 325-108 | 12-Apr-11 | 15-Apr-11 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
In Madison & East | SHPO concur req | 31950 | 325-108 | 11-Oct-11 | 12-Oct-11 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
In Madison | SHPO concur req - revised | 31950 | 325-108 | 6/19/2013 | 6/24/2013 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
E Jct N-45 to Madison, In Madison | 4(f) de minimis | 31950 | 325-108 | 9/13/2013 | 9/17/2013 | 4 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Osmond Community School Improvement | Cat Ex reeval | 31953 | 70-18 | 4/10/2013 | 4/22/2013 | 12 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
25th St Improvments Norfolk | 4(f) De Minimis | 31975 | 6001-1 | 12-May-10 | 14-May-10 | 2 | NDOR/address FHWA comments and resubmit |
3rd Ave, Columbus | DR 53 | 31990 | 6065-6 | 12-Aug-11 | 17-Aug-11 | 5 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Windom, E 7 to E 3, Wayne | DR 53 | 31991 | 6709-2 | 10-Nov-10 | 12-Nov-10 | 2 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Windom St, E 7th - E 3rd, Wayne | SHPO concur req | 31991 | 6709-2 | 02-Sep-11 | 06-Sep-11 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Windom St, from E. 3rd to E. 7th | Bio doc version 1 | 31991 | 6709-2 | 12/22/2011 | 12/23/2011 | 1 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Windom St., E 3rd - E 7th, Wayne | 4(f) exception | 31991 | 6709-2 | 8/23/2012 | 8/31/2012 | 8 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Windom St Improvement | SHPO concur req | 31991 | 6709-2 | 9/10/2012 | 9/14/2012 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Jct US 75 & US 77, N-35 | SHPO concur req | 31995 | 754-110 | 29-Sep-10 | 04-Oct-10 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Winside East | DR 53 | 32011 | 3100-1 | 24-Jan-11 | 31-Jan-11 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Winside East | Bio doc vers 1 | 32011 | 3100-1 | 08-Apr-11 | 08-Apr-11 | 0 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Winside East | SHPO concur req | 32011 | 3100-1 | 25-Apr-11 | 25-Apr-11 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Winside East | CE | 32011 | 3100-1 | 07-Jul-11 | 08-Jul-11 | 1 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Howells North | DR 53 | 32043 | 3175-3 | 06-Dec-10 | 15-Dec-10 | 9 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Howells North | SHPO concur request | 32043 | 3175-3 | 12/1/2011 | 12/8/2011 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Howells North | Bio doc version 1 | 32043 | 3175-3 | 12/7/2011 | 12/14/2011 | 7 | NDOR/address FHWA comments and resubmit |
Howells North | Bio doc - revised | 32043 | 3175-3 | 12/15/2011 | 12/20/2011 | 5 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Howells North | CE | 32043 | 3175-3 | 3/27/2012 | 4/23/2012 | 27 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Howells North | Cat Ex - revised | 32043 | 3175-3 | 6/6/2012 | 6/12/2012 | 6 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
N-9 - US-77 | DR 53 | 32049 | 516-105 | 8/28/2012 | 8/31/2012 | 3 | NDOR/address FHWA comments and resubmit |
N-9 to US-77 | DR 53 re-submittal | 32049 | 516-105 | 8/31/2012 | 9/7/2012 | 7 | None |
N-91 to N-32 | DR 53 | 32060 | 573-108 | 11/2/2012 | 11/15/2012 | 13 | NDOR/address FHWA comments and resubmit |
US-91 to N-32 | DR 53 | 32060 | 573-108 | 2/7/2013 | 2/8/2013 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Crofton East | DR 53 | 32061 | 125-115 | 12/7/2011 | 12/15/2011 | 8 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Crofton East | SHPO concur request | 32061 | 125-115 | 6/5/2012 | 6/6/2012 | 1 | NDOR/address FHWA comments and resubmit |
Norfolk to Stanton | SHPO concur req | 32063 | 246-102 | 03-Aug-11 | 04-Aug-11 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Wayne West | DR 53 | 32067 | 7090-20 | 11-Apr-11 | 12-Apr-11 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Autumn Olive Land - Riverview Dr | DR 53 | 32074 | 5314-2 | 06-Apr-11 | 12-Apr-11 | 6 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
East 17th St. Paving | SHPO concur req | 32074 | 5314-2 | 10/1/2012 | 10/12/2012 | 11 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Autumn Olive Ln - Riverview Dr | Bio doc version 1 | 32074 | 5314-2 | 12/28/2012 | 1/11/2013 | 14 | None |
Pierce Co SRTS | DR 53 | 32076 | 70-20 | 02-Mar-11 | 02-Mar-11 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Pierce Community SRTS | SHPO concur req | 32076 | 70-20 | 13-Jun-11 | 20-Jun-11 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Pierce SRTS | 106 concur req | 32076 | 70-20 | 3/7/2013 | 3/13/2013 | 6 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Pierce Safe Routes to School | Sectopm 4(f) | 32076 | 70-20 | 7/22/2013 | 7/25/2013 | 3 | NDOR/address FHWA comments and resubmit |
Pierce SRTS | Section 4(f) req | 32076 | 70-20 | 8/23/2013 | 8/29/2013 | 6 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Santee Community SRTS | DR 53 | 32078 | 54-17 | 7/13/2012 | 7/24/2012 | 11 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Dakota Ave | Bio doc - version 1 | 32081 | 5305-10 | 07-May-10 | 20-May-10 | 13 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Dakota Ave Resurfacing 29th to Regency Parkway | Noise review | 32081 | 5305-11 | 4/16/2013 | 4/29/2013 | 13 | None |
Dakota Ave - I-129 - 29th St | 4(f) | 32081 | 5305-10 | 7/24/2013 | 7/24/2013 | 0 | NDOR/address FHWA comments and resubmit |
Dakota Ave Ave, South Sioux City | Cat Ex | 32081 | 5305-10 | 7/23/2013 | 7/24/2013 | 1 | NDOR/address FHWA comments and resubmit |
Dakota Ave - I-129 - 29th St | 4(f) - revised | 32081 | 5305-10 | 7/25/2013 | 7/26/2013 | 1 | NDOR/address FHWA comments and resubmit |
Dakota Ave | rev 4F | 32081 | 5305-11 | 7/30/2013 | 8/8/2013 | 9 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Dakota Avenue | Cat Ex | 32081 | 5305-10 | 8/29/2013 | 8/29/2013 | 0 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Cedar Rapids Bridge Renova. | DR 53 | 32083 | 5-Jun | 19-Aug-11 | 03-Sep-11 | 15 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Cedar Rapids Bridge Renovation | SHPO concur req | 32083 | 6-5 | 9/4/2012 | 9/13/2012 | 9 | NDOR/address FHWA comments and resubmit |
Cedar Rapids Bridge Renovation | 106 concur request | 32083 | 6-5 | 1/9/2013 | 1/16/2013 | 7 | None |
Cedar Rapids Bridge Renovation | 106 concur req - revised | 32083 | 6-5 | 1/31/2013 | 1/31/2013 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Cedar Rapids Bridge Renovation | Section 4(f) | 32083 | 6-5 | 3/25/2013 | 4/3/2013 | 9 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Cedar Rapids Bridge Renovation | Cat Ex | 32083 | 6-5 | 5/3/2013 | 5/21/2013 | 18 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Cedar Rapids Bridge Renovation | SHPO review | 32083 | 6-5 | 7/19/2013 | 7/24/2013 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Dakota City Depot Renovation | SHPO concur req | 32084 | 22-29 | 7/26/2012 | 8/14/2012 | 19 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Dakota City Depot Renovation | SHPO concur req | 32084 | 22-29 | 9/10/2012 | 9/17/2012 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Distr 3 High Mast Twr | Bio doc version 1 | 32090 | 3-101 | 16-Jun-10 | 21-Jun-10 | 5 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Missing Link Trail | DR 53 | 32107 | 22-30 | 21-Sep-11 | 26-Sep-11 | 5 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
South Sioux City Missing Link | Bio doc version 1 | 32107 | 22-30 | 3/2/2012 | 3/8/2012 | 6 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
South Sioux City Missing Link Trail | 106 Concur Req | 32107 | 22-30 | 3/28/2012 | 4/25/2012 | 28 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
South Sioux City Missing Link Trail | 4(f) excep req | 32107 | 22-30 | 8/28/2012 | 9/4/2012 | 7 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
South Sioux City Missing Link Trail | Cat Ex | 32107 | 22-30 | 1/17/2013 | 1/25/2013 | 8 | NDOR/address FHWA comments and resubmit |
S. Sioux City Missing Link Trail | Cat Ex | 32107 | 22-30 | 2/20/2013 | 3/4/2013 | 12 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
US-30 NE of Schuyler | Bio Assessment | 32109 | 306-136 | 06-Aug-10 | 18-Aug-10 | 12 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
US30 NE of Schuyler | SHPO concurrence request | 32109 | 306(106) | 01-Sep-10 | 23-Sep-10 | 22 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Jct N-91 and US-81 | Bio doc vers 1 | 32113 | 915-123 | 26-Oct-10 | 27-Oct-10 | 1 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
US-77 Intersection Improvement | DR 53 | 32114 | 327-111 | 1/4/2012 | 1/16/2012 | 12 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Jct N-32/US-77 | SHPO concur req | 32114 | 327-111 | 6/7/2012 | 6/14/2012 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Jct N-32 - US-77 | Cat Ex | 32114 | 327-111 | 4/25/2013 | 5/1/2013 | 6 | NDOR/address FHWA comments and resubmit |
Jct N-32/US-77 | Cat Ex - revised | 32114 | 327-111 | 5/22/2013 | 6/10/2013 | 19 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Jct Us-20 - Jct N-59 | Bio doc vers 1 | 32117 | 814-119 | 29-Sep-10 | 04-Oct-10 | 5 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Decatur South | DR 53 | 32121 | 753-117 | 3/16/2012 | 4/6/2012 | 21 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Decatur South in Burt Co; Jct N-12 to Jct N-121 in Cedar Co | Cat Ex | 32121 | 753-117 | 9/23/2013 | 10/1/2013 | 8 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
In South Sioux City | DR 53 | 32122 | 774-126 | 1/23/2012 | 2/1/2012 | 9 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Wynot E and W | DR 53 | 32131 | 126-117 | 5/30/2013 | 5/31/2013 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Santee Spur East | DR 53 | 32135 | 125-116 | 11/7/2011 | 11/14/2011 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Santee Spur East | SHPO and THPO concur requests | 32135 | 125-116 | 5/22/2012 | 6/6/2012 | 15 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Santee Spur East | ThPO concur - 2nd request | 32135 | 125-116 | 9/21/2012 | 10/11/2012 | 20 | None |
Santee Spur East | Bio doc v1 - 3 drafts | 32135 | 125-116 | 12/5/2012 | 12/26/2012 | 21 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Santee Spur E | CE | 32135 | 125-116 | 8/8/2013 | 8/8/2013 | 0 | NDOR/address FHWA comments and resubmit |
Santee Spur East | Cat Ex - revised | 32135 | 125-116 | 8/16/2013 | 8/16/2013 | 0 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Macy to Winnebago | Bio doc vers 1 | 32140 | 754-111 | 15-Mar-11 | 16-Mar-11 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Macy - Winnebago | SHPO concur req | 32140 | 754-111 | 13-Jul-11 | 19-Jul-11 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
N-57 East Bridges | DR 53 | 32148 | 326-114 | 1/30/2013 | 1/31/2013 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
N-57 East Bridges | 106 concur req | 32148 | 326-114 | 3/8/2013 | 3/12/2013 | 4 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Wayne underpass | DR 53 | 32153 | 90-6 | 07-Dec-10 | 15-Dec-10 | 8 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Norfolk Elkhorn River Trail | Bio doc version 1 | 32154 | 59-22 | 7/12/2012 | 7/26/2012 | 14 | NDOR/address FHWA comments and resubmit |
Norfolk Elkhorn River Trail | Bio doc version 2 | 32154 | 59-22 | 7/26/2012 | 7/26/2012 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Norfolk Elkhorn River Trail | SHPO concur req | 32154 | 59-22 | 8/6/2012 | 8/16/2012 | 10 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Elkhorn River Trail | 4(f) net benefit concur req | 32154 | 59-22 | 8/24/2012 | 8/31/2012 | 7 | NDOR/address FHWA comments and resubmit |
TaHaZouka Park, Norfolk | SHPO concur req - revised | 32154 | 59-22 | 9/18/2012 | 10/11/2012 | 23 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Elkhorn River Trail | SHPO and 4(f) - NDOR inq | 32154 | 59-22 | 10/4/2012 | 11/5/2012 | 32 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Elkhorn River Trail | Cat Ex | 32154 | 59-22 | 4/17/2013 | 4/30/2013 | 13 | NDOR/address FHWA comments and resubmit |
Elkhorn River Trail | Cat Ex - revised | 32154 | 59-22 | 5/21/2013 | 6/5/2013 | 15 | NDOR/address FHWA comments and resubmit |
Elkhorn River Trail | 4(f) | 32154 | 59-22 | 7/8/2013 | 7/9/2013 | 1 | NDOR/address FHWA comments and resubmit |
Elkhorn River Trail | Section 4(f) - revised | 32154 | 59-22 | 7/17/2013 | 7/22/2013 | 5 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Elkhorn River Trail | Cat Ex - revised | 32154 | 59-22 | 7/31/2013 | 7/31/2013 | 0 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
West of Columbus | DR 53 | 32163 | 813-145 | 09-Mar-11 | 10-Mar-11 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Jct US-81/N-22 West of Columbus | SHPO concur request | 32163 | 813-145 | 12/6/2011 | 12/9/2011 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Jct US-81/N-22 West of Columbus | THPO concur request | 32163 | 813-145 | 3/5/2012 | 3/6/2012 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Jct US-81/N22 West of Columbus | Cat Ex | 32163 | 813-145 | 10/3/2012 | 10/26/2012 | 23 | NDOR/address FHWA comments and resubmit |
Jct US-81/N-22 W of Columbus | Cat Ex - 2nd submittal | 32163 | 813-145 | 12/6/2012 | 12/12/2012 | 6 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Thurston Spur North and South | DR 53 | 32164 | 94-117 | 01-Jun-11 | 10-Jun-11 | 9 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Thurston Spur South and North | Bio doc version 1 | 32164 | 94-117 | 11/22/2011 | 11/28/2011 | 6 | NDOR/address FHWA comments and resubmit |
Thurston Spur South and North | Bio Doc V2 | 32164 | 94-117 | 11/30/2011 | 12/13/2011 | 13 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Thurston Spur North and South | SHPO concur request | 32164 | 94-117 | 2/28/2012 | 3/6/2012 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Thurston Spur North and South | THPO concur request - 2nd submittal | 32164 | 94-117 | 4/23/2012 | 5/9/2012 | 16 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
DMS Replacement | DR-53 | 32167 | ITSN-14 | 8/21/2013 | 8/22/2013 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Tilden North Bank Repair | DR 53 | 32168 | ER 2580-2 | 23-Sep-11 | 23-Sep-11 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
South Sioux City Trail | DR 53 | 32169 | 22-32 | 12-Sep-11 | 16-Sep-11 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
South Sioux city Connecting Schools Trail | SHPO concur req | 32169 | 22-32 | 8/13/2013 | 8/19/2013 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Emergency Repair Projects | DR 53 | 32173 | ER 3-102 | 11/9/2011 | 11/10/2011 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Temp 2010 ER Projects | SHPO concur request | 32173 | 3-102 | 1/3/2012 | 1/3/2012 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Knox Co Rumble Bars | DR 53 | 32176 | 54-20 | 22-Feb-11 | 23-Feb-11 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Knox County Rumble Bars | Bio doc version 1 | 32176 | 54-20 | 4/17/2012 | 4/23/2012 | 6 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Orchard South | Dr53 | 32177 | ER 2605(4) | 07-Mar-11 | 07-Mar-11 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Orchard South | ShPO concur request | 32177 | ER 2605-4 | 12/6/2011 | 12/6/2011 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Orchard South | Bio doc version 1 | 32177 | ER 2605-4 | 12/19/2011 | 12/19/2011 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Orchard South | CE | 32177 | ER 2605-4 | 1/10/2012 | 1/11/2012 | 1 | NDOR/address FHWA comments and resubmit |
Orchard South | draft CE | 32177 | ER 2605-4 | 1/13/2012 | 1/17/2012 | 4 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Wakefield Logan Crk Trl Phse 2 | DR 53 | 32178 | 26-14 | 04-Mar-11 | 08-Mar-11 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Logan Creek Trail, Phase II | 106 concur request | 32178 | 26-14 | 2/6/2013 | 2/13/2013 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Wakefield Logan Creek Trail Phase II | Section 4(f) | 32178 | 26-14 | 7/2/2013 | 7/8/2013 | 6 | NDOR/address FHWA comments and resubmit |
Wakefield Logan Creek Trail - Phase II | Section 4(f) - revised | 32178 | 26-14 | 7/17/2013 | 7/22/2013 | 5 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Meadow Grove N | DR 53 | 32180 | ER 2895-2 | 23-Sep-11 | 23-Sep-11 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Meadow Grove North | Change in ER project descriptions | 32180 | 2895-2 | 5/16/2013 | 5/20/2013 | 4 | None |
Meadow Grove North | Scope Change memo | 32180 | 2895-2 | 5/16/2013 | 5/22/2013 | 6 | NDOR/address FHWA comments and resubmit |
Battle Creek North | DR 53 - 1 | 32181 | ER 2915-3 | 23-Sep-11 | 23-Sep-11 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Battle Creek North 2?? | DR 53 - 2 | 32181 | ER 2915-3 | 23-Sep-11 | 23-Sep-11 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Riverview Dr to Foundary Road, Dakota County | DR 53 | 32184 | 5314-3 | 11/25/2011 | 12/1/2011 | 6 | NDOR/address FHWA comments and resubmit |
W 29th, US-77 to Lake Ave | DR 53 | 32186 | 5306-8 | 11/25/2011 | 12/1/2011 | 6 | NDOR/address FHWA comments and resubmit |
East 14th Ave, Columbus | DR 53 | 32187 | 6067-1 | 28-Jun-11 | 30-Jun-11 | 2 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
SRTS Clarkson and Howells | DR 53 | 32188 | 19-11 | 01-Jun-11 | 10-Jun-11 | 9 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Clarkson, Howells SRTS | SHPO and THPO concur req | 32188 | 19-11 | 1/30/2013 | 1/31/2013 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Schuyler Resurfacing | DR 53 | 32189 | 6957-1 | 28-Jun-11 | 30-Jun-11 | 2 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Schuyler Citywide Resurfacing | 106 concur req | 32189 | 6957-1 | 11/28/2012 | 12/3/2012 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Columbus East Viaduct | DR 53 | 32190 | 71-33 | 1/13/2012 | 1/17/2012 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Columbus East Viaduct | Purpose and Need review | 32190 | 71-33 | 7/22/2013 | 7/30/2013 | 8 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Primrose East | DR 53 | 32192 | 6-Jun | 13-Jul-11 | 20-Jul-11 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Primrose East | SHPO concur request | 32192 | 6-Jun | 12/7/2011 | 12/9/2011 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Primrose East | CE | 32192 | 6-Jun | 1/30/2012 | 2/3/2012 | 4 | NDOR/address FHWA comments and resubmit |
Primrose East | Cat Ex | 32192 | 6-Jun | 2/9/2012 | 2/17/2012 | 8 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Santee Sioux E. Village St. Improvement | DR 53 | 32206 | 54-21 | 10/3/2012 | 10/26/2012 | 23 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
N-32 North | DR 53 | 32208 | 1213-105 | 8/15/2013 | 8/19/2013 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Norfolk-Stanton | Bio doc vers 1 | 32603 | 246-102 | 04-Feb-11 | 08-Feb-11 | 4 | NDOR/address FHWA comments and resubmit |
Norfolk - Stanton | Bio doc vers 2 | 32603 | 246-102 | 08-Feb-11 | 08-Feb-11 | 0 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Bloomfield West | SHPO concur req | 38122 | 7054-20 | 21-Apr-11 | 25-Apr-11 | 4 | NDOR/address FHWA comments and resubmit |
Red Cloud Northwest | DR-53 | 41149 | 7091-5 | 4/2/2012 | 4/6/2012 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Red Cloud NW | SHPO concur request | 41149 | 7091-5 | 5/17/2012 | 5/31/2012 | 14 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Red Cloud West | DR 53 | 41380 | 2145-7 | 08-Apr-11 | 12-Apr-11 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
In Polk and West | Cat Ex | 41516 | 665-104 | 3/11/2013 | 3/22/2013 | 11 | NDOR/address FHWA comments and resubmit |
In Polk and West | DR 53 | 41526 | 665-104 | 23-Feb-11 | 23-Feb-11 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
In Polk & West | SHPO concur req | 41526 | 665-104 | 9/19/2012 | 10/11/2012 | 22 | NDOR/address FHWA comments and resubmit |
In Polk & West | 106 concur req follow-up | 41526 | 665-104 | 11/27/2012 | 12/3/2012 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
In Polk and West | Cat Ex - revised | 41526 | 665-104 | 3/27/2013 | 4/5/2013 | 9 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Bradshaw Southeast | DR-53 | 41634 | 7093-23 | 21-Oct-10 | 21-Oct-10 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Bradshaw SE | SHPO concur req | 41634 | 7093-23 | 29-Oct-10 | 04-Nov-10 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Red Cloud South | DR 53 | 41877 | 2811-112 | 03-Oct-11 | 05-Oct-11 | 2 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Red Cloud South | SHPO concur req | 41877 | 2811-112 | 11-Oct-11 | 13-Oct-11 | 2 | NDOR/address FHWA comments and resubmit |
Red Cloud South | SHPO concur req - revised | 41877 | 2811-112 | 4/2/2013 | 4/17/2013 | 15 | NDOR/address FHWA comments and resubmit |
Red Cloud South | SHPO concur req - revised | 41877 | 2811-112 | 8/26/2013 | 8/29/2013 | 3 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Red Cloud South | Bio doc | 41877 | 2811-112 | 8/27/2013 | 8/29/2013 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Ord North | DR 53 | 41914 | 704-106 | 30-Nov-10 | 13-Dec-10 | 13 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Ord North | SHPO concur req | 41914 | 704-106 | 25-Feb-11 | 28-Feb-11 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Greeley South | DR 53 | 41954 | 2813-110 | 9/12/2012 | 9/17/2012 | 5 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Greeley South | SHPO concur req | 41954 | 2813-110 | 10/17/2012 | 10/23/2012 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Locust St., Grand Island | DR 53 | 41994 | 344-126 | 27-Sep-10 | 04-Oct-10 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Locust St, Grand Island | SHPO concur | 41994 | 344-126 | 13-Oct-10 | 22-Oct-10 | 9 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
US-281 to Locust Sreet, Grand Island | Bio doc version 1 | 41994 | 344-126 | 12/14/2011 | 12/15/2011 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
US-281 - Locust Street, Grand Island | Suppl 106 concur request | 41994 | 344-126 | 2/13/2012 | 2/14/2012 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Locst St, Grand Island | Cat Ex - revised | 41994 | 344-126 | 6/11/2012 | 6/12/2012 | 1 | NDOR/address FHWA comments and resubmit |
Central City viaduct | DR 53 | 42013 | 142-123 | 09-Mar-11 | 10-Mar-11 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Central City Viaduct | 106 concur req | 42013 | 142-123 | 3/14/2013 | 3/25/2013 | 11 | NDOR/address FHWA comments and resubmit |
Wood River West | SHPO concur req | 42032 | 112-114 | 29-Oct-10 | 08-Nov-10 | 10 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Wood River West | Bio doc vers 1 | 42032 | 112-114 | 30-Nov-10 | 10-Dec-10 | 10 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Wood River West | Reevaluation | 42032 | 112-114 | 25-Apr-11 | 02-May-11 | 7 | NDOR/address FHWA comments and resubmit |
North Loup to Ord | DR 53 | 42089 | 113-116 | 12-Apr-11 | 15-Apr-11 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
North Loup to Ord | SHPO concur req | 42089 | 113-116 | 20-Jul-11 | 26-Jul-11 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
North Loup to Ord | Purpose and Need | 42089 | 113-116 | 5/7/2012 | 5/11/2012 | 4 | NDOR/address FHWA comments and resubmit |
North Loup to Ord | Purpose & Need | 42089 | 113-116 | 12/6/2012 | 1/7/2013 | 32 | NDOR/address FHWA comments and resubmit |
Kearney Bypass | Draft final EA | 42103 | Oct-51 | 02-Jul-10 | 23-Jul-10 | 21 | NDOR/address FHWA comments and resubmit |
Kearney | Final EA | 42103 | Oct-51 | 08-Sep-10 | 10-Sep-10 | 2 | NDOR/address FHWA comments and resubmit |
Kearney Bypass | Final EA | 42103 | 10--51 | 27-Sep-10 | 28-Sep-10 | 1 | document approved, FHWA to issue decision document |
Kearney East | Merge letter | 42103 | Oct-51 | 01-Oct-10 | 01-Oct-10 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Kearney East Bypass | Draft Public Responses | 42103 | Oct-51 | 09-Dec-10 | 10-Dec-10 | 1 | NDOR/address FHWA comments and resubmit |
Kearney Bypass | ACE P&N com review | 42103 | Oct-51 | 17-Dec-10 | 20-Dec-10 | 3 | NDOR/address FHWA comments and resubmit |
Kearney Bypass | Errata doc | 42103 | Oct-51 | 03-Jan-11 | 06-Jan-11 | 3 | document approved, FHWA to issue decision document |
In Superior | DR 53 | 42136 | 1990-7 | 07-Jul-11 | 11-Jul-11 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
In Superior | Bio doc version 1 | 42136 | 1990-7 | 11/18/2011 | 11/23/2011 | 5 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
In Superior | SHPO concur request | 42136 | 1990-7 | 1/30/2012 | 2/3/2012 | 4 | NDOR/address FHWA comments and resubmit |
In Superior | 4(f) concurrence | 42136 | 1990-7 | 1/31/2012 | 2/13/2012 | 13 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
In Superior | SHPO concur request | 42136 | 1990-7 | 2/8/2012 | 2/14/2012 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
In Superior | Cat Ex | 42136 | 1990-7 | 6/12/2012 | 6/12/2012 | 0 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
In Superior | Cat Ex | 42136 | 1990-7 | 8/9/2012 | 8/14/2012 | 5 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Jct. N-78 West | DR 53 | 42162 | 1364-112 | 30-Mar-11 | 31-Mar-11 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Jct N-78 West | SHPO Concur Req | 42162 | 1364-112 | 07-Jul-11 | 11-Jul-11 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Jct N-78 West | Bio doc version 1 | 42162 | 1364-112 | 2/3/2012 | 2/17/2012 | 14 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Jct N-78 West | 106 Concur Req | 42162 | 1364-112 | 4/2/2012 | 4/25/2012 | 23 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Jct. N-78 West | Cat Ex | 42162 | 1364-112 | 6/11/2012 | 6/12/2012 | 1 | NDOR/address FHWA comments and resubmit |
Jct. N-78 West | Cat Ex - revised | 42162 | 1364-112 | 6/18/2012 | 6/26/2012 | 8 | NDOR/address FHWA comments and resubmit |
Jct. N-78 West | Cat Ex - 3rd submittal | 42162 | 1364-112 | 6/27/2012 | 6/28/2012 | 1 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Geneva Northwest | Bio doc vers 1 | 42226 | 7030-30 | 21-Sep-10 | 29-Sep-10 | 8 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Geneva NW | DR 53 | 42226 | 7030-30 | 24-Jan-11 | 31-Jan-11 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Geneva NW | SHPO concur request | 42226 | 7030-30 | 2/3/2012 | 2/14/2012 | 11 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Ayr NE | DR 53 | 42235 | 7001-11 | 24-Jan-11 | 31-Jan-11 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Ayr Northeast | SHPO concur request | 42235 | 7001-11 | 12/1/2011 | 12/8/2011 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Ayr Northeast | Bio doc version 1 | 42235 | 7001-11 | 1/23/2012 | 1/25/2012 | 2 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Ayr Northeast | CE and Checklist | 42235 | 7001-11 | 3/28/2012 | 4/23/2012 | 26 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Ayr Northeast | CE - revised with comments | 42235 | 7001-11 | 5/3/2012 | 5/9/2012 | 6 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Ayr Northeast | Cat Ex | 42235 | 7001-11 | 5/10/2012 | 5/10/2012 | 0 | NDOR/address FHWA comments and resubmit |
7001-11 | Cat Ex - version 3 | 42235 | Ayr NE | 5/11/2012 | 5/11/2012 | 0 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
12th, Elm Ave - 6th Ave | DR 53 | 42292 | 5516-7 | 28-Jan-11 | 31-Jan-11 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
12th St. Elm to 6th Ave | SHPO concur request | 42292 | 5516-7 | 4/17/2012 | 4/27/2012 | 10 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
12th St Improvements | 4(f) exception | 42292 | 5516-7 | 6/14/2012 | 6/14/2012 | 0 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
12th St. Elm to 6th Ave | SHPO concur req -revised | 42292 | 5516-7 | 6/6/2012 | 6/25/2012 | 19 | None |
12th St. Improvements | SHPO letter | 42292 | 5516-7 | 6/28/2012 | 7/2/2012 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
12th St, Elm - 6th Ave | 4(f) determ | 42292 | 5516-7 | 7/26/2012 | 7/26/2012 | 0 | None |
12th St Improvements, Hastings | Cat Ex | 42292 | 5516-7 | 8/3/2012 | 8/3/2012 | 0 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
12th St Improvement, Elm Ave to 6th Ave | Construction Phasing change | 42292 | 5516-7 | 6/18/2013 | 6/18/2013 | 0 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Platte River to US-81 | DR 53 | 42302 | 925-107 | 11/16/2011 | 11/23/2011 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Platte River to US-81 | SHPO concur req | 42302 | 925-107 | 8/8/2012 | 8/16/2012 | 8 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Platte River to US-81 | Cat Ex | 42302 | 925-107 | 2/8/2013 | 2/13/2013 | 5 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Grand Island NW | DR 53 | 42322 | 7040-25 | 1/11/2012 | 1/16/2012 | 5 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Palmer NW | DR 53 | 42335 | 7061-27 | 1/23/2012 | 2/3/2012 | 11 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Archer Southwest | DR 53 | 42368 | 7061-28 | 1/24/2012 | 2/3/2012 | 10 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Lushton Northeast | DR 53 | 42372 | 2690-3 | 12-Aug-11 | 15-Aug-11 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Lushton Northeast | Bio doc version 1 | 42372 | 2690-3 | 2/1/2012 | 2/3/2012 | 2 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Wood River - Grand Island | DR 53 | 42399 | 304-149 | 11/25/2011 | 12/5/2011 | 10 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Wood River - Grand Island | SHPO concur request | 42399 | 304-149 | 2/22/2012 | 3/6/2012 | 13 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Worms Rd to 5 mi East of Archer Corner | DR 53 | 42400 | 925-108 | 4/4/2013 | 4/17/2013 | 13 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Hampton Link | Bio doc vers 1 | 42402 | L41D-101 | 29-Sep-10 | 29-Sep-10 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Hampton Link | SHPO concur req | 42402 | L41D-101 | 17-Nov-10 | 23-Nov-10 | 6 | NDOR/address FHWA comments and resubmit |
Hampton Link | SHPO concur req | 42402 | L41D(101) | 24-Nov-10 | 24-Nov-10 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Fullerton South | CE Determination | 42403 | 142-124 | 12-Apr-10 | 19-Apr-10 | 7 | NDOR/address FHWA comments and resubmit |
Fullerton South | DR-53 | 42403 | 142-124 | 22-Nov-10 | 15-Dec-10 | 23 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Fullerton S & in Fullerton | Altern Analysis memo | 42403 | 142-124 | 03-Feb-11 | 15-Feb-11 | 12 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Fullerton South | SHPO concur req | 42403 | 142-124 | 14-Feb-11 | 16-Feb-11 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Fullerton South & In Fullerton and South | CE | 42403 | 142-124 | 16-Sep-11 | 19-Sep-11 | 3 | NDOR/address FHWA comments and resubmit |
Fullerton South | revised CE - 9/21/11 | 42403 | 142-124 | 21-Sep-11 | 22-Sep-11 | 1 | NDOR/address FHWA comments and resubmit |
