U.S. Department of Transportation
Federal Highway Administration
1200 New Jersey Avenue, SE
Washington, DC 20590
202-366-4000
Nebraska Division
To search this page, use your browser's Find feature (Ctrl+F).
FHWA Nebraska Division Environmental Document Review Delivery
February 10, 2010 through August 16, 2012
Number of Submittals = 1,546
Average Review Time, Calendar Days = 6.59
INFORMATION: The typical environmental submittals that are prepared/approved by NDOR and submitted to FHWA for Categorical Exclusions (CE's) are: DR 53*, Biology review, Section 106 package, and the Categorical Exclusion (CE). If a project fits the stipulations of the 2008 Programmatic Agreement between FHWA-NE and NDOR, NDOR has the authority to approve the NEPA document without FHWA approval. These are referred to as PCE's. Likewise, FHWA has also provided programmatic approval authority to NDOR for certain actions under the Endangered Species Act(ESA) and Section 106 (historic preservation). Since there is no FHWA project-level approval for the projects and actions that are covered by these programmatic agreements, that project level documentation is not recorded on this list.
BASIC NEPA STEPS FOR PROJECTS: 1) NDOR approves and submits the DR53 to FHWA; NDOR/local sign program agreements and procure consultant (for local fed-aid projects); 2) NDOR/local govt. start NEPA; 3) NDOR/local complete tech reviews (ex, wetland, bio, and cultural resource); 4)NDOR submit bio and cultural tech docs to FHWA for agency consultation, when needed; 5) NDOR/local prepare NEPA doc; 6) NDOR review/approve NEPA doc; 7) NDOR submit NEPA doc to FHWA for review/acceptance (except for PCE's)
| Project Name | Subject | Control No | Project No | Date Received | Date Completed | Action Time * | Comments | Responsible party/pending action *** |
|---|---|---|---|---|---|---|---|---|
| Tracy Creek Bank | Monitoring Report | 713 | STWD-1044 | 07-Mar-11 | 21-Mar-11 | 14 | FHWA sent the material to the resource agency(s) for review/concurrrence, which takes up to 4 weeks. Once all tech reviews and concurrences complete, next step is for NDOR to review/ approve the NEPA doc. If not a PCE, NDOR will submit CE to FHWA | |
| STWD Intersection Signage Project | Bio doc | 00772 | STWD-86 | 8/9/2012 | 8/16/2012 | 7 | sent back to clarify the affect determination and rationale behind it | NDOR / address FHWA comments and resubmit |
| Horizontal Curved Signing Project - Phase III | Bio doc review | 00787 | STWD-90 | 8/6/2012 | 8/16/2012 | 10 | comment to clarify affect determination and add the justification | NDOR / address FHWA comments and resubmit |
| Statewide rural traf control dev | DR 53 | 850 | STWD-108 | 16-Feb-11 | 28-Feb-11 | 12 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Centerline Rumble Strips | DR 53 | 865 | HSIP-STWD-112 | 31-Aug-11 | 03-Sep-11 | 3 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Statewide Centerline Rumble Strips | Bio doc version 1 | 865 | STWD-112 | 1/18/2012 | 1/25/2012 | 7 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| NE Hwy Hist Markers | DR 53 | 00875 | STWD-119 | 7/3/2012 | 7/12/2012 | 9 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Nebr Hwy Historical Markers - Statewide | SHPO concur req | 00875 | STWD-119 | 7/13/2012 | 7/24/2012 | 11 | SHPO & THPO letters sent | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Crab Orchard Southwest | DR 53 | 11473 | 7049-11 | 19-May-11 | 27-May-11 | 8 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Barneston West | SHPO concur req | 11678 | 86-106 | 28-Mar-11 | 31-Mar-11 | 3 | letter sent to SHPO | FHWA sent the material to the resource agency(s) for review/concurrrence, which takes up to 4 weeks. Once all tech reviews and concurrences complete, next step is for NDOR to review/ approve the NEPA doc. If not a PCE, NDOR will submit CE to FHWA |
| Barneston West | Bio doc version 1 | 11678 | 86-106 | 10/27/2011 | 10/28/2011 | 1 | letters sent to NGPC for concurrence and USFWS for their info | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Barneston West | CE | 11678 | 86-106 | 1/26/2012 | 2/7/2012 | 12 | sent comments back to NDOR | NDOR / address FHWA comments and resubmit |
| Barneston West | CE - revised | 11678 | 86-106 | 2/27/2012 | 3/6/2012 | 8 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Adams Northwest | DR 53 | 11776 | 7034-18 | 1/12/2012 | 1/16/2012 | 4 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Seward South | DR 53 | 11781 | 7080-27 | 12-Sep-11 | 16-Sep-11 | 4 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Wahoo Bypass | Cat Ex proposal request | 11801 | 772-1025 | 5/8/2012 | 6/27/2012 | 50 | emailed comments to NDOR | NDOR / address FHWA comments and resubmit |
| Cordova North | T&E Consultation Memo | 12002 | 3045-5 | 12-Jul-10 | 26-Jul-10 | 14 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Beaver Cross SW | Bio doc vers 1 | 12012 | 7080-40 | 08-Oct-10 | 13-Oct-10 | 5 | rb approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Beaver Crossing SW | DR 53 | 12012 | 7080-40 | 06-Dec-10 | 14-Dec-10 | 8 | approved with comments | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Beaver Crossing SW | SHPO concur req | 12012 | 7080-40 | 27-Jun-11 | 28-Jun-11 | 1 | mm: reviewed and gave letter to front office for submittal | FHWA sent the material to the resource agency(s) for review/concurrrence, which takes up to 4 weeks. Once all tech reviews and concurrences complete, next step is for NDOR to review/ approve the NEPA doc. If not a PCE, NDOR will submit CE to FHWA |
| Beaver Crossing Southwest | CE | 12012 | 7080-40 | 14-Oct-11 | 17-Oct-11 | 3 | comments sent back to NDOR | NDOR / assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
| Beaver Crossing SW | CE | 12012 | 7080-40 | 11/9/2011 | 12/7/2011 | 28 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| South & East Beltway | NDOR draft letter for review | 12153 | 3300-1 | 12/6/2011 | 1/6/2012 | 31 | sent comments back to NDOR | NDOR / address FHWA comments and resubmit |
| Crete North | DR 53 | 12222 | 1031-108 | 07-Apr-11 | 07-Apr-11 | 0 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Crete North | Bio doc vers 1 | 12222 | 1031-108 | 07-Apr-11 | 07-Apr-11 | 0 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| In Wymore | Bio doc vers 1 | 12299 | 3265-5 | 14-Dec-10 | 17-Dec-10 | 3 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| In Wymore | DR 53 | 12299 | 3265-5 | 24-Jan-11 | 31-Jan-11 | 7 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| In Wymore | 106 letter | 12299 | 3265-5 | 09-May-11 | 13-May-11 | 4 | letter sent to SHPO | FHWA sent the material to the resource agency(s) for review/concurrrence, which takes up to 4 weeks. Once all tech reviews and concurrences complete, next step is for NDOR to review/ approve the NEPA doc. If not a PCE, NDOR will submit CE to FHWA |
| In Wymore | CE | 12299 | 3265-5 | 09-Sep-11 | 13-Sep-11 | 4 | mm approved CE, had some minor QC issues, sent heads-up to NDOR separate, but approved the doc | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| In Wymore | Design change Memo | 12299 | 3265-5 | 6/4/2012 | 6/11/2012 | 7 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Filley North | Bio doc vers 1 | 12300 | 3285-5 | 07-Jan-11 | 07-Jan-11 | 0 | sent comments to Alllison and Zach, need DR53 first | NDOR / assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
| Filley North | DR 53 | 12300 | 3285-5 | 24-Jan-11 | 31-Jan-11 | 7 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Filley North, Gage Co. | SHPO concur req | 12300 | 3285-5 | 13-Jun-11 | 23-Jun-11 | 10 | mm reviewed and to AB for formatting/mailing | FHWA sent the material to the resource agency(s) for review/concurrrence, which takes up to 4 weeks. Once all tech reviews and concurrences complete, next step is for NDOR to review/ approve the NEPA doc. If not a PCE, NDOR will submit CE to FHWA |
| Filley North | Cat Ex | 12300 | 3285-5 | 2/2/2012 | 2/17/2012 | 15 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| I-80 Upgrade | bio doc | 12312 | 809-872 | 20-May-10 | 21-May-10 | 1 | 10/21 mm reviewed and signed doc. With Sue to format letter and send to agencies | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| -80 Upgrade Lincoln - Omaha | Reeval | 12312 | 809-872 | 20-Aug-10 | 24-Aug-10 | 4 | comments addressed. Rb approved. | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Mahoney Park Intrch ramps | SHPO concur req | 12312 | 809-872 | 28-Mar-11 | 31-Mar-11 | 3 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| I-80 Upgrade | Bio doc reeval | 12312 | 809-872 | 25-Mar-11 | 01-Apr-11 | 7 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Nebraska City Northwest | DR 53 | 12347 | 7066-29 | 1/12/2012 | 1/16/2012 | 4 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Rouleau St, Rulo Bridge | Reeval Memo T&E change | 12381 | 1597-106 | 05-Apr-11 | 07-Apr-11 | 2 | comments sent to Eric | NDOR / address FHWA comments and resubmit |
| Rouleau Street, Rulo | T&E Reeval | 12381 | 1597-105 | 13-Apr-11 | 19-Apr-11 | 6 | comments sent back to Eric | NDOR / address FHWA comments and resubmit |
| Waverly - Greenwood | CO 22 | 12457 | 809-842 | 1/17/2012 | 1/20/2012 | 3 | Original on your desk. approved | None |
| US-77 - 56th St Interch to Waverly Interch | Scope Change memo | 12477 | 809-850 | 8/8/2012 | 8/15/2012 | 7 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| 14th St Bridge, Lincoln | SHPO concur req | 12482 | 809-855 | 21-Mar-11 | 29-Mar-11 | 8 | commenets sent back to Steve. | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| 14th St Bridge, Lincoln | SHPO concur req | 12482 | 809-855 | 05-Apr-11 | 07-Apr-11 | 2 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| NW 56th to US-77 South | SHPO concur req | 12489 | 809-862 | 7/17/2012 | 7/26/2012 | 9 | sent comments to NDOR | NDOR / address FHWA comments and resubmit |
| Syracuse Southeast | DR 53 | 12510 | 7066-32 | 1/12/2012 | 1/16/2012 | 4 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Syracuse SE | SHPO and THPO concur req | 12510 | 7066-32 | 6/25/2012 | 6/27/2012 | 2 | Letters sent to SHPO & THPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Dorchester SE | Bio doc vers 1 | 12519 | 7076-16 | 20-Sep-10 | 29-Sep-10 | 9 | rb approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Dorechester Southeast | SHPO concur req | 12519 | 7076-16 | 01-Nov-10 | 08-Nov-10 | 7 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Dorchester SE | DR 53 | 12519 | 7076-16 | 10-Nov-10 | 12-Nov-10 | 2 | rb approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Denton East | SHPO concur req | 12541 | 3305-9 | 07-Dec-10 | 10-Dec-10 | 3 | letter to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Denton East | Bio doc vers 1 | 12541 | 3305-9 | 10-Dec-10 | 10-Dec-10 | 0 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Denton East | CE | 12541 | 3305-9 | 22-Aug-11 | 06-Sep-11 | 15 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| In Friend | DR 53 | 12577 | 2982-1 | 14-Jul-11 | 15-Jul-11 | 1 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| In Friend | Bio doc version 1 | 12577 | 2982-1 | 11/4/2011 | 11/9/2011 | 5 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| In Friend | SHPO concur request | 12577 | 2982-1 | 11/8/2011 | 11/14/2011 | 6 | " | |
| letter sent to SHPO" | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA | |||||||
| In Friend | CE | 12577 | 2982-1 | 1/30/2012 | 2/9/2012 | 10 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Greenwood Northeast | DR 53 | 12658 | 7013-10 | 12/22/2011 | 12/23/2011 | 1 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Greenwood Northeast | SHPO concur request | 12658 | 7013-10 | 5/14/2012 | 5/25/2012 | 11 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Greenwood Northeast | THPO concur req | 12658 | 7013-10 | 6/21/2012 | 6/26/2012 | 5 | letter sent to THPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Verdon NW | SHPO concur req | 12666 | 7074-23 | 7/6/2012 | 7/16/2012 | 10 | SHPO and THPO letters sent out | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Pawee City SW | DR 53 | 12677 | 7067-16 | 1/3/2012 | 1/16/2012 | 13 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| N Columbia Ave, Seward | DR 53 | 12693 | 6759-2 | 27-Dec-10 | 07-Jan-11 | 11 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Columbia Ave, Seward | SHPO concur request | 12693 | 6759-2 | 12/1/2011 | 12/8/2011 | 7 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Columbia Ave, Seward | Bio doc version 1 | 12693 | 6759-2 | 1/23/2012 | 2/1/2012 | 9 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| N. Columbia Ave | Cat Ex | 12693 | 6759-2 | 6/27/2012 | 7/13/2012 | 16 | comments sent back to NDOR | NDOR / address FHWA comments and resubmit |
| N Columbia Ave, Seward | Cat Ex | 12693 | 6759-2 | 8/9/2012 | 8/14/2012 | 5 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| SW 40th St, Lincoln | Reeval | 12744 | 5267-1 | 20-Sep-10 | 29-Sep-10 | 9 | rb approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Southwest 40th Street | Reevaluation Memo | 12744 | 5267-1 | 3/20/2012 | 4/5/2012 | 16 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required | |
| Brock Southwest | DR 53 | 12746 | 7064-13 | 24-Jan-11 | 31-Jan-11 | 7 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Weeping Water SE | Bio Assessment | 12764 | 7013-12 | 12-Jul-10 | 26-Jul-10 | 14 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Weeping Water SE | DR53 | 12764 | 7013(12) | 06-Dec-10 | 15-Dec-10 | 9 | approved with comments | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Weeping Water SE | SHPO concur req | 12764 | 7013-12 | 25-Apr-11 | 25-Apr-11 | 0 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Weeping Water Southeast | CE | 12764 | 7013-12 | 10/21/2011 | 10/28/2011 | 7 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Burchard South | Bio doc vers 1 | 12773 | 87-113 | 14-Apr-11 | 19-Apr-11 | 5 | letters sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Burchard South | SHPO concur req | 12773 | 87-113 | 28-Apr-11 | 02-May-11 | 4 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Burchard South | CE | 12773 | 87-113 | 16-Sep-11 | 20-Sep-11 | 4 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Haymarket Ball Park Trail | Memo | 12781 | 55-151 | 09-Jun-10 | 09-Jun-10 | 0 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required | |
| Syracuse Southwest | DR 53 | 12785 | 7066-43 | 1/12/2012 | 1/16/2012 | 4 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Sprague East | Bio doc vers 1 | 12786 | 3280-4 | 21-Sep-10 | 29-Sep-10 | 8 | rb approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Sprague East | SHPO concur req | 12786 | 3280-4 | 17-Nov-10 | 23-Nov-10 | 6 | letter to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Sprague East | DR 53 | 12786 | 3280-4 | 17-Dec-10 | 23-Dec-10 | 6 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Sprague East | CE | 12786 | 3280-4 | 22-Jul-11 | 03-Aug-11 | 12 | comments sent back to NDOR | NDOR / assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
| Sprague East | CE - vers 2 | 12786 | 3280-4 | 09-Aug-11 | 09-Aug-11 | 0 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Ithaca - Ashland | DR 53 | 12831 | 666-104 | 12-Aug-11 | 17-Aug-11 | 5 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Ithaca - Ashland | SHPO concur req | 12831 | 666-104 | 17-Aug-11 | 17-Aug-11 | 0 | letter sent to SHPO today | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Table Rock Southeast | SHPO concur req | 12835 | 7067-22 | 6/26/2012 | 6/28/2012 | 2 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Friend South | DR 53 | 12850 | 7076-18 | 15-Dec-10 | 17-Dec-10 | 2 | approved with comments | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Friend South | Bio doc vers 1 | 12850 | 7076-18 | 20-Jan-11 | 31-Jan-11 | 11 | approved no affect bio mm | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Friend South | SHPO concur req | 12850 | 7076-18 | 18-Apr-11 | 22-Apr-11 | 4 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Friend South | CE | 12850 | 7076-18 | 16-Sep-11 | 20-Sep-11 | 4 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Table Rock SE | DR 53 | 12853 | 7067-22 | 1/3/2012 | 1/16/2012 | 13 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Stella SE | DR 53 | 12855 | 7074-24 | 12/20/2011 | 12/23/2011 | 3 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Stella SE | SHPO concur req | 12855 | 7074-24 | 7/10/2012 | 7/16/2012 | 6 | letters sent to SHPO and THPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Hickman North | DR 53 | 12859 | 3265-9 | 25-Feb-11 | 01-Mar-11 | 4 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Hickman North | SHPO concur req | 12859 | 3265-9 | 21-Mar-11 | 21-Mar-11 | 0 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Hickman North | Bio doc vers 1 | 12859 | 3265-9 | 13-May-11 | 18-May-11 | 5 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Sterling Southeast | DR 53 | 12860 | 7049-22 | 20-May-11 | 27-May-11 | 7 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Sterling Southeast | SHPO concur request | 12860 | 7049-22 | 11/3/2011 | 11/14/2011 | 11 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Sterling Southeast | Bio doc version 1 | 12860 | 7049-22 | 12/7/2011 | 12/14/2011 | 7 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Sterling Southeast | Cat Ex | 12860 | 7049-22 | 4/17/2012 | 5/8/2012 | 21 | comments sent back to NDOR | NDOR / assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