Fullerton South | revised CE - 9/23/11 | 42403 | 142-124 | 23-Sep-11 | 23-Sep-11 | 0 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Chapman-Central City | Bio doc vers 1 | 42405 | 305-130 | 18-Oct-10 | 21-Oct-10 | 3 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Chapman - Central City | DR 53 | 42405 | 305-130 | 04-Nov-10 | 08-Nov-10 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Phillips - Giltner | Bio doc vers 1 | 42415 | 807-151 | 30-Nov-10 | 13-Dec-10 | 13 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Aurora E & W | DR 53 | 42416 | 807-152 | 17-Mar-11 | 17-Mar-11 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Aurora East & West | Bio doc vers 1 | 42416 | 807-152 | 06-May-11 | 06-May-11 | 0 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Geneva West | DR 53 | 42435 | 7030-32 | 19-Aug-11 | 03-Sep-11 | 15 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Geneva West | Bio doc version 1 | 42435 | 7030-32 | 12/4/2012 | 12/26/2012 | 22 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Geneva West | 106 concur req | 42435 | 7030-32 | 2/21/2013 | 2/28/2013 | 7 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
In Blue Hill & South | SHPO concur req | 42443 | 2811-114 | 31-Mar-11 | 31-Mar-11 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
In Blue Hill & South | Bio doc vers 1 | 42443 | 2811-114 | 09-Aug-11 | 09-Aug-11 | 0 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
In Blue Hill and South | CE | 42443 | 2811-114 | 12/5/2011 | 12/12/2011 | 7 | NDOR/address FHWA comments and resubmit |
In Blue Hill and South | CE - revised | 42443 | 2811-114 | 1/27/2012 | 2/7/2012 | 11 | NDOR/address FHWA comments and resubmit |
Hastings Northeast | DR 53 | 42445 | 2038-1 | 14-Oct-11 | 17-Oct-11 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Hastings Northeast | Bio doc version 1 | 42445 | 2038-1 | 11/1/2011 | 11/2/2011 | 1 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Hastings Northeast | SHPO concur request | 42445 | 2038-1 | 12/15/2011 | 12/21/2011 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Hastings Northeast | Cat Ex | 42445 | 2038-1 | 5/25/2012 | 6/6/2012 | 12 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Little Blue River, Ayr | DR 53 | 42446 | 744-109 | 06-May-11 | 11-May-11 | 5 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Little Blue River Ayr | SHPO concur req | 42446 | 744-109 | 12-Aug-11 | 17-Aug-11 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Little Blue River, Ayr | SHPO supplemental concur req | 42446 | 744-109 | 11/6/2012 | 11/9/2012 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Little Blue River, Ayr | draft Cat Ex package | 42446 | 744-109 | 3/5/2013 | 3/8/2013 | 3 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Pleasanton Depot Renovation, Pleasanton Park | 4(f) except req | 42450 | 10-60 | 11/29/2012 | 12/7/2012 | 8 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Pleasanton Depot Renovation | 106 concur req | 42450 | 10-60 | 12/7/2012 | 12/7/2012 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Pleasanton Depot Renovation | Re-evaluation | 42450 | 10-60 | 12/18/2012 | 12/21/2012 | 3 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Geneva North | DR 53 | 42453 | 811-121 | 11/15/2011 | 11/23/2011 | 8 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
In Ashton | DR 53 | 42460 | 2065-4 | 19-Nov-10 | 24-Nov-10 | 5 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
In Ashton | SHPO concur req | 42460 | 2065-4 | 22-Feb-11 | 24-Feb-11 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
In Ashton | Bio doc vers 1 | 42460 | 2065-4 | 05-Apr-11 | 07-Apr-11 | 2 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Alexandria South Historic Bridge | Alternatives Evaluation | 42474 | 531-103 | 7/26/2013 | 8/7/2013 | 12 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Central City North | DR 53 | 42475 | 142-127 | 29-Jun-11 | 01-Jul-11 | 2 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Central City North | SHPO concur request | 42475 | 142-127 | 2/6/2012 | 2/14/2012 | 8 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Central City North | SHPO Re-eval supplement | 42475 | 142-127 | 5/16/2013 | 5/30/2013 | 14 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Central City North | Cat Ex | 42475 | 142-127 | 8/22/2013 | 8/27/2013 | 5 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
In Fullerton and South | Bio doc vers 1 | 42476 | 142-124 | 21-Apr-11 | 27-Apr-11 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Prosser Spur | SHPO concur req | 42482 | S40D-105 | 29-Oct-10 | 08-Nov-10 | 10 | NDOR/address FHWA comments and resubmit |
Prosser Spur | Bio doc vers 1 | 42482 | S40D-105 | 09-Nov-10 | 12-Nov-10 | 3 | NDOR/address FHWA comments and resubmit |
Prosser Spur | Rev 106 Concur Request Letter | 42482 | S40D-105 | 24-Nov-10 | 10-Dec-10 | 16 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Prosser Spur | Bio doc vers 2 | 42482 | S40D-105 | 30-Nov-10 | 10-Dec-10 | 10 | NDOR/address FHWA comments and resubmit |
Prosser Spur | NEPA Determ form | 42482 | S40D-105 | 25-Oct-10 | 14-Dec-10 | 50 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Prosser Spur | Bio doc vers 3 | 42482 | S40D-105 | 14-Dec-10 | 17-Dec-10 | 3 | NDOR/address FHWA comments and resubmit |
Prosser Spur | Bio doc vers 3 | 42482 | S40D-105 | 17-Dec-10 | 17-Dec-10 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Prosser Spur | NDOR Concur Req | 42482 | S40D-105 | 19-Jan-11 | 24-Jan-11 | 5 | NDOR/address FHWA comments and resubmit |
Prosser Spur | Detour memo | 42482 | S40D-105 | 25-Jan-11 | 31-Jan-11 | 6 | NDOR/address FHWA comments and resubmit |
Prosser Spur | SHPO Detour Resurf memo | 42482 | S40D-105 | 01-Feb-11 | 02-Feb-11 | 1 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Prosser Spur | BIO Detour Resurf memo | 42482 | S40D-105 | 02-Feb-11 | 02-Feb-11 | 0 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Prosser Spur | SHPO Detour Memo R2 | 42482 | S40D-105 | 16-Mar-11 | 17-Mar-11 | 1 | NDOR/address FHWA comments and resubmit |
Prosser spur | SHPO Detour resurf memo R2 | 42482 | S40D-105 | 25-Mar-11 | 30-Mar-11 | 5 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Prosser Spur | CE doc | 42482 | S40D-105 | 04-May-11 | 06-May-11 | 2 | NDOR/address FHWA comments and resubmit |
Prosser Spur | CE submittal 2 | 42482 | S40D-105 | 26-May-11 | 27-May-11 | 1 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Nance Co Resurfacing | DR 53 | 42487 | 2490-4 | 05-Oct-11 | 06-Oct-11 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Nance County Resurfacing | Bio doc version 1 | 42487 | 2490-4 | 2/14/2012 | 2/17/2012 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Kearney - Minden | DR-53 | 42510 | 806-102 | 1/3/2013 | 1/3/2013 | 0 | NDOR/address FHWA comments and resubmit |
Kearney - Minden | DR 53 - revised | 42510 | 806-102 | 1/8/2013 | 1/11/2013 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Gibbon - Shelton | DR 53 | 42511 | 806-103 | 17-Mar-11 | 17-Mar-11 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Gibbon - Shelton | Bio Doc | 42511 | 806-103 | 26-Apr-11 | 27-Apr-11 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Shelton - Wood River | DR 53 | 42512 | 806-104 | 04-Feb-11 | 07-Feb-11 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Shelton to Wood River | Bio doc vers 1 | 42512 | 806-104 | 07-Mar-11 | 08-Mar-11 | 1 | NDOR/address FHWA comments and resubmit |
Shelton - Wood River | Bio doc vers 2 | 42512 | 806-104 | 11-Mar-11 | 15-Mar-11 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Hampton to Henderson | DR 53 | 42514 | 807-155 | 1/24/2012 | 2/3/2012 | 10 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Hampton - Henderson | Bio doc re-eval | 42514 | 807-155 | 3/26/2013 | 4/5/2013 | 10 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Hampton to Waco | Cat Ex Reeval | 42514 | 807-155 | 5/16/2013 | 5/23/2013 | 7 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Henderson-Waco | DR 53 | 42515 | 807-156 | 11/4/2011 | 11/9/2011 | 5 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Waco - Utica | DR 53 | 42516 | 808-144 | 09-Dec-10 | 15-Dec-10 | 6 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Waco to Utica | Bio doc vers 1 | 42516 | 808-144 | 07-Mar-11 | 08-Mar-11 | 1 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Minden-Giddon | DR-53 | 42517 | 806-105 | 4/2/2012 | 4/6/2012 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Walk to Walnut - SRTS | DR 53 | 42521 | 40-57 | 03-Jan-11 | 11-Jan-11 | 8 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
SRTS Walk to Walnut | 4(f) de minimis | 42521 | 40-57 | 31-Aug-11 | 19-Sep-11 | 19 | NDOR/address FHWA comments and resubmit |
Walk to Walnut SRTS | Bio doc vers 1 | 42521 | 40-57 | 19-Sep-11 | 19-Sep-11 | 0 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Walk to Walnut | SHPO concur req | 42521 | 40-57 | 03-Oct-11 | 05-Oct-11 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Walk to Walnut | 4(f) De Minimis | 42521 | 40-57 | 13-Oct-11 | 17-Oct-11 | 4 | NDOR/address FHWA comments and resubmit |
Walk to Walnut SRTS | 4(f) de minimis | 42521 | 40-57 | 10/27/2011 | 11/2/2011 | 6 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Walk to Walnut | CE | 42521 | 40-57 | 12/27/2011 | 1/4/2012 | 8 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Grand Island Walk to Walnut | 4(f) reconsideration | 42521 | 40-57 | 8/6/2012 | 8/6/2012 | 0 | None |
Walnut Middle School SRTS | Re-eval | 42521 | 40-57 | 9/27/2013 | 10/3/2013 | 6 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
East Lochland Rd | Traffic Noise Summary | 42525 | 7552-1 | 25-Mar-10 | 25-Mar-10 | 0 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Grand Island Walk to Walnut | 4(f) Decl of Use Memo | 42532 | 40-57 | 9/10/2012 | 9/17/2012 | 7 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Ft Kearney Bridge Rehab | DR 53 | 42551 | Oct-62 | 02-Nov-10 | 03-Nov-10 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Ft Kearny Trail | SHPO concur req | 42551 | 10-62 | 7/30/2013 | 7/30/2013 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Fort Kearny Trail and Bridge Rehab | Bio doc V1 | 42551 | 10-62 | 8/9/2013 | 8/16/2013 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Fort Kearny Trail | Section 4(f) | 42551 | 10-62 | 8/14/2013 | 8/19/2013 | 5 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Fort Kearny Trail Bridges | 4F rev | 42551 | 10-62 | 8/22/2013 | 8/22/2013 | 0 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Loup City Red Raider SRTS | DR 53 | 42558 | 82-14 | 12-Sep-11 | 16-Sep-11 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Kearney West | DR 53 | 42560 | 304-154 | 1/30/2013 | 1/31/2013 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
York East | DR 53 | 42564 | 345-114 | 18-Apr-11 | 21-Apr-11 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
York East | Bio doc version 1 | 42564 | 345-114 | 1/12/2012 | 1/17/2012 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Hastings East | DR 53 | 42565 | 64-126 | 10/26/2011 | 10/28/2011 | 2 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
St. Paul North | DR-53 | 42567 | 2812-126 | 4/2/2012 | 4/23/2012 | 21 | NDOR/address FHWA comments and resubmit |
St. Paul North | 106 concur req | 42567 | 2812-126 | 12/7/2012 | 12/13/2012 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Alda Link | DR 53 | 42568 | L40C-106 | 05-Apr-11 | 11-Apr-11 | 6 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Alda Link | Cat Ex | 42568 | L40C-106 | 10/16/2012 | 10/19/2012 | 3 | None |
Alda Link | 106 concur request | 42568 | L40C-106 | 11/21/2012 | 12/3/2012 | 12 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Alda Link | Cat Ex | 42568 | L40C-106 | 1/11/2013 | 1/16/2013 | 5 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Red Cloud East | DR 53 | 42569 | 1364-113 | 12/7/2011 | 12/15/2011 | 8 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Red Cloud East | SHPO concur req | 42569 | 1364-113 | 8/2/2013 | 8/5/2013 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Wood River North and South | DR 53 | 42570 | 112-117 | 9/19/2013 | 9/20/2013 | 1 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Buffalo / Dawson County Line | SHPO concur req | 42571 | 304-155 | 20-May-11 | 27-May-11 | 7 | NDOR/address FHWA comments and resubmit |
Buffalo-Dawson Co. Line East | SHPO concur req | 42571 | 304-155 | 13-Jun-11 | 23-Jun-11 | 10 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Buffalo/Dawson County Line East | Bio doc version 1 | 42571 | 304-155 | 11/1/2011 | 11/2/2011 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Buffalo/Dawson County Line East | Cat Ex | 42571 | 304-155 | 7/12/2012 | 7/23/2012 | 11 | NDOR/address FHWA comments and resubmit |
Buffalo/Dawson County Line East | Cat Ex - revised | 42571 | 304-155 | 8/2/2012 | 8/9/2012 | 7 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Hastings South | DR 53 | 42577 | 2811-115 | 18-Apr-11 | 21-Apr-11 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Grafton West | Bio doc | 42579 | 65-113 | 13-Sep-10 | 23-Sep-10 | 10 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Grafton West | NDF | 42579 | 65-113 | 22-Sep-10 | 04-Oct-10 | 12 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Grafton West | SHPO concur req | 42579 | 65-113 | 10-Dec-10 | 17-Dec-10 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Grafton West | CE determ form - V1 | 42579 | 65-113 | 31-Jan-11 | 02-Feb-11 | 2 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
2nd Av, 25th-31st, Kearney | SHPO concur req | 42580 | 304-156 | 23-Nov-10 | 23-Nov-10 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
25th - 31st, Kearney | Bio Doc vers 1 | 42580 | 102-119 | 10/18/2011 | 10/28/2011 | 10 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
2nd Ave, 25th - 31st, Kearney | SHPO concur request | 42580 | 102-119 | 12/15/2011 | 12/20/2011 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
25th - 31st St, Kearney | CE | 42580 | 102-119 | 2/27/2012 | 3/8/2012 | 10 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
5th Ave, Kearney | DR-53 | 42585 | 304-156 | 17-Nov-10 | 23-Nov-10 | 6 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
5th Ave, Kearney | Bio doc vers 1 | 42585 | 304-156 | 05-Jan-11 | 07-Jan-11 | 2 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
5th Ave - Kearney | SHPO concur req | 42585 | 304-156 | 05-Jan-11 | 07-Jan-11 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
East Jct US-281 East | DR 53 | 42590 | 744-110 | 14-Dec-10 | 14-Dec-10 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
E Jct US-281 East | SHPO concur req | 42590 | 744-110 | 25-Mar-11 | 31-Mar-11 | 6 | NDOR/address FHWA comments and resubmit |
E Jct US-281 East | SHPO concur req - rev | 42590 | 744-110 | 08-Apr-11 | 13-Apr-11 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
In Geneva & West | DR 53 | 42591 | 415-107 | 5/24/2012 | 6/8/2012 | 15 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
In Geneva and West | 106 concur req | 42591 | 415-107 | 12/4/2012 | 12/7/2012 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Cairo West | DR 53 | 42592 | 24-110 | 3/7/2013 | 3/7/2013 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
In North Loup and South | DR 53 | 42593 | 113-120 | 11/15/2011 | 11/17/2011 | 2 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
North Loup and South | SHPO concur request | 42593 | 113-120 | 3/13/2012 | 3/15/2012 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
In North Loup & South | Bio doc | 42593 | 113-120 | 6/25/2012 | 7/2/2012 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
In North Loup and South | Cat Ex | 42593 | 113-120 | 1/11/2013 | 1/25/2013 | 14 | NDOR/address FHWA comments and resubmit |
North Loup and South | Cat Ex - 2nd submittal | 42593 | 113-120 | 2/6/2013 | 2/22/2013 | 16 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
In Guide Rock & South | SHPO concur req | 42594 | 781-104 | 01-Apr-11 | 07-Apr-11 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
In Guide Rock & South | DR 53 | 42594 | 781-104 | 06-Apr-11 | 07-Apr-11 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
In Guide Rock and South | Bio doc version 1 | 42594 | 781-104 | 11/5/2012 | 11/14/2012 | 9 | NDOR/address FHWA comments and resubmit |
In Guide Rock and South | Bio doc - version 2 | 42594 | 781-104 | 11/19/2012 | 11/26/2012 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
In Guide Rock and South | Cat Ex | 42594 | 781-104 | 6/6/2013 | 6/10/2013 | 4 | NDOR/address FHWA comments and resubmit |
In Guide Rock and South | Cat Ex - revised | 42594 | 781-104 | 7/31/2013 | 8/1/2013 | 1 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Jct N-92 North | Bio doc vers 1 | 42595 | 112-118 | 18-Oct-10 | 21-Oct-10 | 3 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Hwy N-11, Jct N-92 N, Howard County | SHPO concur req | 42595 | 112-118 | 17-Nov-10 | 23-Nov-10 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Phillips East | Bio Doc | 42596 | 345-115 | 08-Nov-10 | 08-Nov-10 | 0 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
South Junction N-58 East | 106 Consultation Letter | 42597 | 924-109 | 14-Jul-10 | 26-Jul-10 | 12 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
N Jct N-14 to Genoa | DR-53 | 42600 | 225-116 | 4/2/2012 | 4/23/2012 | 21 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
N Jct N-14 - Genoa | SHPO and THPO concur req | 42600 | 225-116 | 7/17/2013 | 7/26/2013 | 9 | NDOR/address FHWA comments and resubmit |
N Jct N-14 to Genoa | Bio doc | 42600 | 225-116 | 9/11/2013 | 9/13/2013 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
E. Jct. US-30 South | DR 53 | 42601 | 102-120 | 12-Oct-10 | 13-Oct-10 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
E. Jct. US-30 South | SHPO concur | 42601 | 102-120 | 15-Oct-10 | 22-Oct-10 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
East Jct US-30 South | Bio doc vers 1 | 42601 | 102-120 | 14-Dec-10 | 20-Dec-10 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
S Jct US-281 - E Jct Howard-Nance Co Line - Fullerton | DR 53 batched | 42606 | 224-109 | 3/21/2013 | 4/2/2013 | 12 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Loup City Northeast | DR 53 | 42614 | 2085-4 | 09-Jun-11 | 16-Jun-11 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
N-78 - S Jct N-14 | DR-53 | 42616 | 1364-114 | 6/21/2013 | 6/24/2013 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
St. Paul East | DR 53 | 42618 | 924-112 | 11/15/2011 | 11/22/2011 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Giltner E & W | Bio doc vers 1 | 42630 | 807-158 | 24-Mar-11 | 01-Apr-11 | 8 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Giltner East & West | SHPO concur req | 42630 | 807-158 | 16-May-11 | 27-May-11 | 11 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Multi-location Resurfacing Hastings | DR53 | 42631 | 5516(8) | 06-Dec-10 | 14-Dec-10 | 8 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Hastings resurfacing | SHPO concur req | 42631 | 5516-8 | 14-Dec-10 | 17-Dec-10 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Resurf Hastings - mult. Locates | Bio doc vers 1 | 42631 | 5516-8 | 05-Jan-11 | 07-Jan-11 | 2 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
GI State & Capitol Av Trl | DR 53 | 42650 | 40-59 | 03-Feb-11 | 03-Feb-11 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
GI Connector Trail | SHPO concur req | 42650 | 40-59 | 06-Oct-11 | 07-Oct-11 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
State St & Cap Ave Connect Trail | Bio doc vers 1 | 42650 | 40-59 | 07-Oct-11 | 07-Oct-11 | 0 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
State Street & Capital Ave Connector Trail | 4(f) | 42650 | 40-59 | 10/28/2011 | 11/2/2011 | 5 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
State Street to Capital Ave Connector Trail | CE | 42650 | 40-59 | 12/29/2011 | 1/10/2012 | 12 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
13th & Wheeler Dwntwn lighting | DR 53 | 42651 | 40-60 | 24-Jan-11 | 31-Jan-11 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
3rd and Wheeler Downtown Historic Lighting | Bio doc version 1 | 42651 | 40-60 | 12/14/2011 | 12/20/2011 | 6 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
3rd & Wheeler Downtown Historic Lighting Project | SHPO concur request | 42651 | 40-60 | 3/8/2012 | 3/15/2012 | 7 | NDOR/address FHWA comments and resubmit |
3rd & Wheeler Downtown Historic Lighting | Revised SHPO concur request | 42651 | 40-60 | 3/16/2012 | 3/22/2012 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Kearney E Via removal | DR 53 | 42653 | 805-70 | 01-Oct-10 | 01-Oct-10 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Kearney E viad removal | Bio doc vers 1 | 42653 | 805-70 | 30-Nov-10 | 10-Dec-10 | 10 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Kearney E viaduct removal | CE doc | 42653 | 805-70 | 08-Apr-11 | 13-Apr-11 | 5 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
US-281 - Lawrence | SHPO concur req | 42654 | 44-108 | 24-Jan-11 | 31-Jan-11 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
US-281 - Lawrence | DR 53 | 42654 | 44-108 | 25-Jan-11 | 31-Jan-11 | 6 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
E. Jct. US-281 - Lawrence | Bio doc version 1 | 42654 | 44-108 | 10/2/2012 | 10/30/2012 | 28 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Structures W of Aurora | DR 53 | 42661 | 807-160 | 04-Apr-11 | 11-Apr-11 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
I-80 Structures W of Aurora | SHPO concur req | 42661 | 807-160 | 12-Aug-11 | 17-Aug-11 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Rose Creek Bridge | Bio doc vers 1 | 42663 | 85-109 | 01-Oct-10 | 12-Oct-10 | 11 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Rose Creek Bridge | NEPA Determ form | 42663 | 85-109 | 01-Dec-10 | 14-Dec-10 | 13 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Rose Creek NE of Hubbell | SHPO concur req | 42663 | 85-109 | 31-Mar-11 | 31-Mar-11 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Rose Creek Bridge | NEPA CE | 42663 | 85-109 | 11-Jul-11 | 13-Jul-11 | 2 | NDOR/address FHWA comments and resubmit |
Rose Creek Bridge NE of Hubbell | CE form | 42663 | 85-109 | 29-Aug-11 | 06-Sep-11 | 8 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Mormon Island Trl Br | DR 53 | 42666 | 40-61 | 21-Mar-11 | 23-Mar-11 | 2 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Wood River - Grand Island | DR 53 | 42667 | 806-109 | 11-Feb-11 | 14-Feb-11 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
WoodRiver - Grand Island | Bio doc vers 1 | 42667 | 806-109 | 22-Feb-11 | 24-Feb-11 | 2 | NDOR/address FHWA comments and resubmit |
Platte River - Phillips | DR 53 | 42668 | 806-110 | 11-Feb-11 | 14-Feb-11 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Platte Rvr to Phillips | Bio doc vers 1 | 42668 | 806-110 | 22-Feb-11 | 24-Feb-11 | 2 | NDOR/address FHWA comments and resubmit |
Platte River - Phillips | DR 53 | 42674 | 806-108 | 6/6/2013 | 6/10/2013 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Cotesfield N&S | DR 53 | 42681 | 112-119 | 14-Apr-11 | 15-Apr-11 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Waco Interchange Bridge | DR 53 | 42687 | 808-152 | 16-Sep-11 | 19-Sep-11 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Waco Interchange Bridge | SHPO concur req | 42687 | 808-152 | 26-Sep-11 | 26-Sep-11 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Waco Interchange Bridge | Bio doc version 1 | 42687 | 808-152 | 3/21/2012 | 4/20/2012 | 30 | NDOR/address FHWA comments and resubmit |
Waco Interchange Bridge | Bio doc version 2 | 42687 | 808-152 | 5/2/2012 | 5/10/2012 | 8 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Pioneer Spirit Trail Phase III | 4(f) exception | 42688 | Jan-50 | 12/16/2011 | 12/27/2011 | 11 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Waco Interchange | Bio doc vers 1 | 42689 | 808-151 | 19-Oct-10 | 21-Oct-10 | 2 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
In Central City and South | DR 53 | 42691 | 142-126 | 7/1/2013 | 7/5/2013 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
19th St., York | DR 53 | 42696 | 6312-2 | 13-Oct-10 | 21-Oct-10 | 8 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
19th Street, Blackburn-Delaware, York | Bio doc version 1 | 42696 | 6312-2 | 10/28/2011 | 10/28/2011 | 0 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
19th Street, Blackburn - Delaware, York | SHPO concur request | 42696 | 6312-2 | 12/21/2011 | 12/23/2011 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
19th Street Blackburn to Delaware | Cat Ex | 42696 | 6312-2 | 4/12/2012 | 4/30/2012 | 18 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
19th St., Blackburn-Delaware | Cat Ex | 42696 | 6312-2 | 8/29/2012 | 8/31/2012 | 2 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Marquis to US 34, York | DR 53 | 42697 | 6303-4 | 13-Oct-10 | 21-Oct-10 | 8 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Division Ave, Marquis - US 34, York | SHPO concur req | 42697 | 6303-4 | 6/25/2012 | 6/27/2012 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
York Division Ave | Cat Ex | 42697 | 6303-4 | 5/22/2013 | 6/7/2013 | 16 | NDOR/address FHWA comments and resubmit |
York Division Ave | Cat Ex - revised | 42697 | 6303-4 | 8/20/2013 | 8/22/2013 | 2 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Little Blue Rvr Ped Trl | DR 53 | 42698 | 85-11 | 03-Feb-11 | 03-Feb-11 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
In Grand Island | DR 53 | 42699 | 304-157 | 06-Apr-11 | 12-Apr-11 | 6 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
In Grand Island | Bio doc version 1 | 42699 | 304-157 | 12/20/2011 | 12/23/2011 | 3 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Baltimore Ave, 12th - 14th | DR 53 | 42704 | 5505-4 | 27-Jun-11 | 30-Jun-11 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Baltimore Ave, 12th to 14th | SHPO concur req | 42704 | 5505-4 | 4/1/2013 | 4/17/2013 | 16 | NDOR/address FHWA comments and resubmit |
Baltimore Ave, 12th-14th | SHPO concur req - revised | 42704 | 5505-4 | 5/3/2013 | 5/14/2013 | 11 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
9th St Burlington Ave to Elm, Grand Island | DR 53 | 42705 | 5514-4 | 30-Jun-11 | 01-Jul-11 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
9th St - Burlington to Elm Ave | SHPO concur request | 42705 | 5514-4 | 11/21/2011 | 11/25/2011 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
9th St - Burlington to Elm Ave | Bio doc version 1 | 42705 | 5514-4 | 11/21/2011 | 11/25/2011 | 4 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
9th St, Burlington to Elm Ave, Hastings | SHPO concur req - revised | 42705 | 5514-4 | 9/10/2013 | 9/10/2013 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
9th St - Hastings | SHPO Supplement | 42705 | 5514-4 | 9/10/2013 | 9/10/2013 | 0 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
GI Resurf - various | DR 53 | 42706 | 5409-2 | 06-May-11 | 11-May-11 | 5 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Various Locations in Grand Island | Bio doc version 1 | 42706 | 5409-2 | 1/25/2012 | 2/3/2012 | 9 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Grand Island Resurfacing - Various Locations | SHPO concur request | 42706 | 5409-2 | 3/7/2012 | 3/15/2012 | 8 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Grand Island Resurfacing | Cat Ex | 42706 | 5409-2 | 9/13/2012 | 10/4/2012 | 21 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Grand Island Resurfacing | Cat Ex | 42706 | 5409-2 | 1/10/2013 | 1/16/2013 | 6 | NDOR/address FHWA comments and resubmit |
Cap Ave - Webb Road to Broadwell, GI | DR 53 | 42707 | 5436-5 | 06-May-11 | 11-May-11 | 5 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Capital Ave - Webb Rd to Broadwell Ave | Env Class Request | 42707 | 5436-5 | 5/22/2012 | 6/6/2012 | 15 | NDOR/address FHWA comments and resubmit |
Capital Ave - Webb Rd to Broadwell Ave | Cat Ex | 42707 | 5436-5 | 11/5/2012 | 11/15/2012 | 10 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Capital Ave, Grand Island | Noise study inquiry | 42707 | 5436-5 | 3/1/2013 | 3/1/2013 | 0 | None |
Capital Avenue | Section 4(f) de minimis | 42707 | 5436-5 | 2/27/2013 | 3/4/2013 | 5 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Capital Avenue, Grand Island | 106 concur req | 42707 | 5436-5 | 3/5/2013 | 3/6/2013 | 1 | NDOR/address FHWA comments and resubmit |
Capital Ave, Grand Island | 106 concur req - revised | 42707 | 5436-5 | 3/8/2013 | 3/11/2013 | 3 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Capital Ave, Grand Island | Temporary drive documenting | 42707 | 5436-5 | 3/25/2013 | 3/25/2013 | 0 | None |
Capital Avenue | Cat Ex | 42707 | 5436-5 | 4/4/2013 | 4/9/2013 | 5 | NDOR/address FHWA comments and resubmit |
Capital Ave Veterans Memorial Park | 4(f) | 42707 | 5436-5 | 4/15/2013 | 4/17/2013 | 2 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Capital Ave, Grand Island | Cat Ex | 42707 | 5436-5 | 4/19/2013 | 4/22/2013 | 3 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
North Loup - Ord resurfacing | Bio doc version 1 | 42708 | 113-121 | 12/19/2011 | 12/21/2011 | 2 | NDOR/address FHWA comments and resubmit |
North Loup to Ord | DR 53 | 42708 | 113-121 | 12/21/2011 | 12/21/2011 | 0 | NDOR/address FHWA comments and resubmit |
Gibbon Link | DR 53 | 42710 | L10C-103 | 2/1/2013 | 2/4/2013 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Gibbon Link | SHPO concur req | 42710 | L10C-103 | 7/9/2013 | 7/23/2013 | 14 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Deweese Spur Bridge | DR 53 | 42716 | S18C-107 | 3/8/2013 | 3/12/2013 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Superior Schools Safe Routes | DR 53 | 42718 | 65-24 | 10/21/2011 | 10/28/2011 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Superior Public Schools | 4(f) Except Req | 42718 | 65-24 | 9/27/2013 | 10/3/2013 | 6 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Scotia East Bridges | DR 53 | 42723 | 224-112 | 10/30/2012 | 11/13/2012 | 14 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Scotia East Bridge | SHPO concur req | 42723 | 224-112 | 3/27/2013 | 4/5/2013 | 9 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Ong Spur West Bridges | DR 53 | 42724 | 745-111 | 3/8/2013 | 3/12/2013 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Ong Spur West Bridges | SHPO concur req | 42724 | 745-111 | 7/18/2013 | 7/23/2013 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
DMS Replacement | DR 53 | 42730 | ITSM-12 | 1/28/2013 | 1/31/2013 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
DMS Replacements | 106 concur req | 42730 | ITSM-12 | 2/25/2013 | 2/28/2013 | 3 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
DMS Replacements | D4 D5 D6 DMS Replacement | 42730 | ITSN-12 | 4/29/2013 | 5/1/2013 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Osborne Drive East Guardrail | DR 53 | 42733 | 5519-5 | 6/6/2012 | 6/12/2012 | 6 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Hastings Regional Center Spur Bridge | DR-53 | 42742 | S01C-102 | 9/12/2013 | 9/13/2013 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Hemingford to Berea | SHPO concur req | 51182 | 21-77 | 08-Dec-10 | 10-Dec-10 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Hemingford - Berea | Bio doc vers 1 | 51182 | 21-117 | 29-Dec-10 | 07-Jan-11 | 9 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Morril West | CE | 51216 | 261-153 | 04-Mar-10 | 17-Mar-10 | 13 | NDOR/address FHWA comments and resubmit |
Morrill West | 106 Consultation Letter | 51216 | 261-153 | 15-Jul-10 | 26-Jul-10 | 11 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Morrill West | NEPA CE V2 | 51216 | 261-153 | 13-Aug-10 | 13-Aug-10 | 0 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Dix South & East | DR 53 | 51233 | 301-134 | 5/25/2012 | 6/8/2012 | 14 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Scottsbluff West Viaduct | DR 53 | 51250 | 921-121 | 5/18/2012 | 6/5/2012 | 18 | NDOR/address FHWA comments and resubmit |
Scottsbluff West Viaduct | DR 53 - revised | 51250 | 921-121 | 6/19/2012 | 6/26/2012 | 7 | NDOR/address FHWA comments and resubmit |
Scottsbluff Viaduct | DR-53 Scottsbluff Viaduct | 51250 | 921-121 | 7/15/2013 | 7/15/2013 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Bayard North | DR-53 | 51260 | 261-156 | 1/4/2013 | 1/8/2013 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Bayard North, In Bayard and South | SHPO concur req | 51260 | 261-156 | 4/10/2013 | 4/17/2013 | 7 | NDOR/address FHWA comments and resubmit |
Bayard North | SHPO concur req - revised | 51260 | 261-156 | 5/21/2013 | 5/31/2013 | 10 | NDOR/address FHWA comments and resubmit |
In Bayard and N | 106 rev | 51260 | 261-160 | 8/8/2013 | 8/8/2013 | 0 | NDOR/address FHWA comments and resubmit |
Bayard North | SHPO and Section 4(f) request | 51260 | 261-156 | 8/23/2013 | 8/30/2013 | 7 | NDOR/address FHWA comments and resubmit |
Bayard Batched | 4F | 51260 | 261-160 (261-156) | 8/23/2013 | 9/13/2013 | 21 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Bayard North & In Bayard and South | Section 4(f) approval | 51260 | 261-156 | 9/18/2013 | 10/1/2013 | 13 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Oshkosh - Lewellen | DR 53 | 51261 | 261-157 | 4/11/2012 | 4/27/2012 | 16 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Oshkosh - Lewellen | SHPO concur request | 51261 | 261-157 | 5/21/2012 | 6/4/2012 | 14 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Oshkosh - Lewellen | SHPO Supplemental | 51261 | 261-157 | 6/25/2012 | 6/27/2012 | 2 | NDOR/address FHWA comments and resubmit |
Oshkosh - Lewellen | SHPO concur req - revised | 51261 | 261-157 | 6/29/2012 | 7/13/2012 | 14 | NDOR/address FHWA comments and resubmit |
Oshkosh - Lewellen | SHPO revised concur req | 51261 | 261-157 | 7/18/2012 | 7/26/2012 | 8 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Oshkosh - Lewellen | Cat Ex | 51261 | 261-157 | 1/11/2013 | 1/25/2013 | 14 | NDOR/address FHWA comments and resubmit |
Oshkosh - Lewellen | 106 Re-eval concur req | 51261 | 261-157 | 2/26/2013 | 2/28/2013 | 2 | NDOR/address FHWA comments and resubmit |
Oshkosh - Lewellen | 106 re-eval concur req | 51261 | 261-157 | 2/28/2013 | 3/1/2013 | 1 | None |
Oshkosh - Lewellen | Cat Ex - revised | 51261 | 261-157 | 5/8/2013 | 5/14/2013 | 6 | NDOR/address FHWA comments and resubmit |
Oshkosh - Lewellen | Cat Ex - V3 | 51261 | 261-157 | 6/18/2013 | 6/19/2013 | 1 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
In Chadron | DR 53 | 51271 | 201-135 | 5/22/2012 | 6/4/2012 | 13 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Pine St - Spruce St, Chadron | SHPO concur req | 51271 | 201-135 | 8/15/2012 | 8/29/2012 | 14 | NDOR/address FHWA comments and resubmit |
Pine St - Spruce St, Chadron | SHPO concur req - revised | 51271 | 201-135 | 10/19/2012 | 11/9/2012 | 21 | NDOR/address FHWA comments and resubmit |
Pine - Spruce, Chadron | 106 concur req - version 3 | 51271 | 201-135 | 11/15/2012 | 11/19/2012 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Hay Springs South | DR 53 | 51284 | 874-116 | 25-Mar-11 | 29-Mar-11 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Hay Springs South | Bio doc version 1 | 51284 | 874-116 | 3/1/2012 | 3/8/2012 | 7 | NDOR/address FHWA comments and resubmit |
Rushville to Gordon | DR 53 | 51289 | 201-136 | 3/13/2012 | 4/5/2012 | 23 | NDOR/address FHWA comments and resubmit |
Harrison West | Bio doc vers 1 | 51290 | 201-137 | 21-Sep-10 | 29-Sep-10 | 8 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
In Bayard and South | DR 53 | 51292 | 261-160 | 4/6/2012 | 4/26/2012 | 20 | NDOR/address FHWA comments and resubmit |
In Bayard & South | DR-53 resubmittal | 51292 | 261-160 | 6/5/2012 | 6/12/2012 | 7 | NDOR/address FHWA comments and resubmit |
In Bayard & South | DR 53 | 51292 | 261-160 | 6/14/2012 | 6/26/2012 | 12 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
In Bayard and South | 106 concur req | 51292 | 261-160 | 1/2/2013 | 1/8/2013 | 6 | NDOR/address FHWA comments and resubmit |
In Bayard and South | Reconsider decision - batch projects | 51292 | 261-160 | 3/14/2013 | 3/19/2013 | 5 | None |
BNSF - Bridgeport Viad study | DR 53 | 51299 | 261-161 | 09-Mar-11 | 10-Mar-11 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Bushnell to W Kimball | Bio doc vers 1 | 51309 | 801-171 | 28-Sep-10 | 01-Oct-10 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Bushnell to W Kimball | Bio doc vers 2 | 51309 | 801-171 | 07-Dec-10 | 10-Dec-10 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
East Kimball - Potter | DR 53 | 51311 | 801-172 | 14-Apr-11 | 15-Apr-11 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
East Kimball - Potter | Bio doc version 1 | 51311 | 801-172 | 12/9/2011 | 12/15/2011 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
East Kimball - Potter | Bio doc version 2 | 51311 | 801-172 | 1/4/2012 | 1/9/2012 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Sidney Deadwood Trail | Bio Doc | 51326 | 17-24 | 13-Aug-10 | 20-Aug-10 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Sidney Deadwood Trl - phase 3 | DR 53 | 51326 | 17-24 | 23-Jan-11 | 31-Jan-11 | 8 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Sidney Deadwood Trail | Reeval | 51326 | 17-24 | 15-Apr-11 | 19-Apr-11 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Sidney Deadwood Trl, Phase 3 | SHPO concur req | 51326 | 17-24 | 06-Jun-11 | 10-Jun-11 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Sidney Deadwood Trl Ph. III | CE | 51326 | 17-24 | 03-Aug-11 | 05-Aug-11 | 2 | NDOR/address FHWA comments and resubmit |
Sidney Deadwood Trail Ph III | CE - version 2 | 51326 | 17-24 | 20-Sep-11 | 26-Sep-11 | 6 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
N-88 Jct North & South | Bio doc vers 1 | 51335 | 713-126 | 30-Sep-10 | 01-Oct-10 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Kimball East | DR 53 | 51342 | 801-176 | 9/27/2012 | 10/12/2012 | 15 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Agate South | DR-53 | 51346 | 294-109 | 8/23/2013 | 8/27/2013 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
South Potash Ave, Alliance | DR 53 | 51347 | 6263-1 | 12-Oct-10 | 13-Oct-10 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
South Potash Avenue | SHPO concur request | 51347 | 6263-1 | 12/19/2011 | 12/21/2011 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
South Potash Ave, Alliance | Bio doc version 1 | 51347 | 6263-1 | 3/8/2012 | 3/15/2012 | 7 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Agate South | DR 53 | 51361 | 294-107 | 09-Feb-11 | 09-Feb-11 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Agate South | Bio Doc | 51361 | 294-107 | 20-Apr-11 | 27-Apr-11 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Sioux/Box Butte Co Line to N-2 | DR 53 | 51373 | 714-119 | 6/14/2012 | 6/26/2012 | 12 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Sioux-Box Butte Co Line to N-2 | DR 53 | 51373 | 714-119 | 8/20/2012 | 8/28/2012 | 8 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Sioux/Box Butte Co Line | 106 concur req | 51373 | 714-119 | 11/28/2012 | 12/5/2012 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Sioux Box Butte County Line | Cat Ex | 51373 | 714-119 | 6/25/2013 | 7/9/2013 | 14 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Sunol and Lodgepole Links | DR 53 | 51389 | L17E-108 | 11/22/2011 | 11/28/2011 | 6 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Sunol and Lodgepole Links | SHPO concur request | 51389 | L17E-108 | 12/8/2011 | 12/9/2011 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Sunol and Lodgepole Links | SHPO Suppl concur req | 51389 | L17E-108 | 10/1/2012 | 10/12/2012 | 11 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Sunol and Lodgepole Links | Cat Ex | 51389 | L17E-108 | 2/22/2013 | 2/26/2013 | 4 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Kimball to Dix | DR 53 | 51395 | 301-127 | 12/13/2011 | 12/20/2011 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Chadron North | 106 Consultation Letter | 51397 | 3854-133 | 15-Jul-10 | 26-Jul-10 | 11 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Chadron North | Bio doc vers 1 | 51397 | 3854-133 | 28-Sep-10 | 01-Oct-10 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Chadron South | DR-53 | 51398 | 3854-134 | 4/2/2012 | 4/6/2012 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Chadron South | Archeological testing plan | 51398 | 3854-134 | 7/12/2012 | 7/25/2012 | 13 | NDOR/address FHWA comments and resubmit |
Chadron South | Revised Arch Testing Plan | 51398 | 3854-134 | 9/18/2012 | 10/11/2012 | 23 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Chadron South | Bio doc version 2 - USFS | 51398 | 3854-134 | 11/8/2012 | 12/7/2012 | 29 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Chadron South | 106 concur req | 51398 | 3854-134 | 12/13/2012 | 12/26/2012 | 13 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Chadron South | Cat Ex | 51398 | 3854-134 | 6/17/2013 | 6/21/2013 | 4 | NDOR/address FHWA comments and resubmit |
Chadron South | Cat Ex - revised | 51398 | 3854-134 | 7/18/2013 | 7/23/2013 | 5 | NDOR/address FHWA comments and resubmit |
Chadron South | Cat Ex - revised | 51398 | 3854-134 | 7/23/2013 | 7/24/2013 | 1 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Cody Ave East, Alliance | DR 53 | 51399 | 21-123 | 4/18/2013 | 4/30/2013 | 12 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Chadron State Park South | DR 53 | 51400 | 3854-135 | 6/28/2013 | 7/1/2013 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Sidney West | DR 53 | 51402 | 301-130 | 07-Jul-11 | 11-Jul-11 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Sidney West | Bio doc version 1 | 51402 | 301-130 | 4/17/2012 | 4/23/2012 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Berea North | DR 53 | 51403 | 3854-136 | 25-Jul-11 | 29-Jul-11 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Berea North | Bio doc version 1 | 51403 | 3854-136 | 1/23/2012 | 2/1/2012 | 9 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Gering Northfield | DR 53 | 51407 | 79-40 | 08-Apr-11 | 12-Apr-11 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
High Mast Towers | Effect Determ Pkg | 51413 | 5-101 | 12-May-10 | 21-May-10 | 9 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
L62A/US-385 - Alliance | NDOR Review request | 51432 | 3853-118 | 04-Nov-10 | 04-Dec-10 | 30 | NDOR/address FHWA comments and resubmit |
Jct L62A/US385 - Alliance | Purp and Need | 51432 | 3853-118 | 16-Mar-11 | 28-Mar-11 | 12 | NDOR/address FHWA comments and resubmit |
Jct L62A/US-385 - Alliance | Purp & Need | 51432 | 3853-118 | 19-Apr-11 | 02-May-11 | 13 | NDOR/address FHWA comments and resubmit |
Heartland Express Alliance Section | SHPO concur req | 51432 | 3853-118 | 01-Jun-11 | 10-Jun-11 | 9 | NDOR/address FHWA comments and resubmit |
Heartland Expressway | Alternatives letter for agencies review | 51432 | 3853-118 | 12/20/2011 | 1/4/2012 | 15 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Heartland Expressway | SHPO concur request | 51432 | 3853-118 | 1/4/2012 | 1/17/2012 | 13 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Heartland Expr, Jct L62A/US 385 to Alliance | THPO concur req | 51432 | 3853-118 | 7/20/2012 | 7/24/2012 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Jct. L62A/US-385 to Alliance | Bio doc version 1 | 51432 | 3853-118 | 10/10/2012 | 11/5/2012 | 26 | NDOR/address FHWA comments and resubmit |
N-27 - South Platte River | DR-53 | 51444 | 802-95 | 7/17/2013 | 7/22/2013 | 5 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
N-27 to South Platte River | SHPO concur req | 51444 | 802-95 | 8/28/2013 | 8/29/2013 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Broadway, 14th to 20th, Scottsbluff | Bio doc version 1 | 51449 | 5701-8 | 1/12/2012 | 1/16/2012 | 4 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Broadway, 14th to 20th, Scottsbluff | SHPO concur request | 51449 | 5701-8 | 3/7/2012 | 3/15/2012 | 8 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Emerson Ave, Alliance | DR 53 | 51450 | 6255-3 | 12-Oct-10 | 13-Oct-10 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Emerson Ave- 18th St to 25th St | SHPO Concur Req 106 | 51450 | 6255-3 | 10-Jun-11 | 10-Jun-11 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
18th St. - 25th St. | Bio Doc V1 | 51450 | 6255-3 | 11-Jul-11 | 20-Jul-11 | 9 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Potter - Brownson | DR 53 | 51451 | 801-178 | 02-Sep-11 | 14-Sep-11 | 12 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
BoxButte Historic lighting | DR 53 | 51453 | 6257-2 | 01-Mar-11 | 02-Mar-11 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Box Butte Ave Hist Lighting | 106 concur request | 51453 | 6257-2 | 1/8/2013 | 1/14/2013 | 6 | None |
Box Butte Ave Historic Lighting | 106 concur req | 51453 | 6257-2 | 1/30/2013 | 1/31/2013 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
27th Ave I, to Hwy 26 | DR 53 | 51454 | 5720-1 | 18-Oct-10 | 21-Oct-10 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
27th St, Ave I - Hwy 26, Scottsbluff | Bio doc vers 1 | 51454 | 5720-1 | 01-Feb-11 | 02-Feb-11 | 1 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
27th, Ave I to Hwy 26, Scottsbluff | SHPO concur req | 51454 | 5720-1 | 25-Feb-11 | 28-Feb-11 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
10th Ave, Sidney | DR 53 | 51456 | 6363-3 | 04-Jan-11 | 11-Jan-11 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
10th Ave - Osage to Illinois, Sidney | SHPO concur request | 51456 | 6363-3 | 4/25/2012 | 5/8/2012 | 13 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
10th Ave, Illinois to Osage, Sidney | Cat Ex | 51456 | 6363-3 | 1/28/2013 | 1/31/2013 | 3 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Sidney West | DR 53 | 51458 | 801-181 | 5/31/2013 | 5/31/2013 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Sidney West | SHPO concur req | 51458 | 801-181 | 6/28/2013 | 7/3/2013 | 5 | NDOR/address FHWA comments and resubmit |
Sidney West and Sidney Crossovers | SHPO concur req - revised | 51458 | 801-181 | 7/22/2013 | 7/25/2013 | 3 | NDOR/address FHWA comments and resubmit |
Sidney West, Sidney West Crossovers | SHPO concur request - revised | 51458 | 801-181 | 9/24/2013 | 10/3/2013 | 9 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Sunol-Chappell | DR-53 | 51459 | 802-97 | 4/2/2012 | 4/20/2012 | 18 | None |
West Sunol - West Lodgepole | 106 Supplement concur req | 51459 | 802-97 | 2/11/2013 | 2/13/2013 | 2 | NDOR/address FHWA comments and resubmit |
W. Sunol - W. Lodgepole, etc | Bio doc - version 1 | 51459 | 802-97 | 2/21/2013 | 3/6/2013 | 13 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Sunol to Chappel | Cat Ex - V3 | 51459 | 802-97 | 5/24/2013 | 5/29/2013 | 5 | NDOR/address FHWA comments and resubmit |
Wyoming Line - N-71 | DR 53 | 51460 | 881-108 | 01-Apr-11 | 05-Apr-11 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Wyoming Line - N-71 | Bio doc version 1 | 51460 | 881-108 | 12/14/2011 | 12/20/2011 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Wyoming Line - N-71 | Bio doc version 2 | 51460 | 881-108 | 1/4/2012 | 1/9/2012 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Wyoming Line - Bushnell | DR 53 | 51461 | 301-131 | 7/1/2013 | 7/5/2013 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Chappell E and Jct US-138 | DR 53 - batched | 51462 | 301-132 | 2/28/2013 | 2/28/2013 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Chappel East | SHPO concur req | 51462 | 301-132 | 6/19/2013 | 6/24/2013 | 5 | NDOR/address FHWA comments and resubmit |
US-26 & N-71, Scottsbluff | DR 53 | 51464 | 261-165 | 28-Mar-11 | 29-Mar-11 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
US-26 and N-71, Scottsbluff | Bio doc version one | 51464 | 261-165 | 12/19/2011 | 12/22/2011 | 3 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Kimball North | DR 53 | 51466 | 712-113 | 7/1/2013 | 7/1/2013 | 0 | NDOR/address FHWA comments and resubmit |
Gordon East Bridge | 106 concur req | 51469 | 201-144 | 2/11/2013 | 2/13/2013 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
District 5 sidemount DMS | DR-53 | 51475 | ITSN-24 | 8/20/2013 | 8/22/2013 | 2 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
DMS | DR 53 | 51477 | ITSN-37 | 8/15/2013 | 8/16/2013 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
DMS - D5 | SHPO concur req | 51477 | ITSN-13 | 9/12/2013 | 10/9/2013 | 27 | None |
Hemingford Non-infra | DR 53 | 51478 | Jul-58 | 08-Apr-11 | 12-Apr-11 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
In Melbeta | DR 53 | 51480 | 921-125 | 11/21/2011 | 11/25/2011 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
In Melbeta | SHPO concur request | 51480 | 921-125 | 2/21/2012 | 3/6/2012 | 14 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
In Melbeta | SHPO concur request | 51480 | 915-118 | 3/14/2012 | 3/15/2012 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Weyerts South | DR 53 | 51484 | ER 1140-4 | 23-Sep-11 | 23-Sep-11 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Ft Sidney Rd - Hwy 30 to 11th Ave, Sidney | DR 53 | 51486 | 6359-1 | 30-Jun-11 | 01-Jul-11 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Sidney - Sunol | DR-53 | 51487 | 802-98 | 29-Sep-11 | 30-Sep-11 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Ave I, West Overland - 27th, Scottsbluff | DR 53 | 51488 | 5703-2 | 09-Jun-11 | 16-Jun-11 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Avenue I, Scottsbluff | 106 concur req | 51488 | 5703-2 | 12/20/2012 | 12/26/2012 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
10th St Crescent Dr to River Bridge, Gering | DR 53 | 51489 | 5701-9 | 30-Jun-11 | 01-Jul-11 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
10th Street, Crescent Dr to River Bridge | SHPO concur request | 51489 | 5701-9 | 12/9/2011 | 12/9/2011 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
10th Street Cresent Drive - River Bridge | Bio doc version 1 | 51489 | 5701-9 | 1/4/2012 | 1/16/2012 | 12 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
10th St Box Butte to Flack Ave, Alliance | DR 53 | 51490 | 6254-7 | 30-Jun-11 | 01-Jul-11 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
10th St - Box Butte to Flack | SHPO concur req | 51490 | 6254-7 | 4/17/2013 | 4/22/2013 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Potter Link Bridge | DR 53 | 51495 | L17B-109 | 10/22/2012 | 11/9/2012 | 18 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Potter Link Bridge | 106 concur req | 51495 | L17B-109 | 11/14/2012 | 11/15/2012 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Gordon East Bridge | DR 53 | 51496 | 201-144 | 10/30/2012 | 11/13/2012 | 14 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
I-80 Bridges North | DR 53 | 51497 | 272-105 | 10/31/2012 | 11/13/2012 | 13 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
I-80 North Bridges | SHPO concur req | 51497 | 272-105 | 8/14/2013 | 8/22/2013 | 8 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Interstate Canal Bridge | DR 53 | 51498 | 294-108 | 10/31/2012 | 11/13/2012 | 13 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Interstate Canal Bridge | 106 concur req | 51498 | 294-108 | 3/14/2013 | 3/15/2013 | 1 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Cottonwood Creek N of Crawford | Bio doc | 51499 | 714-120 | 4/25/2013 | 5/14/2013 | 19 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Cottonwood Creek N of Crawford, Crawford-SD Line | US Forest Svc concur req | 51499 | 714-120 | 9/18/2013 | 9/20/2013 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
E Jct US-20 North | DR 53 | 51506 | 874-117 | 7/12/2012 | 8/8/2012 | 27 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
SB Valley Pathway N | DR-53 | 51512 | 79-42 | 4/3/2012 | 4/26/2012 | 23 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Scottsbluff Valley Pathway North | SHPO concur request | 51512 | 79-42 | 4/25/2012 | 4/27/2012 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Scottsbluff Valley Trail North | probable class clarification | 51512 | 79-42 | 4/18/2013 | 4/18/2013 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Brownson Interch Lighting | DR-53 | 51526 | 801-191 | 11/29/2012 | 12/3/2012 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Brownson Interchange Lighting | 106 concur req | 51526 | 801-191 | 12/10/2012 | 12/13/2012 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Dunning Northeast | SHPO concur req | 60818 | 913-103 | 22-Feb-11 | 24-Feb-11 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Dunning Northeast | SHPO concur request | 60818 | 913-103 | 2/23/2012 | 3/6/2012 | 12 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Dunning Northeast | Bio doc version 1 | 60818 | 913-103 | 3/21/2012 | 4/20/2012 | 30 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Dunning Northeast | Scope Change Memo | 60818 | 913-103 | 5/23/2012 | 5/25/2012 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Dunning Northeast | Cat Ex | 60818 | 913-103 | 6/18/2012 | 6/26/2012 | 8 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Merna - Broken Bow | DR 53 | 60938 | 23-117 | 28-Sep-10 | 04-Oct-10 | 6 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Merna-Broken Bow | Bio doc vers 1 | 60938 | 23-117 | 02-Nov-10 | 03-Nov-10 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Merna - Broken Bow | SHPO concur req | 60938 | 23-117 | 05-Jan-11 | 07-Jan-11 | 2 | NDOR/address FHWA comments and resubmit |
Merna - Broken Bow | SHPO concur req | 60938 | 23-117 | 10-Jan-11 | 31-Jan-11 | 21 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Merna to Broken Bow | SHPO concur req | 60938 | 23-117 | 10-Jan-11 | 31-Jan-11 | 21 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Merna to Broken Bow | Scope Change Memo | 60938 | 23-117 | 4/25/2012 | 4/26/2012 | 1 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Big Blue Springs | SHPO concurrence letter | 60939 | 302(133) | 14-Sep-10 | 23-Sep-10 | 9 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Big Springs-Brule | Bio doc vers 1 | 60939 | 302-133 | 19-Oct-10 | 22-Oct-10 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Sargent South | SHPO concur req | 60943 | 1833-113 | 18-May-11 | 19-May-11 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Sargent South | Bio doc | 60943 | 1833-113 | 1/14/2013 | 1/17/2013 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Sargent South | 106 concur req | 60943 | 1833-113 | 3/13/2013 | 3/14/2013 | 1 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Sargent South | Scope Change Memo | 60943 | 1833-113 | 3/21/2013 | 3/27/2013 | 6 | NDOR/address FHWA comments and resubmit |
Seneca East & West | SHPO Concur | 61009 | 22-113 | 20-Aug-10 | 27-Aug-10 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Seneca East & West | DR 53 | 61009 | 22-113 | 25-Oct-10 | 26-Oct-10 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Seneca East and West | Bio Doc vers 1 | 61009 | 22-113 | 10/18/2011 | 10/28/2011 | 10 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Seneca East & West | CE | 61009 | 22-113 | 1/27/2012 | 2/7/2012 | 11 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
In Broken Bow | SHPO concur req | 61200 | 23-118 | 19-Jan-11 | 31-Jan-11 | 12 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
In Broken Bow | SHPO concur req | 61200 | 23-118 | 31-May-11 | 10-Jun-11 | 10 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
In Broken Bow | Bio doc vers 1 | 61200 | 23-118 | 18-Aug-11 | 23-Aug-11 | 5 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
In Broken Bow | 4(f) concur letters | 61200 | 23-118 | 1/3/2012 | 1/13/2012 | 10 | NDOR/address FHWA comments and resubmit |
In Broken Bow | 4(f) de minimis forms | 61200 | 23-118 | 1/17/2012 | 1/25/2012 | 8 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
In Broken Bow | CE | 61200 | 23-118 | 1/31/2012 | 2/8/2012 | 8 | NDOR/address FHWA comments and resubmit |
In Broken Bow | CE - revised | 61200 | 23-118 | 2/27/2012 | 3/5/2012 | 7 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Sutherland North | DR 53 | 61231 | 1475-5 | 24-Jan-11 | 31-Jan-11 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Sargent North | Bio doc vers 1 | 61232 | 1833-115 | 04-Oct-10 | 12-Oct-10 | 8 | NDOR/address FHWA comments and resubmit |
Sargent North | DR 53 | 61232 | 1833-115 | 08-Oct-10 | 12-Oct-10 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Sargent North | Bio doc vers 1 - revised | 61232 | 1833-115 | 15-Oct-10 | 19-Oct-10 | 4 | NDOR/address FHWA comments and resubmit |
Sargent North | Bio doc - revised | 61232 | 1833-115 | 22-Oct-10 | 22-Oct-10 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Sargent North | SHPO concur | 61232 | 1833-115 | 09-Nov-10 | 12-Nov-10 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Sargent North | CE | 61232 | 1833-115 | 16-Feb-11 | 22-Feb-11 | 6 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Overton Southwest | DR 53 | 61260 | 7024-22 | 1/18/2012 | 1/25/2012 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Overton SW | 106 concur req | 61260 | 7024-22 | 2/21/2013 | 2/28/2013 | 7 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Overton SW | Cat Ex | 61260 | 7024-22 | 9/18/2013 | 9/18/2013 | 0 | None |
Overton SW | CE rev | 61260 | 7024-22 | 9/19/2013 | 9/20/2013 | 1 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Hershey viaduct | DR 53 | 61277 | L56C-106 | 14-Mar-11 | 15-Mar-11 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Colorado Line Northeast | Cat Ex Re-eval Memo | 61280 | 1382-108 | 4/11/2013 | 4/17/2013 | 6 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Buffalo Bill | reeval for additl easement | 61283 | 5805(5) | 09-Mar-10 | 11-Mar-10 | 2 | NDOR/address FHWA comments and resubmit |
Anselmo Northeast | DR 53 | 61302 | 7021-27 | 11/25/2011 | 12/1/2011 | 6 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Anselmo Northeast | 4(f) concur memo | 61302 | 7021-27 | 1/19/2012 | 1/31/2012 | 12 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Anselmo Northeast | SHPO concur request | 61302 | 7021-27 | 1/25/2012 | 1/31/2012 | 6 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Anselmo Northeast | Bio doc version 1 | 61302 | 7021-27 | 3/23/2012 | 4/23/2012 | 31 | NDOR/address FHWA comments and resubmit |
Anselmo Northeast | Bio doc - version 2 | 61302 | 7021-27 | 6/27/2012 | 7/2/2012 | 5 | NDOR/address FHWA comments and resubmit |
Anselmo Northeast | Bio doc - version 2 | 61302 | 7021-27 | 7/3/2012 | 7/12/2012 | 9 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Anselmo Northeast | SHPO concur req | 61302 | 7021-27 | 7/10/2012 | 8/8/2012 | 29 | NDOR/address FHWA comments and resubmit |
Anselmo Northeast | SHPO concur req - revised | 61302 | 7021-27 | 8/27/2012 | 8/31/2012 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Anselmo Northeast Historic Bridge | 4(f) review | 61302 | 7021-27 | 7/2/2013 | 7/8/2013 | 6 | NDOR/address FHWA comments and resubmit |
Anselmo NE Historic Bridge | 4(f) revised | 61302 | 7021-27 | 7/24/2013 | 7/29/2013 | 5 | NDOR/address FHWA comments and resubmit |
Ansley Southeast | DR 53 | 61303 | 7021-28 | 11/25/2011 | 12/5/2011 | 10 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Ansley Southeast | SHPO concur request | 61303 | 7021-28 | 12/7/2011 | 12/9/2011 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Ansley Southeast | Bio doc version 1 | 61303 | 7021-28 | 2/24/2012 | 3/8/2012 | 13 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Ansley SE | Cat Ex | 61303 | 7021-28 | 5/15/2013 | 5/21/2013 | 6 | NDOR/address FHWA comments and resubmit |
Ansley Southeast | Cat Ex - revised | 61303 | 7021-28 | 5/31/2013 | 6/5/2013 | 5 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
13th St | bio memo | 61338 | 6556(4) | 10-Feb-10 | 22-Feb-10 | 12 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
North Platte East | Bio doc version 2 | 61339 | 803-136 | 7/26/2012 | 7/26/2012 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
1st - 6th Sts., North Platte | DR 53 | 61359 | 832-128 | 7/30/2012 | 8/14/2012 | 15 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
1st St. - 6th St., North Platte | SHPO concur req | 61359 | 832-128 | 8/24/2012 | 8/31/2012 | 7 | NDOR/address FHWA comments and resubmit |
Lewellen South | Bio doc vers 1 | 61368 | 261-158 | 18-Oct-10 | 22-Oct-10 | 4 | NDOR/address FHWA comments and resubmit |
Lewellen South | Bio doc - revised | 61368 | 261-158 | 22-Oct-10 | 22-Oct-10 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
North Platte - Maxwell | DR 53 | 61399 | 803-136 | 06-Oct-10 | 12-Oct-10 | 6 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
North Platte East | 106 Concur Req | 61399 | 803-136 | 3/29/2012 | 4/25/2012 | 27 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
North Platte East | Bio doc version 1 | 61399 | 803-136 | 7/23/2012 | 7/26/2012 | 3 | NDOR/address FHWA comments and resubmit |
North Platte East | FHWA review req | 61399 | 803-138 | 7/19/2012 | 7/26/2012 | 7 | NDOR/address FHWA comments and resubmit |
North Platte East | Cat Ex | 61399 | 803-136 | 10/15/2012 | 11/8/2012 | 24 | NDOR/address FHWA comments and resubmit |
North Platte East | CE - revised | 61399 | 803-136 | 12/6/2012 | 12/6/2012 | 0 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Paxton East | DR 53 | 61401 | 803-149 | 14-Oct-11 | 17-Oct-11 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Maxwell SW | DR 53 | 61414 | 1480-11 | 01-Mar-11 | 02-Mar-11 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Maxwell Southwest | Bio doc vers 1 | 61414 | 1480-11 | 06-May-11 | 06-May-11 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Maxwell Southwest | SHPO concur req | 61414 | 1480-11 | 18-Jul-11 | 20-Jul-11 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Maxwell SW | Categorical Exclusion | 61414 | 1480-11 | 12/21/2011 | 12/27/2011 | 6 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Bridwood Grade Separation | Reevaluation | 61416 | 1390-3 | 2/7/2012 | 2/15/2012 | 8 | NDOR/address FHWA comments and resubmit |
Birdwood Grade Separation | Re-evaluation revised | 61416 | 1390-3 | 2/24/2012 | 3/8/2012 | 13 | NDOR/address FHWA comments and resubmit |
Bridwood Grade Separation | Re-eval version 2 | 61416 | 1390-3 | 6/18/2012 | 6/19/2012 | 1 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Bridwood Grade Separation | Re-eval version 2 | 61416 | 1390-3 | 6/21/2012 | 6/21/2012 | 0 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
OA project | Bio doc version 1 | 61424 | 804-136 | 06-Aug-10 | 11-Aug-10 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Bio doc vers 1 | Gothenburg E and W | 61425 | 804-137 | 28-Feb-11 | 01-Mar-11 | 1 | NDOR/address FHWA comments and resubmit |
Bio doc vers 1 | Cozad to Darr | 61426 | 804-138 | 28-Feb-11 | 01-Mar-11 | 1 | NDOR/address FHWA comments and resubmit |
Hershey East | DR 53 | 61427 | 803-140 | 11/22/2011 | 12/5/2011 | 13 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Hershey East | draft SHPO concur req | 61427 | 803-140 | 9/11/2012 | 9/14/2012 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Hershey East | Bio doc version 1 | 61427 | 803-140 | 3/25/2013 | 4/4/2013 | 10 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Hershey East | Cat Ex | 61427 | 803-140 | 7/3/2013 | 7/9/2013 | 6 | NDOR/address FHWA comments and resubmit |