| Sterling SE Bridge, Johnson County | Congr inq - Noise Analysis | 12860 | 7049-22 | 6/29/2012 | 7/6/2012 | 7 | mm req for info to NDOR on 6/29/12; jaw draft to HQ on 7/6/12. | None |
| Malcolm Souteast | NEPA | 12864 | 7055-102 | 15-Sep-10 | 23-Sep-10 | 8 | rb approved with comments | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| In Seward | Bio doc vers 1 | 12876 | 346-136 | 05-Jan-11 | 07-Jan-11 | 2 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| In Seward | SHPO concur req | 12876 | 346-136 | 24-May-11 | 27-May-11 | 3 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| In Seward | SHPO concur req for 4(f) | 12876 | 346-136 | 6/12/2012 | 6/25/2012 | 13 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Jamacia trail | 4(f) exemp req | 12879 | 55-160 | 22-Apr-10 | 28-Apr-10 | 6 | mm- Raegan asking Allison to check and see if rail line is historic before approval | NDOR / address FHWA comments and resubmit |
| Yutan Trail, Phase 1 | DR 53 | 12881 | 78-27 | 06-Oct-11 | 07-Oct-11 | 1 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Yutan Trail | SHPO concur req | 12881 | 78-27 | 8/2/2012 | 8/16/2012 | 14 | sent email to NDOR requesting verification that scope has not changed since March 2010 consultation. If it hasn't changed, no need to re-consult. mm 8/16/12 | NDOR / address FHWA comments and resubmit |
| Yutan Trail System - Phase 1 | Bio doc version 1 | 12881 | 78-27 | 7/17/2012 | 7/26/2012 | 9 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Blue Rvr Br, Crete | DR 53 | 12886 | 7076-22 | 06-Dec-10 | 15-Dec-10 | 9 | approved with comments | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| 13th St./Blue River Bridge, Crete | SHPO concur req | 12886 | 7076-22 | 6/15/2012 | 6/26/2012 | 11 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Utica - Goehner | DR 53 | 12907 | 808-145 | 14-Mar-11 | 15-Mar-11 | 1 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Super St, I-180 E Ramp | Bio doc vers 1 | 12928 | 5254-8 | 12-Nov-10 | 12-Nov-10 | 0 | rb approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Superior St, I-180 E Ramp Safety | DR 53 | 12928 | 5254-8 | 24-Jan-11 | 31-Jan-11 | 7 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Superior at I-180, Lincoln | SHPO concur req | 12928 | 5254-8 | 29-Mar-11 | 31-Mar-11 | 2 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Superior Street - I-180 East ramp | 4(f) exception concur request | 12928 | 5254-8 | 1/23/2012 | 2/1/2012 | 9 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Superior Street & I-80 East Ramp Safety | Cat Ex | 12928 | 5254-8 | 3/7/2012 | 3/15/2012 | 8 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Humboldt East & West | Bio Doc | 12936 | 47-105 | 26-Apr-11 | 27-Apr-11 | 1 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Humbolt East & West | SHPO concur req | 12936 | 47-105 | 19-Jul-11 | 20-Jul-11 | 1 | ltr to SHPO on 7/21/11. | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| 4th and Corso Overlay | DR53 | 12938 | 06-Dec-10 | 14-Dec-10 | 8 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation | |
| 4th Corso Overlay | Bio doc vers 1 | 12938 | 6217-3 | 24-Jan-11 | 31-Jan-11 | 7 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| 4th Corso, Nebr City | Project Scope Change | 12938 | 6217-3 | 8/2/2012 | 8/9/2012 | 7 | comments sent to NDOR | NDOR / address FHWA comments and resubmit |
| N 14th St, EB On-ramp to US-6 | DR 53 | 12944 | 5227-7 | 2/24/2012 | 3/7/2012 | 12 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Lincoln Rosa Parks Way Trail | NEPA Determ | 12945 | 55-164 | 23-Aug-10 | 02-Sep-10 | 10 | NDOR (or LPA) / Must prepare technical and NEPA documentation | |
| Lincoln West O Historic | DR 53 | 12946 | 5266-2 | 25-Oct-10 | 26-Oct-10 | 1 | rb approved with comments | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Lincoln West O Hist Hwy | Bio doc vers 1 | 12946 | 5266-2 | 23-Dec-10 | 27-Dec-10 | 4 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Lincoln West O St Hist Hwy | SHPO concur req | 12946 | 5266-2 | 05-Jan-11 | 07-Jan-11 | 2 | comments sent to Allison | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Lincoln West O Street | SHPO concur req | 12946 | 5266-2 | 10-Feb-11 | 16-Feb-11 | 6 | original materials were sent for review. Waiting on revised attachments. | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| West O, Lincoln | SHPO concur req | 12946 | 5266-2 | 22-Feb-11 | 22-Feb-11 | 0 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Lincoln West O Street | CE | 12946 | 5266-2 | 1/24/2012 | 2/6/2012 | 13 | comments sent back to NDOR | NDOR / assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
| Lincoln West O Street | Cat Ex | 12946 | 5266-2 | 2/8/2012 | 2/17/2012 | 9 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| us6/n103 roundabout | concur req | 12953 | 66-159 | 16-Sep-10 | 01-Oct-10 | 15 | letter to shpo | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| US-6/N-103 intersection | NEPA determ 1st subm | 12953 | 66-159 | 01-Oct-10 | 04-Oct-10 | 3 | rb approved with comments | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| US-6, N-103 intersection | Bio doc vers 1 | 12953 | 66-159 | 29-Oct-10 | 02-Nov-10 | 4 | rb approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| US-6/N-103 intersec impro | CE | 12953 | 66-159 | 09-Dec-10 | 16-Dec-10 | 7 | comments sent back to Sara | NDOR / address FHWA comments and resubmit |
| US-6/N-103 intersection | NEPA determ 1st subm w Add Info | 12953 | 66-159 | 12-Jan-11 | 27-Jan-11 | 15 | comments sent to NDOR | NDOR / address FHWA comments and resubmit |
| Jct US-6/N-103 intersect | Sum of Alt & Citizn com V-2 | 12953 | 66-159 | 01-Feb-11 | 02-Feb-11 | 1 | approved to be incorporated into CE | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| US-6/N-103 inters impr | CE - revised | 12953 | 66-159 | 07-Feb-11 | 07-Feb-11 | 0 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Otoe Creek Bridge | SHPO Concur req | 12957 | 772-159 | 16-Mar-11 | 16-Mar-11 | 0 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Oak Creek Bridge | Bio doc vers 1 | 12957 | 772-159 | 16-May-11 | 18-May-11 | 2 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Otoe Creek Bridge N | CE | 12957 | 772-159 | 19-Jul-11 | 20-Jul-11 | 1 | comments sent back to NDOR | NDOR / address FHWA comments and resubmit |
| Otoe Creek Bridge N, Jct N-64 | CE subm 2 | 12957 | 772-159 | 26-Jul-11 | 01-Aug-11 | 6 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Goehner - Milford | DR 53 | 12961 | 808-147 | 03-Feb-11 | 03-Feb-11 | 0 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Goehner to Milford | Bio doc vers 1 | 12961 | 808-147 | 07-Mar-11 | 08-Mar-11 | 1 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Goehner - Milford | Reeval Scope Change | 12961 | 808-147 | 19-May-11 | 27-May-11 | 8 | approved, also sent comment to Carin to re-evaluate PCE based on scope change | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Lincoln East | DR 53 | 12975 | 346-141 | 11/29/2011 | 12/5/2011 | 6 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| N-63 to N-50 | DR 53 | 12987 | 347-125 | 11/25/2011 | 12/5/2011 | 10 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Wilber West | Bio doc version 1 | 12990 | 416-113 | 10/25/2011 | 10/28/2011 | 3 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Auburn East | SHPO concur req | 12994 | 1366-119 | 11-Oct-11 | 13-Oct-11 | 2 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Dwight to N-79 | Bio Assessment | 13018 | 666-105 | 12-Jul-10 | 23-Jul-10 | 11 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| N-64 to Schuyler | DR 53 | 13019 | 152-122 | 14-Mar-11 | 15-Mar-11 | 1 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Brock NW | DR 53 | 13024 | 7064-19 | 12-Jul-11 | 19-Jul-11 | 7 | mm signed dr53 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Brock Northwest | Bio doc version 1 | 13024 | 7064-19 | 11/4/2011 | 11/10/2011 | 6 | document signed, letters to go to agencies on Monday 11/14/11. | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Brock NW | SHPO concur req | 13024 | 7064-19 | 7/9/2012 | 7/16/2012 | 7 | letters sent to THPO and SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Ulysses Spur | DR 53 | 13029 | S12C-105 | 12/7/2011 | 12/15/2011 | 8 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Preston North & South | DR 53 | 13031 | 3615-8 | 29-Aug-11 | 06-Sep-11 | 8 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Preston North & South | SHPO concur request | 13031 | 3615-8 | 1/30/2012 | 2/3/2012 | 4 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Preston North & South | 106 Tribal Coord | 13031 | 3615-8 | 1/30/2012 | 2/3/2012 | 4 | letters sent to Tribes | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Preston North and South | CE | 13031 | 3615-8 | 3/29/2012 | 4/23/2012 | 25 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| N-112 - Beatrice | DR 53 | 13034 | 771-130 | 11/15/2011 | 11/23/2011 | 8 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| N-112 - Beatrice | SHPO concur req | 13034 | 771-130 | 7/9/2012 | 7/16/2012 | 7 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Sterling East | DR 53 | 13045 | 417-102 | 11/15/2011 | 11/17/2011 | 2 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Sterling East | SHPO concur request | 13045 | 417-102 | 5/18/2012 | 5/25/2012 | 7 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Nebr. City Steinhart Park Trl | DR 53 | 13055 | 66-34 | 13-Oct-10 | 13-Oct-10 | 0 | rb approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Steinhart Park Trail | Bio Doc vers 1 | 13055 | 66-34 | 20-Dec-10 | 27-Dec-10 | 7 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Steinhart Park Trail Phase II | SHPO Concur req | 13055 | 66-34 | 16-Mar-11 | 16-Mar-11 | 0 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Steinhart Park Trail Phase II | SHPO concur request | 13055 | 66-34 | 5/23/2012 | 6/8/2012 | 16 | comments sent to NDOR | NDOR / address FHWA comments and resubmit |
| Steinhart Park Trail Phase II | SHPO rev; NPS coordination | 13055 | 66-34 | 8/6/2012 | 8/16/2012 | 10 | letters sent to NPS and SHPO today | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Steinhart Trail Phs II | SHPO concur req | 13055 | 66-34 | 7/11/2012 | 7/24/2012 | 13 | comments sent back to NDOR to revise NPS letter to be a 106 consultation letter rather than a 4(f) coordination letter. | NDOR / assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
| Beatrice Homestead Trail | NEPA det form | 13059 | 34-38 | 15-Sep-10 | 23-Sep-10 | 8 | sent back, completed incorrectly | NDOR to address FHWA comments and resubmit |
| Beatrice Homestead Trl | NEPA Determ form | 13059 | 34-38 | 27-Sep-10 | 01-Oct-10 | 4 | rb approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Seward West Trail | SHPO concur req | 13060 | 80-32 | 4/5/2012 | 4/25/2012 | 20 | sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| In Auburn | SHPO concur req | 13062 | 1367-123 | 24-May-11 | 27-May-11 | 3 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Wyuka Stables Restoration | Bio doc vers 1 | 13063 | 55-170 | 04-Aug-11 | 05-Aug-11 | 1 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Wyuka Stable Restoration | SHPO concur req | 13063 | 55-170 | 13-Sep-11 | 16-Sep-11 | 3 | comments sent back to NDOR | NDOR / assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
| Wyuka Stable Restoration | SHPO concur request | 13063 | 55-170 | 10/24/2011 | 11/14/2011 | 21 | comments sent back to NDOR | NDOR / assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
| Wyuka Stable Restoration | Wyuka MOA | 13063 | 55-170 | 12/21/2011 | 1/17/2012 | 27 | Review complete, however waiting on signatures from proejct sponsor and NDOR on the MOA before sending consultation package to SHPO. | NDOR / address FHWA comments and resubmit |
| Wyuka Stables Renovation | Cat Ex | 13063 | 55-170 | 4/10/2012 | 4/27/2012 | 17 | comments sent back to NDOR | NDOR / assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
| Wyuka Stables | Cat Ex - revised | 13063 | 55-170 | 6/12/2012 | 6/14/2012 | 2 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Cavett Connector Trail | DR 53 | 13079 | 55-172 | 10-Jun-11 | 16-Jun-11 | 6 | concurred with CE.mm | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Lincoln Cavett Connector Trail | SHPO concur req | 13079 | 55-172 | 6/11/2012 | 6/26/2012 | 15 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Beatrice Main St Signage | DR 53 | 13080 | 34-39 | 23-Nov-10 | 24-Nov-10 | 1 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Bio doc vers 1 | Beatrice Main Histor Byway Sign | 13080 | 34-39 | 28-Feb-11 | 01-Mar-11 | 1 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Beatrice Main St Hist Byway Sign | SHPO concur req | 13080 | 34-39 | 25-Mar-11 | 31-Mar-11 | 6 | comments sent back to Allison | NDOR / assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
| Beatrice Main St Hist Byway Sign | SHPO concur req | 13080 | 34-39 | 18-Apr-11 | 21-Apr-11 | 3 | comments sent to Allison | NDOR / assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
| Beatrice Main Street Historic Byway Signage | 106 Concur | 13080 | 34-39 | 26-Apr-11 | 27-Apr-11 | 1 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Kansas Line - W Jct N-8 | DR 53 | 13083 | 1121-103 | 11/15/2011 | 11/17/2011 | 2 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Furnas St - Silver St, Ashland | DR 53 | 13084 | 666-107 | 11/28/2011 | 12/5/2011 | 7 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Furnas St - Silver St, Ashland | SHPO concur req | 13084 | 666-107 | 7/2/2012 | 7/13/2012 | 11 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Beatrice Wide Resurf. | DR 53 | 13086 | 6108-1 | 06-Dec-10 | 15-Dec-10 | 9 | sent comments back to Allison | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Beatrice Citywide resurf | DR 53 | 13086 | 6108-1 | 18-Jan-11 | 31-Jan-11 | 13 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Beatrice City Wide Resurfacing | Bio doc vers 1 | 13086 | 6108-1 | 10/27/2011 | 10/28/2011 | 1 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Beatrice City Wide Resurfacing | SHPO concur request | 13086 | 6108-1 | 11/30/2011 | 11/30/2011 | 0 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| N-15 west | bio doc | 13087 | 86(114) | 16-Sep-10 | 23-Sep-10 | 7 | NDOR / address FHWA comments and resubmit | |
| S. Jct. N-15 West | Bio doc | 13087 | 86-114 | 17-Sep-10 | 23-Sep-10 | 6 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| BNSF/Middle Creek | SHPO Concur Req | 13089 | 772-161 | 11-Jul-11 | 11-Jul-11 | 0 | mm asked for a fix to scope of work, got it and sent out today | NDOR / address FHWA comments and resubmit |
| BNSF-Middle Creek, Lincoln | Bio doc version 1 | 13089 | 772-161 | 2/3/2012 | 2/17/2012 | 14 | letters sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| US-6/SW 40th Street | SHPO Concur Req | 13093 | 66-161 | 12-Jan-11 | 31-Jan-11 | 19 | letter sent to shpo | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Nemaha - E. Jct. US-136 | DR 53 | 13094 | 671-117 | 12/15/2011 | 12/20/2011 | 5 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| W. Jct. US-136 - Peru Spur | DR 53 | 13095 | 671-118 | 4/5/2012 | 4/26/2012 | 21 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Lincoln Citywide Durable | Bio doc version 1 | 13096 | 5239-8 | 16-Jun-10 | 21-Jun-10 | 5 | BA approved, letters to USFWS and NGPC to go out for concurrence | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| OA 50 Challenge proj | Bio doc version 1 | 13097 | 5221-3 | 18-Jun-10 | 21-Jun-10 | 3 | bio doc approved, letters going to NGPC and USFWS for concurrence | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Seward North | DR 53 | 13099 | 152-121 | 18-Apr-11 | 21-Apr-11 | 3 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Goehner West | Bio doc vers 1 | 13107 | 808-149 | 02-Nov-10 | 02-Nov-10 | 0 | rb approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Milford to Airpark | DR 53 | 13108 | 808-515 | 04-Apr-11 | 11-Apr-11 | 7 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Milford - Air Park | Bio doc vers 1 | 13108 | 808-515 | 08-Apr-11 | 12-Apr-11 | 4 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Airpark W-Jct, US-77 Lincoln | PCA | 13113 | 809-58 | 02-Feb-11 | 02-Feb-11 | 0 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Airpark W, Jct US-77 | Bio doc vers 1 | 13113 | 809-58 | 01-Mar-11 | 02-Mar-11 | 1 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Nebraska City North | DR 53 | 13123 | 752-171 | 28-Jul-11 | 03-Aug-11 | 6 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Beatrice Museum and 2nd St Historical Preservation | DR-53 | 13127 | 6105-6 | 15-Sep-10 | 22-Sep-10 | 7 | sent back, missing suggested level of NEPA | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| 2nd St-Court to Ella, Beatrice | SHPO concur req | 13127 | 6105-6 | 26-Aug-11 | 14-Sep-11 | 19 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| 2nd St, Court to Ella, Beatrice | Bio doc version 1 | 13127 | 6105-6 | 10/31/2011 | 11/2/2011 | 2 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Court to Ella, Beatrice | 4(f) | 13127 | 6105-6 | 2/1/2012 | 2/14/2012 | 13 | comments sent back to NDOR | NDOR / address FHWA comments and resubmit |