Hershey East | Cat Ex - revised | 61427 | 803-140 | 7/18/2013 | 7/23/2013 | 5 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Paxton East | DR 53 | 61428 | 803-141 | 6/19/2012 | 6/27/2012 | 8 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Paxton East | SHPO concur req | 61428 | 803-141 | 4/9/2013 | 4/17/2013 | 8 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Paxton East | Cat Ex | 61428 | 803-141 | 8/22/2013 | 8/27/2013 | 5 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Maxwell - Brady | DR 53 | 61429 | 804-139 | 2/20/2013 | 2/22/2013 | 2 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Maxwell - Brady | 106 concur req | 61429 | 804-139 | 3/14/2013 | 3/15/2013 | 1 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Ash - Jefferson St, Lexington | NEPA & CE | 61433 | 2832-102 | 06-Apr-10 | 07-Apr-10 | 1 | NDOR/address FHWA comments and resubmit |
Sutherland West | DR 53 | 61442 | 803-143 | 21-Mar-11 | 21-Mar-11 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Sutherland West | SHPO concur request | 61442 | 803-143 | 5/23/2012 | 6/8/2012 | 16 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Thomas County Line South | SHPO concur req | 61456 | 833-109 | 8/26/2013 | 8/27/2013 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Lexington East Viad. | DR 53 | 61457 | 1705-3 | 27-Dec-10 | 05-Jan-11 | 9 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Lexington East Viaduct | NEPA-404 Merge participation req letter | 61457 | 1705-3 | 5/13/2013 | 5/14/2013 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Lexington East Viaduct | P&N Alts Screening | 61457 | 1705-3 | 9/6/2013 | 10/15/2013 | 39 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Ansley East | SHPO concur req | 61458 | 923-105 | 04-Jan-11 | 07-Jan-11 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Ansley East | DR 53 | 61458 | 923-105 | 11/1/2011 | 11/2/2011 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Ansley East | Cat Ex | 61458 | 923-105 | 10/24/2012 | 11/9/2012 | 16 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Dunning SE | DR 53 | 61459 | 23-119 | 5/23/2013 | 5/30/2013 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Overton East | DR 53 | 61460 | 303-115 | 10-Mar-11 | 10-Mar-11 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Overton East | SHPO concur req | 61460 | 303-115 | 23-Sep-11 | 26-Sep-11 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Overton East | Bio doc vers 1 | 61460 | 303-115 | 10/21/2011 | 10/28/2011 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Paxton to Sutherland | CE | 61461 | 302-138 | 22-Feb-10 | 17-Mar-10 | 23 | NDOR/address FHWA comments and resubmit |
Paxton - Sutherland | NEPA & CE | 61461 | 302-138 | 06-Apr-10 | 07-Apr-10 | 1 | NDOR/address FHWA comments and resubmit |
Paxton - Sutherland | CE v2 | 61461 | 302-138 | 12-Apr-10 | 15-Apr-10 | 3 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Roscoe - Paxton | DR 53 | 61462 | 302-139 | 5/30/2013 | 5/31/2013 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Roscoe to Paxton | SHPO concur request | 61462 | 302-139 | 7/24/2013 | 7/30/2013 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Stapleton North | SHPO concur req | 61463 | 833-108 | 28-Mar-11 | 31-Mar-11 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Stapleton North | DR 53 | 61463 | 833-108 | 30-Mar-11 | 31-Mar-11 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Stapleton North & Stapleton South | CE | 61463 | 833-108 | 4/4/2012 | 4/23/2012 | 19 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Stapleton South | 106 Consultation Letter | 61464 | 832-133 | 15-Jul-10 | 26-Jul-10 | 11 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Wellfleet North | DR 53 | 61466 | 832-134 | 12-Apr-11 | 12-Apr-11 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Wellfleet North | Bio doc vers 1 | 61466 | 832-134 | 27-Jun-11 | 30-Jun-11 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Gothenburg West | DR 53 | 61467 | 302-140 | 12/5/2011 | 12/6/2011 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Cozad to Lexington | Bio doc - vers 1 | 61468 | 303-116 | 9/25/2012 | 10/16/2012 | 21 | NDOR/address FHWA comments and resubmit |
Cozad to Lexington | Bio doc - revised | 61468 | 303-116 | 10/17/2012 | 11/9/2012 | 23 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Cozad to Lexington | Cat Ex | 61468 | 303-116 | 1/17/2013 | 1/28/2013 | 11 | NDOR/address FHWA comments and resubmit |
Cozad to Lexington | bio re-consultation | 61468 | 303-116 | 1/31/2013 | 1/31/2013 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Cozad to Lexington | 106 concur request | 61468 | 303-116 | 2/7/2013 | 2/13/2013 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Cozad to Lexington | Cat Ex revised | 61468 | 303-116 | 3/26/2013 | 3/27/2013 | 1 | NDOR/address FHWA comments and resubmit |
Cozad to Lexington | Cat Ex - revised | 61468 | 303-116 | 4/22/2013 | 4/22/2013 | 0 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Halsey Spur Bridge | DR 53 | 61472 | S86B-102 | 2/2/2012 | 2/17/2012 | 15 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Halsey Spur Bridge | SHPO concur req | 61472 | FL86B3-102 | 9/11/2012 | 9/17/2012 | 6 | NDOR/address FHWA comments and resubmit |
Halsey Spur Bridge | SHPO and USFS concur req - revised | 61472 | FL86B-102 | 9/27/2012 | 10/12/2012 | 15 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Halsey Spur Bridge | Bio doc | 61472 | S86B-102 | 7/19/2013 | 7/24/2013 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Hyannis North | SHPO concur req | 61473 | 613-109 | 29-Mar-11 | 01-Apr-11 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Hyannis North | Bio Doc Vers 1 | 61473 | 613-109 | 11/23/2011 | 11/28/2011 | 5 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Arnold West | DR 53 | 61474 | 922-109 | 12/7/2011 | 12/15/2011 | 8 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Arnold West | SHPO concur request | 61474 | 922-109 | 4/25/2012 | 4/27/2012 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Arnold West | SHPO concur req - revised | 61474 | 922-109 | 5/29/2012 | 6/4/2012 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Arnold West and East | TE Effect Determination, | 61474 | 922-109 | 7/12/2013 | 7/16/2013 | 4 | NDOR/address FHWA comments and resubmit |
Arnold E W | Bio rev | 61474 | 922-109 | 8/6/2013 | 8/16/2013 | 10 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
N Jct US-83 West | DR 53 | 61475 | 232-125 | 11/7/2011 | 11/14/2011 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
North Jct. US-83 West | SHPO concur request | 61475 | 232-125 | 12/13/2011 | 12/20/2011 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
North Jct. US-83 West | Bio doc version 1 | 61475 | 232-125 | 6/5/2012 | 6/12/2012 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Lincoln - Logan County Line South | DR-53 | 61476 | 832-135 | 10/31/2012 | 11/13/2012 | 13 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Lincoln - Logan County Line South | 106 concur req | 61476 | 832-135 | 1/3/2013 | 1/9/2013 | 6 | None |
Arnold East | DR 53 | 61477 | 923-106 | 5/18/2012 | 5/31/2012 | 13 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Arnold East | SHPO concur req | 61477 | 923-106 | 9/4/2012 | 9/13/2012 | 9 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Gothenburg - Custer Co. Line | DR 53 | 61479 | 472-111 | 2/29/2012 | 3/8/2012 | 8 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Gothenburg - Custer Co Line | SHPO concur req | 61479 | 472-111 | 4/9/2013 | 4/17/2013 | 8 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Gothenburg to Custer County Line | Cat Ex | 61479 | 472-111 | 8/1/2013 | 8/2/2013 | 1 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
R56F to North Platte | DR-53 | 61480 | 832-136 | 6/12/2013 | 6/18/2013 | 6 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
R-56F - North Platte | SHPO concur req | 61480 | 832-136 | 6/18/2013 | 6/21/2013 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Mullen east & west | DR 53 | 61481 | 22-116 | 06-Apr-11 | 12-Apr-11 | 6 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Mullen East and West | 106 | 61481 | 22(116) | 09-May-11 | 13-May-11 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Mullen East & West | SHPO concur req | 61481 | 22-116 | 1/18/2012 | 1/25/2012 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Mullen East and West | Cat Ex | 61481 | 22-116 | 5/21/2013 | 6/12/2013 | 22 | NDOR/address FHWA comments and resubmit |
Mullen East & West | Cat Ex - V1 comment coordination | 61481 | 22-116 | 7/3/2013 | 7/8/2013 | 5 | NDOR/address FHWA comments and resubmit |
Mullen East and West | Cat Ex - V2 | 61481 | 22-116 | 7/26/2013 | 7/30/2013 | 4 | NDOR/address FHWA comments and resubmit |
Mullen East and West | Cat Ex - V4 | 61481 | 22-116 | 8/20/2013 | 8/22/2013 | 2 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Oconto - Eddyville | DR 53 | 61482 | 403-106 | 7/30/2012 | 8/14/2012 | 15 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Oconto - Eddyville | SHPO concur req | 61482 | 403-106 | 8/22/2012 | 8/31/2012 | 9 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Sargent Safet Routes | DR 53 | 61483 | 21-24 | 11/25/2011 | 12/5/2011 | 10 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
North Platte Canal Trl | DR 53 | 61488 | 56-35 | 15-Dec-10 | 17-Dec-10 | 2 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
North Platte Canal Trail | 106 Concur Req | 61488 | 56-35 | 3/28/2012 | 4/25/2012 | 28 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Jackson St Improves | DR 53 | 61489 | 6561-2 | 22-Feb-11 | 23-Feb-11 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Jackson St Improvements | Bio Doc V1 | 61489 | 6561-2 | 22-Jul-11 | 29-Jul-11 | 7 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Jackson St, Lexington | SHPO concur req | 61489 | 6561-2 | 24-Aug-11 | 06-Sep-11 | 13 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Jackson Street Improvements | Cat Ex | 61489 | 6561-2 | 1/20/2012 | 1/25/2012 | 5 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Jackson St Improvements, Lexington | Cat Ex | 61489 | 6561-2 | 2/9/2012 | 2/17/2012 | 8 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
South Platte River Bridges North Platte | DR 53 | 61500 | 832-137 | 11/25/2011 | 12/1/2011 | 6 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
South Platte River Bridge - North Platte | 106 concur req | 61500 | 832-137 | 2/11/2013 | 2/22/2013 | 11 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
S Platte River Bridges - North Platte | 4(f) concur req | 61500 | 832-137 | 4/18/2013 | 4/30/2013 | 12 | NDOR/address FHWA comments and resubmit |
South Platte River Bridges North Platte | De minimis | 61500 | 832-137 | 8/12/2013 | 8/29/2013 | 17 | NDOR/address FHWA comments and resubmit |
Cozad South Bridge | DR 53 | 61501 | 212-110 | 3/13/2012 | 4/5/2012 | 23 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Cozad South Bridges | Section 106 consultation package | 61501 | 212-110 | 5/2/2012 | 5/9/2012 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Cozad Bridge South | Bio doc - v1 | 61501 | 212-110 | 2/21/2013 | 3/6/2013 | 13 | NDOR/address FHWA comments and resubmit |
Cozad South Bridge | 106 concur request | 61501 | 212-110 | 3/26/2013 | 4/3/2013 | 8 | None |
Cozad South Bridge | Bio doc - version 2 | 61501 | 212-110 | 4/11/2013 | 4/22/2013 | 11 | NDOR/address FHWA comments and resubmit |
Cozad Bridge South | Revised bio | 61501 | 212-110 | 7/10/2013 | 7/23/2013 | 13 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Cozad South Bridge | Cat Ex | 61501 | 212-110 | 9/20/2013 | 9/25/2013 | 5 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
North Platte North | Bio Doc vers 1 | 61510 | 832-138 | 19-Jan-11 | 31-Jan-11 | 12 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Sutherland South | Bio Doc | 61511 | 252-108 | 20-Apr-11 | 27-Apr-11 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Sutherland South | Scope Change Memo | 61511 | 252-108 | 27-Jun-11 | 28-Jun-11 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Comstock South | DR 53 | 61513 | 1833-116 | 05-Apr-11 | 11-Apr-11 | 6 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Comstock South | SHPO concur req | 61513 | 1833-116 | 01-Aug-11 | 04-Aug-11 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Comstock South | Bio doc version 1 | 61513 | 1833-116 | 3/21/2012 | 4/20/2012 | 30 | NDOR/address FHWA comments and resubmit |
Comstock South | Bio doc version 2 | 61513 | 1833-116 | 5/2/2012 | 5/11/2012 | 9 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
In Lexington | DR 53 | 61514 | 212-111 | 2/1/2013 | 2/4/2013 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Lexington - Overton | DR 53 | 61531 | 805-74 | 12-Jan-11 | 26-Jan-11 | 14 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Lexington - Overton | Bio doc vers 1 | 61531 | 805-74 | 22-Feb-11 | 24-Feb-11 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Lexington, Walnut &17th | DR 53 | 61537 | 6558-1 | 16-Dec-10 | 17-Dec-10 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Lexington Resurfacing | SHPO concur | 61537 | 6558-1 | 25-Jan-11 | 31-Jan-11 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
17th & Walnut, Lexington | Bio doc vers 1 | 61537 | 6558-1 | 22-Mar-11 | 23-Mar-11 | 1 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
North Platte East Bridge | DR 53 | 61539 | 804-142 | 11/15/2011 | 11/22/2011 | 7 | NDOR/address FHWA comments and resubmit |
Brownlee Road South | DR 53 | 61540 | 974-111 | 10-Feb-11 | 16-Feb-11 | 6 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Brownlee Road South | Bio doc vers 1 | 61540 | 974-111 | 22-Feb-11 | 24-Feb-11 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Arthur - Grant Co, Hyannis | DR 53 | 61541 | 613-110 | 03-Feb-11 | 03-Feb-11 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Arthur-Grant Co Line | Bio doc vers 1 | 61541 | 613-110 | 22-Feb-11 | 24-Feb-11 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Tryon North | DR 53 | 61542 | 973-103 | 11/18/2011 | 11/23/2011 | 5 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Broken Bow 5th Ave Trail | DR 53 | 61548 | 21-27 | 08-Apr-11 | 12-Apr-11 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
West 5th, East A - West O | DR-53 | 61552 | 6850-1 | 12/7/2012 | 12/11/2012 | 4 | None |
West 5th, East A t0 West O | DR 53 | 61552 | 6850-1 | 2/14/2013 | 2/14/2013 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
West 5th Street, East A to West O | SHPO concur request | 61552 | 6850-1 | 6/13/2013 | 6/19/2013 | 6 | NDOR/address FHWA comments and resubmit |
West 5th Street | SHPO concur req - revised | 61552 | 6850-1 | 7/16/2013 | 7/16/2013 | 0 | NDOR/address FHWA comments and resubmit |
5th Street, West O to East A | Rev Sect 106, | 61552 | 6850-1 | 7/16/2013 | 7/16/2013 | 0 | NDOR/address FHWA comments and resubmit |
West 5th Ogallala | Sect 106 rev | 61552 | 6850-1 | 8/13/2013 | 8/13/2013 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
6th, Jackson St, 13th St Improvements | DR 53 | 61554 | 6552-1 | 30-Jun-11 | 30-Jun-11 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
6th St., Jackson St., 13th St Improvements | 106 concur req | 61554 | 6552-1 | 1/16/2013 | 1/25/2013 | 9 | NDOR/address FHWA comments and resubmit |
6th St, Jackson St, 13th St improvments | 106 concur req | 61554 | 6552-1 | 2/15/2013 | 2/27/2013 | 12 | NDOR/address FHWA comments and resubmit |
6th, Jackson, 13th St Improvements | SHPO concur req -revised | 61554 | 6552-1 | 4/2/2013 | 4/17/2013 | 15 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
6th St, Jackson St, and 13th Improvements | 4(f) Exception Req | 61554 | 6552-1 | 6/6/2013 | 6/19/2013 | 13 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
6th St, Jackson St, and 13th St Improvements | Cat Ex | 61554 | 6552-1 | 7/26/2013 | 8/6/2013 | 11 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
6th St, Jackson St, and 13th St Improvements | SHPO concur req - revised | 61554 | 6552-1 | 8/21/2013 | 8/29/2013 | 8 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Big Springs - Brule | DR 53 | 61555 | 803-150 | 11/1/2012 | 11/15/2012 | 14 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Big Springs to Brule | SHPO concur request | 61555 | 803-150 | 6/13/2013 | 6/19/2013 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Maxwell UPRR Bridge | DR 53 | 61557 | 302-141 | 8/2/2012 | 8/16/2012 | 14 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Maxwell UPRR Bridge | SHPO concur req | 61557 | 302-141 | 8/20/2012 | 8/29/2012 | 9 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Platte River Bridge, South of Gothenburg | DR 53 | 61558 | 472-112 | 8/2/2012 | 8/15/2012 | 13 | None |
Platte River Bridge, south of Gothenburg | SHPO concur req | 61558 | 472-112 | 8/24/2012 | 8/31/2012 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Broken Bow East | DR 53 | 61559 | 23-120 | 12/7/2011 | 12/15/2011 | 8 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Buffalo Creek Bridges, W of Cozad | DR 53 | 61563 | 804-143 | 9/27/2012 | 10/12/2012 | 15 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
D6 Overhead DMS | DR 53 | 61572 | ITSN-7 | 1/25/2013 | 1/28/2013 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
D6 Overhead DMS | 106 concur req | 61572 | ITSN-7 | 2/25/2013 | 2/28/2013 | 3 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
D6 Overhead DMS | Bio doc | 61572 | ITSN-7 | 4/29/2013 | 5/1/2013 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
DMS - D6 | Cat Ex | 61572 | ITSN-7 | 8/23/2013 | 8/29/2013 | 6 | NDOR/address FHWA comments and resubmit |
Overhead DMS | Cat Ex - 2nd submittal | 61572 | ITSN-7 | 9/3/2013 | 9/4/2013 | 1 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
North Platte - Maxwell Bridges | DR 53 | 61575 | 804-144 | 11/1/2012 | 11/13/2012 | 12 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
North Platte Maxwell Bridges | Bio doc | 61575 | 804-144 | 9/9/2013 | 9/10/2013 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
In Alma | DR 53 | 70460 | 1732-1 | 13-Jun-11 | 16-Jun-11 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Franklin South | DR 53 | 70510 | 101-104 | 12/1/2011 | 12/6/2011 | 5 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Oxford South Bridge | DR 53 | 70565 | 461-102 | 15-Dec-10 | 23-Dec-10 | 8 | NDOR/address FHWA comments and resubmit |
Oxford South Bridge | DR 53 - revised | 70565 | 461-102 | 18-Jan-11 | 15-Feb-11 | 28 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Oxford South Bridge | SHPO concur req | 70565 | 461-102 | 13-Jun-11 | 23-Jun-11 | 10 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Oxford South Bridge | Bio doc vers 1 | 70565 | 461-102 | 21-Sep-11 | 26-Sep-11 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Oxford South Bridge | Cat Ex | 70565 | 461-102 | 5/7/2012 | 5/9/2012 | 2 | NDOR/address FHWA comments and resubmit |
Benkelman South | DR 53 | 70696 | 342-124 | 04-Jan-11 | 21-Jan-11 | 17 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Benkelman South Section | SHPO Concur Req 106 | 70696 | 342-124 | 10-Jun-11 | 10-Jun-11 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Benkelman South | Bio doc vers 1 | 70696 | 342-124 | 07-Sep-11 | 15-Sep-11 | 8 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Benkelman South | CE | 70696 | 342-124 | 1/26/2012 | 2/8/2012 | 13 | NDOR/address FHWA comments and resubmit |
Benkelman South | CE 2nd Submittal | 70696 | 342-124 | 3/28/2012 | 4/9/2012 | 12 | NDOR/address FHWA comments and resubmit |
Benkelman South | Cat Ex - 3rd version | 70696 | 342-124 | 4/11/2012 | 4/19/2012 | 8 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Trenton Southeast | DR 53 | 70811 | 7044-27 | 1/18/2012 | 1/25/2012 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Stamford East & West | DR-53 | 70838 | 893-106 | 9/26/2013 | 9/30/2013 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Palisade Southeast | DR 53 | 70862 | 7044-29 | 23-Sep-11 | 26-Sep-11 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Palisade SE | SHPO concur req | 70862 | 7044-29 | 9/7/2012 | 9/14/2012 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Palisade SE | SHPO concur req | 70862 | 7044-29 | 9/7/2012 | 9/14/2012 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Hendley East & West | DR 53 | 70871 | 893-108 | 4/10/2012 | 4/27/2012 | 17 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Hendley East and West | Public involve inq | 70871 | 893-108 | 5/29/2012 | 6/4/2012 | 6 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Hendley E & W (Arch Test Plan) | SHPO concur req Arch Test Plan | 70871 | 893-108 | 9/10/2012 | 9/14/2012 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Hendley E and W | SHPO concur req | 70871 | 893-108 | 8/12/2013 | 8/19/2013 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Elwood SW, Gosper Co. | DR 53 | 70877 | 1530-5 | 22-Oct-10 | 26-Oct-10 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Elwood SW | SHPO concur req | 70877 | 1530-5 | 29-Mar-11 | 31-Mar-11 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Elwood Southwest | Bio Doc V1 | 70877 | 1530-5 | 06-Jul-11 | 11-Jul-11 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Culbertson to McCook | 106 Consultation Letter | 70881 | 62-122 | 14-Jul-10 | 26-Jul-10 | 12 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Moorefield E & W | DR 53 | 70889 | 232-121 | 14-Mar-11 | 15-Mar-11 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Moorefield East and West | SHPO Concur Req 106 | 70889 | 232-121 | 10-Jun-11 | 10-Jun-11 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Moorefield East and West | SHPO concur req | 70889 | 232-121 | 7/17/2012 | 7/26/2012 | 9 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
McCook North | SHPO concur request | 70923 | 1553-1 | 12/30/2011 | 1/3/2012 | 4 | NDOR/address FHWA comments and resubmit |
McCook North | SHPO concur revised | 70923 | 1553-1 | 1/10/2012 | 1/17/2012 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
McCook North | Bio doc version 1 | 70923 | 1553-1 | 3/6/2012 | 3/15/2012 | 9 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Hildreth South | Bio doc vers 1 | 70952 | 1955-2 | 19-Oct-10 | 26-Oct-10 | 7 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Hildreth South | DR 53 | 70952 | 1955-2 | 06-Dec-10 | 15-Dec-10 | 9 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Minden E and S | Bio doc vers 1 | 71028 | 64-124 | 22-Feb-11 | 24-Feb-11 | 2 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Minden East & South | 106 Concur Req | 71028 | 64-124 | 26-Apr-11 | 27-Apr-11 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Stockville SW | DR 53 | 71037 | 7032-24 | 4/12/2012 | 4/23/2012 | 11 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Stockville Southwest | SHPO concur req | 71037 | 7032-24 | 4/18/2012 | 4/25/2012 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
In Naponee | DR 53 | 71043 | 1925-3 | 06-Dec-10 | 15-Dec-10 | 9 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
In Naponee | SHPO concur req | 71043 | 1925-3 | 14-Oct-11 | 17-Oct-11 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
In Naponee | Bio doc version 1 | 71043 | 1925-3 | 1/10/2012 | 1/16/2012 | 6 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
In Naponee | Cat Ex | 71043 | 1925-3 | 7/9/2012 | 7/16/2012 | 7 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Holdrege Public Schools Safe Routes to School | DR 53 | 71070 | 69-27 | 10-Jun-11 | 16-Jun-11 | 6 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Holdrege Public Schools - Infrastructure | Bio doc version 1 | 71070 | 69-27 | 1/23/2012 | 1/25/2012 | 2 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Holdrege Public School SRTS | SHPO concur request | 71070 | 69-27 | 3/7/2012 | 3/15/2012 | 8 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Holdrege Safe Routes to School | Sect 4(f) Eval | 71070 | 69-27 | 6/6/2012 | 6/14/2012 | 8 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Holdrege SRTS | Cat Ex | 71070 | 69-27 | 11/1/2012 | 11/15/2012 | 14 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Holdrege SRTS | Memo - project changes | 71070 | 69-27 | 7/25/2013 | 7/26/2013 | 1 | None |
Holdrege SRTS | CE reeval memo | 71070 | 69(27) | 7/29/2013 | 8/9/2013 | 11 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Franklin Sterner Trail | T&E consult update | 71079 | 31-2 | 14-Dec-10 | 17-Dec-10 | 3 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Jct US-34 North | DR 53 | 71084 | 611-110 | 11-Jul-11 | 12-Jul-11 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Jct US-34 North | SHPO concur req | 71084 | 611-110 | 03-Aug-11 | 04-Aug-11 | 1 | NDOR/address FHWA comments and resubmit |
Jct US-34 North Section | SHPO concur req - 2nd | 71084 | 611-110 | 12-Aug-11 | 17-Aug-11 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Benkelman East and West | DR 53 | 71098 | 342-120 | 7/2/2013 | 7/5/2013 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Curtis East | SHPO concur req | 71102 | 232-124 | 15-Mar-11 | 16-Mar-11 | 1 | NDOR/address FHWA comments and resubmit |
Curtis East | SHPO concur req | 71102 | 232-124 | 04-Apr-11 | 07-Apr-11 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Curtis East | SHPO Supplemental | 71102 | 232-124 | 5/8/2012 | 5/9/2012 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Curtis East | Cat Ex Re-eval memo | 71102 | 232-124 | 2/15/2013 | 2/22/2013 | 7 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
US-6 West | Bio doc vers 1 | 71105 | 342-121 | 01-Oct-10 | 01-Oct-10 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
US-6 West | Bio doc vers 1 | 71105 | 342-121 | 17-Nov-10 | 23-Nov-10 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Frontier Lincoln Dawson Gosper Counties | SHPO concur request | 71122 | 233-108 | 4/9/2013 | 4/17/2013 | 8 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Farnam West | DR 53 | 71124 | 232-126 | 03-Aug-11 | 05-Aug-11 | 2 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Farnam West | SHPO concur req | 71124 | 232-126 | 31-Aug-11 | 06-Sep-11 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Hamlet - Palisade | DR 53 | 71126 | 62-129 | 9/17/2012 | 10/11/2012 | 24 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Hamlet - Palisade | 106 concur req | 71126 | 62-129 | 11/27/2012 | 12/3/2012 | 6 | NDOR/address FHWA comments and resubmit |
Hamlet - Palisade | 106 concur req - revised | 71126 | 62-129 | 1/14/2013 | 1/21/2013 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Wauneta - Hamlet | DR 53 | 71127 | 62-130 | 19-May-11 | 27-May-11 | 8 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Wauneta - Hamlet | SHPO concur req | 71127 | 62-130 | 03-Aug-11 | 04-Aug-11 | 1 | NDOR/address FHWA comments and resubmit |
Wauneta - Hamlet | SHPO concur req - 2 | 71127 | 62-130 | 22-Aug-11 | 06-Sep-11 | 15 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Wauneta to Hamlet | Cat Ex | 71127 | 62-130 | 6/26/2012 | 6/27/2012 | 1 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Trenton East & West | DR 53 | 71129 | 342-122 | 8/29/2013 | 8/30/2013 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Holdrege North | DR 53 | 71130 | 1831-114 | 8/21/2012 | 8/29/2012 | 8 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Holdrege North | SHPO concur req | 71130 | 1831-114 | 9/25/2012 | 10/12/2012 | 17 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Jct. N-21 to Elwood | DR 53 | 71131 | 232-127 | 12/7/2011 | 12/15/2011 | 8 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
H Street & Norris Ave, McCook | DR 53 | 71135 | 6154-1 | 25-Aug-10 | 01-Sep-10 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
H Street Improvements - Norris Ave to Airport Road | Bio doc version 1 | 71135 | 6154-1 | 11/18/2011 | 11/25/2011 | 7 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
H Street Improvements, Norris Ave to Airport Road | SHPO concur request | 71135 | 6154-1 | 2/1/2012 | 2/3/2012 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
H Street - Norris Ave to Airport Road, McCook | Cat Ex | 71135 | 6154-1 | 4/10/2012 | 4/23/2012 | 13 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Alma North & South | DR 53 | 71137 | 1831-115 | 25-Oct-10 | 27-Oct-10 | 2 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Alma North and South | DR53 | 71137 | 1831-115 | 27-Oct-10 | 27-Oct-10 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Alma North & South | SHPO concur | 71137 | 1831-115 | 09-Nov-10 | 12-Nov-10 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Alma North & South | Bio doc vers 1 | 71137 | 1831-115 | 05-Jan-11 | 07-Jan-11 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Minden Hike & Bike Trail | DR 53 | 71138 | 50-36 | 16-Feb-11 | 22-Feb-11 | 6 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Arapahoe South | SHPO concur req | 71139 | 2831-114 | 21-Sep-11 | 26-Sep-11 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Jct N-46 - Holdrege | Bio doc vers 1 | 71144 | 63-125 | 07-Apr-11 | 08-Apr-11 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Jct. N-46 to Holdrege | DR 53 | 71144 | 63-125 | 20-Jun-11 | 28-Jun-11 | 8 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
11th Av, Holdrege | DR 53 | 71145 | 6602-2 | 15-Dec-10 | 17-Dec-10 | 2 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
11th Ave, Holdrege | SHPO concur req | 71145 | 6602-2 | 8/2/2012 | 8/16/2012 | 14 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
11th Ave, Holdrege | 4(f) | 71145 | 6602-2 | 9/21/2012 | 10/11/2012 | 20 | NDOR/address FHWA comments and resubmit |
11th Ave, Morton - Logan, Holdrege | 4(f) de minimis | 71145 | 6602-2 | 12/6/2012 | 1/3/2013 | 28 | NDOR/address FHWA comments and resubmit |
11th Ave, Holdrege | 4(f) De minimis | 71145 | 6602-2 | 1/11/2013 | 1/16/2013 | 5 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
11th Ave, Morton - Logan St, Holdrege | CE ver 1 | 71145 | 6602(2) | 2/26/2013 | 4/1/2013 | 34 | NDOR/address FHWA comments and resubmit |
11th Ave, Morton - Logan, Holdrege | Cat Ex - revised | 71145 | 6602-2 | 6/13/2013 | 6/19/2013 | 6 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Stockville SW Road Repair | DR 53 | 71147 | ER 1460-2 | 20-Dec-10 | 27-Dec-10 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Stockville Southwest | ROW within Env Study Area | 71147 | 1460-2 | 3/22/2013 | 3/22/2013 | 0 | None |
Eustis SW | DR 53 | 71148 | ER 1675-3 | 16-Feb-11 | 16-Feb-11 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
E 7th/ Seminole, H St - Park Ave, McCook | DR 53 | 71151 | 6158-1 | 30-Jun-11 | 30-Jun-11 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
E. 7th - Seminole - H St - Park Ave, McCook | 106 concur req | 71151 | 6158-1 | 1/30/2013 | 1/31/2013 | 1 | NDOR/address FHWA comments and resubmit |
E 7th Seminol H St-Park Ave, McCook | SHPO concur req - revised | 71151 | 6158-1 | 3/28/2013 | 4/10/2013 | 13 | None |
E 17th St - Seminole Dr, from H to park Ave | Section 4(f) | 71151 | 6158-1 | 7/19/2013 | 7/24/2013 | 5 | NDOR/address FHWA comments and resubmit |
E 7th St - Seminole Dr from H St to Park Ave | Section 4(f) - v2 | 71151 | 6158-1 | 8/16/2013 | 8/27/2013 | 11 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
McCook, 7th to Seminole, H to Park Ave | CE | 71151 | 6158-1 | 9/9/2013 | 9/10/2013 | 1 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
E 7th St - Seminole, H St to Park Ave | Cat Ex - revised | 71151 | 6158-1 | 9/12/2013 | 9/13/2013 | 1 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
18th Ave, Burlington St to West Ave | DR53 | 71152 | 6606-2 | 09-May-11 | 13-May-11 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
18th Ave, Burlington - West Ave, Holdrege | SHPO concur req | 71152 | 6606-2 | 7/11/2012 | 7/24/2012 | 13 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
18th Avenue | 4(f) Excception | 71152 | 6606-2 | 1/7/2013 | 1/11/2013 | 4 | None |
18th Ave Burlington - West | Cat Ex | 71152 | 6606-2 | 5/23/2013 | 6/4/2013 | 12 | NDOR/address FHWA comments and resubmit |
18th Ave Burlington - West | Cat Ex | 71152 | 6606-2 | 7/1/2013 | 7/8/2013 | 7 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Franklin - Webster Co Line | DR 53 | 71156 | 1364-116 | 8/22/2013 | 8/27/2013 | 5 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Ericson East | DR 53 | 80643 | 704-104 | 11/7/2011 | 11/14/2011 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Ericson East | Bio doc version 1 | 80643 | 704-104 | 3/21/2012 | 4/20/2012 | 30 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Ericson East | 106 Concur Req | 80643 | 704-104 | 4/2/2012 | 4/25/2012 | 23 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Ericson East | Cat Ex | 80643 | 704-104 | 6/5/2012 | 6/11/2012 | 6 | NDOR/address FHWA comments and resubmit |
Ericson East | Cat Ex - 2nd submittal | 80643 | 704-104 | 6/27/2012 | 6/28/2012 | 1 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Niobrara River South | DR 53 | 80690 | 1834-109 | 7/27/2012 | 8/14/2012 | 18 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Burwell West | DR 53 | 80709 | 964-101 | 1/25/2012 | 2/13/2012 | 19 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Nenzel West | Bio doc vers 1 | 80727 | 202-131 | 01-Oct-10 | 12-Oct-10 | 11 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
O'Neill West | DR 53 | 80758 | 7045-28 | 1/18/2012 | 1/25/2012 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Ericson South | DR 53 | 80785 | 2325-3 | 06-Dec-10 | 15-Dec-10 | 9 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Ericson South | SHPO concur request | 80785 | 2325-3 | 12/19/2011 | 12/21/2011 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Ericson South | Bio doc version 1 | 80785 | 2325-3 | 3/23/2012 | 4/23/2012 | 31 | None |
Ericson South | Bio doc version 2 | 80785 | 2325-3 | 5/4/2012 | 5/11/2012 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Ericson South | Cat Ex | 80785 | 2325-3 | 6/3/2013 | 6/11/2013 | 8 | None |
Ericson South | Cat Ex - revised | 80785 | 2325-3 | 7/22/2013 | 7/25/2013 | 3 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Burwell North | DR-53 | 80798 | 113-118 | 4/2/2012 | 4/23/2012 | 21 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Burwell North | SHPO concur req | 80798 | 113-118 | 8/23/2012 | 8/31/2012 | 8 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Valentine East | DR-53 | 80799 | 122-104 | 4/2/2012 | 4/6/2012 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Valentine East | 106 concur req | 80799 | 122-104 | 1/16/2013 | 1/25/2013 | 9 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Valentine East | Bio doc | 80799 | 122-104 | 8/21/2013 | 8/22/2013 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Valentine North | Bio doc vers 1 | 80800 | 834-112 | 08-Oct-10 | 13-Oct-10 | 5 | NDOR/address FHWA comments and resubmit |
Valentine North | Bio doc | 80800 | 834-112 | 13-Oct-10 | 27-Oct-10 | 14 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Valentine North | SHPO concur req | 80800 | 834-112 | 25-Oct-10 | 27-Oct-10 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Valentine North | Scope change memo | 80800 | 834-112 | 22-Apr-11 | 27-Apr-11 | 5 | NDOR/address FHWA comments and resubmit |
Valentine North | Scope Change Memo V2 | 80800 | 834-112 | 27-Apr-11 | 27-Apr-11 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Valentine North (scope change) | SHPO concur req | 80800 | 834-112 | 20-May-11 | 27-May-11 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Rose - Bassett | Bio doc vers 1 | 80801 | 1834-111 | 20-Sep-10 | 29-Sep-10 | 9 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Rose North | Bio doc vers 1 | 80802 | 1834-112 | 20-Sep-10 | 29-Sep-10 | 9 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Bristow East and West | DR 53 | 80805 | 124-107 | 07-Jul-11 | 08-Jul-11 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Bristow E - W | SHPO concur req | 80805 | 124-107 | 4/5/2013 | 4/17/2013 | 12 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Bristow East & West | Bio doc | 80805 | 124-107 | 8/28/2013 | 8/30/2013 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Rose Mitigation Bank | Monitoring Report | 80810 | 75-7 | 07-Mar-11 | 21-Mar-11 | 14 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Rose Southeast Mitigation Bank | Management Plan | 80810 | 75-7 | 7/3/2013 | 7/15/2013 | 12 | NDOR/address FHWA comments and resubmit |
Niobrara Scenic Rvr Corr Roads | SHPO concur req | 80817 | 16-36 | 13-Jul-11 | 19-Jul-11 | 6 | NDOR/address FHWA comments and resubmit |
Niobrara Scenic Rvr Roads | SHPO concur req - 8 ltrs | 80817 | 16-36 | 11-Aug-11 | 16-Aug-11 | 5 | NDOR/address FHWA comments and resubmit |
Niobrara ScenRvr Cor Rds | SHPO concur req - revised | 80817 | 16-36 | 26-Aug-11 | 06-Sep-11 | 11 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Niobrara, Cherry & Keya Paha Counties | Tribal coord request | 80817 | 16-36 | 12/1/2011 | 12/6/2011 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Niobrara Scenic River Corridor | Bio doc version 2 | 80817 | 16-36 | 5/7/2012 | 5/11/2012 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Chambers West | DR-53 | 80829 | 954-105 | 7/30/2013 | 7/30/2013 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Springview SRTS | 106 concur req | 80840 | 53-12 | 11/15/2012 | 11/15/2012 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Merriman West | DR 53 | 80846 | 202-132 | 10/19/2011 | 10/28/2011 | 9 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Spencer North | Bio doc vers 1 | 80847 | 2814-117 | 22-Dec-10 | 27-Dec-10 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Spencer North | Scope Change memo | 80847 | 2814-117 | 07-Apr-11 | 15-Apr-11 | 8 | NDOR/address FHWA comments and resubmit |
Spencer North | Bio Re-eval memo - vers 2 | 80847 | 2814-117 | 21-Apr-11 | 26-Apr-11 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Chambers East | DR 53 | 80860 | 954-104 | 11/22/2011 | 11/28/2011 | 6 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Chambers East | SHPO concur request | 80860 | 954-104 | 12/8/2011 | 12/9/2011 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Chambers East | Bio doc version 1 | 80860 | 954-104 | 5/31/2012 | 6/8/2012 | 8 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Chambers East | Cat Ex | 80860 | 954-104 | 7/30/2012 | 8/14/2012 | 15 | NDOR/address FHWA comments and resubmit |
Sheridan & Cherry Line East | DR 53 | 80861 | 202-136 | 09-Dec-10 | 13-Dec-10 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Sheridan Co Line East | Bio doc vers 1 | 80861 | 202-136 | 03-Feb-11 | 03-Feb-11 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Merriman North | DR 53 | 80874 | 614-113 | 2/28/2013 | 2/28/2013 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Merriman North | 106 concur req | 80874 | 614-113 | 3/26/2013 | 4/4/2013 | 9 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Calamus River - Ainsworth | DR 53 | 80876 | 74-115 | 9/28/2012 | 10/12/2012 | 14 | NDOR/address FHWA comments and resubmit |
Calamus - Ainsworth | DR 53 | 80876 | 74-115 | 7/2/2013 | 7/5/2013 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Calamus - Ainsworth | SHPO concur request | 80876 | 74-115 | 7/1/2013 | 7/8/2013 | 7 | NDOR/address FHWA comments and resubmit |
Calamus River - Ainsworth North | 106 rev | 80876 | 74-115 | 9/12/2013 | 9/13/2013 | 1 | NDOR/address FHWA comments and resubmit |
Sparks West | DR 53 | 80877 | 122-105 | 26-Jul-11 | 29-Jul-11 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Sparks West | SHPO concur request | 80877 | 122-105 | 12/6/2011 | 12/9/2011 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Sparks West | Bio doc version 1 | 80877 | 122-105 | 5/31/2012 | 6/8/2012 | 8 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Crookston West | DR 53 | 80878 | 202-133 | 06-Oct-10 | 12-Oct-10 | 6 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Crookston West | Bio doc vers 1 | 80878 | 202-133 | 04-Feb-11 | 08-Feb-11 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Crookston West | SHPO concur req | 80878 | 202-133 | 24-Mar-11 | 31-Mar-11 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Crookston West | SHPO concur req | 80878 | 202-133 | 24-Mar-11 | 31-Mar-11 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Nenzel - Kilgore | DR 53 | 80879 | 202-134 | 11/7/2011 | 11/14/2011 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Wood Lake West | DR-53 | 80880 | 202-135 | 4/2/2012 | 4/23/2012 | 21 | NDOR/address FHWA comments and resubmit |
Wood Lake West | SHPO concur request | 80880 | 202-135 | 5/4/2012 | 5/9/2012 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Wood Lake West | Bio doc - version 1 | 80880 | 202-135 | 4/10/2013 | 4/22/2013 | 12 | NDOR/address FHWA comments and resubmit |
Wood Lake West | Cat Ex | 80880 | 202-135 | 7/1/2013 | 7/5/2013 | 4 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
S16B North & South | Bio doc vers 1 | 80881 | 834-114 | 06-Oct-10 | 13-Oct-10 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
S16B North & South | Bio doc vers 1 | 80881 | 834-114 | 06-Oct-10 | 13-Oct-10 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Valentine Cowboy Trl Conect Phs 1 | DR 53 | 80886 | 16-38 | 13-Jun-11 | 16-Jun-11 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Valentine Cowboy Trl Conect Phs 1 | DR 53 | 80886 | 16-38 | 13-Jun-11 | 16-Jun-11 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Valentine Cowboy Trail Connection - Phase 1 | 4(f) Exception Req | 80886 | 16-38 | 3/28/2012 | 4/25/2012 | 28 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Valentine Cowboy Trail Connection - Phase 1 | 106 Concur Req | 80886 | 16-38 | 3/28/2012 | 4/25/2012 | 28 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Valentine Cowboy Trail Phase 1 | 4(f) exempt request | 80886 | 16-38 | 5/18/2012 | 5/31/2012 | 13 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Valentine - Cowboy Trail Connector Ph. I | Cat Ex | 80886 | 16-38 | 11/1/2012 | 11/9/2012 | 8 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
North Loup Rvr North | Bio doc vers 1 | 80895 | 834-115 | 29-Dec-10 | 07-Jan-11 | 9 | NDOR/address FHWA comments and resubmit |
North Loup River North | bio doc version 2 | 80895 | 834-115 | 07-Jan-11 | 07-Jan-11 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
North Loup Rvr North | Bio doc vers 1 | 80895 | 834-115 | 29-Dec-10 | 07-Jan-11 | 9 | NDOR/address FHWA comments and resubmit |
North Loup River North | bio doc version 2 | 80895 | 834-115 | 07-Jan-11 | 07-Jan-11 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
North Loup Rvr North | SHPO concur req | 80895 | 834-115 | 10-Feb-11 | 15-Feb-11 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
North Loup Rvr North | SHPO concur req | 80895 | 834-115 | 10-Feb-11 | 15-Feb-11 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
North Loup Rvr North | Bio doc vers 3 | 80895 | 834-115 | 21-Mar-11 | 29-Mar-11 | 8 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
North Loup Rvr North | Bio doc vers 3 | 80895 | 834-115 | 21-Mar-11 | 29-Mar-11 | 8 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Kilgore East | Bio doc vers 1 | 80896 | 202-137 | 22-Dec-10 | 27-Dec-10 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Kilgore East | Bio doc vers 1 | 80896 | 202-137 | 22-Dec-10 | 27-Dec-10 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Inman East & West | Bio doc vers 1 | 80897 | 204-123 | 20-Dec-10 | 27-Dec-10 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Inman East & West | Bio doc vers 1 | 80897 | 204-123 | 20-Dec-10 | 27-Dec-10 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Brewster - Calamus River | DR 53 | 80899 | 73-102 | 25-Mar-11 | 29-Mar-11 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Brewster - Calamus River | DR 53 | 80899 | 73-102 | 25-Mar-11 | 29-Mar-11 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Brewster - Calamus River | Bio doc version 1 | 80899 | 73-102 | 6/1/2012 | 6/11/2012 | 10 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Brewster - Calamus River | Cat Ex | 80899 | 73-102 | 8/1/2012 | 8/13/2012 | 12 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Wheeler-Antelope Co. Line West | DR 53 | 80900 | 704-110 | 25-Jul-11 | 29-Jul-11 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Wheeler-Antelope Co. Line West | DR 53 | 80900 | 704-110 | 25-Jul-11 | 29-Jul-11 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Crookston - Valentine | DR 53 | 80901 | 202-138 | 09-Mar-11 | 10-Mar-11 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Crookston - Valentine | DR 53 | 80901 | 202-138 | 09-Mar-11 | 10-Mar-11 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Crookston - Valentine | Bio Doc | 80901 | 202-138 | 26-Apr-11 | 27-Apr-11 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Crookston - Valentine | Bio Doc | 80901 | 202-138 | 26-Apr-11 | 27-Apr-11 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Ewing Link | DR 53 | 80906 | ER SL45B-103 | 02-Sep-11 | 14-Sep-11 | 12 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Ewing Link | DR 53 | 80906 | ER SL45B-103 | 02-Sep-11 | 14-Sep-11 | 12 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Ewing Link, Loup County | SHPO concur req | 80906 | ER SL45B-103 | 11-Oct-11 | 12-Oct-11 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Ewing Link, Loup County | SHPO concur req | 80906 | ER SL45B-103 | 11-Oct-11 | 12-Oct-11 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Ewing Link | Bio doc version 1 | 80906 | SL45B-103 | 3/22/2012 | 3/22/2012 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
O'Neill SE | DR 53 | 80907 | ER 204-124 | 02-Sep-11 | 14-Sep-11 | 12 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
O'Neill SE | DR 53 | 80907 | ER 204-124 | 02-Sep-11 | 14-Sep-11 | 12 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
O'Neill Southeast | SHPO concur req | 80907 | ER 204-124 | 12-Oct-11 | 12-Oct-11 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
O'Neill Southeast | SHPO concur req | 80907 | ER 204-124 | 12-Oct-11 | 12-Oct-11 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
ER - Gracie Creek Culvert | DR 53 | 80908 | ER 964-103 | 02-Sep-11 | 19-Sep-11 | 17 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
ER - Gracie Creek Culvert | DR 53 | 80908 | ER 964-103 | 02-Sep-11 | 19-Sep-11 | 17 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Burwell Northwest | DR 53 ver 2 | 80908 | ER 964-103 | 07-Oct-11 | 07-Oct-11 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Burwell Northwest | SHPO concur req | 80908 | ER 964-103 | 07-Oct-11 | 07-Oct-11 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Burwell Northwest | DR 53 ver 2 | 80908 | ER 964-103 | 07-Oct-11 | 07-Oct-11 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Burwell Northwest | SHPO concur req | 80908 | ER 964-103 | 07-Oct-11 | 07-Oct-11 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
ER - North Loup River | DR 53 | 80909 | ER 1833-117 | 02-Sep-11 | 16-Sep-11 | 14 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
ER - North Loup River | DR 53 | 80909 | ER 1833-117 | 02-Sep-11 | 16-Sep-11 | 14 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
North Loup River, Taylor | SHPO concur request | 80909 | 1833-117 | 11/18/2011 | 11/25/2011 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
North Loup Taylor | Reevaluation Memo | 80909 | 1833-117 | 5/30/2012 | 6/5/2012 | 6 | NDOR/address FHWA comments and resubmit |
North Loup Taylor | Reeval Memo | 80909 | 1833-117 | 6/12/2012 | 6/19/2012 | 7 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Thedford - Valentine | DR 53 | 80911 | 834-116 | 22-Aug-11 | 06-Sep-11 | 15 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Thedford - Valentine | DR 53 | 80911 | 834-116 | 22-Aug-11 | 06-Sep-11 | 15 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Thedford to Valentine | Bio doc version 1 | 80911 | 834-116 | 12/16/2011 | 12/23/2011 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
SE Jct US275 Antelope Co Line | DR 53 | 80913 | 204-125 | 05-Oct-11 | 06-Oct-11 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
SE Jct US275 Antelope Co Line | DR 53 | 80913 | 204-125 | 05-Oct-11 | 06-Oct-11 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Ahntelope County Line | Bio doc version 1 | 80913 | 204-125 | 12/19/2011 | 12/23/2011 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Ewing East and West | DR 53 | 80914 | 2754-105 | 12/21/2011 | 12/6/2011 | -15 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Ewing East & West | SHPO concur request | 80914 | 2754-105 | 5/21/2012 | 6/4/2012 | 14 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Loup County Line - Burwell | DR 53 | 80915 | 914-108 | 11/18/2011 | 11/23/2011 | 5 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Loup County Line - Burwell | Bio doc version 1 | 80915 | 914-108 | 6/26/2012 | 7/2/2012 | 6 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Loup County Line - Burwell | Cat Ex | 80915 | 914-108 | 9/13/2012 | 9/17/2012 | 4 | NDOR/address FHWA comments and resubmit |
Loup County Line - Burwell | Cat Ex | 80915 | 914-108 | 11/7/2012 | 11/15/2012 | 8 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Merriman - Eli | DR 53 | 80916 | 202-140 | 30-Aug-11 | 06-Sep-11 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Merriman - Eli | DR 53 | 80916 | 202-140 | 30-Aug-11 | 06-Sep-11 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Merriman to Eli | Bio doc version one | 80916 | 202-140 | 12/19/2011 | 12/23/2011 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
N Jct. N-70 Northwest | DR 53 | 80917 | 2813-111 | 02-Sep-11 | 14-Sep-11 | 12 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
N Jct. N-70 Northwest | DR 53 | 80917 | 2813-111 | 02-Sep-11 | 14-Sep-11 | 12 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
N Jct. N-70 Northwest | Bio doc version 1 | 80917 | 2813-111 | 12/19/2011 | 12/23/2011 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Ewing Southwest | DR 53 | 80921 | ER 2260-2 | 23-Sep-11 | 23-Sep-11 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Ewing Southwest | DR 53 | 80921 | ER 2260-2 | 23-Sep-11 | 23-Sep-11 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Ewing SW | Scope Change Memo | 80921 | 2260-2 | 8/22/2013 | 8/27/2013 | 5 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Inman Northeast | DR 53 | 80922 | ER 2270-2 | 23-Sep-11 | 23-Sep-11 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Inman Northeast | DR 53 | 80922 | ER 2270-2 | 23-Sep-11 | 23-Sep-11 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Emmet South | DR 53 | 80923 | ER 2105-3 | 23-Sep-11 | 23-Sep-11 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Emmet South | DR 53 | 80923 | ER 2105-3 | 23-Sep-11 | 23-Sep-11 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Stuart Northeast | DR 53 | 80924 | ER 2115-4 | 23-Sep-11 | 23-Sep-11 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Stuart Northeast | DR 53 | 80924 | ER 2115-4 | 23-Sep-11 | 23-Sep-11 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Naper South | DR 53 | 80925 | ER 2115-5 | 23-Sep-11 | 23-Sep-11 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Naper South | DR 53 | 80925 | ER 2115-5 | 23-Sep-11 | 23-Sep-11 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Burwell NW Bridge | DR 53 | 80926 | 964(104) | 5/2/2012 | 5/11/2012 | 9 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Atkinison - Bush Creek, Atkinson North | DR 53 | 80932 | 114-113 | 3/6/2013 | 3/7/2013 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
CCTV, Snapshot | DR 53 for multiple ITSN projects | 80935 | ITSN-8 | 2/6/2013 | 2/8/2013 | 2 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Naper East | DR 53 | 80937 | 124-108 | 3/14/2013 | 3/15/2013 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Holt - Garfield County Line | DR 53 | 80938 | 113-122 | 3/15/2013 | 3/22/2013 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Hackberry Lake Northwest | DR-53 | 80939 | S16B-103 | 1/18/2013 | 1/25/2013 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Hackberry Lake Northwest | Bio doc version 1 | 80939 | S16B-103 | 3/29/2013 | 4/10/2013 | 12 | None |
Tier 1 - Chicago to Omaha Regional Passenger Rail System | Cooperating Agency request | 5/23/2012 | 7/18/2012 | 56 | None | ||
Bison Bridge | Cat Ex | RTP 2011-5 | 7/26/2012 | 8/9/2012 | 14 | None | |
Pioneers Park Trail Renovation | Cat Ex | RTP 2012-1 | 8/30/2012 | 8/31/2012 | 1 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required | |
Blair culvert and Jackson St projects | ER bio clarification memo | 3675-7; 3680-7 | 2/27/2013 | 2/27/2013 | 0 | None | |
2008-2010 LPA ER projects | Scope Modifications Memo | 3/7/2013 | 3/8/2013 | 1 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required | ||
Effects of Compac and Soil Moisture on Amer Buring Beetles | Action | SPR 1-14 | 4/18/2013 | 4/19/2013 | 1 | None | |
Develop NE Culvert Aquatic Organism Passing Screen Tool | Bio doc | SPR 1-13 | 4/22/2013 | 4/30/2013 | 8 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA | |
Swift Fox survey along Heartland Hwy Coord | Bio doc | SPR 1-14 | 4/23/2013 | 4/30/2013 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA | |
McCook Rec Trail System Phase III - Southview Trail | NEPA Compliance | RTP 2012-002 | 4/22/2013 | 5/30/2013 | 38 | NDOR/address FHWA comments and resubmit | |
Trail in McCook | CE | RTP 2012 002 | 6/19/2013 | 6/19/2013 | 0 | NGPC/address FHWA comments and resubmit | |
McCook Rec Trail System | NGP - NEPA doc review | RTP2012-2 | 6/27/2013 | 7/9/2013 | 12 | NGPC/address FHWA comments and resubmit | |
Statewide Guardrail Districts 6 & 7 | DR53-STWD-00863_HSIP-STP-STWD 110 Guardrail | 7/12/2013 | 7/12/2013 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation | ||
Overhead DMS | DR 53 | ITSN-16 -28 -25 | 8/15/2013 | 8/16/2013 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation | |
Marv Holubar Trail - Sarpy County | Cat Ex | RTP 2012-3 | 8/23/2013 | 9/5/2013 | 13 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required | |
Statewide Concrete ROW Marker Evaluation | SHPO concur req | 9/10/2013 | 9/10/2013 | 0 | None | ||
No Potential to Cause Effects to Historic Properties | THPO concur req | 9/10/2013 | 9/11/2013 | 1 | NDOR/address FHWA comments and resubmit | ||
Southview Trail - McCook | NEPA doc - revised | RTP2012-002 | 9/16/2013 | 9/17/2013 | 1 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required | |
Wayne South & Wayne South Bridge | CE |  31886 & 31893 | STP-15-4(117) & BR-STP-15-4(118) | 12/11/2012 | 12/11/2012 | 0 | NDOR/address FHWA comments and resubmit |
Rest Area Information Kiosks | Bio doc | 00645B | ITSN-115 | 4/25/2013 | 5/14/2013 | 19 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
I-80 Rest Area Kiosks | SHPO and THPO concur req | 00645B | ITSN-115 | 4/29/2013 | 5/14/2013 | 15 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
D2-D1 Device Deployment | Bio doc vers 1 | 00649J | ITSN-209 | 26-Oct-10 | 27-Oct-10 | 1 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval |
D1/D2 Device Deploy | SHPO concur req | 00649J | ITSN-209 | 02-Dec-10 | 10-Dec-10 | 8 | FHWA sent the material to the resource agency(s) for review/concurrrence, which takes up to 4 weeks. Once all tech reviews and concurrences complete, next step is for NDOR to review/approve the NEPA doc. If not a PCE, NDOR will submit CE to FHWA |
LPA/NDOR Statewide Workforce Development | DR 53 | 00841A | STWD-113 | 12-Jul-11 | 19-Jul-11 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Agnew N & S | DR 53 | 10584A | 792-108 | 3/21/2013 | 4/2/2013 | 12 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
North/South Rd., K-Q, Lincoln | CO 12 | 11215A | 55-142 | 11/29/2012 | 12/3/2012 | 4 | None |
Alvo North Bridges | DR 53 | 11450A | 632-114 | 08-Oct-10 | 15-Oct-10 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Alvo North Bridge | Bio Doc vers 1 | 11450A | 632-114 | 20-Dec-10 | 27-Dec-10 | 7 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Alvo North bridges | SHPO concur req | 11450A | 632-114 | 15-Mar-11 | 16-Mar-11 | 1 | FHWA sent the material to the resource agency(s) for review/concurrrence, which takes up to 4 weeks. Once all tech reviews and concurrences complete, next step is for NDOR to review/approve the NEPA doc. If not a PCE, NDOR will submit CE to FHWA |
Alvo North bridges | CE | 11450A | 632-114 | 19-Aug-11 | 03-Sep-11 | 15 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Rulo Bridge Removal | Project description memo | 12381D | 1597-109 | 11/30/2012 | 12/3/2012 | 3 | None |
Rulo Bridge Removal | 106 and THPO concur req | 12381D | 1597-109 | 11/29/2012 | 1/8/2013 | 40 | None |
Rulo Bridge Removal | Bio Assess - Reeval Memo | 12381D | 1597-109 | 1/11/2013 | 1/28/2013 | 17 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Rulo Bridge | EIS Reeval | 12381D | 1597-105 | 4/18/2013 | 4/30/2013 | 12 | NDOR/address FHWA comments and resubmit |
Rulo Bridge | EIS Re-evaluation | 12381D | 1597-105 | 6/14/2013 | 6/26/2013 | 12 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
14th St Br, Linc; Mahoney Intrch ramps | Reevaluation | 12482, 12312 | 809-855, -872 | 28-Apr-11 | 11-May-11 | 13 | NDOR/address FHWA comments and resubmit |
Lincoln South Beltway | NEPA Beltway Negotiations Questions response | 12578D | 26-120 | 9/9/2013 | 9/12/2013 | 3 | None |
Lincoln South Beltway | SOS Negotiated Eng Supple One | 12578D | 26-120 | 9/9/2013 | 9/16/2013 | 7 | None |
Fordyce East and West, Crofton East | Cat Ex | 126-116 | 126-116 | 4/2/2013 | 4/5/2013 | 3 | NDOR/address FHWA comments and resubmit |
Goehner Safety Rest Area Truck Parking | Cat Ex Re-eval | 12888B | 808-155 | 6/25/2013 | 7/3/2013 | 8 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Auburn E & In Auburn | DR 53 | 12994, 13062 | 1366(119), 1367(123) | 08-Mar-11 | 08-Mar-11 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Jct N-64 to Schuyler; Jct Us-34 North; Ewing East & West | Cat Ex | 13019; 71084; 80914 | 152-122; 611-110; 2754-105 | 7/31/2012 | 8/15/2012 | 15 | None |
Jct N-64 to Schuyler; Jct US-34 North; Ewing E & W | Cat Ex - revised | 13019; 71084; 80914 | 152-122; 611-110; 2754-105 | 8/20/2012 | 8/28/2012 | 8 | NDOR/address FHWA comments and resubmit |
Jct N-64 to Schuyler; Jct US-34 North; Ewing E&W | Batch Projects Cat Ex revisions | 13019; 71084; 80914 | 152-122; 611-110; 2754-105 | 8/29/2012 | 8/29/2012 | 0 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
In Auburn and Auburn East | Bio doc | 13062, 12994 | 1367-123, -126 | 7/19/2013 | 7/25/2013 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Seward E Bridges - I-80 Structures W of Aurora - North Platte E Bridge | Cat Ex | 13136, 42661, 61539 | 808-153 | 7/31/2013 | 8/1/2013 | 1 | NDOR/address FHWA comments and resubmit |
Installation of Anti-Icing Systems | DR 53 | 13136; 42661; 61539 | 808-153; 807-160; 804-142 | 12/7/2011 | 12/15/2011 | 8 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Seward E Brgs; I-80 Struc W of Aurora; North Platte E Bridge | 106 concur req - batched 3 projects | 13136; 42661; 61539 | 808-153; 807-160; 804-142 | 12/5/2012 | 12/7/2012 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Statewide Cameras | SHPO and THPO concur requests | 13138 et al | ITSN-11 et al | 6/17/2013 | 6/17/2013 | 0 | NDOR/address FHWA comments and resubmit |
Bellwood E and W, US-77 to Platte River | DR 53 | 13165; 13052 | 646-104, 646-105 | 2/6/2013 | 2/8/2013 | 2 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Falls City to US-75; Kansas State Line to Auburn | DR 53 - resubmittal | 13205; 13206 | 731-117; 751-106 | 2/22/2012 | 3/5/2012 | 12 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Falls City-US75; K-State Line-Auburn | Bio doc version 1 | 13205; 13206 | 731-117; 751-106 | 3/5/2012 | 3/8/2012 | 3 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
N-133, N-36, North-Blair South | SHPO concur request | 21791- 21791a | 1333-102; 1333-103 | 4/5/2012 | 4/26/2012 | 21 | NDOR/address FHWA comments and resubmit |
N-36 North & Blair South | SHPO concur request - version 2 | 21791; 21791A | 1333-102; 1333-103 | 5/14/2012 | 5/25/2012 | 11 | NDOR/address FHWA comments and resubmit |
Blair South / N-36 North Omaha | Noise Study | 21791; 21791A | 1333-102; 1333-103 | 5/23/2012 | 6/27/2012 | 35 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
N-133, Jct. N-36 North, Omaha; Blair South | 4(f) req | 21791; 21791a | 1333-102; 1333-103 | 6/29/2012 | 7/11/2012 | 12 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
N-36 North and Blair South | Cat Ex Reeval | 21791; 21791A | 1333-102; 1333-103 | 7/17/2012 | 7/24/2012 | 7 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Blair South | Bio doc vers 1 | 21791A | 1333-103 | 14-Jan-11 | 31-Jan-11 | 17 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Oreopolis Wetland Mitigation Site | NEPA Det. Form V2 | 21849F | 752-168 | 10-Jun-10 | 10-Jun-10 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Oreapolis Wetland Mitigation site | Bio doc | 21849F | 752-168 | 14-Jun-10 | 22-Jun-10 | 8 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Omaha Riverfront Trail - Phase 4 | DR 53 | 21973A | 28-109 | 23-Sep-11 | 26-Sep-11 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Omaha Interstate projects | Grouping for NEPA Analysis | 22143, etc | 809-897 | 02-Nov-10 | 18-Nov-10 | 16 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
144th St - Dodge to Corby | Re-evaluation | 22202A | 5001-15 | 7/24/2013 | 8/2/2013 | 9 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Western Douglas Co. Trls; Phase 1 & 2 | SHPO concur req | 22227; 22227A | 28-87; 28-102 | 6/12/2012 | 6/14/2012 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
WDCT Phase 1; WDCT Phase 2 | Bio doc version 1 | 22227; 22227A | 28-87; 28-102 | 7/5/2012 | 7/12/2012 | 7 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
WDCT - Valley to Waterloo, Ph 2 | DR 53 | 22227A | 28-102 | 09-Jun-11 | 10-Jun-11 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Fort St - MO River Bridges; Resurfacing | Cat Ex | 22264; 22264A | 6809-29; 6809-30 | 11/27/2012 | 12/4/2012 | 7 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Fremont Main St Hist Lighting | SHPO concur req | 22272A | 27-60 | 04-Apr-11 | 07-Apr-11 | 3 | NDOR/address FHWA comments and resubmit |
Fremont Main St Hist Lighting | Bio doc | 22272A | 27-60 | 13-Oct-11 | 14-Oct-11 | 1 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
36th St Roadway Impr Ph 1 & 2 | DR 53 | 22276 & 22288 | 5061-5, 3773-1 | 10-Jan-11 | 26-Jan-11 | 16 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
36th Street Improvements, Ph 1 & 2, Bellevue | Alt Carried Forward concurrence | 22276; 22283 | 5061-5; 3773-1 | 12/12/2012 | 1/7/2013 | 26 | NDOR/address FHWA comments and resubmit |
144th and Blondo | ESA review | 22376a | 5001-15 | 4/19/2013 | 4/22/2013 | 3 | None |
Omaha Cocnrete Repair pkgs. | Bio doc vers 1 | 22498, etc | 5001-18, etc | 04-Aug-11 | 05-Aug-11 | 1 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
I-80/680 Interch Q-L CD Roads, (WB); L-50th, Omaha | SHPO & THPO concur req | 22526; 22527 | 809-65; 809-66 | 9/24/2012 | 10/11/2012 | 17 | NDOR/address FHWA comments and resubmit |