| 2nd St, Court - Ella | 4(f) exception comments | 13127 | 6105-6 | 2/29/2012 | 3/8/2012 | 8 | 4(f) exception approved, no addtional 4(f) coordination needed. | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| 2nd Street, Court - Ella | Cat Ex | 13127 | 6105-6 | 6/27/2012 | 7/2/2012 | 5 | comments sent back to NDOR; change in scope, need to reconsult with SHPO | NDOR / address FHWA comments and resubmit |
| Alvo - I-80 | Bio doc vers 1 | 13131 | 632-115 | 28-Sep-10 | 01-Oct-10 | 3 | rb approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Hickman Road Trl Connect | DR 53 | 13134 | 55-174 | 18-Jan-11 | 31-Jan-11 | 13 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Seward East Bridges | DR 53 | 13136 | 808-153 | 06-Jul-11 | 11-Jul-11 | 5 | concurred | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| 27th & Leighton Viad. | DR 53 | 13137 | 5231-13 | 11-Nov-10 | 12-Nov-10 | 1 | rb approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| 27th & Leighton Viad Rehab | Bio doc vers 1 | 13137 | 5231-13 | 17-Oct-11 | 18-Oct-11 | 1 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| 27th & Leighton Viaduct Rehabilitation | SHPO concur request | 13137 | 5231-13 | 12/7/2011 | 12/9/2011 | 2 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Lincoln Citywd resurf. | DR 53 | 13138 | 5228-4 | 11-Nov-10 | 12-Nov-10 | 1 | rb approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Lincoln Citywide Resurfacing | SHPO concur request | 13138 | 5228-4 | 1/6/2012 | 1/17/2012 | 11 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Lincoln City Street Resurfacing | Bio doc version 1 | 13138 | 5228-4 | 2/22/2012 | 3/8/2012 | 15 | letters sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Lincoln Citywide Resurfacing | Cat Ex | 13138 | 5228-4 | 6/7/2012 | 6/12/2012 | 5 | comments sent back to NDOR | NDOR / assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
| Lincoln Citywide Resurfacing | Cat Ex - version 2 | 13138 | 5228-4 | 8/3/2012 | 8/3/2012 | 0 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Lincoln Microsurfacing | DR 53 | 13139 | 5249-7 | 09-Nov-10 | 12-Nov-10 | 3 | rb approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Lincoln Streets Microsurf | Bio doc vers 1 | 13139 | 5249-7 | 05-Jan-11 | 06-Jan-11 | 1 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Lincoln Downtown Resurf | DR 53 | 13140 | 5230-2 | 04-Nov-10 | 08-Nov-10 | 4 | rb approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Lincoln Dwntwn Str Resurf | Bio doc vers 1 | 13140 | 5230-2 | 05-Jan-11 | 06-Jan-11 | 1 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| 56th, Shadow Pines - Old Cheney | NEPA memo | 13141 | 5241-5 | 25-Mar-11 | 28-Mar-11 | 3 | mm-the request to FHWA didn't make sense, sent questions back to NDOR concluding the review | NDOR / address FHWA comments and resubmit |
| South 56th, Shadow Pines to Old Cheney | SHPO concur request | 13141 | 5241-5 | 5/4/2012 | 5/9/2012 | 5 | comments sent back to NDOR | NDOR / address FHWA comments and resubmit |
| South 56th, Shadow Pines to Old Cheney | SHPO concur req - revised | 13141 | 5241-5 | 6/28/2012 | 7/2/2012 | 4 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Wahoo Northwest | DR 53 | 13143 | 78-30 | 09-Jun-11 | 16-Jun-11 | 7 | mm sent back- not enough info to understand what the proposal is | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Brock N Brdg Repair | DR 53 | 13145 | ER 3675-7 | 27-Dec-10 | 06-Jan-11 | 10 | signed by Nemaha Co representative 10/28/10. Approved by NDOR 12/27/10 and emailed to FHWA. 1/6/11, FHWA approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| NE Butler Co Brg Repair | DR 53 | 13146 | ER 3020-1 | 27-Dec-10 | 06-Jan-11 | 10 | signed by Butler Co 12/6/10, approved by NDOR 12/27/10. approved by FHWA 1/6/10 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| S. Coddington Ave. W. Van Dorn St. | DR 53 | 13147 | 5205-1 | 12-Jan-11 | 27-Jan-11 | 15 | approved with comments | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Diller/Odell Elem Sch SRTS | DR 53 | 13153 | 48-24 | 09-Jun-11 | 16-Jun-11 | 7 | mm approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| 3 Sites in Otoe County | DR 53 | 13154 | ER 3680-7 | 30-Sep-11 | 30-Sep-11 | 0 | when submitted by NDOR 1st time, sent back because 2008 event not an accepted event yet, hadn't hit cost thresholds. In Sept, FHWA pulled up old doc and approved, to save NDOR step of re-submitting | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| 4th Corso Viad, NE City | DR 53 | 13159 | 6217-4 | 09-Jun-11 | 16-Jun-11 | 7 | proponent needs to hold early scoping so we can determine NEPA level.mm | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Seward West Trail | DR 53 | 13160 | 80-32 | 18-Jan-11 | 31-Jan-11 | 13 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Karol Kay Blvd Extension | DR 53 | 13161 | 6763-1 | 11/30/2011 | 12/5/2011 | 5 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| N-2, 56th - 84th | Bio Doc V1 | 13164 | 26-122 | 21-Jul-11 | 29-Jul-11 | 8 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| N-2, 56th - 84th, Lincoln | DR 53 | 13164 | 26-122 | 03-Aug-11 | 05-Aug-11 | 2 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| North Jct N-15 West | DR 53 | 13166 | 416-114 | 05-May-11 | 11-May-11 | 6 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| North Jct N-15 West | Bio Doc V1 | 13166 | 416-114 | 21-Jul-11 | 29-Jul-11 | 8 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| N-4 to Wilber | DR 53 | 13168 | 1031-110 | 30-Aug-11 | 06-Sep-11 | 7 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| N-4 - Wilber | Bio doc vers 1 | 13168 | 1031-110 | 11/18/2011 | 11/23/2011 | 5 | sent comment back to NDOR. | NDOR / address FHWA comments and resubmit |
| N-4 - Wilber | Bio doc vers 2 | 13168 | 1031-110 | 12/2/2011 | 12/6/2011 | 4 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Cornhusker - S Jct US-34 | DR 53 | 13173 | 1809-2 | 11/15/2011 | 11/23/2011 | 8 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Prague South | DR 53 | 13175 | 78-31 | 18-Jul-11 | 20-Jul-11 | 2 | approved. | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Crete Elem BOLTAGE Prgm | DR 53 | 13176 | 76-47 | 02-Sep-11 | 08-Sep-11 | 6 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Lets All Pedal to Prescott, Lincoln | DR 53 | 13187 | 55-176 | 10/18/2011 | 10/28/2011 | 10 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Salt Creek Bridge, Lincoln | DR 53 | 13194 | L55X-103 | 2/9/2012 | 2/17/2012 | 8 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Salt Creek Bridge, Lincoln | SHPO concur request | 13194 | L55X-103 | 4/25/2012 | 4/27/2012 | 2 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Bruno Spur Bridges | DR 53 | 13197 | S12B-106 | 8/2/2012 | 8/16/2012 | 14 | NDOR (or LPA) / Must prepare technical and NEPA documentation | |
| Water Park to Hannibal Park Trail, Beatrice | DR 53 | 13212 | 34-42 | 3/8/2012 | 4/5/2012 | 28 | NDOR (or LPA) / Must prepare technical and NEPA documentation | |
| Beatrice Water Park to Hannibal Park Trail | SHPO concur req | 13212 | 34-42 | 7/12/2012 | 7/24/2012 | 12 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Lincoln Stonebridge Trail | DR 53 | 13213 | 55-177 | 3/26/2012 | 4/6/2012 | 11 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Tecumseh Historic Square | DR 53 | 13214 | 49-46 | 3/29/2012 | 4/6/2012 | 8 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Swan Creek Bridge, South of Western | DR 53 | 13221 | 151-116 | 7/27/2012 | 8/14/2012 | 18 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Seward Trail | DR 53 | 13255 | 80-33 | 8/6/2012 | 8/16/2012 | 10 | NDOR (or LPA) / Must prepare technical and NEPA documentation | |
| N-36 North, Omaha | Bio doc vers 1 | 21791 | 1333-102 | 14-Jan-11 | 31-Jan-11 | 17 | mmapproved bio contingent on NEPA questions answered | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| US-75, Plattsmouth - Bellevue | re-eval ESA | 21849 | 752-155 | 28-May-10 | 01-Jun-10 | 4 | Sent out to USFWS and NGPC for concurrence | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| US-75, Plattsmouth to Bellevue | Re-evaluation | 21849 | 752-155 | 21-Jul-10 | 23-Jul-10 | 2 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| US 275 Stockyards | DR 53 | 21853 | 2757-180 | 17-Oct-11 | 18-Oct-11 | 1 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| US-275/Stockyards, Omaha | SHPO concur request | 21853 | 2757-180 | 1/11/2012 | 1/17/2012 | 6 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| US-275/Stockyards, Omaha | Bio doc version 1 | 21853 | 2757-180 | 1/13/2012 | 1/17/2012 | 4 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| US 275 Omaha Stock Yards | Hazmat review | 21853 | 2757-180 | 7/5/2012 | 7/11/2012 | 6 | emailed comments to NDOR | NDOR / address FHWA comments and resubmit |
| US-275/Stockyards, Omaha | Cat Ex | 21853 | 2757-180 | 8/8/2012 | 8/13/2012 | 5 | sent comments back to NDOR | NDOR / address FHWA comments and resubmit |
| US-275/Omaha Stockyards | HazMat Review - update | 21853 | 2757-180 | 8/2/2012 | 8/7/2012 | 5 | sent comments back to NDOR. Need to obtain EPA and NDEQ concurrence. | NDOR / address FHWA comments and resubmit |
| US-275, Omaha Stock Yards | Hazmat memo review | 21853 | 2757-180 | 7/16/2012 | 7/18/2012 | 2 | NDOR has decided to conduct testing for this project. A revised report will be sent once testing is completed. | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Elkhorn North | DR 53 | 21911 | 312-110 | 6/15/2012 | 6/26/2012 | 11 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Elkhorn North | SHPO and THPO concur req | 21911 | 312-110 | 6/26/2012 | 6/27/2012 | 1 | letter sent to SHPO & THPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Bell St Viad, Fremont | Reeval Form | 21953 | 5625-2 | 23-Sep-10 | 01-Oct-10 | 8 | rb approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Blair West | DR 53 | 22026 | 7089-23 | 15-Dec-10 | 17-Dec-10 | 2 | approved with comments | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Blair West | Bio doc vers 1 | 22026 | 7089-23 | 15-Apr-11 | 21-Apr-11 | 6 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Blair West | SHPO concur req | 22026 | 7089-23 | 25-Apr-11 | 25-Apr-11 | 0 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Blair West | CE | 22026 | 7089-23 | 19-Aug-11 | 03-Sep-11 | 15 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Hooper North | DR 53 | 22052 | 3495-3 | 23-Sep-11 | 26-Sep-11 | 3 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Hooper North | SHPO concur request | 22052 | 3495-2 | 1/26/2012 | 2/3/2012 | 8 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Hooper North | Bio doc version 1 | 22052 | 3495-3 | 2/15/2012 | 2/17/2012 | 2 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Hooper North | CE 1st review | 22052 | 3495(3) | 5/18/2012 | 6/1/2012 | 14 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required | |
| Blair Bypass | P/N Chapter | 22075 | 89(17) | 27-Jun-11 | 29-Jun-11 | 2 | mm told Blair would take a prelim review. Sent back comments | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Blair Bypass | Bio doc version 1 | 22075 | 89-17 | 4/12/2012 | 4/23/2012 | 11 | BA missed a few species listed in the county, didn't properly assess indirect water quality impacts to the Missouri (fish spp), and needed committment to survey for ginseng (previous survey over 6 yrs old and construction for some phases won't occur for y | NDOR / address FHWA comments and resubmit |
| Blair Bypass | SHPO concur request | 22075 | 89-17 | 4/12/2012 | 5/7/2012 | 25 | comments sent back to NDOR | NDOR / assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
| Blair Bypass | Bio doc - version 2 | 22075 | 89-17 | 6/7/2012 | 6/12/2012 | 5 | comment sent back to NDOR | NDOR / address FHWA comments and resubmit |
| Blair Bypass | SHPO THPO concur req revised | 22075 | 89-17 | 6/22/2012 | 6/25/2012 | 3 | letters sent to NDOR to send to SHPO and THPOs (attachments were too large to print from FHWA). | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Blair Bypass | Bio doc - version 3 | 22075 | 89-17 | 6/25/2012 | 7/2/2012 | 7 | comments sent back to NDOR | NDOR / address FHWA comments and resubmit |
| Blair Bypass | Bio doc - version 4 | 22075 | 89-17 | 7/3/2012 | 7/13/2012 | 10 | sent letters to USFWS and NGPC | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Blair Bypass | 106 Non-Conur Resp Req | 22075 | 89-17 | 8/15/2012 | 8/15/2012 | 0 | Hardcopy to Raegan. noted that additional consultation will be required in the future for the project, once access is granted to survey Cargill. review finished.mm | None |
| Blair Bypass | draft EIS | 22075 | 89-17 | 6/29/2012 | 7/27/2012 | 28 | Comments to Raegan by 7/27. You have this doc on your desk. | None |
| Fremont West | Bio doc vers 1 | 22097 | 3460-4 | 01-Dec-10 | 10-Dec-10 | 9 | letters sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Fremont West | DR 53 | 22097 | 3460-4 | 15-Dec-10 | 17-Dec-10 | 2 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Westbound I-80 Expansion | SHPO Concur | 22143 | 809-897 | 13-Sep-10 | 13-Sep-10 | 0 | mm 9/13/10 sent email to NDOR asking status of NEPA - we've never been coordinated with regarding this interstate widening in Omaha, but they're asking us to consult under 106 right now | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Westbound I-80 expansion | SHPO concur req | 22143 | 809-897 | 20-Sep-11 | 26-Sep-11 | 6 | comments sent back to NDOR | NDOR / assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
| WB I-80 Expansion | SHPO concur req | 22143 | 809-897 | 26-Sep-11 | 26-Sep-11 | 0 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| I-80, Omaha | DR 53 | 22150 | 809-901 | 19-Apr-11 | 26-Apr-11 | 7 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| #NAME? | DR 53 | 22162 | 6809-910 | 27-Jul-11 | 03-Aug-11 | 7 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| I-680 NB Lanes | SHPO concur req | 22162 | 6809-910 | 15-Sep-11 | 16-Sep-11 | 1 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Fremont viaducts | Draft EA | 22177 | 5616-1 | 04-Jan-11 | 28-Jan-11 | 24 | comments sent back to NDOR | NDOR / assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
| 23rd Street Viaduct, Fremont | SHPO concur req | 22177 | 5616-1 | 6/18/2012 | 7/13/2012 | 25 | comments sent back to NDOR | NDOR / assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
| Ruff Road to Millard | DR 53 | 22201 | 809-63 | 27-Jul-11 | 03-Aug-11 | 7 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Ruff Road - Millard | Bio doc version 1 | 22201 | 809-63 | 12/29/2011 | 1/3/2012 | 5 | letters sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| 144th St West Dodge, Omaha | ERRATA FONSI Approval Req | 22202 | 5001-15 | 21-Dec-10 | 21-Dec-10 | 0 | comment sent back to Allison | NDOR / assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
| 144th W Dodge to Eagle Run | ERRATA doc | 22202 | 5001-15 | 22-Dec-10 | 11-Jan-11 | 20 | sent back comments to Allison | NDOR / assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
| 144th, et al, Omaha | 404 b 1 analysis | 22202 | 5001-15 | 10-Feb-11 | 15-Feb-11 | 5 | needs to be included in FEA submittal | NDOR / assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
| 144th & Blondo, Omaha | Errata | 22202 | 5001-15 | 03-Mar-11 | 08-Mar-11 | 5 | Discussed comments with Jon B. Consultant revising mitigaiton measures and 2035 LRTP wording. | NDOR / assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
| 144th & Blondo | Errata Doc - final | 22202 | 5001-15 | 09-Mar-11 | 09-Mar-11 | 0 | FEA signed; FONSI issued. | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| 144th & Blondo | Wetland Mit memo | 22202 | 5001-15 | 13-Oct-11 | 17-Oct-11 | 4 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Bennington South | DR 53 | 22221 | 3805-4 | 16-Jun-11 | 23-Jun-11 | 7 | signed, added comment to talk w TE eligibility/need for added grading | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Bennington South | SHPO concur request | 22221 | 3805-4 | 12/1/2011 | 12/8/2011 | 7 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| WDCT - Valley to YMCA, Ph 1 | DR 53 | 22227 | 28-87 | 09-Jun-11 | 10-Jun-11 | 1 | approved, to be combined with 28-102 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Western Douglas County Trail | Sect 4(f) Eval | 22227 | 28-87 | 6/6/2012 | 6/14/2012 | 8 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| 156th St Improvements | Purpose and Need review | 22233 | 3805-5 | 8/6/2012 | 8/16/2012 | 10 | provided comments that the radii issue needs a bit more work but to carry forward with the process | None |
| N 96th St. Bridge | DR 53 | 22235 | 7028-47 | 3/28/2012 | 4/6/2012 | 9 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| 144th - Pierce Pl to Burke St | Bio doc vers 1 | 22236 | 5011-8 | 01-Feb-11 | 02-Feb-11 | 1 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Pierce Plaza - Burke St | SHPO concur req | 22236 | 5011-8 | 21-Mar-11 | 21-Mar-11 | 0 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| 114th St, Pierce Plaza to Burke St. | two 4(f) except requests | 22236 | 5011-8 | 16-Jun-11 | 23-Jun-11 | 7 | accepted one, rejected other, QA/QC problem led to inconsistent statements in doc. Mm | NDOR / address FHWA comments and resubmit |
| Pierce Plaza to Burke Street | 4f exception request | 22236 | 5011-8 | 11-Jul-11 | 20-Jul-11 | 9 | comments sent back to NDOR | NDOR / address FHWA comments and resubmit |
| 108th, Madison to Q | NEPA Action Memo | 22237 | 5011-9 | 10-Nov-10 | 12-Nov-10 | 2 | rb sent comments to Alllison Zach | NDOR / assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
| 108th, Madison - Q | 4(f) and NEPA action | 22237 | 5011-9 | 29-Dec-10 | 10-Jan-11 | 12 | 4(f) letter ok to go to City parks dept. Can't concur with rest of request until all pieces requested on DR53 are completed and submitted. Comments regarding this sent to Allison. | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| 108th, Madison - Q, Omaha | 4(f) and CE Memo req | 22237 | 5011-9 | 22-Feb-11 | 01-Mar-11 | 7 | 4(f) memo approved, NEPA Det still an EA | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Missouri River Trail | letter to ACHP with MOA | 22252 | 28(89) | 16-Aug-10 | 19-Aug-10 | 3 | need to send the ACHP copy of executed MOA | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Mo River Trail phs 2 | Data revovery plan | 22252 | 28-89 | 19-Aug-10 | 26-Aug-10 | 7 | requested meeting to discuss comments | NDOR / assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
| Missouri River Trail Phase 2 | NEPA CE | 22252 | 28-89 | 25-Aug-10 | 27-Aug-10 | 2 | sent email requesting meeting to discuss comments. Meeting on 9/1 at NDOR. | NDOR / assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
| Missouri Rvr Trl, Phase 2 | Section 106 doc | 22252 | 28-89 | 26-Oct-10 | 27-Oct-10 | 1 | letter to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Fremont - Winslow | DR 53 | 22256 | 773-130 | 06-Apr-11 | 12-Apr-11 | 6 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Frermont - Winslow | Bio doc version one | 22256 | 773-130 | 12/19/2011 | 12/22/2011 | 3 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Bennington SE | Bio doc vers 1 | 22258 | 3806-1 | 20-Sep-10 | 29-Sep-10 | 9 | rb approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Fort Street - Missouori River | DR 53 | 22264 | 6809-29 | 11/22/2011 | 11/28/2011 | 6 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Fort Street - Missouri River | SHPO concur request | 22264 | 6809-29 | 2/9/2012 | 2/14/2012 | 5 | " | |
| letter sent to SHPO" | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA | |||||||
| Fremont South Bridge | Temp Occ Monnich Letter | 22265 | 773-128 | 11-Mar-10 | 11-Mar-10 | 0 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. | |
| Fremont Bridge | 1st draft DEA | 22265 | 773-128 | 09-Mar-10 | 16-Mar-10 | 7 | NDOR / address FHWA comments and resubmit | |
| Freemont South Bridge | Eff Determ Pkg v2 | 22265 | 773-128 | 25-Mar-10 | 25-Mar-10 | 0 | sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Fremont South | additl info; bio memo | 22265 | 24-Apr-10 | 01-May-10 | 7 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, | ||
| Fremont Bridge | FEA-Errata, DEA | 22265 | 773-128 | 20-Jul-10 | 21-Jul-10 | 1 | sent comments to NDOR | NDOR / address FHWA comments and resubmit |
| Fremont South Bridge | FEA/Errata - FONSI Rec | 22265 | 773-128 | 27-Jul-10 | 11-Aug-10 | 15 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Fremont South Bridge | Final EA Approval | 22265 | 773-128 | 30-Jul-10 | 11-Aug-10 | 12 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Rumsey Station SRTS | Bio doc vers 1 | 22270 | 77-53 | 23-Nov-10 | 23-Nov-10 | 0 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Rumsey Station SRTS | DR 53 | 22270 | 77-53 | 23-Nov-10 | 24-Nov-10 | 1 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Papillion-Rumsey Sta School | SHPO concur req | 22270 | 77-53 | 07-Dec-10 | 10-Dec-10 | 3 | letter to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| 36th Street Improvements | P&N review | 22276 | 5061-5 | 01-Apr-11 | 04-Apr-11 | 3 | no comments | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| 36th ST Bellevue | NEPA Merge concurrence point 2 package | 22276 | 5061(5) | 5/2/2012 | 5/10/2012 | 8 | letters will go out to agencies tomorrow | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| 120th St, Stonegate to Roanoke | Bio doc vers 1 | 22277 | 5009-3 | 19-Nov-10 | 24-Nov-10 | 5 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Stonegate Dr to Roanoke Blvd | SHPO concur req | 22277 | 5009-3 | 07-Dec-10 | 10-Dec-10 | 3 | comments sent back to Allison | NDOR / address FHWA comments and resubmit |
| Stonegate Dr -Roanoke | SHPO concur req | 22277 | 5099-3 | 14-Dec-10 | 17-Dec-10 | 3 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| 120th, Stonegate to Roanoke | Purp & Need | 22277 | 5009-3 | 28-Dec-10 | 04-Jan-11 | 7 | approved with comments | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Inters Sorensen Prk & N Frwy | DR 53 | 22278 | 5114-6 | 15-Dec-10 | 17-Dec-10 | 2 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Intersect Sorensen Parkwy & N Freeway | Bio doc vers 1 | 22278 | 5114-6 | 26-May-11 | 27-May-11 | 1 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Intersection of Sorensen Parkway and North Freeway | SHPO Concur Req | 22278 | 5114-6 | 22-Jul-11 | 26-Jul-11 | 4 | mm approved letter 7/26, with front office for formatting/submission | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Sorensen Parkway & North Freeway | CE | 22278 | 5114-6 | 11/29/2011 | 12/5/2011 | 6 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| 42nd & Q | Purpose & Need | 22279 | 5057-9 | 18-Oct-10 | 20-Oct-10 | 2 | comments sent back to Allison | NDOR / assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
| 42nd & Q, Omaha | Purp and Need | 22279 | 5058-9 | 22-Oct-10 | 26-Oct-10 | 4 | rb approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| 42nd & Q Brdg & Intersec | Bio doc vers 1 | 22279 | 5057-9 | 01-Feb-11 | 02-Feb-11 | 1 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| 42nd & Q, Omaha | SHPO concur req | 22279 | 5057-9 | 19-May-11 | 27-May-11 | 8 | comments sent back to Allison | NDOR / address FHWA comments and resubmit |
| 42nd & Q, Omaha | SHPO concur req | 22279 | 5057-9 | 18-Jul-11 | 20-Jul-11 | 2 | comments sent back to NDOR | NDOR / address FHWA comments and resubmit |
| 42nd & Q | SHPO Concur Req V3 | 22279 | 5057-9 | 21-Jul-11 | 22-Jul-11 | 1 | Package sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| 42nd & Q Intersection, Omaha | Section 4(f) | 22279 | 5057-9 | 02-Sep-11 | 15-Sep-11 | 13 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| 42nd and Q | SHPO effects concurrence letter | 22279 | 5057-9 | 12/20/2011 | 12/21/2011 | 1 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| 42nd & Q, Omaha | draft EA Chapter 1-3 Final | 22279 | 5057-9 | 12/30/2011 | 1/11/2012 | 12 | Reviewed by 4 Division members; delivered comments to NDOR, City and consultant on 1/12/12 at meeting | NDOR / address FHWA comments and resubmit |
| 42nd & Q, Omaha | draft EA | 22279 | 5057-9 | 3/14/2012 | 3/28/2012 | 14 | NDOR / assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA | |
| 42nd & Q Bridge Replacement | Hazmat coord letters | 22279 | 5057-9 | 4/17/2012 | 4/19/2012 | 2 | NDOR / address FHWA comments and resubmit | |
| 42nd & Q Bridge Replacement | HazMat memos review request | 22279 | 5057-9 | 4/26/2012 | 4/26/2012 | 0 | follow-up questions sent to the City for outstanding items. Need those items before letter can be sent to the agencies. | NDOR / assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
| 42nd & Q | DEA - revised | 22279 | 5057-9 | 8/7/2012 | 8/16/2012 | 9 | ready for official signatures once the hard copies are provided. | NDOR / address FHWA comments and resubmit |
| 42nd & Q | draft EA Revisions | 22279 | 5057-9 | 7/9/2012 | 7/23/2012 | 14 | comments sent to NDOR | NDOR / assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
| Intersec 132 & W Giles Rd | DR 53 | 22283 | 5005-1 | 11-Nov-10 | 12-Nov-10 | 1 | rb approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| F St. Bridge | DR 53 | 22284 | 5028-4 | 3/27/2012 | 4/6/2012 | 10 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Washington St Reconstr | Bio doc vers 1 | 22290 | 5023-14 | 05-Apr-11 | 07-Apr-11 | 2 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Washington St, Papillion | SHPO concur req | 22290 | 5023-14 | 05-Apr-11 | 07-Apr-11 | 2 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Washington St, Caphard to Cedardale Rd | CE Form concurrent review | 22290 | 5023-14 | 31-May-11 | 06-Jun-11 | 6 | sent comments back to Jon | NDOR / assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
| Washington St. | CE v2 | 22290 | 5023-14 | 20-Jun-11 | 23-Jun-11 | 3 | mm told NDOR to submit the next version, with sigs, for final review/approval | NDOR / assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
| Washington St, Capehard to Cedardale Rd | CE - Version 3 | 22290 | 5023-14 | 27-Jun-11 | 28-Jun-11 | 1 | mm approved doc after comparing to rb comments on last version | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Bennington Papio Creek Bridge and Trail | DR 53 | 22307 | 28-90 | 23-Sep-11 | 26-Sep-11 | 3 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Papillion Midland Creek Trl | SHPO concur req | 22309 | 77-55 | 02-Sep-11 | 06-Sep-11 | 4 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Papillion Midland Creek Trail | Bio Doc | 22309 | 77-55 | 30-Sep-11 | 30-Sep-11 | 0 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Papillion Midland Trail | 4(f) exemption request | 22309 | 77-55 | 11/15/2011 | 11/15/2011 | 0 | Request came directly to FHWA from the City. Emailed the request to NDOR so document can go through standard review procedures (NDOR reviews and approves prior to submitting to FHWA). | NDOR / address FHWA comments and resubmit |
| Papillion Midland Creek Trail | CE | 22309 | 77-55 | 1/6/2012 | 1/16/2012 | 10 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Springfield Trail Project | 4(f) PA Memo | 22310 | 77-56 | 23-Aug-10 | 08-Sep-10 | 16 | rb sent comments to allison | NDOR / address FHWA comments and resubmit |
| Springfied Trail | 4(f) #2 | 22310 | 77(56) | 13-Sep-10 | 23-Sep-10 | 10 | comments | NDOR / address FHWA comments and resubmit |
| Springfield Trail | 4-f Memo | 22310 | 77-56 | 04-Oct-10 | 12-Oct-10 | 8 | rb approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Springfield Trail Phase III | SHPO concur request | 22310 | 77-56 | 04-Nov-10 | 08-Nov-10 | 4 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Springfield Trl - Phase III | Bio doc vers 1 | 22310 | 77-56 | 18-Nov-10 | 23-Nov-10 | 5 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Springfield Trl Phs 3 | DR 53 | 22310 | 77-56 | 15-Dec-10 | 17-Dec-10 | 2 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Springfield Trail, Ph 3 | Reeval Memo | 22310 | 77-56 | 05-May-11 | 11-May-11 | 6 | approved | NDOR / address FHWA comments and resubmit |
| Springfield Trail | 106 reeval | 22310 | 77-56 | 09-May-11 | 13-May-11 | 4 | comments sent to Allison | NDOR / address FHWA comments and resubmit |
| Springfield Trail | 106 Concur Letter | 22310 | 77-56 | 20-May-11 | 27-May-11 | 7 | sent comments back to Allison | NDOR / address FHWA comments and resubmit |
| Springfield Trl, Phase 3 | SHPO concur req | 22310 | 77-56 | 30-Jun-11 | 01-Jul-11 | 1 | mm approved, gave to front office to format/mail 7/1 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Springfield Trail | 4(f) reeval memo | 22310 | 77-56 | 13-Sep-11 | 16-Sep-11 | 3 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| City of Springfield | CE | 22310 | 77-56 | 12/19/2011 | 12/23/2011 | 4 | comment sent back to NDOR to address. | NDOR / assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
| City of Springfield | CE - 2nd | 22310 | 77-56 | 1/12/2012 | 1/16/2012 | 4 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| 4th Ave: 16th-Hillcrest | DR 53 | 22313 | 6404-1 | 01-Oct-10 | 04-Oct-10 | 3 | rb approved with comments | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| In Plattsmouth | 106 Concur Req | 22313 | 6404-1 | 4/2/2012 | 4/25/2012 | 23 | sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| In Plattsmouth | 4(f) exception | 22313 | 6404-1 | 7/26/2012 | 8/14/2012 | 19 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Omaha McMillan Magnet Middle School - infras. | DR 53 | 22321 | 28-93 | 19-Aug-11 | 03-Sep-11 | 15 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Q St Bridge repl, Omaha | DR 53 | 22325 | 5026-11 | 18-Jan-11 | 31-Jan-11 | 13 | mm sent back- recommended level of NEPA missing from document | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Q St Br repla, 26 - 27th, Omaha | DR 53 | 22325 | 5026-11 | 02-Feb-11 | 02-Feb-11 | 0 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Q St Bridge, 26th - 27th | Bio doc vers 1 | 22325 | 5026-11 | 07-Oct-11 | 07-Oct-11 | 0 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Q Street Bridge Replacement | SHPO THPO concur req | 22325 | 5026-11 | 8/9/2012 | 8/16/2012 | 7 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA | |
| Inters N-133 & N-64 | Bio doc vers 1 | 22336 | 1332-112 | 22-Sep-10 | 01-Oct-10 | 9 | rb approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Intersec N-133 & N-64 | DR 53 | 22336 | 1332-112 | 11-Feb-11 | 16-Feb-11 | 5 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Intersection N-133 (90th & Maple) | Variance approval | 22336 | 1332-112 | 11/9/2011 | 11/10/2011 | 1 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Colfax-Dodge Co Line East | DR 53 | 22338 | 306-134 | 25-Oct-10 | 26-Oct-10 | 1 | rb approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Fort Calhoun SW - 2 sites | DR 53 | 22341 | 89-25 | 16-Feb-11 | 22-Feb-11 | 6 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Fort Calhoun SW | SHPO concur request | 22341 | 89-25 | 10/28/2011 | 10/28/2011 | 0 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Fort Calhoun Southwest - 2 sites | Bio doc version 1 | 22341 | 89-25 | 12/29/2011 | 1/3/2012 | 5 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Ft. Calhoun SW | Cat Ex | 22341 | 89-25 | 3/16/2012 | 4/20/2012 | 35 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required | |
| 10th St Brdg, Omaha | SHPO concur req | 22352 | 5103-14 | 14-Dec-10 | 17-Dec-10 | 3 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| 10th St Bridge, Omaha | DR 53 | 22353 | 5013-4 | 10-Nov-10 | 12-Nov-10 | 2 | rb approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| 10th St. Brdg Widen | Bio doc vers 1 | 22353 | 5103-14 | 30-Dec-10 | 06-Jan-11 | 7 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| 10th St. Brg. Widening | 4(f) concur req review | 22353 | 5013-14 | 16-Mar-11 | 16-Mar-11 | 0 | comments sent to Allison. | NDOR / address FHWA comments and resubmit |
| 10th St Brg Wide, Omaha | SHPO concur req | 22353 | 5103-14 | 23-Mar-11 | 24-Mar-11 | 1 | comments given back to Allison at NEPA workshop | NDOR / address FHWA comments and resubmit |
| 10th St Bridge, Omaha | 4(f) DeMin Form | 22353 | 5103-14 | 06-May-11 | 06-May-11 | 0 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| 10th St Bridge, Omaha | CE | 22353 | 5103-14 | 13-May-11 | 18-May-11 | 5 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| 58th Street, Omaha | NEPA Determination Form | 22363 | 5086-1 | 02-Aug-10 | 20-Aug-10 | 18 | rb conditionally approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Intersec 58th & NW Radial Hwy, Omaha | CE | 22363 | 5086-1 | 06-Apr-11 | 07-Apr-11 | 1 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Kennedy and Cornhusker Exit Ramps | DR 53 | 22366 | 5006-4 | 12/29/2011 | 1/4/2012 | 6 | document not signed by NDOR. sent comment back to NDOR. | NDOR / address FHWA comments and resubmit |
| Kennedy and Cornhusker Exit Ramps | DR 53 | 22366 | 5006-4 | 1/4/2012 | 1/16/2012 | 12 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Kennedy Freeway and Cornhusker Road | SHPO concur request | 22366 | 5006-4 | 3/7/2012 | 3/15/2012 | 8 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| US-275 East | Bio doc vers 1 | 22368 | 917-108 | 22-Feb-11 | 24-Feb-11 | 2 | letters sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| US-275 East | SHPO concur req | 22368 | 917-108 | 28-Apr-11 | 02-May-11 | 4 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| US-275 East | CE | 22368 | 917-108 | 02-Jun-11 | 10-Jun-11 | 8 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| US-275 East | Scope change memo | 22368 | 917-108 | 5/31/2012 | 6/1/2012 | 1 | None | |
| Inters F/16th & Spring Lake Dr | Bio doc vers 1 | 22371 | 5089-1 | 14-Dec-10 | 17-Dec-10 | 3 | comments sent to Allison and Zach, waiting on DR53 | NDOR / address FHWA comments and resubmit |