I-80/680 Interch Q-L CD Rds; L-50th | SHPO and THPO concur req - revised | 22526; 22527 | 809-65;809-66 | 10/16/2012 | 10/23/2012 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Douglas County in Omaha | DR 53 | 22539; 22540; 22541; 22542 | 647-122; 752-174; 752-175; L28K-103 | 9/26/2012 | 10/11/2012 | 15 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
88th St/Maple Paillion Creek Br; Q St Br; N Freeway Brgs; Military Ave Papillion Cr Br | SHPO and THPO concur req | 22539; 22540; 22541; 22542 | 647-122;752-174;752-175;L28K-103 | 10/12/2012 | 10/23/2012 | 11 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Macy South | SHPO Concur | 30848B | 754-108 | 13-Sep-10 | 23-Sep-10 | 10 | NDOR/address FHWA comments and resubmit |
Macy South | Tribal Monitoring Agrmt | 30848B | 754-108 | 18-Oct-10 | 05-Nov-10 | 18 | NDOR/address FHWA comments and resubmit |
Macy South | Tribal concur | 30848B | 754-108 | 08-Nov-10 | 09-Nov-10 | 1 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Belden East Bridge | DR 53 | 31342A | 206-109 | 11/9/2011 | 11/14/2011 | 5 | NDOR/address FHWA comments and resubmit |
Belden East Bridge | SHPO concur request | 31342A | 206-109 | 4/6/2012 | 4/25/2012 | 19 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Belden East Bridge | 106 concur req | 31342A | 206-109 | 3/12/2013 | 3/13/2013 | 1 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
In Norfolk | Future bike trail accommodation request memo | 31416A | 353-107 | 5/4/2012 | 5/8/2012 | 4 | NDOR/address FHWA comments and resubmit |
Norfolk Northeast | Cat Ex Reeval | 31416B | 353-108 | 8/13/2012 | 8/20/2012 | 7 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Norfolk Ave, Norfolk | DR 53 | 31417A | 2755-143 | 15-Apr-11 | 21-Apr-11 | 6 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
37th to Norfolk Ave, Norfolk | SHPO concur req | 31417A | 2755-143 | 01-Aug-11 | 04-Aug-11 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Norfolk SE, In Norfolk Norfolk NE | Bio doc version 1 | 31442, 31416A, 31416B | 353-105, 353-107, 353-108 | 10/24/2011 | 10/28/2011 | 4 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Norfolk SE, In Norfolk, Norfolk NE | CE | 31442, 31416A, 31416B | 353-105; 353-107; 353-108 | 11/21/2011 | 11/28/2011 | 7 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Newman Grove N Bridges | DR 53 | 31490a | 453-109 | 05-Nov-10 | 12-Nov-10 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Newman Grove North Bridges | Bio Doc | 31490A | 453-109 | 08-Nov-10 | 12-Nov-10 | 4 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Newman Grove North | SHPO concur req | 31490a | 453-109 | 15-Nov-10 | 15-Nov-10 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Newman Grove N brdgs | 4(f) temp occpcy ltr review | 31490A | 453-109 | 10-Feb-11 | 16-Feb-11 | 6 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Hwy N-45, Newman Grove N brdges | 4(f) concur letter | 31490A | 453-109 | 10-Mar-11 | 10-Mar-11 | 0 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Tilden South; In Tilden & BattleCreek North | SHPO concur req | 31808; 31897 | 453-107; 453-110 | 7/17/2012 | 7/26/2012 | 9 | NDOR/address FHWA comments and resubmit |
Tilden South; In Tilden & Battle Creek North | SHPO concur req - version 2 | 31808; 31897 | 453-107; 453-110 | 7/31/2012 | 8/16/2012 | 16 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Tilden South & In Tilden; Battle Creek North | Bio doc - version 2 | 31808; 31897 | 453-107; 453-110 | 8/8/2012 | 8/17/2012 | 9 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
E Jct N-45 to Madison; In Madison & East | 106 concur req | 31829, 31950 | 325-107; 325-108 | 1/31/2013 | 1/31/2013 | 0 | NDOR/address FHWA comments and resubmit |
E. Jct. N-45 to Madison; In Madison and East | Bio doc version 1 | 31829; 31950 | 325-107; 325-108 | 8/27/2012 | 8/31/2012 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Juct N-52, W and E | DR 53 | 31833A | 915-124 | 04-Apr-11 | 11-Apr-11 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Wayne South & Wayne South Bridge | Bio doc version 1 | 31886, 31893 | 154-117, 154-118 | 1/13/2012 | 1/17/2012 | 4 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Wayne South and Bridge | DR 53 | 31886, 318933189 | 154-117, -118 | 09-Nov-10 | 12-Nov-10 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Wayne South; Wayne South Bridge | SHPO concur req - combine two projects | 31886; 31893 | 154-117; 154-118 | 9/20/2012 | 10/11/2012 | 21 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
US-81 to Leigh | DR 53 | 31899A | 915-122 | 1/24/2013 | 1/28/2013 | 4 | NDOR/address FHWA comments and resubmit |
US81 to leigh | DR53 | 31899A | 915(122) | 1/29/2013 | 1/29/2013 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
US81 to Leigh, Platte and Colfax Counties | SHPO and THPO concur request | 31899A | 915-122 | 5/9/2013 | 5/13/2013 | 4 | None |
Fordyce E & W; Crofton East | SHPO concur req - revised | 31912; 32061 | 126-116; 125-115 | 6/7/2012 | 6/8/2012 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Columbus Viaducts | SHPO concur request | 31924, etc | 6061-8, etc | 30-Nov-10 | 02-Dec-10 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Columbus viaducts | HazMat Memo | 31924, etc | 6065-5, etc | 08-Dec-10 | 09-Dec-10 | 1 | NDOR/address FHWA comments and resubmit |
Columbus Viaducts | Draft EA | 31924, etc | 6065-5, etc | 06-Dec-10 | 10-Dec-10 | 4 | NDOR/address FHWA comments and resubmit |
Norfolk South | Bio doc vers 1 | 31941A | 813-139 | 02-Feb-11 | 02-Feb-11 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Dakota Ave resurv; Regency Prkwy | Bio doc vers 1 | 32081 and A | 5305-10, -11 | 03-Mar-11 | 08-Mar-11 | 5 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Dakota Ave projects | DR 53 | 32081, 32081A | 5305-10 and -11 | 21-Oct-10 | 21-Oct-10 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Dakota Ave, I-129 to REgency Parkway and REgency Parkway to 29th St | public meeting notice review | 32081, 32081A | 5305(10), 5035 (11) | 7/1/2013 | 7/1/2013 | 0 | None |
Dakote Ave 29th to Regency Parkway to I-129 | SHPO concur req | 32081/32081A | 5305-10, -11 | 04-Apr-11 | 07-Apr-11 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Dakota Ave, 29th to Regency Prkwy to I-129 | SHPO concur request | 32081; 32081A | 5305-10; 5305-11 | 6/8/2012 | 6/14/2012 | 6 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Dakota Ave | SHPO concur - revised | 32081; 32081A | 5305-10; 5305-11 | 9/21/2012 | 10/11/2012 | 20 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Dakota Avenue | Cat Ex - revised | 32081A | 5305-10 -11 | 8/14/2013 | 8/19/2013 | 5 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Decatur South; Jct N-12 to Jct N-121 | 106 concur req | 32121; 32123 | 753-117; 814-120 | 12/20/2012 | 12/26/2012 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
US-30 Drain Impr, GI | DR 53 | 40352A | 304-158 | 06-May-11 | 11-May-11 | 5 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
US-30 Drainage Improvements | Bio doc version 1 | 40352A | 304-158 | 12/7/2011 | 12/14/2011 | 7 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
US-30 Drainage Improvements | SHPO concur request | 40352A | 304-158 | 2/7/2012 | 2/14/2012 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
US-30 Drainage Improvements, Grand Island | Cat Ex | 40352A | 304-158 | 5/8/2012 | 5/25/2012 | 17 | NDOR/address FHWA comments and resubmit |
US-30 Drainage Improvements | Cat Ex - revised | 40352A | 304-158 | 6/28/2012 | 7/2/2012 | 4 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Stone School, coord with KPS | Coordination letter | 42103, 42103B | 10-51; 102-116 | 10/19/2012 | 11/8/2012 | 20 | None |
Kearney East Bypass 11th St - 56th St | EA Re-eval Memo | 42103B | 102-116 | 9/19/2013 | 9/20/2013 | 1 | NDOR/address FHWA comments and resubmit |
Kearney East bypass | Re-Eval Memo - 2nd Submittal | 42103B | 102-116 | 9/25/2013 | 10/9/2013 | 14 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Wood River W viaduct | SHPO concur req | 42-32 | 112-114 | 22-Feb-11 | 25-Feb-11 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Glenvil Spur & East Jct US-281 East | Bio doc vers 1 | 42421, 42590 | S18E-106 & 744-110 | 12/6/2011 | 12/14/2011 | 8 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Alexandria South Bridges | SHPO concur request | 42474 & 42533 | 531-103 & 531-104 | 5/21/2012 | 6/14/2012 | 24 | NDOR/address FHWA comments and resubmit |
Alexandria South Bridges | SHPO concur req | 42474, 42533 | 531-103, 531-104 | 8/8/2013 | 8/16/2013 | 8 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Alexandria South | SHPO concur req | 42474, etc | 531-103, -104 | 28-Jan-11 | 31-Jan-11 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Alexandria South Bridges | 106 concur request | 42474; 42533 | 531-103; 531-104 | 12/12/2012 | 1/7/2013 | 26 | NDOR/address FHWA comments and resubmit |
Alexandria S Bridges; Hist Br Alt Eval | 106 concur request | 42474; 42533 | 531-103; 531-104 | 1/28/2013 | 3/8/2013 | 39 | NDOR/address FHWA comments and resubmit |
Alexandria S and Alex S Bridges | SHPO concur req | 42533, 42474 | 531-103 & -104 | 12-Nov-10 | 15-Nov-10 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Alexandria South & South Bridges | Purpose & Need for comments | 42533; 42474 | 531-103; 531-104 | 3/6/2012 | 4/20/2012 | 45 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
E Jct US-281 East - Glenvil Spur | Cat Ex | 42590, 42421 | 744-110, S18E-106 | 2/7/2012 | 2/15/2012 | 8 | NDOR/address FHWA comments and resubmit |
E Jct US-281 East; Glenvil Spur | draft CE | 42590; 42421 | 744-110; S18E-106 | 2/21/2012 | 3/5/2012 | 13 | NDOR/address FHWA comments and resubmit |
E. Jct. US-281 East; Glenvil Spur | Cat Ex | 42590; 42421 | 744-110; S18E-106 | 3/7/2012 | 3/15/2012 | 8 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Platte River BR E of GI; N Loup W Brdge; Kearney S Platte Rvr BR; Rockville S Brdge | DR 53 | 42607; 42715; 42719; 42725 | 345-118; 224-111; 442-109; 682-104 | 8/6/2012 | 8/16/2012 | 10 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Platte Rvr Br E Grand Island; North Loup W Br; Kearney S Platt Rvr Br; Rockville S Br | SHPO concur req | 42607; 42715; 42791; 42725 | 345-118; 224-111; 442-109; 682-104 | 10/15/2012 | 11/9/2012 | 25 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Bio doc vers 1 | Wood Rvr - GI; Platte - Phillips | 42667; 42668 | 806-109, -110 | 28-Feb-11 | 02-Mar-11 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Pioneer Spirit Trail Ph III | SHPO concur req | 42688, 42688A | 1-50, 1-51 | 13-Oct-11 | 14-Oct-11 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Pioneer Spirit Trail | SHPO concur request | 42688, 42688A | 1-50, 1-51 | 11/18/2011 | 11/25/2011 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Pioneer Spirit Trail Phase III | 4(f) | 42688, 42688A | 1-50; 1-51 | 12/7/2011 | 12/15/2011 | 8 | NDOR/address FHWA comments and resubmit |
Pioneer Spirit Trail | Cat Ex | 42688a | 1-50 | 7/19/2012 | 7/26/2012 | 7 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Alexandria S and Alex S Bridges | DR 53 - revised | 442533, 42474 | 531-103 & -104 | 12-Nov-10 | 12-Nov-10 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Dix South & East; Kimball to Dix | SHPO concur req | 51233; 51395 | 301-134; 301-127 | 6/25/2012 | 6/27/2012 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
In Bayard & South; Sioux/Box Butte Co Line to N-2 | DR-53 approvals | 51292, 51373 | 261-160; 714-119 | 6/1/2012 | 6/12/2012 | 11 | NDOR/address FHWA comments and resubmit |
D-5 I-80 Bridge repairs | DR 53 | 51431A | 801-182 | 18-May-11 | 27-May-11 | 9 | NDOR/address FHWA comments and resubmit |
District 5 - I-80 Bridge Repair | Bio doc version 1 | 51431A | 801-182 | 12/13/2011 | 12/20/2011 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
District 5 - I-80 Bridge Repair Part 2 | Bio doc version 2 | 51431A | 801-182 | 1/4/2012 | 1/9/2012 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
D5 I-80 Bridge Repair Part II | Scope Change Memo | 51431A | 801-182 | 9/17/2012 | 10/10/2012 | 23 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Potter-Brownson Crossovers | SHPO concur request | 51451, 51451A | 801-178; 801-184 | 12/8/2011 | 12/9/2011 | 1 | NDOR/address FHWA comments and resubmit |
Potter - Brownson, Potter Brownson crossovers | SHPO concur request - revised | 51451, 51451A | 801-178, 701-184 | 12/19/2011 | 12/21/2011 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Potter - Brownson, Potter - Brownson Crossovers | Bio doc version 1 | 51451, 51451A | 801-178, 801-184 | 12/27/2011 | 1/3/2012 | 7 | NDOR/address FHWA comments and resubmit |
Potter - Brownson & Potter - Brownson Crossovers | Bio doc version 2 | 51451, 51451A | 801-178, 801-184 | 1/3/2012 | 1/3/2012 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
West Sunol - W Lodgepole Sunol Crossovers | 106 suppl concur req | 51459 - 51459a - 51459b | 802-97, 802-99, 802-106 | 2/14/2013 | 2/22/2013 | 8 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Sunol to Lodgepole | CE v4 | 51459, 51459A, & 51459B | 80-2(97), 80-2(99), and 80-2(106) | 5/30/2013 | 5/30/2013 | 0 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Sunol to Chapel and crossovers | CE v1 | 51459, 51459A, 5149B | 802(97), 802(99), 802(106) | 5/6/2013 | 5/6/2013 | 0 | NDOR/address FHWA comments and resubmit |
Sunol-Chappell; Sunol-Chappell Crossovers | SHPO concur req | 51459; 51459A | 802-97; 802-99 | 6/5/2012 | 6/8/2012 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Sunol to Chappell | Cat Ex - V2 | 51459A | 802-99 | 5/8/2013 | 5/21/2013 | 13 | NDOR/address FHWA comments and resubmit |
Chappell East and US-138 East | SHPO concur req | 51462, 51463 | 301-132 -133 | 7/17/2013 | 7/23/2013 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Cottonwood Crk N of Crawford; Crawford - SD line | DR 53 | 51499; 51505 | 714-120; 714-121 | 7/11/2012 | 7/13/2012 | 2 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Cottonwood Creek N of Crawford; Crawford - SD Line | SHPO concur req | 51499; 51505 | 714-120; 714-121 | 7/18/2012 | 7/26/2012 | 8 | NDOR/address FHWA comments and resubmit |
Crawford Creek N of Crawford; Crawford - SD Line | SHPO concur - version 2 | 51499; 51505 | 714-120; 714-121 | 7/27/2012 | 8/17/2012 | 21 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Big Springs SW and Colorado Line NE | SHPO concur request | 61279, 61280 | 1382-107, 1382-108 | 11/18/2011 | 11/25/2011 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Big Springs SW; Colorado Line NE | DR 53 | 61279, 80 | 1382-107, -108 | 06-Oct-11 | 06-Oct-11 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Big Springs SW and Colorado Line NE | SHPO concur req - revised | 61279; 61280 | 1382-107; 1382-108 | 8/15/2012 | 8/30/2012 | 15 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Big Springs SW; Colorado Line NE | Cat Ex - revised | 61279; 61280 | 1382-107; 1382-108 | 10/22/2012 | 11/9/2012 | 18 | NDOR/address FHWA comments and resubmit |
Big Springs SW; Colorado Line NE | Cat Ex - 2nd submittal | 61279; 61280 | 1382-107; 1382-108 | 1/11/2013 | 1/16/2013 | 5 | NDOR/address FHWA comments and resubmit |
Big Springs SW; Colorado Line NE | Cat Ex - 3rd submittal | 61279; 61280 | 1382-107; 1382-108 | 1/28/2013 | 1/31/2013 | 3 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Gothenburg E & W, Cozad - Darr | Bio doc vers 1 revised | 61425, 61426 | 804-137 & -138 | 16-Mar-11 | 16-Mar-11 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
North Platte | Bio Doc | 61449 & 61449A | 832-139 & 832-140 | 30-Sep-11 | 30-Sep-11 | 0 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
S Platte Rvr N & In North Platte | DR 53 | 61449 and -A | 832-139, -140 | 06-Jun-11 | 10-Jun-11 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Stapleton North & Stapleton South | Bio doc version 1 | 61463, 61464 | 833-108, 832-133 | 12/6/2011 | 12/14/2011 | 8 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Arnold West; Arnold East | Combine CE request | 61474; 61477 | 922-109; 923-106 | 9/13/2012 | 10/10/2012 | 27 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
O'Neill West | SHPO concur req | 7045-28 | 7045-28 | 7/10/2012 | 7/16/2012 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Campbell West | CE | 70476a | 4-4(103) | 17-Feb-10 | 22-Feb-10 | 5 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Stamford West | DR 53 | 70589A | 892-109 | 11/21/2011 | 11/25/2011 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Stamford West | Bio doc version 1 | 70589a | 892-109 | 4/20/2012 | 4/23/2012 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Bloomington to Franklin | DR 53 | 70592A | 1364-111 | 3/29/2012 | 4/20/2012 | 22 | NDOR/address FHWA comments and resubmit |
Bloomington-Franklin | DR-53 resubmittal | 70592A | 1364-111 | 4/26/2012 | 5/8/2012 | 12 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Bloomington to Franklin | Archeological testing plan | 70592a | 1364-111 | 7/12/2012 | 7/25/2012 | 13 | NDOR/address FHWA comments and resubmit |
Bloomington to Franklin | Arechaeological testing plan - version 2 | 70592A | 1364-111 | 8/1/2012 | 8/16/2012 | 15 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Bloomington - Franklin | Bio doc version 1 | 70592A | 1364-111 | 10/10/2012 | 11/5/2012 | 26 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Danbury West; Danbury - Lebanon; Lebanon - Jct N-47 | DR 53 | 70727, 70890, 71099 | 892-108; -110; -112 | 1/31/2012 | 2/13/2012 | 13 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Danbury West; Danbury-Lebanon; Lebanon-Jct N-47 | SHPO concur req - version 2 | 70727; 70890; 71099 | 892-108; 892-110; 892-112 | 5/11/2012 | 5/25/2012 | 14 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Danbury West;Danbury-Lebanon;Lebanon-Jct N-47 | SHPO concur request | 70727;70890;71099 | 892-108; 892-110; 892-112 | 4/18/2012 | 4/27/2012 | 9 | NDOR/address FHWA comments and resubmit |
Moorefield E & W; Curtis East | Bio doc - version 1 | 70889; 71102 | 232-121; 232-124 | 6/27/2012 | 7/2/2012 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Moorefield East and West; Curtis East | Cat Ex | 70889; 71102 | 232-121; 232-124 | 10/15/2012 | 11/8/2012 | 24 | NDOR/address FHWA comments and resubmit |
Curtis East; Moorefield E & W | CE - v3 | 70889; 71102 | 232-121; 232-124 | 12/7/2012 | 12/7/2012 | 0 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Curtis East; Moorefield E & W | CE - batched | 71102; 70889 | 232-124; 232-121 | 12/6/2012 | 12/6/2012 | 0 | NDOR/address FHWA comments and resubmit |
Elwood - Smithfield; Farnam - Jct. N-21 | DR 53 | 71122; 71125 | 233-108; 233-110 | 10/12/2012 | 11/5/2012 | 24 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
In Bassett and North | DR 53 | 80684A | 74-114 | 13-Jun-11 | 16-Jun-11 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
In Bassett & North | SHPO concur req | 80684A | 74-114 | 02-Sep-11 | 07-Sep-11 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
In Bassett and North | SHPO concur req | 80684A | S16B-103 | 4/30/2013 | 5/2/2013 | 2 | NDOR/address FHWA comments and resubmit |
In Basett and North | 4(f) concur request | 80684A | 74-114 | 6/6/2013 | 6/10/2013 | 4 | NDOR/address FHWA comments and resubmit |
In Bassett and North | SHPO concur req | 80684A | 74-114 | 7/16/2013 | 7/22/2013 | 6 | NDOR/address FHWA comments and resubmit |
In Bassett and North - Cowboy Trail | Section 4(f) - revised | 80684A | 74-114 | 7/17/2013 | 7/30/2013 | 13 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
In Bassett and North | Bio doc - V1 | 80684A | 74-114 | 8/6/2013 | 8/16/2013 | 10 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
In Bassett & North | SHPO concur req | 80684A | 74-114 | 9/18/2013 | 9/20/2013 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Temporary Emergency Repair Projects | DR 53 | 80909T | ER 1833-117T | 12/20/2011 | 12/22/2011 | 2 | None |
Atkinson - Bush Creek, Atkinson North | DR 53 | 80932, 80926 | 114-113 -114 | 3/5/2013 | 3/6/2013 | 1 | NDOR/address FHWA comments and resubmit |
South Platte River Bridges in North Platte | Section 4(f) de minimis | 832-137 | 832-137 | 9/19/2013 | 9/20/2013 | 1 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
ER 2010 Relief Projects | DR 53 -batched multiple projects | ER | ER | 01-Jul-11 | 08-Jul-11 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
ER 2010 Relief Projects | DR 53 -batched multiple projects | ER | ER | 01-Jul-11 | 08-Jul-11 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
ER 2010 Relief Projects | SHPO Concur Req - batched multiple projects | ER | ER | 07-Jul-11 | 11-Jul-11 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
ER 2010 Relief Projects | SHPO Concur Req - batched multiple projects | ER | ER | 07-Jul-11 | 11-Jul-11 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
2010 ER Temp Repairs | Bio doc - batched multiple projects | ER | ER 2010 | 07-Oct-11 | 07-Oct-11 | 0 | NDOR/address FHWA comments and resubmit |
2010 ER Temp Repairs | Bio doc - batched multiple projects | ER | ER 2010 | 07-Oct-11 | 07-Oct-11 | 0 | NDOR/address FHWA comments and resubmit |
ER 2010 Temp repairs | batched bio doc for all 2010 temp repairs, ver 2 | ER | ER2010 | 11-Oct-11 | 11-Oct-11 | 0 | awaiting submittal of NEPA memo from NDOR ( a quick paragraph summary of their "unusual circumstance" review) |
ER 2010 Temp repairs | batched bio doc for all 2010 temp repairs, ver 2 | ER | ER2010 | 11-Oct-11 | 11-Oct-11 | 0 | awaiting submittal of NEPA memo from NDOR ( a quick paragraph summary of their "unusual circumstance" review) |
Wolff Trail Renovation, Lincoln | CE | RTP | RTP2010-007 | 06-Dec-10 | 16-Dec-10 | 10 | NEPA document approved, NGPC to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Oak Park Trail | CE | RTP | RTP2010-003 | 06-Dec-10 | 16-Dec-10 | 10 | NEPA document approved, NGPC to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Wolff Trail Renovation, Lincoln | CE | RTP | RTP2010-007 | 06-Dec-10 | 16-Dec-10 | 10 | NEPA document approved, NGPC to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Oak Park Trail | CE | RTP | RTP2010-003 | 06-Dec-10 | 16-Dec-10 | 10 | NEPA document approved, NGPC to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Bison Bridge Replacement | SHPO MOA Comments | RTP | RTP2011-005 | 15-Feb-11 | 28-Feb-11 | 13 | NGPC/address FHWA comments and resubmit |
Bison Bridge Replacement | SHPO MOA Comments | RTP | RTP2011-005 | 15-Feb-11 | 28-Feb-11 | 13 | NGPC/address FHWA comments and resubmit |
S Park Trl, Schuyler, Cole Prk Trl, Aurora | State T&E review | RTP | RTP2010-002, 006 | 28-Feb-11 | 07-Mar-11 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
S Park Trl, Schuyler, Cole Prk Trl, Aurora | State T&E review | RTP | RTP2010-002, 006 | 28-Feb-11 | 07-Mar-11 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NGPC review/approve the NEPA document. 2) NGPC submit NEPA to FHWA |
Deshler Park Trail | NEPA Compliance | RTP | RTP2011-003 | 26-Apr-11 | 12-May-11 | 16 | NGPC/address FHWA comments and resubmit |
Deshler Park Trail | NEPA Compliance | RTP | RTP2011-003 | 26-Apr-11 | 12-May-11 | 16 | NGPC/address FHWA comments and resubmit |
Cowboy Trail - RTP | NEPA compl docs | RTP | RTP2011-4 | 06-Jun-11 | 10-Jun-11 | 4 | NEPA document approved, NGPC to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Cowboy Trail - RTP | NEPA compl docs | RTP | RTP2011-4 | 06-Jun-11 | 10-Jun-11 | 4 | NEPA document approved, NGPC to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Motocross Track, Lincoln | Archeological Report | RTP | RTP2009-006 | 25-Jul-11 | 09-Aug-11 | 15 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Motocross Track, Lincoln | Archeological Report | RTP | RTP2009-006 | 25-Jul-11 | 09-Aug-11 | 15 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Streeter Park Trl, Aurora | NEPA compliance | RTP | RTP2010-004 | 16-Aug-11 | 07-Sep-11 | 22 | NEPA document approved, NGPC to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Streeter Park Trl, Aurora | NEPA compliance | RTP | RTP2010-004 | 16-Aug-11 | 07-Sep-11 | 22 | NEPA document approved, NGPC to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Hebron Rock Island Trail | NEPA compliance | RTP | RTP2010-005 | 19-Sep-11 | 20-Sep-11 | 1 | NEPA document approved, NGPC to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Hebron Rock Island Trail | NEPA compliance | RTP | RTP2010-005 | 19-Sep-11 | 20-Sep-11 | 1 | NEPA document approved, NGPC to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
RTP Motocross parking lot report | Sect 106 final report | RTP | RTP2009-006 | 05-Oct-11 | 12-Oct-11 | 7 | NGPC/address FHWA comments and resubmit |
RTP Motocross parking lot report | Sect 106 final report | RTP | RTP2009-006 | 05-Oct-11 | 12-Oct-11 | 7 | NGPC/address FHWA comments and resubmit |
RTP Motocross parking lot report | Sect 106 final report2 | RTP | RTP2009-006 | 14-Oct-11 | 17-Oct-11 | 3 | NGPC/address FHWA comments and resubmit |
Bison Bridge Replacement | NGP Bridge Recordation Plan | RTP2011-005 | 12/1/2011 | 12/13/2011 | 12 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA | |
ER 2008-2010 Perm Repair Projects | SHPO concur request | 1/23/2012 | 1/25/2012 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA | ||
Louisville to Springfield | CE V2 | 22456 | 502(134) | 10/23/2014 | 10/23/2014 | 0 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
US 81 to Leigh; N91&N32 | CE | 31899A; 32060 | 915(122); 573(108) | 9/11/2014 | 10/23/2014 | 42 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Louisville to Springfield | 4(f) temp occupancy | 22456 | 502(134) | 10/23/2014 | 10/23/2014 | 0 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
I-80 North | DR-53 | 51277 | 272-104 | 10/10/2014 | 10/20/2014 | 10 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Winside South & North | DR-53 | 32134 | 354-124 | 10/7/2014 | 10/20/2014 | 13 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Comstock Spur Bridge | DR-53 | 61582 | S21C-103 | 10/7/2014 | 10/20/2014 | 13 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
McCook - Indianola | DR-53 | 70879 | 62-120 | 10/7/2014 | 10/20/2014 | 13 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Whitman East | DR-53 | 61008 | 22-112 | 10/7/2014 | 10/20/2014 | 13 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Brule-Ogallala | DR-53 | 61565 | 803-152 | 10/8/2014 | 10/20/2014 | 12 | NDOR/address FHWA comments and resubmit |
Omaha McMillan Magnet School SRTS | SHPO/THPO/CLG concur req | 22321 | 28-93 | 10/9/2014 | 10/20/2014 | 11 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Worms Rd to 5 miles E of Archer Corner | SHPO concur req | 42400 | 925-108 | 10/9/2014 | 10/20/2014 | 11 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Logan Creek Trail Phase II | Cat Ex | 32178 | 26-14 | 10/10/2014 | 10/20/2014 | 10 | None |
Elwood South | DR-53 | 71089 | 2831-116 | 10/10/2014 | 10/20/2014 | 10 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Center - Bloomfield | DR-53 | 31892 | 845-109 | 10/10/2014 | 10/20/2014 | 10 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Bridgeport Viaduct | Alt Analysis Memo | 51299 | 261-161 | 9/30/2014 | 10/20/2014 | 20 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Smithfield - Bertrand | DR-53 | 71123 | 233-109 | 10/10/2014 | 10/20/2014 | 10 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
N Jct N-12 - South Dakota Line | DR-53 | 80875 | 1834-114 | 10/14/2014 | 10/20/2014 | 6 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
North 66th & Fremont | SHPO and CLG concur req | 13227 | 5253-1 | 10/14/2014 | 10/20/2014 | 6 | None |
St Edward to Albion | Cat Ex - 2nd submittal | 31921 | 393-105 | 10/14/2014 | 10/20/2014 | 6 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Lincoln - Syracuse | THPO concur req | 13263 | 26-123 | 10/14/2014 | 10/20/2014 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Sutherland - Hershey | DR-53 | 61490 | 803-144 | 10/15/2014 | 10/20/2014 | 5 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Red Cloud | Cat Ex - 2nd submittal | 42569 | 1364-113 | 10/15/2014 | 10/20/2014 | 5 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Auburn West | DR-53 | 13223 | 1367-125 | 10/15/2014 | 10/20/2014 | 5 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Cairo West | SHPO concur req | 42592 | 24-110 | 10/15/2014 | 10/20/2014 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Kearney West | SHPO concur req | 42560 | 304-154 | 10/15/2014 | 10/20/2014 | 5 | NDOR/address FHWA comments and resubmit |
108th St, Madison to Q | SHPO, THPO, CLG concur req | 22237 | 5011-9 | 10/15/2014 | 10/20/2014 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
N-62 North | DR-53 | 13101 | 671-119 | 10/7/2014 | 10/15/2014 | 8 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Red Cloud West | DR-53 | 42617 | 1364-115 | 9/24/2014 | 10/15/2014 | 21 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Burwell - Ericson | DR-53 | 80972 | 914-109 | 9/26/2014 | 10/15/2014 | 19 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Beatrice Hannibal Park Trail | Cat Ex | 13212 | 34-42 | 9/22/2014 | 10/15/2014 | 23 | None |
Spencer Southeast | DR-53 | 80950 | 2814-122 | 10/7/2014 | 10/15/2014 | 8 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Monroe Southwest | DR-53 | 31883 | 7071-9 | 10/7/2014 | 10/15/2014 | 8 | NDOR/address FHWA comments and resubmit |
Albion to N-45 | Cat Ex - revised | 31517 | 915-114 | 10/7/2014 | 10/15/2014 | 8 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Bradshaw Southeast | Re-eval Memo | 41634 | 7093-23 | 10/9/2014 | 10/15/2014 | 6 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Bellwood East and West | Cat Ex | 13165 | 646-104 | 9/29/2014 | 10/14/2014 | 15 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Holt/Garfield County Line South | Cat Ex | 80938 | 113-122 | 9/29/2014 | 10/14/2014 | 15 | None |
70th St, Van Dorn to Eastborough | Cat Ex | 13243 | 5247-13 | 9/22/2014 | 10/14/2014 | 22 | NDOR/address FHWA comments and resubmit |
St Paul North | Cat Ex | 42567 | 2812-126 | 10/10/2014 | 10/14/2014 | 4 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Holt/Garfield County Line South | Cat Ex inquiry | 80938 | 113-122 | 10/14/2014 | 10/14/2014 | 0 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Broken Bow 5th Ave connector trail | 106 letter V2 | 61548 | 21(27) | 10/8/2014 | 10/8/2014 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Gretna East Re-eval | Plan change review | 21543 | 3707-119 | 3/14/2014 | 10/6/2014 | 206 | None |
Albion to N-45 | Submittal 2 - CE comments | 31517 | 915-114 | 10/1/2014 | 10/6/2014 | 5 | NDOR/address FHWA comments and resubmit |
Scottsbluff Valley Pathway North | Cat Ex | 51512 | 79-42 | 9/22/2014 | 10/6/2014 | 14 | NDOR/address FHWA comments and resubmit |
Atkinson - Brush Creek | Bio Doc | 80932 | 114-113 | 9/10/2014 | 10/6/2014 | 26 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
St Edward to Albion | Cat Ex | 31921 | 393-105 | 9/12/2014 | 10/6/2014 | 24 | NDOR/address FHWA comments and resubmit |
Red Cloud East | Cat Ex | 42569 | 1364-113 | 9/15/2014 | 10/1/2014 | 16 | NDOR/address FHWA comments and resubmit |
Statewide Guardrails D-3, D-4 | SHPO and 3 THPO concur req | 00864 | STWD-111 | 9/16/2014 | 10/1/2014 | 15 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Snake River North & South | SHPO concur req | 80640 | 614-107 | 9/23/2014 | 10/1/2014 | 8 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Wynot East & West | Testing Plan for SHPO | 32131 | 126-117 | 9/9/2014 | 10/1/2014 | 22 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Callaway West | SHPO concur req | 61556 | 403-107 | 9/23/2014 | 10/1/2014 | 8 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