| F/16th & Spring Lake Dr | DR 53 | 22371 | 5089-1 | 28-Dec-10 | 07-Jan-11 | 10 | approved with comments | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Intersec of F & 16th | SHPO Concur Req | 22371 | 5089-1 | 22-Jul-11 | 26-Jul-11 | 4 | mm approved letter 7/26, with front office for formatting/submission | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Intersection of F/16th St and Spring Lake Drive | 4(f) determ | 22371 | 5089-1 | 7/26/2012 | 8/14/2012 | 19 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| 102nd & Maple Improv. | DR 53 | 22372 | 5015-1 | 29-Dec-10 | 18-Jan-11 | 20 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| 102nd & Maple, Omaha | SHPO concur req | 22372 | 5015-1 | 15-Apr-11 | 21-Apr-11 | 6 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| 102nd & Maple Improv, Omaha | Bio doc vers 1 | 22372 | 5015-1 | 19-Apr-11 | 21-Apr-11 | 2 | comments sent back to Zach | NDOR / address FHWA comments and resubmit |
| 102nd & Maple, Omaha | Bio doc vers 2 | 22372 | 5015-1 | 22-Apr-11 | 25-Apr-11 | 3 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| 156Th St - Pepperwood Dr | P&N | 22376 | 5127-1 | 30-Sep-11 | 13-Oct-11 | 13 | provided comments to NDOR | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| 156th St, West Dodge - Corby, Phase 2 | Bio doc version 1 | 22376 | 5127-1 | 1/10/2012 | 1/16/2012 | 6 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| 156th St, Pepperwood Dr to Corby Street | SHPO concur request | 22376 | 5127-1 | 3/8/2012 | 3/15/2012 | 7 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| 108th, L to M, Omaha | Bio doc vers 1 | 22378 | 5011-12 | 22-Sep-10 | 29-Sep-10 | 7 | rb approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| 108th, L-M, Omaha | DR 53 | 22378 | 5011-12 | 28-Dec-10 | 18-Jan-11 | 21 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| 108th, from L to M, Omaha | SHPO concur req | 22378 | 5011-12 | 25-Jul-11 | 26-Jul-11 | 1 | mm approved letter 7/26, with front office for formatting/submission | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| 108th, from L to M, Omaha | Bio reintiation | 22378 | 5011-12 | 02-Sep-11 | 15-Sep-11 | 13 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| 108th Street, from L to M | CE | 22378 | 5011-12 | 1/23/2012 | 2/3/2012 | 11 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Traf Signals 15th & Farnam | Bio doc vers 1 | 22379 | 5097-1 | 29-Oct-10 | 02-Nov-10 | 4 | rb approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| 15th & Farnam, Omaha | SHPO concur req | 22379 | 5097-1 | 21-Apr-11 | 25-Apr-11 | 4 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| 52nd & NW Radial Traf Sigs, Medians, curb ramps | DR 53 | 22380 | 5049-3 | 16-Jun-11 | 23-Jun-11 | 7 | mm concurred | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| 52nd & NW Radial | Bio Doc V1 | 22380 | 5049-3 | 22-Jul-11 | 29-Jul-11 | 7 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| 52nd and NW Radial | SHPO concur request | 22380 | 5049-3 | 11/10/2011 | 11/14/2011 | 4 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Trfc Sigs - 42nd & Dodge | DR 53 | 22381 | 5057-11 | 17-Dec-10 | 23-Dec-10 | 6 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Traf Sigs 42nd & Dodge | Bio doc vers 1 | 22381 | 5057-11 | 03-Jan-11 | 06-Jan-11 | 3 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Traf Sigs - 42nd & Dodge | SHPO concur | 22381 | 5057-11 | 27-Dec-10 | 07-Jan-11 | 11 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Traf Sigs - 13th & Harney, etc | SHPO concur | 22383 | 5121-2 | 27-Dec-10 | 07-Jan-11 | 11 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Traf Sigs 13th & Harney | Bio doc vers 1 | 22383 | 5121-2 | 03-Jan-11 | 07-Jan-11 | 4 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Traf sigs, various Omaha | DR 53 | 22383 | 5121-2 | 22-Feb-11 | 22-Feb-11 | 0 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Valley DC West School Sidewalk | DR 53 | 22411 | 28-97 | 10/24/2011 | 10/28/2011 | 4 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| 32nd Ave | DR 53 | 22414 | 28-99 | 14-Dec-10 | 17-Dec-10 | 3 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| 32nd St Streetscape & Bike Trail | revised DR53 | 22414 | 28-99 | 23-Sep-11 | 07-Oct-11 | 14 | approved (scope changed) | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Fremont Johnson Rd Trail | DR 53 | 22427 | 27-55 | 08-Apr-11 | 12-Apr-11 | 4 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Johnson Rd Trail - Military Ave to 20th St. | Bio doc vers 1 | 22427 | 27-55 | 17-Oct-11 | 18-Oct-11 | 1 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Johnson Road Trail | SHPO concur request | 22427 | 27-55 | 11/30/2011 | 12/6/2011 | 6 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Scribner Ped Trail | DR 53 | 22428 | 27-56 | 02-Sep-11 | 14-Sep-11 | 12 | sent comments to NDOR | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Scribner Ped Trail | DR 53 | 22428 | 27-56 | 13-Oct-11 | 17-Oct-11 | 4 | Sent comments back to NDOR. | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| 84th & L Improvement | DR 53 | 22429 | 5023-16 | 29-Dec-10 | 11-Jan-11 | 13 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| 84th & L, Omaha | SHPO concur req | 22429 | 5023-16 | 15-Apr-11 | 21-Apr-11 | 6 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| 84th & L Improv, Omaha | Bio doc vers 1 | 22429 | 5023-16 | 19-Apr-11 | 21-Apr-11 | 2 | comments sent back to Zach | NDOR / address FHWA comments and resubmit |
| 84th & L, Omaha | Bio doc vers 2 | 22429 | 5023-16 | 22-Apr-11 | 25-Apr-11 | 3 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| US-77, 5th-10th, Fremont | DR 53 | 22434 | 773-129 | 14-Jul-11 | 19-Jul-11 | 5 | mm signed dr53 with a few notes | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| US-77 5th - 10th, Fremont | SHPO Concur req | 22434 | 773-129 | 10/18/2011 | 10/28/2011 | 10 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Omaha Traf Signals Pkg 4 | DR 53 | 22435 | 5091-4 | 17-Dec-10 | 23-Dec-10 | 6 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Traf Sigs pkg 4 | Bio doc vers 1 | 22435 | 5091-4 | 30-Dec-10 | 06-Jan-11 | 7 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Traf Sigs - pkg 4 | SHPO concur | 22435 | 5091-4 | 27-Dec-10 | 07-Jan-11 | 11 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Traff signals various | SHPO concur req | 22436 | 5089-3 | 07-Dec-10 | 10-Dec-10 | 3 | letter to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Traf Sigs - pkg 5 | Bio doc vers 1 | 22436 | 5089-3 | 30-Dec-10 | 06-Jan-11 | 7 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Traf Signls various - Pkg 6 | DR 53 | 22437 | 5083-6 | 17-Dec-10 | 23-Dec-10 | 6 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Traf Sigs - pkg 6 | Bio doc vers 1 | 22437 | 5083-6 | 30-Dec-10 | 06-Jan-11 | 7 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Traf Sigs - pkg 6 | SHPO concur | 22437 | 5083-6 | 27-Dec-10 | 07-Jan-11 | 11 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Adapt Trfc Control Sys 32nd St. | DR 53 | 22438 | 5003-10 | 17-Dec-10 | 23-Dec-10 | 6 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| 132nd St. Adaptive Traffic Control System | Bio Doc V1 | 22438 | 5003-10 | 22-Jul-11 | 29-Jul-11 | 7 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Military Avenue Resurfacing | DR 53 | 22439 | 5610-5 | 14-Feb-11 | 16-Feb-11 | 2 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Military Ave-Broad to Bell, Fremont | Bio doc vers 1 | 22439 | 5610-5 | 17-Oct-11 | 18-Oct-11 | 1 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Military Ave, Broad to Bell, Fremont | SHPO concur request | 22439 | 5610-5 | 10/26/2011 | 10/28/2011 | 2 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Military Ave. Broad-Bell | 106 Concur Req (Resubmission) | 22439 | 5610-5 | 3/28/2012 | 4/25/2012 | 28 | sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| I-480 & US-75 intrchnge | Bio doc vers 1 | 22441 | 4809-102 | 04-Nov-10 | 08-Nov-10 | 4 | rb approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Resurfacing, WB W. Center Rd 114 - 120, Omaha | Env Re-Eval Memo | 22446 | 5038-17 | 05-Oct-11 | 07-Oct-11 | 2 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Ft Calhoun - Blair | DR 53 | 22447 | 753-116 | 4/9/2012 | 4/27/2012 | 18 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Scribner North | DR 53 | 22448 | 2756-141 | 10/27/2011 | 10/28/2011 | 1 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Scribner North | Bio doc version 1 | 22448 | 2756-141 | 1/3/2012 | 1/3/2012 | 0 | letters sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Scribner North | SHPO concur request | 22448 | 2756-141 | 2/16/2012 | 2/17/2012 | 1 | material reviewed and approved. letter will be sent to SHPO Tues 2/21. | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Adapt Trafc Contr 144th St | DR 53 | 22449 | 5001-17 | 20-Dec-10 | 23-Dec-10 | 3 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Adapt Traf Contr Syst | Bio doc vers 1 | 22449 | 5001-17 | 04-Jan-11 | 06-Jan-11 | 2 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Adaptive Traf Control Sys - 144th St. | SHPO concur req | 22449 | 5001-17 | 11-Oct-11 | 12-Oct-11 | 1 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| 108th Decatur to N Brdg Rd, Omaha | DR 53 | 22450 | 5011-14 | 13-Oct-10 | 26-Oct-10 | 13 | rb approved with comments | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Blair West | DR 53 | 22454 | 917-109 | 4/16/2012 | 4/23/2012 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation | |
| Cedar Creek Spur | DR 53 | 22457 | S13H-104 | 11/7/2011 | 11/14/2011 | 7 | Approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Cedar Creek Spur | SHPO concur request | 22457 | S13H-104 | 1/31/2012 | 2/3/2012 | 3 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| N-1 to Plattsmouth | DR 53 | 22458 | 347-128 | 27-Jul-11 | 03-Aug-11 | 7 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Plattsmouth North | DR 53 | 22459 | 752-169 | 13-Jun-11 | 16-Jun-11 | 3 | concurred on CE.mm | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| 30th & McKinley, Omaha | SHPO concur req | 22461 | 752-170 | 04-Apr-11 | 07-Apr-11 | 3 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| 30th&McKinley, Omaha | Bio doc vers 1 | 22461 | 752-170 | 15-Apr-11 | 19-Apr-11 | 4 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Waterloo South | DR 53 | 22463 | 2757-193 | 4/16/2012 | 4/23/2012 | 7 | asked NDOR to check with the FHWA engineer regarding the scope and eligiblity, but concurred CE/PCE would be appropriate if a project | None |
| Waterloo South | SHPO and THPO concur req | 22463 | 2757-193 | 7/5/2012 | 7/13/2012 | 8 | letters sent to SHPO and THPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| 84th St Interchange | Bio doc vers 1 | 22465 | 809-34 | 09-Jun-11 | 10-Jun-11 | 1 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| OA 50 Challenge | Bio doc version 1 | 22468 | 3795-5 | 24-Jun-10 | 02-Jul-10 | 8 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Traf sigs, various Omaha | DR 53 | 22475 | 5099-1 | 22-Feb-11 | 22-Feb-11 | 0 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Traf sigs various, Omaha | Bio doc vers 1 | 22475 | 5099-1 | 24-Mar-11 | 29-Mar-11 | 5 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Traf sigs Omaha vari locates | SHPO concur req | 22475 | 5099-1 | 19-May-11 | 19-May-11 | 0 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Traf Ops & Sigs timing study | DR 53 | 22476 | 28-101 | 22-Feb-11 | 22-Feb-11 | 0 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Papillion Walnut Creek Connector Trail | DR-53 | 22477 | 77-59 | 15-Sep-10 | 23-Sep-10 | 8 | NDOR (or LPA) / Must prepare technical and NEPA documentation | |
| 96th St. Resurfacing | DR 53 | 22478 | 5017-4 | 19-Jan-11 | 31-Jan-11 | 12 | mm concurred CE would be appropriate level of analysis | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| 96th, Portal-Harrison | Bio doc vers 1 | 22478 | 5017-4 | 05-Apr-11 | 07-Apr-11 | 2 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| 69th - 93rd on Dodge | DR 53 | 22482 | 67-180 | 19-Jan-11 | 31-Jan-11 | 12 | mm concurred CE appropriate level of NEPA review | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Dodge St Traf Contr System | Bio doc vers 1 | 22482 | 67-180 | 22-Mar-11 | 23-Mar-11 | 1 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Dodge St 69th - 93rd | SHPO concur req | 22482 | 67-180 | 25-Apr-11 | 25-Apr-11 | 0 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Mud Crk Culvert - Plattsmouth | DR 53 | 22483 | ER 3720-1 | 20-Dec-10 | 27-Dec-10 | 7 | signed by Cass Co 10/26/10 and approved by NDOR 12/20/10. Sent to FHWA via email and approved 12/27/10 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Bellevue signals | DR 53 | 22484 | 5109-8 | 24-Jan-11 | 31-Jan-11 | 7 | mm concurred with completing a CE for project. May fit a PA | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Bellevue Signals | Bio doc vers 1 | 22484 | 5109-8 | 05-Apr-11 | 07-Apr-11 | 2 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Giles Road Signal Coord. | DR 53 | 22485 | 5129-1 | 29-Jul-11 | 03-Aug-11 | 5 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Metro Omaha Bicycle Safety Education | DR 53 | 22492 | 28-111 | 4/13/2012 | 4/23/2012 | 10 | None | |
| Winslow East | DR 53 | 22493 | ER 3860-1 | 23-Sep-11 | 23-Sep-11 | 0 | Dodge Co signed 1/28/11. NDOR signed 9/23/11 and emailed DR53 to FHWA on 9/23/11. FHWA concurred to proceed as PCE/CE | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| North Bend Northwest | DR 53 | 22495 | ER 3465-5 | 23-Sep-11 | 23-Sep-11 | 0 | Dodge Co signed 1/28/11. NDOR signed 9/23/11 and emailed DR53 to FHWA on 9/23/11. FHWA concurred to proceed as PCE/CE | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Omaha Concrete Panel Replacement | DR 53 | 22498 | 5001-18 | 22-Apr-11 | 26-Apr-11 | 4 | approved with comments - packages 1, 2, 3 need to be combined into one NEPA action | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Omaha Major Str concrete panel repair | DR 53 | 22499 | 5026-14 | 22-Apr-11 | 26-Apr-11 | 4 | approved with comments - packages 1, 2, 3 need to be combined into one NEPA action | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Omaha concrete panel replace | DR 53 | 22500 | 5009-4 | 22-Apr-11 | 26-Apr-11 | 4 | approved with comments - packages 1, 2, 3 need to be combined into one NEPA action | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Traf sigs St Marys & Park Ave | DR 53 | 22501 | 5-46-3 | 04-Mar-11 | 08-Mar-11 | 4 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Traf sigs St Marys & Park Ave | Bio doc vers 1 | 22501 | 5046-3 | 15-Mar-11 | 15-Mar-11 | 0 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Traf sigs Inters St Marys Ave & Park Ave | SHPO concur req | 22501 | 5046-3 | 15-Apr-11 | 19-Apr-11 | 4 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| 1st St Ext, Luther to Johnson, Fremont | DR 53 | 22503 | 27-62 | 09-Jun-11 | 16-Jun-11 | 7 | mm signed, with stipulations-Uniform Act, check for prime farmland, need public outreach, then will confirm NEPA class | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Concrete Panel Repair | DR 53 and 530 | 22505 | 5044-6 | 5/16/2012 | 5/25/2012 | 9 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| 24th Street Road Diet, Omaha | DR 53 | 22506 | 5083-7 | 4/12/2012 | 4/23/2012 | 11 | NDOR (or LPA) / Must prepare technical and NEPA documentation | |
| Jackson & Blain Impr, Blair | DR 53 | 22507 | 6462-1 | 09-Jun-11 | 16-Jun-11 | 7 | mm signed, with guidance for use during NEPA | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Platteview Road Corridor Study | DR 53 | 22511 | 3770-4 | 12-Sep-11 | 12-Sep-11 | 0 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Traf signals, Omaha | DR 53 | 22519 | 5103-15 | 14-Jul-11 | 20-Jul-11 | 6 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Traffic Signals at Various Locations-Omaha | Bio Doc Vers 1 | 22519 | 5103-15 | 11/23/2011 | 11/28/2011 | 5 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Traffic Signals at Various Locations, Omaha | SHPO concur request | 22519 | 5103-15 | 12/1/2011 | 12/8/2011 | 7 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Arlington SRTS project | DR 53 | 22523 | 89-29 | 19-Aug-11 | 03-Sep-11 | 15 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Bancroft - Dewey, Omaha | DR 53 | 22525 | 4809-103 | 3/8/2012 | 4/5/2012 | 28 | NDOR (or LPA) / Must prepare technical and NEPA documentation | |
| I-80/680 Interch Q to L CD Roads, Omaha (WB) | DR 53 | 22526 | 809-65 | 8/2/2012 | 8/15/2012 | 13 | None | |
| L St - 50th St, Omaha | DR 53 | 22527 | 809-66 | 3/8/2012 | 4/5/2012 | 28 | NDOR (or LPA) / Must prepare technical and NEPA documentation | |
| Fort Crook Road Striping | DR 53 | 22535 | 5145-3 | 1/13/2012 | 1/17/2012 | 4 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Major Street Resurfacing, Omaha | DR 53 | 22536 | 5103-16 | 2/13/2012 | 2/17/2012 | 4 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Blair Connector Trails | DR 53 | 22549 | 889-30 | 4/18/2012 | 4/23/2012 | 5 | NDOR (or LPA) / Must prepare technical and NEPA documentation | |
| Schuyler to Fremont | purpose and need | 31090 | 305(120) | 09-May-11 | 27-May-11 | 18 | sent comments to Allison and Len | NDOR / address FHWA comments and resubmit |
| US-30, Schuyler - Fremont | Coord Plan | 31091 | 305-120 | 27-Apr-11 | 27-May-11 | 30 | comments sent to Allison and Len | NDOR / address FHWA comments and resubmit |
| Primrose East | Bio doc version 1 | 31192 | 6-Jun | 12/8/2011 | 12/14/2011 | 6 | sent comment back to NDOR | NDOR / address FHWA comments and resubmit |
| Stanton North | DR 53 | 31208 | 7084-7 | 1/3/2012 | 1/16/2012 | 13 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Stanton North | SHPO concur req | 31208 | 7084-7 | 7/9/2012 | 7/13/2012 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA | |
| Craig Northeast | NEPA determ form | 31226 | 3875-2 | 20-Sep-10 | 29-Sep-10 | 9 | rb approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Craig Northeast | SHPO concur req | 31226 | 3875-2 | 22-Sep-10 | 29-Sep-10 | 7 | consultation package sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Craig Northeast | CE | 31226 | 3875-2 | 11/10/2011 | 11/14/2011 | 4 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Norfolk West | Class 2 Update (CE) | 31417 | 2755-137 | 10-Jun-10 | 17-Jun-10 | 7 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required | |
| Norfolk - 3 projects | SHPO concur req | 31442 | 353-105 | 27-Sep-11 | 27-Sep-11 | 0 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Hartington SE | Bio doc vers 1 | 31502 | 7014-31 | 18-Nov-10 | 24-Nov-10 | 6 | requested DR53 be submitted prior to signing off on bio doc | NDOR / address FHWA comments and resubmit |
| Hartington Southeast | DR 53 | 31502 | 7014-31 | 06-Dec-10 | 16-Dec-10 | 10 | approved with comments | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Hartington SE | SHPO letter | 31502 | 7014-31 | 16-Mar-11 | 16-Mar-11 | 0 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Hartington SE | CE Form | 31502 | 7014-31 | 24-May-11 | 01-Jun-11 | 8 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Petersburg | DR 53 | 31535 | 7638-1 | 22-Feb-11 | 22-Feb-11 | 0 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Petersburg Northeast | SHPO Concur Req | 31535 | 2532-1 | 11-Jul-11 | 13-Jul-11 | 2 | mm reviewed, to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Petersburg Northeast | Bio Doc Vers 1 | 31535 | 2532-1 | 11/23/2011 | 12/1/2011 | 8 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Petersburg Northeast | Cat Ex | 31535 | 2532-1 | 2/1/2012 | 2/14/2012 | 13 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Stanton Southeast | DR 53 | 31597 | 7084-10 | 06-Dec-10 | 15-Dec-10 | 9 | approved with comments | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Stanton SE | Bio doc vers 1 | 31597 | 7084-10 | 05-Apr-11 | 07-Apr-11 | 2 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Stanton SE | SHPO concur req | 31597 | 7084-10 | 27-Apr-11 | 06-May-11 | 9 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Stanton SE | Cat Ex | 31597 | 7084-10 | 6/11/2012 | 6/14/2012 | 3 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| N-12 Niobrara E&W | Alt Carried Frwd EIS | 31674 | 125-1011 | 20-Sep-10 | 18-Oct-10 | 28 | NDOR / address FHWA comments and resubmit | |
| Richland NW | DR 53 | 31702 | 7019-10 | 16-Dec-10 | 23-Dec-10 | 7 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Richland NW | SHPO concur req | 31702 | 7019-10 | 22-Mar-11 | 29-Mar-11 | 7 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Richland Southwest | Bio doc vers 1 | 31702 | 7019-10 | 21-Apr-11 | 27-Apr-11 | 6 | sent comments back to Zach | NDOR / address FHWA comments and resubmit |
| Richland NW | Bio doc vers 2 | 31702 | 7019-10 | 27-Apr-11 | 02-May-11 | 5 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Richland Northwest | CE | 31702 | 7019-10 | 28-Jul-11 | 03-Aug-11 | 6 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Concord East | DR 53 | 31723 | 3130-5 | 15-Dec-10 | 17-Dec-10 | 2 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Concord East | SHPO Concur Req | 31723 | 3130-5 | 30-Sep-11 | 30-Sep-11 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA | |
| Concord East | Bio doc version 1 | 31723 | 3130-5 | 10/27/2011 | 10/28/2011 | 1 | sent comment back to NDOR | NDOR / address FHWA comments and resubmit |
| Concord East | Bio doc version 1 | 31723 | 3130-5 | 10/31/2011 | 11/2/2011 | 2 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Fordyce West | DR 53 | 31761 | 7014-34 | 06-Dec-10 | 15-Dec-10 | 9 | approved with comments | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Fordyce West | SHPO concur req | 31761 | 7014-34 | 8/7/2012 | 8/16/2012 | 9 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA | |
| Wayne trail | 4(f) exemption req | 31777 | 90-4 | 22-Apr-10 | 28-Apr-10 | 6 | mm-Raegan asking Allison why she feels exemption fits | NDOR / address FHWA comments and resubmit |
| E Jct N-9 to Dakota City | Bio Assessment | 31784 | 354-120 | 09-Aug-10 | 18-Aug-10 | 9 | rb approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Laurel Northeast | SHPO Letter | 31786 | 206-108 | 12-Aug-10 | 16-Aug-10 | 4 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA | |
| Laurel Northeast | NEPA Determ | 31786 | 206-108 | 20-Aug-10 | 30-Aug-10 | 10 | rb approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Laurel Northeast | Bio doc | 31786 | 206-108 | 13-Sep-10 | 23-Sep-10 | 10 | content of letter to Sue to process.mm | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Laurel Northeast | NEPA CE | 31786 | 206-108 | 29-Oct-10 | 08-Nov-10 | 10 | comments given to Jon Barber to revise mitigastion measure wording and then resubmit | NDOR / address FHWA comments and resubmit |
| Laurel NE | Revised CE | 31786 | 206-108 | 08-Nov-10 | 08-Nov-10 | 0 | rb approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| West Bow and Norwegian Bow Bridges | NEPA Determ | 31788 | 814-115 | 18-Aug-10 | 03-Sep-10 | 16 | NDOR to address FHWA comments and resubmit | |
| West Bow & Norw Bow Brdgs | NEPA Determ 2nd submittal | 31788 | 814-115 | 27-Sep-10 | 29-Sep-10 | 2 | rb approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| West Bow Norw. Bow Crk bridges | 106 consult SHPO concur | 31788 | 814-115 | 20-Oct-10 | 22-Oct-10 | 2 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| West Bow and Norw Bow Crk brgs | CE | 31788 | 814-115 | 03-Dec-10 | 14-Dec-10 | 11 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Petersburg - Elgin | SHPO concur request | 31809 | 143-112 | 5/15/2012 | 5/25/2012 | 10 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Verdigre North | DR-53 | 31821 | 7054-19 | 4/2/2012 | 4/26/2012 | 24 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Bloomfield West | T&E Memo | 31822 | 7054-20 | 12-May-10 | 27-May-10 | 15 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. | |
| Bloomfield West | SHPO concur req | 31822 | 7054-20 | 21-Mar-11 | 29-Mar-11 | 8 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Bloomfield West | DR 53 | 31822 | 7054-20 | 22-Mar-11 | 29-Mar-11 | 7 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Bloomfield West | CE | 31822 | 7054-20 | 01-Aug-11 | 04-Aug-11 | 3 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Bloomfield West | Wetlands determination | 31822 | 7054-20 | 7/25/2012 | 8/15/2012 | 21 | None | |
| Foster Northwest & Southeast | DR 53 | 31825 | 134-110 | 7/10/2012 | 7/13/2012 | 3 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Albion-Petersburg | SHPO Concur Req | 31826 | 143-114 | 12-Jul-11 | 13-Jul-11 | 1 | mm sent back 106 letter, issues involving affects and the determination | NDOR / address FHWA comments and resubmit |
| Albion to Petersburg | SHPO Concur Req R2 | 31826 | 143-114 | 22-Jul-11 | 27-Jul-11 | 5 | mm wrote mitigation for 106 and sent to NDOR for concurrence 7/26. 7/27 sent letter to front office for submission to SHPO | NDOR / address FHWA comments and resubmit |
| Albion - Petersburg | CE | 31826 | 143-114 | 12/5/2011 | 12/9/2011 | 4 | cpmments sent back to NDOR | NDOR / address FHWA comments and resubmit |
| Albion - Petersburg | CE - revised | 31826 | 143-114 | 1/30/2012 | 2/7/2012 | 8 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| E. Jct N-45 to Madison | DR 53 | 31829 | 325-107 | 02-Aug-11 | 05-Aug-11 | 3 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| E Jct N-45 to Madison | SHPO concur request | 31829 | 325-107 | 2/14/2012 | 2/17/2012 | 3 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Albion Wwest | DR 53 | 31833 | 915-118 | 28-Sep-10 | 04-Oct-10 | 6 | rb approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Albion West | SHPO concur request | 31833 | 915-118 | 3/14/2012 | 3/15/2012 | 1 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Albion West | Cat Ex | 31833 | 915-118 | 8/1/2012 | 8/15/2012 | 14 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Norfok 25th St widening | Bio doc vers 1 | 31875 | 6001-1 | 01-Mar-11 | 02-Mar-11 | 1 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Norfolk 25th St. | Reeval | 31875 | 6001-1 | 16-Mar-11 | 17-Mar-11 | 1 | Asked Allison for documentation of the subsequent coordination with USACE that they are ok with the changes to the wetland impacts and corresponding mitigation site. | NDOR / assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
| Norfolk 25th St. | Reeval memo | 31875 | 6001-1 | 29-Mar-11 | 31-Mar-11 | 2 | Mitigation measures from CE and Re-eval need to be compiled in one location (in mit measures section of re-eval) and NDOR cover letter needs revising - discussed comments with Jon | NDOR / assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
| 25th St, Norfolk | Reeval Memo | 31875 | 6001-1 | 01-Apr-11 | 01-Apr-11 | 0 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Martinsburg NE | DR 53 | 31880 | 7026-20 | 22-Mar-11 | 29-Mar-11 | 7 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Martinsburg NE | SHPO concur req | 31880 | 7026-20 | 6/25/2012 | 6/27/2012 | 2 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Union Crk to N-57 | Bio doc vers 1 | 31887 | 326-111 | 09-Nov-10 | 12-Nov-10 | 3 | rb approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Stanton South | DR 53 | 31889 | 573-107 | 11/7/2011 | 11/14/2011 | 7 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Stanton South | SHPO concur request | 31889 | 573-107 | 5/18/2012 | 5/25/2012 | 7 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Stanton South | Bio doc version 1 | 31889 | 573-107 | 7/10/2012 | 7/16/2012 | 6 | letters sent to NGPC and USFWS | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Wayne Bridges | SHPO Concur Req | 31893 | 154-118 | 29-Sep-11 | 30-Sep-11 | 1 | NDOR / address FHWA comments and resubmit | |
| N-32 - Pilger | Bio doc vers 1 | 31894 | 153-113 | 28-Oct-10 | 03-Nov-10 | 6 | letters to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| N-32 to Pilger, Stanton Co | SHPO concur req | 31894 | 153-113 | 06-Jan-11 | 07-Jan-11 | 1 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| In Tilden and Battle Creek North | Bio doc vers 1 | 31897 | 453-110 | 21-Dec-10 | 27-Dec-10 | 6 | letters to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Fordyce East & West | DR 53 | 31912 | 126-116 | 11-Oct-11 | 13-Oct-11 | 2 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| N-13 to Osmond | DR 53 | 31917 | 1214-111 | 12-Jul-11 | 19-Jul-11 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation | |
| N-13 to Osmond | SHPO concur request | 31917 | 1214-111 | 5/17/2012 | 6/4/2012 | 18 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Santee Spur | DR 53 | 31918 | S54D-103 | 01-Aug-11 | 04-Aug-11 | 3 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Santee Spur | SHPO concur request | 31918 | S54D-103 | 11/15/2011 | 11/22/2011 | 7 | sent comments back to NDOR | NDOR / address FHWA comments and resubmit |
| Santee Spur | SHPO concur - revised | 31918 | S54D-103 | 12/6/2011 | 12/8/2011 | 2 | letter sent to SHPO and THPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Santee Spur | Bio doc version 1 | 31918 | S54D-103 | 12/30/2011 | 1/3/2012 | 4 | letters sent to Tribe, BIA, USFWS, and NGPC | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Santee Spur | Tribal SHPO concur request | 31918 | S54D-103 | 1/10/2012 | 1/10/2012 | 0 | letter sent to Tribe | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| W. Jct N-15 to Newcastle | DR 53 | 31919 | 126-115 | 13-Jun-11 | 16-Jun-11 | 3 | concurred on CE.mm | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Wayne West | DR 53 | 31920 | 354-121 | 2/16/2012 | 2/17/2012 | 1 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Columbus projects | Bio doc vers 1 | 31924 | 6065-2 | 28-Sep-10 | 01-Oct-10 | 3 | rb approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Columbus projects | SHPO Concur req | 31924 | 6065-5 | 29-Sep-10 | 01-Oct-10 | 2 | letter to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Columbus Viaducts | HazMat Section review | 31924 | 6061-8 | 06-Dec-10 | 06-Dec-10 | 0 | comments back to Allison | NDOR / address FHWA comments and resubmit |
| Columbus viaducts | DEA | 31924 | 6065-5 | 04-Apr-11 | 05-Apr-11 | 1 | approved for public/agency review and comment | NDOR / prepare for public outreach (if document is a DEA, the outreach is a hearing) |
| UPRR/3rd Ave. & UPRR/12th & 18th Ave., Columbus | Public Meeting Materials | 31924 | 6065-5 | 20-Apr-11 | 25-Apr-11 | 5 | comments provided to City/HDR during monthly conference call | NDOR / address FHWA comments and resubmit |
| Columbus Viaducts | Final EA | 31924 | 6065-5 | 20-Jun-11 | 21-Jun-11 | 1 | mm sent comments directly to consultant and NDOR vai email | NDOR / address FHWA comments and resubmit |
| Columbus Viaducts | partial submittal FEA#2 | 31924 | 6065(5) | 01-Jul-11 | 01-Jul-11 | 0 | mm reviewed and sent back a few notes | NDOR / address FHWA comments and resubmit |
| Columbus Viaducts | FEA, version 3 | 31924 | 6065-5 | 08-Jul-11 | 08-Jul-11 | 0 | mm sent back a few minor edits in response to the new text added | NDOR / address FHWA comments and resubmit |
| N-57 to Wisner | Bio doc version 1 | 31938 | 2756-140 | 11/22/2011 | 11/25/2011 | 3 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| N-57 to Wisner | SHPO concur request | 31938 | 2756-140 | 2/8/2012 | 2/17/2012 | 9 | comments sent back to NDOR | NDOR / address FHWA comments and resubmit |
| N-57 to Wisner | 106 Concur Req (2nd Submittal) | 31938 | 2756-140 | 3/28/2012 | 4/25/2012 | 28 | sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| N-57 to Wisner | Cat Ex | 31938 | 2756-140 | 6/12/2012 | 6/21/2012 | 9 | comments sent back to NDOR | NDOR / address FHWA comments and resubmit |
| N57 to Wisner | Cat Ex v4 | 31938 | 2756-140 | 8/14/2012 | 8/14/2012 | 0 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| N-57 - Wisner | Cat Ex - 3rd submittal | 31938 | 2756-140 | 8/7/2012 | 8/9/2012 | 2 | comments sent back to ndor | NDOR / address FHWA comments and resubmit |
| N-57 to Wisner | Cat Ex - 2nd submittal | 31938 | 2756-140 | 7/16/2012 | 7/23/2012 | 7 | comment regarding hazmat sent to NDOR | NDOR / address FHWA comments and resubmit |
| Rogers East & West | DR 53 | 31942 | 306-132 | 25-Oct-10 | 26-Oct-10 | 1 | rb approved with comments - should be combined with 306-134 project | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| In Madison & East | DR 53 | 31950 | 325-108 | 12-Apr-11 | 15-Apr-11 | 3 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| In Madison & East | SHPO concur req | 31950 | 325-108 | 11-Oct-11 | 12-Oct-11 | 1 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| 25th St Improvments Norfolk | 4(f) De Minimis | 31975 | 6001-1 | 12-May-10 | 14-May-10 | 2 | comments sent back to Allison Zach | NDOR / address FHWA comments and resubmit |
| 3rd Ave, Columbus | DR 53 | 31990 | 6065-6 | 12-Aug-11 | 17-Aug-11 | 5 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Windom, E 7 to E 3, Wayne | DR 53 | 31991 | 6709-2 | 10-Nov-10 | 12-Nov-10 | 2 | rb approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Windom St, E 7th - E 3rd, Wayne | SHPO concur req | 31991 | 6709-2 | 02-Sep-11 | 06-Sep-11 | 4 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Windom St, from E. 3rd to E. 7th | Bio doc version 1 | 31991 | 6709-2 | 12/22/2011 | 12/23/2011 | 1 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Jct US 75 & US 77, N-35 | SHPO concur req | 31995 | 754-110 | 29-Sep-10 | 04-Oct-10 | 5 | letter to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Winside East | DR 53 | 32011 | 3100-1 | 24-Jan-11 | 31-Jan-11 | 7 | mm concurred with completing a CE | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Winside East | Bio doc vers 1 | 32011 | 3100-1 | 08-Apr-11 | 08-Apr-11 | 0 | approved bio doc no affect | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Winside East | SHPO concur req | 32011 | 3100-1 | 25-Apr-11 | 25-Apr-11 | 0 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Winside East | CE | 32011 | 3100-1 | 07-Jul-11 | 08-Jul-11 | 1 | mm approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Howells North | DR 53 | 32043 | 3175-3 | 06-Dec-10 | 15-Dec-10 | 9 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Howells North | SHPO concur request | 32043 | 3175-3 | 12/1/2011 | 12/8/2011 | 7 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Howells North | Bio doc version 1 | 32043 | 3175-3 | 12/7/2011 | 12/14/2011 | 7 | sent comment back to NDOR | NDOR / address FHWA comments and resubmit |