108th Street Widening - Q St - Madison | P&N Version 2 | 22237 | 5011-9 | 9/11/2014 | 9/30/2014 | 19 | NDOR/address FHWA comments and resubmit |
Louisville to Springfield | Cat Ex | 22456 | 502-134 | 9/11/2014 | 9/30/2014 | 19 | NDOR/address FHWA comments and resubmit |
Broken Bow 5th Ave | SHPO concur req | 61548 | 21-27 | 9/12/2014 | 9/30/2014 | 18 | NDOR/address FHWA comments and resubmit |
Tract 20 UPRR 12th Ave Viaduct | Re-Eval Memo | 31925 | 6061-8 | 9/19/2014 | 9/30/2014 | 11 | None |
10th St at Salt Creek Bridge | SHPO and CLG concur req | 13233 | 5215-3 | 9/29/2014 | 9/30/2014 | 1 | NDOR/address FHWA comments and resubmit |
Silver to Furnas, Ashland | Cat Ex | 13084 | 666-107 | 9/10/2014 | 9/22/2014 | 12 | NDOR/address FHWA comments and resubmit |
Jct. N-12 to N-121 | SOW change concur req | 32123 | 814-120 | 9/17/2014 | 9/22/2014 | 5 | None |
N-27 - South Platte River and Crossovers | Bio doc | 51444 | 802-95 | 9/3/2014 | 9/18/2014 | 15 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Ord North | Bio doc | 41914 | 704-106 | 8/29/2014 | 9/18/2014 | 20 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Creighton - Center | Bio doc | 31884 | 135-101 | 8/21/2014 | 9/18/2014 | 28 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Wyoming Line to Bushnell Interchange (EB) | DR-53 | 51551 | 801-193 | 9/10/2014 | 9/18/2014 | 8 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Ithaca - Ashland | Cat Ex | 12831 | 666-104 | 9/9/2014 | 9/18/2014 | 9 | NDOR/address FHWA comments and resubmit |
Bancroft - Dewey, Omaha | SHPO & THPO concur req | 22528 | 4809-104 | 9/3/2014 | 9/17/2014 | 14 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Atkinson North | SHPO concur req | 80936 | 114-114 | 9/11/2014 | 9/17/2014 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Table Rock SE | Cat Ex | 12853 | 7067-22 | 9/5/2014 | 9/17/2014 | 12 | NDOR/address FHWA comments and resubmit |
Wood River North & South | SHPO concur req | 42570 | 112-117 | 8/28/2014 | 9/17/2014 | 20 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Fairbury Southeast | SHPO concur req | 13290 | 7048-17 | 8/27/2014 | 9/17/2014 | 21 | None |
Wood River - Grand Island | Cat Ex | 42399 | 304-149 | 8/26/2014 | 9/17/2014 | 22 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Ord North | SHPO concur req | 41914 | 704-106 | 8/29/2014 | 9/17/2014 | 19 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Albion to N-45; Lindsay EW | Cat Ex | 31517 | 915-114 | 8/21/2014 | 9/17/2014 | 27 | NDOR/address FHWA comments and resubmit |
Naper East | SHPO concur req | 80937 | 124-108 | 8/19/2014 | 9/15/2014 | 27 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Brewster West | DR-53 | 61512 | 913-110 | 8/15/2014 | 9/15/2014 | 31 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Scottsbluff West Viaduct | PN and 404 Merge ltr | 51250 | 921-121 | 9/8/2014 | 9/9/2014 | 1 | None |
Scottsbluff West Viaduct | 404 Merge participation | 51250 | 921-121 | 8/11/2014 | 9/5/2014 | 25 | NDOR/address FHWA comments and resubmit |
Scottsbluff West Viaduct | Purpose & Need - v2 | 51250 | 921-121 | 8/21/2014 | 9/5/2014 | 15 | NDOR/address FHWA comments and resubmit |
Heartland Express | SHPO suppl concur req | 51432 | 3853-118 | 8/20/2014 | 8/21/2014 | 1 | None |
42nd and Q St Bridge | Final Design Commitments review | 22279 | 5057-9 | 8/18/2014 | 8/18/2014 | 0 | None |
N. Jct. N-14 to Genoa | Cat Ex | 42600 | 225-116 | 8/13/2014 | 8/15/2014 | 2 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Wyoming Line - Bushnell | SHPO concur req | 51518 | 801-186 | 8/13/2014 | 8/15/2014 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Alma South Bridge | SHPO concur req | 71180 | 1831-117 | 8/13/2014 | 8/15/2014 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Wayne West | Public Involve review | 31920 | 354-121 | 8/4/2014 | 8/15/2014 | 11 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Scottsbluff West Viaduct | Purpose & Need | 51250 | 921-121 | 7/30/2014 | 8/15/2014 | 16 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
North Loup to Ord | DR-53 revised | 42089 | 113-116 | 8/12/2014 | 8/15/2014 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Wahoo Elementary SRTS | DR-53 | 13291 | 78-33 | 8/13/2014 | 8/14/2014 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Bellwood East and West | SHPO concur req | 13165 | 646-104 | 8/12/2014 | 8/13/2014 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Lincoln - Syracuse | DR-53 | 13263 | 26-123 | 8/12/2014 | 8/13/2014 | 1 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Jct N-105 North | DR-53 | 13104 | 671-122 | 8/12/2014 | 8/13/2014 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
D5 Sidemount DMS | SHPO concur req | 51477 | ITSN-37 | 8/12/2014 | 8/13/2014 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
S Sioux City Connecting Schools | 4(f) De Minimis | 32169 | 22-32 | 8/11/2014 | 8/12/2014 | 1 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Dix South and East | Cat Ex | 51233 | 301-134 | 8/11/2014 | 8/12/2014 | 1 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Fairbury Southeast | DR-53 | 13290 | 7048-17 | 8/11/2014 | 8/12/2014 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
McMillan SRTS NEPA, Omaha | Public involve review | 22321 | 28-93 | 7/9/2014 | 8/12/2014 | 34 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Filley North | scope change reeval | 3285(5) | 8/11/2014 | 8/11/2014 | 0 | None | |
Bancroft - Dewey (Resurf) | DR-53 | 22528 | 4809-104 | 8/7/2014 | 8/11/2014 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Murray - US-34 & 75 | DR-53 - V2 | 22467A | 17-107 | 8/6/2014 | 8/11/2014 | 5 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Scottsbluff West Viaduct | Public Involve Plan | 51250 | 921-121 | 8/5/2014 | 8/11/2014 | 6 | NDOR/address FHWA comments and resubmit |
Westerville East | DR-53 | 61515 | 703-108 | 8/5/2014 | 8/11/2014 | 6 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Wyoming Line - Bushnell | Cat Ex | 51461 | 301-131 | 8/4/2014 | 8/7/2014 | 3 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
1st St - 6th St, North Platte | De Minimis | 61359 | 832-128 | 7/30/2014 | 8/7/2014 | 8 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
19th - Blackburn to Delaware | Reevaluation | 42696 | 6312-2 | 7/28/2014 | 8/6/2014 | 9 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
US-77 - Platte River | Cat Ex | 13052 | 646-105 | 7/28/2014 | 8/6/2014 | 9 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
David City North | DR-53 | 13250 | 152-124 | 7/30/2014 | 8/6/2014 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Valentine Southeast | DR-53 | 80957 | 202-141 | 8/4/2014 | 8/6/2014 | 2 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Niobrara River South | Cat Ex | 80690 | 1834-109 | 7/30/2014 | 8/6/2014 | 7 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Burton East and West | DR-53 | 80603 | 123-105 | 8/5/2014 | 8/6/2014 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Murray - US-34 and 75 | DR-53 | 22467A | 17-107 | 8/4/2014 | 8/6/2014 | 2 | NDOR/address FHWA comments and resubmit |
Furnas St - Silver St, Ashland | 4(f) de minimis | 13084 | 666-107 | 7/23/2014 | 8/4/2014 | 12 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
70th St Pavement Repair | Section 4(f) Exception - revised | 13243 | 5247-13 | 7/22/2014 | 8/4/2014 | 13 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Superior Public Schools SRTS | Cat Ex | 42718 | 65-24 | 7/28/2014 | 8/1/2014 | 4 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Farnam West; Farnam to Jct N-21; Jct N-21 to Elwood; Elwood to Smithfield | Cat Ex | 71124 | 232-126 | 7/16/2014 | 7/30/2014 | 14 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Lindsay East & West | SHPO and THPO suppl eval req | 31518 | 915-115 | 7/28/2014 | 7/30/2014 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
37th to Norfolk Ave, Norfolk | SHPO supplemental eval | 31417a | 2755-143 | 7/28/2014 | 7/30/2014 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
70th St, VanDorn to Eastborough | SHPO and CLG concur req | 13243 | 5247-13 | 7/24/2014 | 7/30/2014 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
South Sioux City Atokad Trail | DR-53 | 32251 | 22-34 | 7/23/2014 | 7/30/2014 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
In Mullen | Reevaluation | 61481A | 22-119 | 7/14/2014 | 7/30/2014 | 16 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Weeping Water SRTS | DR-53 | 13289 | 13-45 | 7/22/2014 | 7/29/2014 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
42nd and C Bridges, Omaha | DR-53 | 22627 | 5057-12 | 7/22/2014 | 7/29/2014 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Ithaca - Ashland | Bio doc - Re-Eval | 12831 | 666-104 | 6/23/2014 | 7/23/2014 | 30 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Creighton - Center | SHPO concur req | 31884 | 135-101 | 7/3/2014 | 7/22/2014 | 19 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
19th St, York | SHPO concur req | 42696 | 6312-2 | 6/25/2014 | 7/22/2014 | 27 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
72nd & D St Bridge | DR-53 | 22628 | 5037-18 | 7/21/2014 | 7/22/2014 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Longs Creek | NEPA documentation | RTP 2014-1 | 7/18/2014 | 7/21/2014 | 3 | None | |
70th St Pavement Repair | 4(f) Except Req | 13243 | 5247-13 | 6/25/2014 | 7/18/2014 | 23 | NDOR/address FHWA comments and resubmit |
Hwy US-385 - Jct L62A-US 385 to Alliance | draft EA | 51432 | 3853-118 | 6/18/2014 | 7/18/2014 | 30 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Kimball Underpass Renovation | ACHP review req | 51242 | 712-110 | 5/8/2014 | 7/17/2014 | 70 | None |
24th Street Road Diet, Omaha | SHPO, THPO, CLG concur req | 22506 | 5083-7 | 6/19/2014 | 7/17/2014 | 28 | None |
108th Street Widening - Q St to Madison | Purpose and Need | 22237 | 5011-9 | 7/11/2014 | 7/17/2014 | 6 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
156th St Improvements, Omaha | Draft EA - July 2014 | 22376 | 5127-1 | 7/17/2014 | 7/16/2014 | -1 | NDOR/prepare for public outreach (if document is a DEA, the outreach is a hearing) |
Kimball Underpass | Section 106 doc | 51242 | 712-110 | 6/30/2014 | 7/16/2014 | 16 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
156Th St Improvements Pepperwood Dr to Corby St | DEA V3 | 22376 | 5127(1) | 7/10/2014 | 7/16/2014 | 6 | NDOR/prepare for public outreach (if document is a DEA, the outreach is a hearing) |
Kimball Underpass | Sec 106 consulting party letters | 51242 | 712-110 | 6/24/2014 | 7/11/2014 | 17 | NDOR/address FHWA comments and resubmit |
Lincoln South Beltway | Purpose and Need | 12578D | 26-120 | 6/16/2014 | 7/11/2014 | 25 | NDOR/address FHWA comments and resubmit |
Wyuka Stables Rehabilitation | Re-eval memo | 13063 | 55-170 | 7/3/2014 | 7/10/2014 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Ithaca to Ashland | SHPO suppl req | 12831 | 666-104 | 7/7/2014 | 7/8/2014 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Holt County Line South | SHPO concur req | 80938 | 113-122 | 6/20/2014 | 7/8/2014 | 18 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Chadron State Park South | Cat Ex | 51400 | 3854-135 | 6/19/2014 | 7/8/2014 | 19 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Dynamic Messaging Signs | SHPO and THPO concur req | 22489 | ITSN-33 | 6/30/2014 | 7/7/2014 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Walthill East | Cat Ex- 2nd submittal | 31511 | 947-105 | 6/19/2014 | 6/26/2014 | 7 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Q, from 26th to 27th | Cat Ex review | 22325 | 5026-11 | 6/17/2014 | 6/26/2014 | 9 | None |
Wyoming Line - Bushnell | DR-53 | 51518 | 801-186 | 6/24/2014 | 6/26/2014 | 2 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Potter Link Bridge | Cat Ex | 51495 | L17B-109 | 6/18/2014 | 6/26/2014 | 8 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Greenwood NE | Cat Ex - revised | 12658 | 7013-10 | 6/18/2014 | 6/24/2014 | 6 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Wyuka Stables Rehabilitation | SHPO supplemental | 13063 | 55-170 | 6/17/2014 | 6/24/2014 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Red Cloud South Bridge | DR-53 | 42717 | 2811-116 | 6/17/2014 | 6/24/2014 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Wayne West | SHPO concur req | 31920 | 354-121 | 6/23/2014 | 6/24/2014 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Niobrara River South | DR-53 | 51508 | 874-118 | 6/19/2014 | 6/23/2014 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Platte River East Structures | DR-53 | 22561 | 927-107 | 6/19/2014 | 6/23/2014 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Gothenburg - Cozad | DR-53 | 61478 | 303-117 | 6/20/2014 | 6/23/2014 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Karol Kay Blvd | Alt #3 alignment review | 13161 | 6763-1 | 6/5/2014 | 6/19/2014 | 14 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
N-13 to Osmond | Cat Ex | 31917 | 1214-111 | 6/5/2014 | 6/19/2014 | 14 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Develop of Model of ABB Occur in Plains Ecoregion of NE | Research T&E review - ABB | M031 | 6/16/2014 | 6/19/2014 | 3 | None | |
Species Distribution Model for Swift Fox in NE | Research T&E Review - Swift Fox | M033 | 6/16/2014 | 6/19/2014 | 3 | None | |
Omaha Resurfacing | SHPO, THPO concur req | 22605 | 5037-17 | 6/16/2014 | 6/18/2014 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Bruno Spur Bridges | Re-Eval | 13197 | S12B-106 | 6/12/2014 | 6/18/2014 | 6 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
N Jct N-14 to Genoa | SHPO, THPO concur request | 42600 | 225-116 | 6/12/2014 | 6/17/2014 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Alma South Bridge | DR-53 | 71180 | 1831-117 | 6/6/2014 | 6/11/2014 | 5 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
1st - 6th St, North Platte | SHPO addendum - historic property eval | 61359 | 832-128 | 6/6/2014 | 6/11/2014 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Stella West Bridges | DR-53 | 13098A | 627-108 | 6/9/2014 | 6/11/2014 | 2 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Snake River North & South | DR-53 | 80640 | 614-107 | 6/9/2014 | 6/11/2014 | 2 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Chadron West | SHPO concur req | 51406 | 201-140 | 6/9/2014 | 6/11/2014 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Talmage North Bridges | DR-53 | 12874A | 672-109 | 6/10/2014 | 6/11/2014 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Western Douglas County Trail Ph 1 & 2 | 4(f) De Min revised | 22227 | 28-87 | 6/5/2014 | 6/9/2014 | 4 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
South Bend - N-50 | DR-53 | 13100 | 667-116 | 6/5/2014 | 6/9/2014 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Lincoln South Beltway | draft Purpose and Need | 12578D | 26-120 | 6/2/2014 | 6/9/2014 | 7 | None |
Dev of a NE Culvert Aquatic Org Passage Screen Tool | Draft Research Report - review | M334 | 5/8/2014 | 6/6/2014 | 29 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. | |
Trap and Relocate Effects, Overwinter and Impact of Vehicles on ABB | Research Report - review | M330 | 5/8/2014 | 6/6/2014 | 29 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. | |
Valley DC West Sidewalk Improvement | Cat Ex | 22411 | 28-97 | 6/2/2014 | 6/6/2014 | 4 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
1st St, Luther Road to Johnson Road in Fremont | Cat Ex | 22503 | 27-62 | 5/9/2014 | 6/6/2014 | 28 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Ansley - Mason City | DR-53 | 61560 | 23-121 | 6/5/2014 | 6/6/2014 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
70th - Van Dorn to Eastborough Pavement Repair | Variance Request | 13243 | 5247-13 | 6/5/2014 | 6/6/2014 | 1 | NDOR/address FHWA comments and resubmit |
Tracy Creek | Certification Request | 6/5/2014 | 6/6/2014 | 1 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. | ||
Hamlet - Palisade | Cat Ex | 71126 | 62-129 | 6/5/2014 | 6/6/2014 | 1 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Kimball North | SHPO concur req | 51466 | 712-113 | 6/3/2014 | 6/5/2014 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Jct N-91 North | DR-53 | 32132 | 153-115 | 6/4/2014 | 6/5/2014 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Ragan - Jct N-44 | DR-53 | 71097 | 43-107 | 6/3/2014 | 6/4/2014 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Walthill East | Cat Ex | 31511 | 947-105 | 6/2/2014 | 6/3/2014 | 1 | NDOR/address FHWA comments and resubmit |
Almeria East & West | DR-53 | 80898 | 913-109 | 5/29/2014 | 6/3/2014 | 5 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
SE Jct US-275 - Omaha | DR-53 | 22533 | 647-121 | 5/29/2014 | 6/3/2014 | 5 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
WDCT | Scope Change review | 22227 | 28-87 | 5/12/2014 | 6/3/2014 | 22 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
US-77 - Platte River | Bio doc | 13052 | 646-105 | 5/22/2014 | 5/29/2014 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
St Edward - Albion | SHPO concur req | 31921 | 393-105 | 5/12/2014 | 5/29/2014 | 17 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Waterloo Viaduct Friction Course | THPO concur req | 22613 | 2757-197 | 5/27/2014 | 5/29/2014 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
1st St - 6th St, North Platte | CLG concur req | 61359 | 832-128 | 4/28/2014 | 5/28/2014 | 30 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Beatrice Hannibal Park Trail | 4(f) Net Benefits | 13212 | 34-42 | 5/7/2014 | 5/28/2014 | 21 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
N-9 - US-77 | SHPO concur req - Arch Test Plan | 32-49 | 516-105 | 5/21/2014 | 5/27/2014 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Schuyler Trail Program | Cat Ex | RTP 2013-2 | 5/21/2014 | 5/27/2014 | 6 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required | |
Dwight to N-79 | SHPO concur req | 13018 | 666-105 | 5/22/2014 | 5/27/2014 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Pleasant Dale North and South | Arch Testing Plan SHPO concur req | 13142 | 1032-103 | 5/22/2014 | 5/27/2014 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Louisville - Springfield | Bio doc | 22456 | 502-134 | 5/20/2014 | 5/27/2014 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
US-77, 5th - 10th St., Fremont | Cat Ex - V2 | 22434 | 773-129 | 5/2/2014 | 5/21/2014 | 19 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Westbrook SRTS Infrastructure | Public Involvement review | 22410 | 28-96 | 5/8/2014 | 5/21/2014 | 13 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Sterling East | Cat Ex | 13045 | 417-102 | 5/9/2014 | 5/21/2014 | 12 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Big Nemaha River Bridge in Humboldt | DR-53 | 13190 | 1051-107 | 5/9/2014 | 5/21/2014 | 12 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
D-5 Roadside DMS | SHPO Supplemental concur req | 51515 | ITSN-13 | 5/12/2014 | 5/21/2014 | 9 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
D1 and D5 I-80 Auto Gates; D6 Auto Ramp Gates | SHPO concur req | 13151 | ITSN-41 | 5/21/2014 | 5/21/2014 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Ord South | DR-53 | 42575 | 704-109 | 5/13/2014 | 5/21/2014 | 8 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Daykin West Bridge | DR-53 | 42748 | 45-105 | 5/9/2014 | 5/20/2014 | 11 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
North Downtown Riverfront Ped Connector | SHPO, THPO, CLG concur req | 22571 | 28-114 | 5/8/2014 | 5/20/2014 | 12 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
S Sioux City Trail | SHPO Supplemental concur req | 32169 | 22-32 | 5/12/2014 | 5/20/2014 | 8 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
BNSF-Middle Creek, Lincoln | Cat Ex - re-eval | 13089 | 772-161 | 5/14/2014 | 5/15/2014 | 1 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Tecumseh Historic Square Preservation | SHPO concur req | 13214 | 49-46 | 5/6/2014 | 5/14/2014 | 8 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Kimball North | DR-53 revised | 51466 | 712-113 | 5/1/2014 | 5/14/2014 | 13 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Holbrook East Bridge | DR-53 | 71170 | 63-126 | 5/6/2014 | 5/14/2014 | 8 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Harrisburg Spur South | DR-53 | 51469 | 713-127 | 5/6/2014 | 5/14/2014 | 8 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Blue River Bridge South of Fairbury | DR-53 | 11599 | 86-104 | 5/7/2014 | 5/14/2014 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Fairbury North | DR-53 | 11718 | 151-110 | 5/7/2014 | 5/14/2014 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Jct N-91 North | DR-53 | 32132 | 153-115 | 5/7/2014 | 5/14/2014 | 7 | NDOR/address FHWA comments and resubmit |
Taylor West | DR-53 | 80857 | 913-111 | 5/7/2014 | 5/14/2014 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Waterloo Viaduct Friction Course | DR-53 | 22613 | 2757-197 | 5/9/2014 | 5/14/2014 | 5 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
US-183/County Road 747 in Phelps County | DR-53 | 71157 | 1831-116 | 5/6/2014 | 5/14/2014 | 8 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Schuyler Phase III Trail, Colfax County | NGP review | RTP2013-002 | 5/13/2014 | 5/13/2014 | 0 | NDOR/address FHWA comments and resubmit | |
156th Street Improvements Phase 2 | Draft EA | 22376 | 5127-1 | 5/1/2014 | 5/13/2014 | 12 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Ord North | 4(f) De minimis | 41914 | 704-106 | 5/12/2014 | 5/12/2014 | 0 | NDOR/address FHWA comments and resubmit |
Arapahoe West Bridge | DR-53 | 71171 | 63-127 | 5/6/2014 | 5/8/2014 | 2 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Dwight East Bridges | SHPO concur req | 13018A | 666-108 | 5/5/2014 | 5/8/2014 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Blair Connector Trail | Cat Ex - revised | 22549 | 89-30 | 5/5/2014 | 5/8/2014 | 3 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Blair West | Cat Ex | 22454 | 917-109 | 4/29/2014 | 5/8/2014 | 9 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Gothenberg West | Cat Ex - revised | 61467 | 302-140 | 4/29/2014 | 5/6/2014 | 7 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Syracuse SW | Cat Ex - V2 | 12785 | 7066-43 | 4/24/2014 | 5/6/2014 | 12 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Omaha Signal System - Phase 1 | DR-53 | 22608 | 5023-17 | 4/29/2014 | 5/1/2014 | 2 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Franklin to Webster County Line | Arch Testing review | 71156 | 1364-116 | 4/24/2014 | 4/28/2014 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Jct L62A - US-385 to Alliance | Bio doc - V4 | 51432 | 3853-118 | 4/22/2014 | 4/28/2014 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Kimball North | Kimball North | 51466 | 712-113 | 4/8/2014 | 4/25/2014 | 17 | NDOR/address FHWA comments and resubmit |
Western Douglas County Trail, Ph 1 & 2 | Scope Change | 22227 | 28-87 | 4/8/2014 | 4/25/2014 | 17 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Omaha Bridges | Cat Ex | 22539 | 647-122 | 4/14/2014 | 4/25/2014 | 11 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Arnold East | Reeval review | 61477 | 923-106 | 4/21/2014 | 4/25/2014 | 4 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Bayard to US-385 | DR-53 | 51468 | L62A-101 | 4/23/2014 | 4/25/2014 | 2 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Lexington East Viaduct | SHPO concur req | 61457 | 1705-3 | 3/26/2014 | 4/24/2014 | 29 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
South Omaha Trail Phase II | Interstate Justification Report | 3/21/2014 | 4/24/2014 | 34 | None | ||
Blair Connector Trails | Cat Ex | 22549 | 89-30 | 3/27/2014 | 4/23/2014 | 27 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Box Butte Ave Historic Lighting | Cate Ex - revised | 51453 | 6257-2 | 4/15/2014 | 4/23/2014 | 8 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
US-77, 5th to 10th, Fremont | Cat Ex | 22434 | 773-129 | 3/13/2014 | 4/22/2014 | 40 | NDOR/address FHWA comments and resubmit |
Jct. US-81 and N-91 | DR-53 | 32222 | 814-146 | 4/10/2014 | 4/22/2014 | 12 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
In Bayard and South | Cat Ex | 51292 | 261-160 | 4/10/2014 | 4/22/2014 | 12 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Blair Bypass | DR-53 and DR-530 | 22508 | 3854-1 | 4/11/2014 | 4/21/2014 | 10 | None |
156th Street Phase 2 | Prelim DEA for review | 22376 | 5127-1 | 4/11/2014 | 4/17/2014 | 6 | None |
26th and Q Street Bridge | EJ Memo | 22325 | 5026-11 | 1/3/2014 | 4/16/2014 | 103 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Furnas St to Silver St, Ashland | Public Involve update review | 13084 | 666-107 | 3/13/2014 | 4/14/2014 | 32 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
4th Corso Viaduct, Nebr City | NEPA Determination Memo | 13159 | 6217-4 | 4/8/2014 | 4/11/2014 | 3 | NDOR/address FHWA comments and resubmit |
Characterization of Bridge Deck Runoff | Quarterly report review | M009 | 3/19/2014 | 4/11/2014 | 23 | None | |
Swift Fox Survey along Heartland Highway Cooridor | Quarterly report review | M011 | 3/19/2014 | 4/11/2014 | 23 | None | |
Stormwater Pollution Treatment BMP Discharge Structures | draft final report | M304 | 3/24/2014 | 4/11/2014 | 18 | None | |
Nemaha E Jct US-135 | Cat Ex | 13094 | 671-117 | 3/26/2014 | 4/11/2014 | 16 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Minatare - L62A | DR-53 | 51465 | 261-166 | 4/8/2014 | 4/11/2014 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
South Coddington Ave and West Van Dorn | Cat Ex - revised | 13147 | 5205-1 | 4/7/2014 | 4/11/2014 | 4 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Effects of Compaction and Soil Moisture on ABB | Quarterly Report Review - M010 | M010 | 3/31/2014 | 4/11/2014 | 11 | None | |
Plymouth to Beatrice | DR-53 | 12958 | 46-115 | 4/7/2014 | 4/10/2014 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
12th - 7th Ave, Kearney | DR-53 | 42728 | 304-159 | 4/4/2014 | 4/10/2014 | 6 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Loup City Northwest Bridge | DR-53 | 42749 | 582-112 | 3/27/2014 | 4/8/2014 | 12 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Gothenberg West | Cat Ex | 61467 | 302-140 | 3/20/2014 | 4/8/2014 | 19 | NDOR/address FHWA comments and resubmit |
In Falls City and North | DR-53 | 13208 | 731-118 | 3/27/2014 | 4/8/2014 | 12 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
South Omaha Trail Phase II | SHPO and THPO concur req | 3/18/2014 | 4/7/2014 | 20 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA | ||
Karol Kay Blvd, Bader - East Hillcrest | SHPO concur req | 13161 | 6763-1 | 3/31/2014 | 4/7/2014 | 7 | NDOR/address FHWA comments and resubmit |
North of Genoa | DR-53 | 42609 | L63A-101 | 3/27/2014 | 4/7/2014 | 11 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Deweese Spur North | Dr-53 | 42566 | 141-119 | 3/24/2014 | 4/7/2014 | 14 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Advance Railroad Signing Statewide | SHPO concur req | 00868 | STWD-116 | 4/1/2014 | 4/7/2014 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
US-81 to Leigh | SHPO supplemental | 31899A | 915-122 | 3/26/2014 | 4/7/2014 | 12 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Fremont Viaduct | draft EA | 22177 | 5616-1 | 2/28/2014 | 4/7/2014 | 38 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Sidney West | Cat Ex | 51458 | 801-181 | 3/26/2014 | 4/2/2014 | 7 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Omaha North DT Ped Connector Bridge | Stakeholder Involvement Plan draft | 22571 | 28-114 | 2/18/2014 | 3/31/2014 | 41 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
I-680/US-6 Bridges, Omaha | DR-53 | 22593 | 6809-33 | 3/18/2014 | 3/31/2014 | 13 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Alexandria South and Alexandria South Bridges | 4(f) analysis | 42533 | 531-104 | 3/20/2014 | 3/31/2014 | 11 | NDOR/address FHWA comments and resubmit |
Box Butte Ave Historic Lighting | Cat Ex | 51453 | 6257-2 | 3/19/2014 | 3/31/2014 | 12 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
West 5th St in Ogallala | Cat Ex - revised | 61552 | 6850-1 | 3/19/2014 | 3/28/2014 | 9 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Geneva Northwest | Cat Ex | 42226 | 7030-30 | 3/14/2014 | 3/28/2014 | 14 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Hendley E & W | Cat Ex | 70871 | 893-108 | 3/14/2014 | 3/28/2014 | 14 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Brainard E & W | Cat Ex | 12980 | 926-120 | 3/14/2014 | 3/28/2014 | 14 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
N-96 Northwest | DR-53 | 80942 | 1833-118 | 3/21/2014 | 3/28/2014 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Springview West | DR-53 | 80941 | 123-109 | 3/21/2014 | 3/28/2014 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Improving Wildflower Longevity in Roadside Seeding Areas | Quarterly Report Review | M329 | 3/19/2014 | 3/19/2014 | 0 | None | |
Walnut Creek Connector Trail | Cat Ex | 22477 | 77-59 | 3/13/2014 | 3/19/2014 | 6 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
In Dalton | DR-53 | 51502 | 3852-112 | 3/14/2014 | 3/19/2014 | 5 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Statewdie ITS Camera Deployment | SHPO and THPO concur req | 13229 | ITSN-29 | 3/13/2014 | 3/17/2014 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
In Bayard | SHO concur req | 51292 | 261-160 | 3/7/2014 | 3/14/2014 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
114th Street - Pacific to Burke Street | Cat Ex revised | 22236 | 5011-8 | 3/11/2014 | 3/14/2014 | 3 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Scottsbluff Pathway | 4(f) - revised | 51512 | 79-42 | 3/10/2014 | 3/14/2014 | 4 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
N Jct. N-14 - Genoa | Archeological testing plan - revised | 42600 | 225-116 | 3/12/2014 | 3/14/2014 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Jct US-136 Peru Spur | Cat Ex | 13095 | 671-118 | 3/12/2014 | 3/14/2014 | 2 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Clarkson Howells SRTS | Cat Ex | 32188 | 19-11 | 3/11/2014 | 3/14/2014 | 3 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
North Platte Canal Trail | Cat Ex | 61488 | 56-35 | 3/11/2014 | 3/14/2014 | 3 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
US-275 to N-9 | DR-53 | 32058 | 516-104 | 3/10/2014 | 3/14/2014 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
SB I-680 to EB I-80, Douglas County | THPO concur req | 22596 | 6809-34 | 3/7/2014 | 3/13/2014 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Coddington & West Van Dorn Roundabout | Cat Ex | 13147 | 5205-1 | 3/5/2014 | 3/13/2014 | 8 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Westbrook SRTS Infrastructure | THPO concur req | 22410 | 28-96 | 3/10/2014 | 3/13/2014 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
1st St - 6th St, North Platte | SHPO concur req | 61359 | 832-128 | 3/6/2014 | 3/12/2014 | 6 | NDOR/address FHWA comments and resubmit |
Elkhorn North | Cat Ex | 21911 | 312-110 | 3/6/2014 | 3/12/2014 | 6 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
I-80, NW56th - US-77 | Cat Ex | 12489 | 809-862 | 3/5/2014 | 3/12/2014 | 7 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
West 5th Street, Ogallala | Cat Ex | 61552 | 6850-1 | 3/4/2014 | 3/12/2014 | 8 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
E Jct US-6 to Aurora | DR-53 | 42598 | 141-120 | 3/4/2014 | 3/11/2014 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Grand Island Re-Surfacing | Detour Revision - concurrence | 42706 | 5409-2 | 2/28/2014 | 3/11/2014 | 11 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Wayne West | DR-53 | 31920 | 354-121 | 3/3/2014 | 3/11/2014 | 8 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Statewide Guardrail D1 & D2 | SHPO and THPO concur req | 00860 | STWD-109 | 3/4/2014 | 3/11/2014 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
N-50 to 50th, Omaha | THPO cocnur req | 22527 | 809-66 | 3/10/2014 | 3/11/2014 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Syracuse SW | Cat Ex | 12785 | 7066-43 | 3/4/2014 | 3/6/2014 | 2 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
US-77, 5th - 10th, Fremont | 4(f) de minimis - revised | 22434 | 773-129 | 3/5/2014 | 3/6/2014 | 1 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Fairbury West Viaduct | DR-53 | 13184 | 1366-122 | 3/5/2014 | 3/6/2014 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Blue River Bridge West of Fairbury | Batching 2 projects review | 13183 | 1366-121 | 3/3/2014 | 3/6/2014 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
US-77, 5th - 10th St, Fremont | 4(f) de Minimis | 22434 | 773-129 | 2/28/2014 | 3/4/2014 | 4 | NDOR/address FHWA comments and resubmit |
Diller-Odell Elementary Schools SRTS | SHPO concur req | 13153 | 48-24 | 2/28/2014 | 3/3/2014 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
EB I-80 to NB I-680 Bridges, Omaha | DR-53 | 22574 | 809-50 | 2/28/2014 | 3/3/2014 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
SB I-680 to EB I-80 Ramp, Omaha | DR-53 | 22596 | 6809-34 | 2/28/2014 | 3/3/2014 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Bruno Bridge Bridges | Cat Ex | 13197 | S12B-106 | 2/24/2014 | 2/28/2014 | 4 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Bennington Papio Creek Bridge and Trail | Re-eval Request | 22307 | 28-90 | 2/19/2014 | 2/28/2014 | 9 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
North Platte Canal Trail | 4(f) Temp Occ req | 61488 | 56-35 | 2/21/2014 | 2/28/2014 | 7 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Albion to N-45 | SHPO and THPO concur req | 31517 | 915-114 | 2/20/2014 | 2/27/2014 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Bancroft - Dewey and 50th - 13th | THPO concur req | 22525 | 4809-103 | 2/19/2014 | 2/27/2014 | 8 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Major Street Resurfacing, City of Omaha | DR-53 | 22605 | 5037-17 | 2/21/2014 | 2/27/2014 | 6 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Kearney South Platte River Bridge | SHPO re-eval req | 42719 | 442-109 | 2/25/2014 | 2/27/2014 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Furnas St - Wilver St (In Ashland) | SHPO reeval req | 13084 | 666-107 | 2/24/2014 | 2/27/2014 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Wyoming Line - Bushnell | SHPO concur req - revised | 51461 | 301-131 | 2/20/2014 | 2/27/2014 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
EB I-80 to NB I-680 Bridges, Omaha | SHPO and THPO concur req | 22574 | 809-50 | 2/20/2014 | 2/26/2014 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
NW 48th St Improvements | 4(f) de minimis | 12489 | 809-862 | 2/14/2014 | 2/25/2014 | 11 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Crawford Creek N of Crawford & Crawford Creek - SD Line | Cat Ex | 51499 | 714-120 | 2/19/2014 | 2/25/2014 | 6 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
N-13 to Osmond | Bio Doc | 31917 | 1214-111 | 2/18/2014 | 2/25/2014 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Pawnee City Southeast | DR-53 | 11895 | 501-109 | 2/18/2014 | 2/25/2014 | 7 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Alexandria South | Bio assessment | 42533 | 531-104 | 2/7/2014 | 2/25/2014 | 18 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Western Douglas County Trail Phs 1 and 2 in Valley | 4(f) de Minimis | 22227 | 28-87 | 2/12/2014 | 2/25/2014 | 13 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Anselmo NE | Cat Ex - V2 | 61302 | 7021-27 | 2/24/2014 | 2/25/2014 | 1 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Fremont Johnson Road Trail | Cat Ex - revised | 22427 | 27-55 | 2/14/2014 | 2/20/2014 | 6 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Arnold East | T&E Reeval | 61477 | 923-106 | 2/10/2014 | 2/19/2014 | 9 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Grand Island NW | SHPO concur req | 42322 | 7040-25 | 2/14/2014 | 2/19/2014 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Geneva West | Cat Ex | 42435 | 7030-32 | 2/14/2014 | 2/19/2014 | 5 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
GI Resurfacing | SHPO re-eval | 42706 | 5409-2 | 2/14/2014 | 2/19/2014 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Cedar Bluffs - US-77 | DR-53 | 13203 | 1092-105 | 2/13/2014 | 2/19/2014 | 6 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
North 96th St Bridge | Cat Ex | 22235 | 7028-47 | 2/13/2014 | 2/18/2014 | 5 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Chadron State Park South | Bio doc | 51400 | 3854-135 | 2/12/2014 | 2/18/2014 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Sidney West | Public Involve Proposal | 51458 | 801-181 | 2/7/2014 | 2/18/2014 | 11 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Furnas St to Silver St, Ashland | draft 4(f) | 13084 | 666-107 | 2/5/2014 | 2/18/2014 | 13 | None |
168th St Improv - Poppletone Ave to Ehlers St. | SHPO and THPO concur req | 22209 | 3811-1 | 2/7/2014 | 2/18/2014 | 11 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Scottsbluff Pathway | 4(f) Eval | 51512 | 79-42 | 2/7/2014 | 2/14/2014 | 7 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Wayne Trail Phase II in Wayne | Cat Ex | 31777 | 90-4 | 2/10/2014 | 2/14/2014 | 4 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
NW 48th Street Improvements | SHPO concur req - revised | 12489 | 809-862 | 2/11/2014 | 2/14/2014 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Bradshaw Southeast Bridge Replacement | Cat Ex | 41634 | 7093-23 | 2/11/2014 | 2/14/2014 | 3 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Anselmo NE | Cat Ex | 61302 | 7021-27 | 2/10/2014 | 2/13/2014 | 3 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
13th St Bridge in Crete | Cat Ex | 12886 | 7076-22 | 2/6/2014 | 2/13/2014 | 7 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
36th St Improvements, Platteview Road to Bline Ave | SHPO and THPO concur req | 22276 | 5061-5 | 2/4/2014 | 2/13/2014 | 9 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Red Cloud South | Cat Ex - revised | 41877 | 2811-112 | 1/16/2014 | 2/11/2014 | 26 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Syracuse SE | Cat Ex - revised | 12510 | 7066-32 | 2/6/2014 | 2/11/2014 | 5 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Blair Connector Trail | 4(f) Net Benefit req | 22549 | 89-30 | 2/3/2014 | 2/11/2014 | 8 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Chappell East and US-138 East | SHPO -Re-eval | 51462 | 301-132 | 2/4/2014 | 2/10/2014 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Fort St - MO River, Bridges | Cat Ex Re-eval | 22264 | 6809-29 | 2/6/2014 | 2/10/2014 | 4 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
D-1, -5, -6 I-80 Automated Gates | DR-53 | 13151 | ITSN-41 | 2/6/2014 | 2/10/2014 | 4 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
South of Jct US-77/N91 at Nickerson | SHPO concur req | 22576 | 773-133 | 2/6/2014 | 2/10/2014 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
N-66 Mahoney Park Interchange | SHPO re-eval req | 13155 | 667-117 | 2/6/2014 | 2/10/2014 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Ralston Viaduct | SHPO concur req | 22203 | 852-111 | 2/5/2014 | 2/10/2014 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Pender to Wakefield | DR-53 | 32059 | 163-109 | 2/7/2014 | 2/10/2014 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
City of Lincoln NW 48th Improvements | SHPO concur req | 12489 | 809-862 | 2/5/2014 | 2/7/2014 | 2 | NDOR/address FHWA comments and resubmit |
Wahoo Trail - Maple Street North | Re-Eval Draft | 12880 | 78-26 | 2/7/2014 | 2/7/2014 | 0 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Foster Northwest and Southeast | SHPO concur req | 31825 | 134-110 | 1/31/2014 | 2/4/2014 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Wahoo Maple Street Trail | 4(f) de minimis | 12880 | 78-26 | 1/31/2014 | 2/4/2014 | 4 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
District 6 and 7 Guardrails | SHPO concur req | 00863 | STWD-110 | 1/31/2014 | 2/3/2014 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Lincoln Cavett Connector Trail | Cat Ex - V2 | 13079 | 55-172 | 1/24/2014 | 1/31/2014 | 7 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Windom Street | Cat Ex | 31991 | 6709-2 | 1/24/2014 | 1/31/2014 | 7 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Plattsmouth - Bellevue | Re-eval inquiry | 21849 | 752-155 | 1/22/2014 | 1/31/2014 | 9 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
50th to I-480 | DR-53 | 22586 | 809-80 | 1/27/2014 | 1/31/2014 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Steinhart Park Trail Phase II | Cat Ex | 13055 | 66-34 | 1/29/2014 | 1/31/2014 | 2 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Gretna East | SHPO/THPO re-eval | 21543 | 3707-119 | 1/30/2014 | 1/31/2014 | 1 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
W Jct N-15 to Newcastle | Cat Ex | 31919 | 126-115 | 1/29/2014 | 1/31/2014 | 2 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Scotia East Bridges | Cat Ex | 42723 | 224-112 | 1/27/2014 | 1/30/2014 | 3 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Sidney West | SHPO re-eval | 51458 | 801-181 | 1/28/2014 | 1/30/2014 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Blair Connector Trails - Lincoln Trail Extension | 4(f) DeMinimis | 22549 | 89-30 | 1/27/2014 | 1/30/2014 | 3 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Hickman Road Trail | Cat Ex | 13134 | 55-174 | 1/24/2014 | 1/29/2014 | 5 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
NW 56th to US-77 | HazMat, Civil Rights | 12489 | 809-862 | 1/28/2014 | 1/28/2014 | 0 | None |
NW 56th to US-77 | Noise Study Report | 12489 | 809-862 | 1/27/2014 | 1/28/2014 | 1 | None |
Overhead DMS | SHPO/THPO Re-consultation | 22487 | ITSN-16 | 1/22/2014 | 1/28/2014 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
NW 56th to US-77 | BA - Reeval Memo | 12489 | 809-862 | 1/27/2014 | 1/28/2014 | 1 | None |
Baltimore Ave | Cat Ex | 42704 | 5505-4 | 1/16/2014 | 1/28/2014 | 12 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
6th St, Jackson St, and 13th St Improvements | Cat Ex - revised | 61554 | 6552-1 | 1/16/2014 | 1/28/2014 | 12 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Belden East Bridges | Cat Ex | 31342A | 206-109 | 1/23/2014 | 1/28/2014 | 5 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
10th St, Box Butte to Flack | Cat Ex | 51490 | 6254-7 | 1/13/2014 | 1/27/2014 | 14 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
N-13 to Osmond | Bio doc review | 31917 | 1214-111 | 1/10/2014 | 1/27/2014 | 17 | None |
Elwood to Smithfield | Batched Bio Doc | 71122 | 233-108 | 1/13/2014 | 1/27/2014 | 14 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
West 5th Street, Ogallala | 4(f) Exception req | 61552 | 6850-1 | 1/16/2014 | 1/27/2014 | 11 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
In North Loup & South | Cat Ex Scope Change review | 42593 | 113-120 | 1/15/2014 | 1/27/2014 | 12 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
North Platte - Maxwell Bridges | Cat Ex | 61575 | 804-144 | 1/16/2014 | 1/27/2014 | 11 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
In Melbeta | Cat Ex | 51480 | 921-125 | 1/21/2014 | 1/27/2014 | 6 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
US-77, 5th to 10th Street | Fremont public involvement plan | 22434 | 773-129 | 1/13/2014 | 1/15/2014 | 2 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
N Jct N-98 - US-20 Bridges | DR-53 | 31787 | 814-114 | 1/14/2014 | 1/15/2014 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Lincoln West O Street Historic Highway | Cat Ex revision | 12946 | 5266-2 | 1/13/2014 | 1/14/2014 | 1 | None |
Fremont Johnson Road Trail | Cat Ex | 22427 | 27-55 | 1/13/2014 | 1/14/2014 | 1 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Albion South | DR-53 | 32130 | 143-116 | 1/13/2014 | 1/14/2014 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
N. 66th and Fremont Sts. | Proposed stakehold mtg review | 13227 | 5253-1 | 1/13/2014 | 1/14/2014 | 1 | None |
Blair West | Working days extension review | 22026 | 7089-23 | 1/2/2014 | 1/13/2014 | 11 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
East 17th St, South Sioux City | Cat Ex | 32074 | 5314-2 | 12/30/2013 | 1/13/2014 | 14 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Cottonwood Creek North of Crawford | Cat Ex | 51499 | 714-120 | 1/3/2014 | 1/13/2014 | 10 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
23rd St Viaduct | 4(f) Ne Benefit - V3 | 22177 | 5616-1 | 12/20/2013 | 1/13/2014 | 24 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Gothenburg West | SHPO concur req | 61467 | 302-140 | 1/9/2014 | 1/13/2014 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Bristow East & West | Cat Ex - review | 80805 | 124-107 | 1/2/2014 | 1/13/2014 | 11 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Box Butte Ave Historic Lighting | 4(f) de Minimis | 51453 | 6257-2 | 1/6/2014 | 1/13/2014 | 7 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Heartland Expressway Planning Study | HEA request | 51432 | 3853-118 | 12/6/2013 | 1/9/2014 | 34 | None |
5th to 10th, in Fremont | Public Involve Info | 22434 | 773-129 | 12/11/2013 | 1/7/2014 | 27 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Ft Kearny Trail and Bridge Rehab | Cat Ex - V2 | 42551 | 10-62 | 1/6/2014 | 1/7/2014 | 1 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
N 27th/O St - I-80 | DR-53 | 13244 | 5231-14 | 1/3/2014 | 1/7/2014 | 4 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Wyoming Line - Bushnell | SHPO concur req | 51461 | 301-131 | 1/3/2014 | 1/7/2014 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Chadron State Park South | draft SHPO concur req | 51400 | 3854-135 | 1/3/2014 | 1/7/2014 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
I-80 | Re-eval NEPA doc | 12489 | 809-862 | 12/12/2013 | 1/6/2014 | 25 | NDOR/address FHWA comments and resubmit |
DMS Replacement | Bio doc - V2 | 32167 | ITSN-14 | 12/17/2013 | 1/6/2014 | 20 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Niobrara River South | Bio doc | 80690 | 1834-109 | 12/19/2013 | 1/6/2014 | 18 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
DMS Replacement | SHPO concur req | 13152 | ITSN-45 | 1/3/2014 | 1/6/2014 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Overhead DMS | Bio doc - V2 | 22487 | ITSN-16 | 12/17/2013 | 1/6/2014 | 20 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
S. 48th/N-2, Lincoln | DR-53 | 13253 | 5239-9 | 1/3/2014 | 1/6/2014 | 3 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Lincoln West O St Historic Highway | Suppl SHPO concur req | 12944 | 5266-2 | 1/3/2014 | 1/3/2014 | 0 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Walnut Creek Connector Trail | 4(f) De Minimis - revised | 22477 | 77-59 | 12/30/2013 | 1/3/2014 | 4 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Farnam - Jct N-21 | SHPO Supplemental | 71125 | 233-110 | 12/30/2013 | 1/3/2014 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
I-80 North Bridges | Cat Ex | 51497 | 272-105 | 12/17/2013 | 1/2/2014 | 16 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Red Cloud South | Cat Ex | 41877 | 2811-112 | 12/17/2013 | 1/2/2014 | 16 | NDOR/address FHWA comments and resubmit |
Camera/Auto Gates | Bio doc - V2 | 42704 | ITSN-21 | 12/17/2013 | 1/2/2014 | 16 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Lincoln Cavett Trail | 4(f) de Minimus | 13079 | 55-172 | 12/6/2013 | 1/2/2014 | 27 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
US-77, 5th - 10th, Fremont | SHPO Suppl concur req | 22434 | 773-129 | 12/12/2013 | 1/2/2014 | 21 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Superior Public Schools | SHPO concur req | 42718 | 65-24 | 12/24/2013 | 1/2/2014 | 9 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Lexington East Viaduct | Purpose and Need - revised | 61457 | 1705-3 | 12/30/2013 | 1/2/2014 | 3 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Wilderness Bridge | NEPA documentation | RTP2013-001 | 12/17/2013 | 1/2/2014 | 16 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required | |
US-75 West In Bellevue | SHPO and THPO concur req | 22534 | 3707-126 | 12/23/2013 | 1/2/2014 | 10 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
A St and Regency, Lincoln | DR-53 | 13262 | 5220-5 | 12/18/2013 | 12/26/2013 | 8 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
L62A - US-385 to Alliance | Bio doc - V3 | 51432 | 3853-118 | 12/12/2013 | 12/26/2013 | 14 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Bristow East & West | Cat Ex | 80805 | 124-107 | 12/18/2013 | 12/26/2013 | 8 | NDOR/address FHWA comments and resubmit |
N Jct US-281 East | DR-53 | 80644 | 704-105 | 12/19/2013 | 12/26/2013 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Bristow East & West | Cat Ex | 80805 | 124-107 | 12/18/2013 | 12/26/2013 | 8 | NDOR/address FHWA comments and resubmit |
Lexington Street Improvements | Public involvement review | 61554 | 6552-1 | 12/20/2013 | 12/20/2013 | 0 | None |
F Street Bridge | Cat Ex | 22284 | 5028-4 | 12/16/2013 | 12/20/2013 | 4 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Q Street Bridge replacement - 26th to 27th | Public involvement review | 22325 | 5026-11 | 12/12/2013 | 12/19/2013 | 7 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
48th & Calvert - 56th & Calvert | DR-53 | 13260 | 5239-10 | 12/16/2013 | 12/18/2013 | 2 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Chadron West | DR-53 | 51406 | 201-140 | 12/16/2013 | 12/18/2013 | 2 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
DMS Overhead | DR-53 | 13149 | ITSN-39 | 12/13/2013 | 12/18/2013 | 5 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
S 1th St Traffic Signals | DR-53 | 13261 | 5227-8 | 12/16/2013 | 12/18/2013 | 2 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
A St and Regency | DR-53 | 13262 | 5220-5 | 12/16/2013 | 12/18/2013 | 2 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Kearney South Platte River Bridge | Bio doc - V1 | 42719 | 442-109 | 12/17/2013 | 12/18/2013 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
N 96th St Bridge | 4(f) de Minimis | 22235 | 7028-47 | 12/17/2013 | 12/18/2013 | 1 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Brule Southwest | DR-53 | 61289 | 51-57 | 12/11/2013 | 12/17/2013 | 6 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Lincoln East | Cat Ex - revised | 12975 | 346-141 | 12/17/2013 | 12/17/2013 | 0 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Turkey Creek Bridge S of Steinauer | SHPO concur req | 13188 | 47-107 | 12/12/2013 | 12/17/2013 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Gordon East Bridge | Cat Ex | 51496 | 201-144 | 12/13/2013 | 12/17/2013 | 4 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
27th over Salt Creek | DR-53 revised | 13247 | 5231-15 | 12/16/2013 | 12/17/2013 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Blue River Bridge West of Fairbury | SHPO concur req | 13183 | 1366-121 | 12/12/2013 | 12/16/2013 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Lincoln East | Cat Ex | 12975 | 346-141 | 12/9/2013 | 12/16/2013 | 7 | NDOR/address FHWA comments and resubmit |
North Platte - Maxwell | ShPO concur req | 61562 | 302-142 | 12/6/2013 | 12/16/2013 | 10 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
27th & Fairfield and West O St Bridges over Salt Creek | DR-53 | 13247 | 5231-15 | 12/6/2013 | 12/16/2013 | 10 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Lexington Street Improvements | Public Involve Review | 61554 | 6552-1 | 12/16/2013 | 12/16/2013 | 0 | None |
DMS Replacement | Bio doc concur req | 32167 | ITSN-14 | 12/3/2013 | 12/12/2013 | 9 | NDOR/address FHWA comments and resubmit |
Platte River Br East of Grand Island | Bio doc | 42607 | 345-118 | 12/10/2013 | 12/12/2013 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Overhead DMS | Bio doc concur req | 22487 | ITSN-16 | 12/3/2013 | 12/12/2013 | 9 | NDOR/address FHWA comments and resubmit |
Genoa | SHPO and THPO concur req | 42600 | 225-116 | 12/6/2013 | 12/11/2013 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Elkhorn | SHPO and THPO supple concur request | 21911 | 312-110 | 12/6/2013 | 12/11/2013 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Walthill East | SHPO & THPO Supplemental concur | 31511 | 947-105 | 12/6/2013 | 12/11/2013 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Tecumseh Historic Square Preservation | SHPO concur req | 13214 | 49-46 | 12/2/2013 | 12/10/2013 | 8 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Walnut Creek Connector Trail | 4(f) de Minimis | 22477 | 77-59 | 12/5/2013 | 12/9/2013 | 4 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Niobrara River South | SHPO concur req | 80690 | 1834-109 | 12/5/2013 | 12/9/2013 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Valentine East | Cat Ex | 80799 | 122-104 | 12/5/2013 | 12/6/2013 | 1 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
In Grand Island & North | DR-53 | 42690 | 2812-127 | 12/5/2013 | 12/6/2013 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
In Melbeta | SHPO Supplemental | 51480 | 921-125 | 12/5/2013 | 12/6/2013 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Hay Springs West | SHPO concur request | 51472 | 201-142 | 12/4/2013 | 12/6/2013 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Ralston Viaduct | DR-53 | 22203 | 852-111 | 11/26/2013 | 12/5/2013 | 9 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Jct L62A - US-285 to Alliance | Bio doc - V2 | 51432 | 3853-118 | 11/18/2013 | 12/5/2013 | 17 | NDOR/address FHWA comments and resubmit |
Lincoln Stonebridge Trail | SHPO concur req | 13213 | 55-177 | 12/2/2013 | 12/5/2013 | 3 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
114th St - Pacific to Burke | Cat Ex | 22236 | 5011-8 | 11/18/2013 | 12/5/2013 | 17 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
DMS Replacement - D-1, 2, 4 | SHPO and THPO concur req | 13231 | ITSN-31 | 11/21/2013 | 12/5/2013 | 14 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
In Geneva and West | Cat Ex | 42591 | 414-107 | 11/27/2013 | 12/3/2013 | 6 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
CCTV | DR-53 | 13229 | ITSN-29 | 12/3/2013 | 12/3/2013 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Wahoo Maple St Trail | SHPO concur req | 12880 | 78-26 | 11/25/2013 | 12/2/2013 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Alexandria South and Alex South Bridges | ACHP Notification | 42474 | 531-104 | 11/22/2013 | 12/2/2013 | 10 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
DMS - D2, 4, 5 | SHPO and THPO concur request | 22487 | ITSN-16 | 11/26/2013 | 12/2/2013 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Wahoo Maple St Trail | Section 4(f) | 12880 | 78-26 | 11/22/2013 | 11/27/2013 | 5 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Sargent South | Cat Ex - revised | 60943 | 1833-113 | 11/21/2013 | 11/27/2013 | 6 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
23rd St Viaduct - Fremont | Section 4(f) De minimis | 22177 | 5616-1 | 10/28/2013 | 11/27/2013 | 30 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Blair Connector Trails | Section 4(f) Eval | 22549 | 89-30 | 11/20/2013 | 11/26/2013 | 6 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
In Crete, 13th Street Bridge | Cat Ex - Logical Termini review | 12886 | 7076-22 | 11/7/2013 | 11/26/2013 | 19 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Bridgeport Viaduct | Purpose & Need | 51299 | 261-161 | 11/12/2013 | 11/26/2013 | 14 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Baltimore Ave, 12th to 14th Street | SHPO concur req | 42704 | 5505-4 | 11/19/2013 | 11/25/2013 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Statewide DMS Replacements | SHPO concur req | 32167 | ITSN-14 | 11/20/2013 | 11/25/2013 | 5 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Lincoln East | MoPac Trail crossing issue review | 12975 | 346-141 | 11/21/2013 | 11/22/2013 | 1 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Sidney West | Bio doc - V1 | 51458 | 801-181 | 11/6/2013 | 11/22/2013 | 16 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
North Platte Canal Trail | Section 4(f) review | 61488 | 56-35 | 11/7/2013 | 11/22/2013 | 15 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
26th & Q Bridge | Outreach Update review | 22325 | 5026-11 | 11/4/2013 | 11/22/2013 | 18 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
E Jct US-281 - Lawrence | Cat Ex | 42654 | 44-108 | 11/7/2013 | 11/22/2013 | 15 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Gothenburg West | Bio Doc - V1 | 61467 | 302-140 | 11/6/2013 | 11/22/2013 | 16 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Snapshot Cameras and Automated Gates | Bio doc - V1 | 42703 | ITSN-21 | 11/13/2013 | 11/22/2013 | 9 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
D1 - I-80 DMS Replacement | DR-53 | 13152 | ITSN-45 | 11/13/2013 | 11/22/2013 | 9 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Hoskins South & East | DR-53 | 32129 | 353-109 | 11/18/2013 | 11/20/2013 | 2 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Dodge Street S Curve Connectivitiy | Purpose and Need v2 | 22282 | 67-179 | 9/12/2013 | 11/20/2013 | 69 | None |
32nd Ave Streetscape and Bike Route | SHPO and THPO concur req | 22414 | 28-99 | 10/31/2013 | 11/19/2013 | 19 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Snapshot Camera and Gate | SHPO concur req | 42703 | ITSN-21 | 11/12/2013 | 11/19/2013 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
In Bassett and North | Cat Ex | 80684A | 74-114 | 11/14/2013 | 11/19/2013 | 5 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Interstate Canal Bridges | Cat Ex | 51498 | 294-108 | 11/8/2013 | 11/19/2013 | 11 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Statewide Sidemount DMS Installs | SHPO concur req | 51475 | ITSN-24 | 11/1/2013 | 11/18/2013 | 17 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
South Platte River Bridges North Platte | Cat Ex | 61500 | 832-137 | 11/6/2013 | 11/18/2013 | 12 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Auburn East | Cat Ex -2nd revision | 12994 | 1366-119 | 11/6/2013 | 11/18/2013 | 12 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
N Jct N-14 to Genoa | 106 Testing Plan revised | 42600 | 225-116 | 10/25/2013 | 11/18/2013 | 24 | NDOR/address FHWA comments and resubmit |
Wyuka Stables Renovation | Contractor qualification language review | 13063 | 55-170 | 11/12/2013 | 11/18/2013 | 6 | None |
E Jct N-45 to Madison | Cat Ex - revised | 31829 | 325-107 | 11/6/2013 | 11/18/2013 | 12 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Lexington E Viaduct | Public Involvement Plan | 61457 | 1705-3 | 11/4/2013 | 11/15/2013 | 11 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
13th St, Jackson St, & 6th St Improvements in Lexington | Public Outreach Plan review | 61554 | 6552-1 | 11/4/2013 | 11/15/2013 | 11 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Lincoln East | Cat Ex | 12975 | 346-141 | 11/15/2013 | 11/15/2013 | 0 | None |
Dodge Street S Curve | Standing Structures Report - revised | 22282 | 67-179 | 10/22/2013 | 11/8/2013 | 17 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
36th Street Improvements | 4(f) De Minimis | 22276 | 5061-5 | 10/31/2013 | 11/6/2013 | 6 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
S Coddington/W Van Dorn, Lincoln | Public Information Discrepancy review | 13147 | 5205-1 | 10/25/2013 | 11/5/2013 | 11 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
56th St, Shadow Pines to Old Cheney | Revised EA Re-Eval | 13141 | 5241-5 | 11/1/2013 | 11/5/2013 | 4 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Bloomington - Franklin | Scope Change Reeval Memo | 70592A | 1364-111 | 10/25/2013 | 11/4/2013 | 10 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
120th Street | Section 4(f) | 22277 | 5009-3 | 10/25/2013 | 11/4/2013 | 10 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Hickman Road Connector Trail | Section 4(f) | 13134 | 55-174 | 10/25/2013 | 11/4/2013 | 10 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Syracuse SE | Cat Ex | 12510 | 7066-32 | 10/28/2013 | 11/4/2013 | 7 | NDOR/assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
Holdrege Regional Center Spur Bridge | SHPO concur req | 42742 | S01C-102 | 10/31/2013 | 11/4/2013 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
E Jct N-45 to Madison & In Madison and East | Cat Ex | 31829 | 325-107 | 10/23/2013 | 10/29/2013 | 6 | NDOR/address FHWA comments and resubmit |
Western Douglas Co Trail | Public Outreach Strategy review | 22227 | 28-87 | 10/18/2013 | 10/28/2013 | 10 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
5th to 10th St, Fremont | Public Involvement Plan Review | 22434 | 773-129 | 10/8/2013 | 10/28/2013 | 20 | NDOR/address FHWA comments and resubmit |
DMS Replacement | Bio doc - v1 | 32167 | ITSN-14 | 10/16/2013 | 10/28/2013 | 12 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Sargent South | Cat Ex | 60943 | 1833-113 | 10/8/2013 | 10/28/2013 | 20 | NDOR/address FHWA comments and resubmit |
Overhead DMS | Bio doc | 22487 | ITSN-16 | 10/15/2013 | 10/28/2013 | 13 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
Rushville South Bridges | DR-53 | 51538 | 2504-105 | 10/15/2013 | 10/28/2013 | 13 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Arnold West and East | Cat Ex | 61474 | 922-109 | 10/23/2013 | 10/28/2013 | 5 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
Callaway West | DR-53 | 61556 | 403-107 | 9/26/2013 | 10/28/2013 | 32 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
Auburn East | Cat Ex | 12994 | 1366-119 | 10/17/2013 | 10/25/2013 | 8 | NDOR/address FHWA comments and resubmit |
Q St Bridge betw 26th and 27th Sts | Public Involve material review | 22325 | 5026-11 | 10/15/2013 | 10/25/2013 | 10 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
Dodge Street S-Curve | SHPO and THPO concur req | 22282 | 67-179 | 10/24/2013 | 10/25/2013 | 1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
AVERAGE FHWA TURNAROUND | 7.45 Calendar days |
* Note: DR 53 is a simple one page yes/no checklist, serving as an early concurrence point for determining if an action will likely be a CE, EA, or EIS. The DR 53 also serves as an early communication tool between FHWA, NDOR, and the project proponent. This is not a NEPA document, but is the "kickoff point" for the environmental review.
** Note: a 0 (zero) value in the Response Time column indicates a document received and responded to in the same day
*** To determine the next step for a project, read the info in this column for the last submittal received related to the project