| Howells North | Bio doc - revised | 32043 | 3175-3 | 12/15/2011 | 12/20/2011 | 5 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Howells North | CE | 32043 | 3175-3 | 3/27/2012 | 4/23/2012 | 27 | sent comments back to NDOR | NDOR / assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
| Howells North | Cat Ex - revised | 32043 | 3175-3 | 6/6/2012 | 6/12/2012 | 6 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Crofton East | DR 53 | 32061 | 125-115 | 12/7/2011 | 12/15/2011 | 8 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Crofton East | SHPO concur request | 32061 | 125-115 | 6/5/2012 | 6/6/2012 | 1 | "comments sent to NDOR | |
| " | NDOR / address FHWA comments and resubmit | |||||||
| Norfolk to Stanton | SHPO concur req | 32063 | 246-102 | 03-Aug-11 | 04-Aug-11 | 1 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Wayne West | DR 53 | 32067 | 7090-20 | 11-Apr-11 | 12-Apr-11 | 1 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Autumn Olive Land - Riverview Dr | DR 53 | 32074 | 5314-2 | 06-Apr-11 | 12-Apr-11 | 6 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Pierce Co SRTS | DR 53 | 32076 | 70-20 | 02-Mar-11 | 02-Mar-11 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation | |
| Pierce Community SRTS | SHPO concur req | 32076 | 70-20 | 13-Jun-11 | 20-Jun-11 | 7 | mm reviewed, gave to SP to format for sig and send to SHPO 6/16/11 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Santee Community SRTS | DR 53 | 32078 | 54-17 | 7/13/2012 | 7/24/2012 | 11 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Dakota Ave | Bio doc - version 1 | 32081 | 5305-10 | 07-May-10 | 20-May-10 | 13 | bio approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Cedar Rapids Bridge Renova. | DR 53 | 32083 | 5-Jun | 19-Aug-11 | 03-Sep-11 | 15 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Dakota City Depot Renovation | SHPO concur req | 32084 | 22-29 | 7/26/2012 | 8/14/2012 | 19 | sent comments back to NDOR | NDOR / assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
| Distr 3 High Mast Twr | Bio doc version 1 | 32090 | 3-101 | 16-Jun-10 | 21-Jun-10 | 5 | rb approved BA | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Missing Link Trail | DR 53 | 32107 | 22-30 | 21-Sep-11 | 26-Sep-11 | 5 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| South Sioux City Missing Link | Bio doc version 1 | 32107 | 22-30 | 3/2/2012 | 3/8/2012 | 6 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| South Sioux City Missing Link Trail | 106 Concur Req | 32107 | 22-30 | 3/28/2012 | 4/25/2012 | 28 | sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| US-30 NE of Schuyler | Bio Assessment | 32109 | 306-136 | 06-Aug-10 | 18-Aug-10 | 12 | rb approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| US30 NE of Schuyler | SHPO concurrence request | 32109 | 306(106) | 01-Sep-10 | 23-Sep-10 | 22 | mm letter to Sue to format 9/23/10 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Jct N-91 and US-81 | Bio doc vers 1 | 32113 | 915-123 | 26-Oct-10 | 27-Oct-10 | 1 | rb approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| US-77 Intersection Improvement | DR 53 | 32114 | 327-111 | 1/4/2012 | 1/16/2012 | 12 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Jct N-32/US-77 | SHPO concur req | 32114 | 327-111 | 6/7/2012 | 6/14/2012 | 7 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Jct Us-20 - Jct N-59 | Bio doc vers 1 | 32117 | 814-119 | 29-Sep-10 | 04-Oct-10 | 5 | rb approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Decatur South | DR 53 | 32121 | 753-117 | 3/16/2012 | 4/6/2012 | 21 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| In South Sioux City | DR 53 | 32122 | 774-126 | 1/23/2012 | 2/1/2012 | 9 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Santee Spur East | DR 53 | 32135 | 125-116 | 11/7/2011 | 11/14/2011 | 7 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Santee Spur East | SHPO and THPO concur requests | 32135 | 125-116 | 5/22/2012 | 6/6/2012 | 15 | letters sent to SHPO and THPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Macy to Winnebago | Bio doc vers 1 | 32140 | 754-111 | 15-Mar-11 | 16-Mar-11 | 1 | letters sent to BIA and tribal contacts | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Macy - Winnebago | SHPO concur req | 32140 | 754-111 | 13-Jul-11 | 19-Jul-11 | 6 | mm reviewed, sent to front office to mail | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Wayne underpass | DR 53 | 32153 | 90-6 | 07-Dec-10 | 15-Dec-10 | 8 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Norfolk Elkhorn River Trail | SHPO concur req | 32154 | 59-22 | 8/6/2012 | 8/16/2012 | 10 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA | |
| Norfolk Elkhorn River Trail | Bio doc version 1 | 32154 | 59-22 | 7/12/2012 | 7/26/2012 | 14 | sent comments back to NDOR | NDOR / address FHWA comments and resubmit |
| Norfolk Elkhorn River Trail | Bio doc version 2 | 32154 | 59-22 | 7/26/2012 | 7/26/2012 | 0 | letters sent to USFWS and NGPC | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| West of Columbus | DR 53 | 32163 | 813-145 | 09-Mar-11 | 10-Mar-11 | 1 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Jct US-81/N-22 West of Columbus | SHPO concur request | 32163 | 813-145 | 12/6/2011 | 12/9/2011 | 3 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Jct US-81/N-22 West of Columbus | THPO concur request | 32163 | 813-145 | 3/5/2012 | 3/6/2012 | 1 | Letter sent to Iowa Tribe | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Thurston Spur North and South | DR 53 | 32164 | 94-117 | 01-Jun-11 | 10-Jun-11 | 9 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Thurston Spur South and North | Bio doc version 1 | 32164 | 94-117 | 11/22/2011 | 11/28/2011 | 6 | need Tribal contact information filled out on BE | NDOR / address FHWA comments and resubmit |
| Thurston Spur South and North | Bio Doc V2 | 32164 | 94-117 | 11/30/2011 | 12/13/2011 | 13 | bio document approved, coordination package sent to Tribes and BIA on 12/13/11 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Thurston Spur North and South | SHPO concur request | 32164 | 94-117 | 2/28/2012 | 3/6/2012 | 7 | letters sent to Omaha, Winnebago, BIA (Aberdeen), and SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Thurston Spur North and South | THPO concur request - 2nd submittal | 32164 | 94-117 | 4/23/2012 | 5/9/2012 | 16 | Letters sent to Tribes and BIA today | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Tilden North Bank Repair | DR 53 | 32168 | ER 2580-2 | 23-Sep-11 | 23-Sep-11 | 0 | Antelope Co signed 3/1/11. NDOR signed 9/23/11 and emailed to FHWA on 9/23/11. FHWA concurred to proceed as PCE/CE. Mm | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| South Sioux City Trail | DR 53 | 32169 | 22-32 | 12-Sep-11 | 16-Sep-11 | 4 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Emergency Repair Projects | DR 53 | 32173 | ER 3-102 | 11/9/2011 | 11/10/2011 | 1 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Temp 2010 ER Projects | SHPO concur request | 32173 | 3-102 | 1/3/2012 | 1/3/2012 | 0 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Knox Co Rumble Bars | DR 53 | 32176 | 54-20 | 22-Feb-11 | 23-Feb-11 | 1 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Knox County Rumble Bars | Bio doc version 1 | 32176 | 54-20 | 4/17/2012 | 4/23/2012 | 6 | made comments, but told NDOR to incorporate teh comments and finalize with no need to re-send to FHWA.mm | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Orchard South | Dr53 | 32177 | ER 2605(4) | 07-Mar-11 | 07-Mar-11 | 0 | received and approved at meeting. FHWA met with project proponent, NDOR, and resource agencies in the field to provide guidance | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Orchard South | ShPO concur request | 32177 | ER 2605-4 | 12/6/2011 | 12/6/2011 | 0 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Orchard South | Bio doc version 1 | 32177 | ER 2605-4 | 12/19/2011 | 12/19/2011 | 0 | USFWS and NGPC know the project is coming their way; they've been informed of the project and had tentatively agreed to the affect determination and the conservation conditions. They've also committed to expediting the review.mm | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Orchard South | CE | 32177 | ER 2605-4 | 1/10/2012 | 1/11/2012 | 1 | comments sent back to NDOR | NDOR / address FHWA comments and resubmit |
| Orchard South | draft CE | 32177 | ER 2605-4 | 1/13/2012 | 1/17/2012 | 4 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Wakefield Logan Crk Trl Phse 2 | DR 53 | 32178 | 26-14 | 04-Mar-11 | 08-Mar-11 | 4 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Meadow Grove N | DR 53 | 32180 | ER 2895-2 | 23-Sep-11 | 23-Sep-11 | 0 | Madison Co signed 2/23/11. NDOR signed 9/23/11 and emailed to FHWA on 9/23/11. FHWA concurred to proceed as PCE/CE- requested they coordinate with FHWA Engineer soon | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Battle Creek North | DR 53 - 1 | 32181 | ER 2915-3 | 23-Sep-11 | 23-Sep-11 | 0 | Madison Co signed 2/23/11. NDOR signed 9/23/11 and emailed to FHWA 9/23/11. FHWA concurred to proceed as PCE/CE -requested they coordinate with FHWA Engineer soon | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Battle Creek North 2?? | DR 53 - 2 | 32181 | ER 2915-3 | 23-Sep-11 | 23-Sep-11 | 0 | Madison Co signed 2/23/11. NDOR signed/approved 9/23/11 and emailed to FHWA 9/23/11. FHWA asked why different scopes for same numbers? Concurred to proceed as PCE/CE requested they coordinate with FHWA Engineer soon | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Riverview Dr to Foundary Road, Dakota County | DR 53 | 32184 | 5314-3 | 11/25/2011 | 12/1/2011 | 6 | emailed comments to NDOR | NDOR / address FHWA comments and resubmit |
| W 29th, US-77 to Lake Ave | DR 53 | 32186 | 5306-8 | 11/25/2011 | 12/1/2011 | 6 | sent comments to NDOR | NDOR / address FHWA comments and resubmit |
| East 14th Ave, Columbus | DR 53 | 32187 | 6067-1 | 28-Jun-11 | 30-Jun-11 | 2 | mm sent back -missing required attachment and scope unclear | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| SRTS Clarkson and Howells | DR 53 | 32188 | 19-11 | 01-Jun-11 | 10-Jun-11 | 9 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Schuyler Resurfacing | DR 53 | 32189 | 6957-1 | 28-Jun-11 | 30-Jun-11 | 2 | mm concurred with some conditions-need early public outreach in NEPA if possible access restrictions | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Columbus East Viaduct | DR 53 | 32190 | 71-33 | 1/13/2012 | 1/17/2012 | 4 | approved with probable class of action an EA. | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Primrose East | DR 53 | 32192 | 6-Jun | 13-Jul-11 | 20-Jul-11 | 7 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Primrose East | SHPO concur request | 32192 | 6-Jun | 12/7/2011 | 12/9/2011 | 2 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Primrose East | CE | 32192 | 6-Jun | 1/30/2012 | 2/3/2012 | 4 | comments sent back to NDOR | NDOR / address FHWA comments and resubmit |
| Primrose East | Cat Ex | 32192 | 6-Jun | 2/9/2012 | 2/17/2012 | 8 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Norfolk-Stanton | Bio doc vers 1 | 32603 | 246-102 | 04-Feb-11 | 08-Feb-11 | 4 | sent comment back to Eric | NDOR / address FHWA comments and resubmit |
| Norfolk - Stanton | Bio doc vers 2 | 32603 | 246-102 | 08-Feb-11 | 08-Feb-11 | 0 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Bloomfield West | SHPO concur req | 38122 | 7054-20 | 21-Apr-11 | 25-Apr-11 | 4 | comments sent to Allison | NDOR / address FHWA comments and resubmit |
| Red Cloud Northwest | DR-53 | 41149 | 7091-5 | 4/2/2012 | 4/6/2012 | 4 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Red Cloud NW | SHPO concur request | 41149 | 7091-5 | 5/17/2012 | 5/31/2012 | 14 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Red Cloud West | DR 53 | 41380 | 2145-7 | 08-Apr-11 | 12-Apr-11 | 4 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| In Polk and West | DR 53 | 41526 | 665-104 | 23-Feb-11 | 23-Feb-11 | 0 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Bradshaw Southeast | DR-53 | 41634 | 7093-23 | 21-Oct-10 | 21-Oct-10 | 0 | rb approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Bradshaw SE | SHPO concur req | 41634 | 7093-23 | 29-Oct-10 | 04-Nov-10 | 6 | letter mailed to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Red Cloud South | DR 53 | 41877 | 2811-112 | 03-Oct-11 | 05-Oct-11 | 2 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Red Cloud South | SHPO concur req | 41877 | 2811-112 | 11-Oct-11 | 13-Oct-11 | 2 | comments sent back to NDOR | NDOR / address FHWA comments and resubmit |
| Ord North | DR 53 | 41914 | 704-106 | 30-Nov-10 | 13-Dec-10 | 13 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Ord North | SHPO concur req | 41914 | 704-106 | 25-Feb-11 | 28-Feb-11 | 3 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Locust St., Grand Island | DR 53 | 41994 | 344-126 | 27-Sep-10 | 04-Oct-10 | 7 | no action - approved in a meeting | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Locust St, Grand Island | SHPO concur | 41994 | 344-126 | 13-Oct-10 | 22-Oct-10 | 9 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| US-281 to Locust Sreet, Grand Island | Bio doc version 1 | 41994 | 344-126 | 12/14/2011 | 12/15/2011 | 1 | letters to be sent to USFWS and NGPC | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| US-281 - Locust Street, Grand Island | Suppl 106 concur request | 41994 | 344-126 | 2/13/2012 | 2/14/2012 | 1 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Locst St, Grand Island | Cat Ex - revised | 41994 | 344-126 | 6/11/2012 | 6/12/2012 | 1 | need commitment added. verbally discussed with NDOR. | NDOR / address FHWA comments and resubmit |
| Central City viaduct | DR 53 | 42013 | 142-123 | 09-Mar-11 | 10-Mar-11 | 1 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Wood River West | SHPO concur req | 42032 | 112-114 | 29-Oct-10 | 08-Nov-10 | 10 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Wood River West | Bio doc vers 1 | 42032 | 112-114 | 30-Nov-10 | 10-Dec-10 | 10 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Wood River West | Reevaluation | 42032 | 112-114 | 25-Apr-11 | 02-May-11 | 7 | comments sent back to Jon | NDOR / address FHWA comments and resubmit |
| North Loup to Ord | DR 53 | 42089 | 113-116 | 12-Apr-11 | 15-Apr-11 | 3 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| North Loup to Ord | SHPO concur req | 42089 | 113-116 | 20-Jul-11 | 26-Jul-11 | 6 | mm: reviewed letter, gave to front office to format and send | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| North Loup to Ord | Purpose and Need | 42089 | 113-116 | 5/7/2012 | 5/11/2012 | 4 | comments sent back to NDOR | NDOR / address FHWA comments and resubmit |
| Kearney Bypass | Draft final EA | 42103 | Oct-51 | 02-Jul-10 | 23-Jul-10 | 21 | sent comments to NDOR | NDOR / address FHWA comments and resubmit |
| Kearney | Final EA | 42103 | Oct-51 | 08-Sep-10 | 10-Sep-10 | 2 | comments given verbally to Jon Barber to make sure MBTA, BGEA and TE conservation conditions are consistent in text and mitigation sections of EA. | NDOR / address FHWA comments and resubmit |
| Kearney Bypass | Final EA | 42103 | 10--51 | 27-Sep-10 | 28-Sep-10 | 1 | document signed | document approved, FHWA to issue decision document |
| Kearney East | Merge letter | 42103 | Oct-51 | 01-Oct-10 | 01-Oct-10 | 0 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA | |
| Kearney East Bypass | Draft Public Responses | 42103 | Oct-51 | 09-Dec-10 | 10-Dec-10 | 1 | NDOR / address FHWA comments and resubmit | |
| Kearney Bypass | ACE P&N com review | 42103 | Oct-51 | 17-Dec-10 | 20-Dec-10 | 3 | NDOR / address FHWA comments and resubmit | |
| Kearney Bypass | Errata doc | 42103 | Oct-51 | 03-Jan-11 | 06-Jan-11 | 3 | contained info needed for incorporation into our decision doc | document approved, FHWA to issue decision document |
| In Superior | DR 53 | 42136 | 1990-7 | 07-Jul-11 | 11-Jul-11 | 4 | mm concurred with CE, but asked why a reeval not considered | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| In Superior | Bio doc version 1 | 42136 | 1990-7 | 11/18/2011 | 11/23/2011 | 5 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| In Superior | SHPO concur request | 42136 | 1990-7 | 1/30/2012 | 2/3/2012 | 4 | comments sent back to NDOR | NDOR / address FHWA comments and resubmit |
| In Superior | 4(f) concurrence | 42136 | 1990-7 | 1/31/2012 | 2/13/2012 | 13 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| In Superior | SHPO concur request | 42136 | 1990-7 | 2/8/2012 | 2/14/2012 | 6 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| In Superior | Cat Ex | 42136 | 1990-7 | 6/12/2012 | 6/12/2012 | 0 | comments sent back to NDOR | NDOR / assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
| In Superior | Cat Ex | 42136 | 1990-7 | 8/9/2012 | 8/14/2012 | 5 | comments sent back to NDOR | NDOR / assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
| Jct. N-78 West | DR 53 | 42162 | 1364-112 | 30-Mar-11 | 31-Mar-11 | 1 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Jct N-78 West | SHPO Concur Req | 42162 | 1364-112 | 07-Jul-11 | 11-Jul-11 | 4 | mm 7/11 gave to front office for mailing | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Jct N-78 West | Bio doc version 1 | 42162 | 1364-112 | 2/3/2012 | 2/17/2012 | 14 | document reviewed, signed, and ready to go to agencies. will go out either today or Monday. | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Jct N-78 West | 106 Concur Req | 42162 | 1364-112 | 4/2/2012 | 4/25/2012 | 23 | sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Jct. N-78 West | Cat Ex | 42162 | 1364-112 | 6/11/2012 | 6/12/2012 | 1 | comments sent back to NDOR | NDOR / address FHWA comments and resubmit |
| Jct. N-78 West | Cat Ex - revised | 42162 | 1364-112 | 6/18/2012 | 6/26/2012 | 8 | sent comments to NDOR concerning culvert location | NDOR / address FHWA comments and resubmit |
| Jct. N-78 West | Cat Ex - 3rd submittal | 42162 | 1364-112 | 6/27/2012 | 6/28/2012 | 1 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Geneva Northwest | Bio doc vers 1 | 42226 | 7030-30 | 21-Sep-10 | 29-Sep-10 | 8 | rb approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Geneva NW | DR 53 | 42226 | 7030-30 | 24-Jan-11 | 31-Jan-11 | 7 | mm concurred CE appropriate - recommended double-checking to ensure ROW already acquired met Uniform Act requirements | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Geneva NW | SHPO concur request | 42226 | 7030-30 | 2/3/2012 | 2/14/2012 | 11 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Ayr NE | DR 53 | 42235 | 7001-11 | 24-Jan-11 | 31-Jan-11 | 7 | mm concurred CE for project-recommended checking eligibility of bridge early | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Ayr Northeast | SHPO concur request | 42235 | 7001-11 | 12/1/2011 | 12/8/2011 | 7 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Ayr Northeast | Bio doc version 1 | 42235 | 7001-11 | 1/23/2012 | 1/25/2012 | 2 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Ayr Northeast | CE and Checklist | 42235 | 7001-11 | 3/28/2012 | 4/23/2012 | 26 | sent comments back to NDOR | NDOR / assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
| Ayr Northeast | CE - revised with comments | 42235 | 7001-11 | 5/3/2012 | 5/9/2012 | 6 | sent comments back to NDOR | NDOR / assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
| Ayr Northeast | Cat Ex | 42235 | 7001-11 | 5/10/2012 | 5/10/2012 | 0 | CE didn't contain NDOR signatures. Verbally told NDOR to review/sign and resubmit. | NDOR / address FHWA comments and resubmit |
| 7001-11 | Cat Ex - version 3 | 42235 | Ayr NE | 5/11/2012 | 5/11/2012 | 0 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| 12th, Elm Ave - 6th Ave | DR 53 | 42292 | 5516-7 | 28-Jan-11 | 31-Jan-11 | 3 | mm concurred a CE should be adequate | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| 12th St. Elm to 6th Ave | SHPO concur request | 42292 | 5516-7 | 4/17/2012 | 4/27/2012 | 10 | sent comments back to NDOR | NDOR / assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
| 12th St Improvements | 4(f) exception | 42292 | 5516-7 | 6/14/2012 | 6/14/2012 | 0 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. | |
| 12th St. Elm to 6th Ave | SHPO concur req -revised | 42292 | 5516-7 | 6/6/2012 | 6/25/2012 | 19 | waiting for 4(f) language from NDOR to insert into SHPO letter | None |
| 12th St. Improvements | SHPO letter | 42292 | 5516-7 | 6/28/2012 | 7/2/2012 | 4 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| 12th St Improvements, Hastings | Cat Ex | 42292 | 5516-7 | 8/3/2012 | 8/3/2012 | 0 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| 12th St, Elm - 6th Ave | 4(f) determ | 42292 | 5516-7 | 7/26/2012 | 7/26/2012 | 0 | None | |
| Platte River to US-81 | DR 53 | 42302 | 925-107 | 11/16/2011 | 11/23/2011 | 7 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Platte River to US-81 | SHPO concur req | 42302 | 925-107 | 8/8/2012 | 8/16/2012 | 8 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA | |
| Grand Island NW | DR 53 | 42322 | 7040-25 | 1/11/2012 | 1/16/2012 | 5 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Palmer NW | DR 53 | 42335 | 7061-27 | 1/23/2012 | 2/3/2012 | 11 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Archer Southwest | DR 53 | 42368 | 7061-28 | 1/24/2012 | 2/3/2012 | 10 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Lushton Northeast | DR 53 | 42372 | 2690-3 | 12-Aug-11 | 15-Aug-11 | 3 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Lushton Northeast | Bio doc version 1 | 42372 | 2690-3 | 2/1/2012 | 2/3/2012 | 2 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Wood River - Grand Island | DR 53 | 42399 | 304-149 | 11/25/2011 | 12/5/2011 | 10 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Wood River - Grand Island | SHPO concur request | 42399 | 304-149 | 2/22/2012 | 3/6/2012 | 13 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Hampton Link | Bio doc vers 1 | 42402 | L41D-101 | 29-Sep-10 | 29-Sep-10 | 0 | letters to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Hampton Link | SHPO concur req | 42402 | L41D-101 | 17-Nov-10 | 23-Nov-10 | 6 | comments sent back to NDOR | NDOR / address FHWA comments and resubmit |
| Hampton Link | SHPO concur req | 42402 | L41D(101) | 24-Nov-10 | 24-Nov-10 | 0 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Fullerton South | CE Determination | 42403 | 142-124 | 12-Apr-10 | 19-Apr-10 | 7 | NDOR / address FHWA comments and resubmit | |
| Fullerton South | DR-53 | 42403 | 142-124 | 22-Nov-10 | 15-Dec-10 | 23 | approved with comments | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Fullerton S & in Fullerton | Altern Analysis memo | 42403 | 142-124 | 03-Feb-11 | 15-Feb-11 | 12 | approved as long as USACE comments addressed | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Fullerton South | SHPO concur req | 42403 | 142-124 | 14-Feb-11 | 16-Feb-11 | 2 | letter sent to SHPO today | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Fullerton South & In Fullerton and South | CE | 42403 | 142-124 | 16-Sep-11 | 19-Sep-11 | 3 | comments sent back to NDOR | NDOR / address FHWA comments and resubmit |
| Fullerton South | revised CE - 9/21/11 | 42403 | 142-124 | 21-Sep-11 | 22-Sep-11 | 1 | NDOR / address FHWA comments and resubmit | |
| Fullerton South | revised CE - 9/23/11 | 42403 | 142-124 | 23-Sep-11 | 23-Sep-11 | 0 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Chapman-Central City | Bio doc vers 1 | 42405 | 305-130 | 18-Oct-10 | 21-Oct-10 | 3 | rb approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Chapman - Central City | DR 53 | 42405 | 305-130 | 04-Nov-10 | 08-Nov-10 | 4 | rb approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Phillips - Giltner | Bio doc vers 1 | 42415 | 807-151 | 30-Nov-10 | 13-Dec-10 | 13 | letters to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Aurora E & W | DR 53 | 42416 | 807-152 | 17-Mar-11 | 17-Mar-11 | 0 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Aurora East & West | Bio doc vers 1 | 42416 | 807-152 | 06-May-11 | 06-May-11 | 0 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Geneva West | DR 53 | 42435 | 7030-32 | 19-Aug-11 | 03-Sep-11 | 15 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| In Blue Hill & South | SHPO concur req | 42443 | 2811-114 | 31-Mar-11 | 31-Mar-11 | 0 | lettter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| In Blue Hill & South | Bio doc vers 1 | 42443 | 2811-114 | 09-Aug-11 | 09-Aug-11 | 0 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| In Blue Hill and South | CE | 42443 | 2811-114 | 12/5/2011 | 12/12/2011 | 7 | comments emailed back to NDOR | NDOR / address FHWA comments and resubmit |
| In Blue Hill and South | CE - revised | 42443 | 2811-114 | 1/27/2012 | 2/7/2012 | 11 | need signature page from NDOR | NDOR / address FHWA comments and resubmit |
| Hastings Northeast | DR 53 | 42445 | 2038-1 | 14-Oct-11 | 17-Oct-11 | 3 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Hastings Northeast | Bio doc version 1 | 42445 | 2038-1 | 11/1/2011 | 11/2/2011 | 1 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Hastings Northeast | SHPO concur request | 42445 | 2038-1 | 12/15/2011 | 12/21/2011 | 6 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Hastings Northeast | Cat Ex | 42445 | 2038-1 | 5/25/2012 | 6/6/2012 | 12 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Little Blue River, Ayr | DR 53 | 42446 | 744-109 | 06-May-11 | 11-May-11 | 5 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Little Blue River Ayr | SHPO concur req | 42446 | 744-109 | 12-Aug-11 | 17-Aug-11 | 5 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Geneva North | DR 53 | 42453 | 811-121 | 11/15/2011 | 11/23/2011 | 8 | approved with comments | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| In Ashton | DR 53 | 42460 | 2065-4 | 19-Nov-10 | 24-Nov-10 | 5 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| In Ashton | SHPO concur req | 42460 | 2065-4 | 22-Feb-11 | 24-Feb-11 | 2 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| In Ashton | Bio doc vers 1 | 42460 | 2065-4 | 05-Apr-11 | 07-Apr-11 | 2 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Central City North | DR 53 | 42475 | 142-127 | 29-Jun-11 | 01-Jul-11 | 2 | 6/28 orig doc sent 6/16, but was only cover pg. NDOR sent actual doc 6/29 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Central City North | SHPO concur request | 42475 | 142-127 | 2/6/2012 | 2/14/2012 | 8 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| In Fullerton and South | Bio doc vers 1 | 42476 | 142-124 | 21-Apr-11 | 27-Apr-11 | 6 | letters sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Prosser Spur | SHPO concur req | 42482 | S40D-105 | 29-Oct-10 | 08-Nov-10 | 10 | rb sent comments to Sara Porter to address and resubmit | NDOR / address FHWA comments and resubmit |
| Prosser Spur | Bio doc vers 1 | 42482 | S40D-105 | 09-Nov-10 | 12-Nov-10 | 3 | comments sent back to Eric Zach | NDOR / address FHWA comments and resubmit |
| Prosser Spur | Rev 106 Concur Request Letter | 42482 | S40D-105 | 24-Nov-10 | 10-Dec-10 | 16 | letter to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Prosser Spur | Bio doc vers 2 | 42482 | S40D-105 | 30-Nov-10 | 10-Dec-10 | 10 | comments sent back to Eric | NDOR / address FHWA comments and resubmit |
| Prosser Spur | NEPA Determ form | 42482 | S40D-105 | 25-Oct-10 | 14-Dec-10 | 50 | approved with comments | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Prosser Spur | Bio doc vers 3 | 42482 | S40D-105 | 14-Dec-10 | 17-Dec-10 | 3 | comments sent to Eric | NDOR / address FHWA comments and resubmit |
| Prosser Spur | Bio doc vers 3 | 42482 | S40D-105 | 17-Dec-10 | 17-Dec-10 | 0 | letters sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Prosser Spur | NDOR Concur Req | 42482 | S40D-105 | 19-Jan-11 | 24-Jan-11 | 5 | mtg held on 1/24. Preferred Alt identified among agencies. NDOR to provide Mtg minutes. | NDOR / address FHWA comments and resubmit |
| Prosser Spur | Detour memo | 42482 | S40D-105 | 25-Jan-11 | 31-Jan-11 | 6 | mm sent back with comments | NDOR / address FHWA comments and resubmit |
| Prosser Spur | SHPO Detour Resurf memo | 42482 | S40D-105 | 01-Feb-11 | 02-Feb-11 | 1 | concurrence received | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Prosser Spur | BIO Detour Resurf memo | 42482 | S40D-105 | 02-Feb-11 | 02-Feb-11 | 0 | approved mm | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Prosser Spur | SHPO Detour Memo R2 | 42482 | S40D-105 | 16-Mar-11 | 17-Mar-11 | 1 | sent comments to Sara. | NDOR / address FHWA comments and resubmit |
| Prosser spur | SHPO Detour resurf memo R2 | 42482 | S40D-105 | 25-Mar-11 | 30-Mar-11 | 5 | SHPO signed letter; signed letter provided to NDOR | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Prosser Spur | CE doc | 42482 | S40D-105 | 04-May-11 | 06-May-11 | 2 | sent comments back to Sara | NDOR / address FHWA comments and resubmit |
| Prosser Spur | CE submittal 2 | 42482 | S40D-105 | 26-May-11 | 27-May-11 | 1 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Nance Co Resurfacing | DR 53 | 42487 | 2490-4 | 05-Oct-11 | 06-Oct-11 | 1 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Nance County Resurfacing | Bio doc version 1 | 42487 | 2490-4 | 2/14/2012 | 2/17/2012 | 3 | letters sent to the agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Gibbon - Shelton | DR 53 | 42511 | 806-103 | 17-Mar-11 | 17-Mar-11 | 0 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Gibbon - Shelton | Bio Doc | 42511 | 806-103 | 26-Apr-11 | 27-Apr-11 | 1 | letters sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Shelton - Wood River | DR 53 | 42512 | 806-104 | 04-Feb-11 | 07-Feb-11 | 3 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Shelton to Wood River | Bio doc vers 1 | 42512 | 806-104 | 07-Mar-11 | 08-Mar-11 | 1 | document missing fed species matrix page. Comment sent to Eric to revise and resubmit. | NDOR / address FHWA comments and resubmit |
| Shelton - Wood River | Bio doc vers 2 | 42512 | 806-104 | 11-Mar-11 | 15-Mar-11 | 4 | letters sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Hampton to Henderson | DR 53 | 42514 | 807-155 | 1/24/2012 | 2/3/2012 | 10 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Henderson-Waco | DR 53 | 42515 | 807-156 | 11/4/2011 | 11/9/2011 | 5 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Waco - Utica | DR 53 | 42516 | 808-144 | 09-Dec-10 | 15-Dec-10 | 6 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Waco to Utica | Bio doc vers 1 | 42516 | 808-144 | 07-Mar-11 | 08-Mar-11 | 1 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Minden-Giddon | DR-53 | 42517 | 806-105 | 4/2/2012 | 4/6/2012 | 4 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Walk to Walnut - SRTS | DR 53 | 42521 | 40-57 | 03-Jan-11 | 11-Jan-11 | 8 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| SRTS Walk to Walnut | 4(f) de minimis | 42521 | 40-57 | 31-Aug-11 | 19-Sep-11 | 19 | Sent comments to NDOR | NDOR / address FHWA comments and resubmit |
| Walk to Walnut SRTS | Bio doc vers 1 | 42521 | 40-57 | 19-Sep-11 | 19-Sep-11 | 0 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Walk to Walnut | SHPO concur req | 42521 | 40-57 | 03-Oct-11 | 05-Oct-11 | 2 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Walk to Walnut | 4(f) De Minimis | 42521 | 40-57 | 13-Oct-11 | 17-Oct-11 | 4 | comment sent back to NDOR | NDOR / address FHWA comments and resubmit |
| Walk to Walnut SRTS | 4(f) de minimis | 42521 | 40-57 | 10/27/2011 | 11/2/2011 | 6 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. | |
| Walk to Walnut | CE | 42521 | 40-57 | 12/27/2011 | 1/4/2012 | 8 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Grand Island Walk to Walnut | 4(f) reconsideration | 42521 | 40-57 | 8/6/2012 | 8/6/2012 | 0 | None | |
| East Lochland Rd | Traffic Noise Summary | 42525 | 7552-1 | 25-Mar-10 | 25-Mar-10 | 0 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. | |
| Ft Kearney Bridge Rehab | DR 53 | 42551 | Oct-62 | 02-Nov-10 | 03-Nov-10 | 1 | rb approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Loup City Red Raider SRTS | DR 53 | 42558 | 82-14 | 12-Sep-11 | 16-Sep-11 | 4 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| York East | DR 53 | 42564 | 345-114 | 18-Apr-11 | 21-Apr-11 | 3 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| York East | Bio doc version 1 | 42564 | 345-114 | 1/12/2012 | 1/17/2012 | 5 | letters sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Hastings East | DR 53 | 42565 | 64-126 | 10/26/2011 | 10/28/2011 | 2 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| St. Paul North | DR-53 | 42567 | 2812-126 | 4/2/2012 | 4/23/2012 | 21 | comment sent back to NDOR | NDOR / address FHWA comments and resubmit |
| Alda Link | DR 53 | 42568 | L40C-106 | 05-Apr-11 | 11-Apr-11 | 6 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Red Cloud East | DR 53 | 42569 | 1364-113 | 12/7/2011 | 12/15/2011 | 8 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Buffalo / Dawson County Line | SHPO concur req | 42571 | 304-155 | 20-May-11 | 27-May-11 | 7 | comments sent back to Carin | NDOR / address FHWA comments and resubmit |
| Buffalo-Dawson Co. Line East | SHPO concur req | 42571 | 304-155 | 13-Jun-11 | 23-Jun-11 | 10 | 6/23 mm sent letter to AB for formatting/mailing, went out today | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Buffalo/Dawson County Line East | Bio doc version 1 | 42571 | 304-155 | 11/1/2011 | 11/2/2011 | 1 | letters sent to agencies. | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Buffalo/Dawson County Line East | Cat Ex - revised | 42571 | 304-155 | 8/2/2012 | 8/9/2012 | 7 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Buffalo/Dawson County Line East | Cat Ex | 42571 | 304-155 | 7/12/2012 | 7/23/2012 | 11 | comments sent back to NDOR | NDOR / address FHWA comments and resubmit |
| Hastings South | DR 53 | 42577 | 2811-115 | 18-Apr-11 | 21-Apr-11 | 3 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Grafton West | Bio doc | 42579 | 65-113 | 13-Sep-10 | 23-Sep-10 | 10 | mm letter given to Sue today to format | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Grafton West | NDF | 42579 | 65-113 | 22-Sep-10 | 04-Oct-10 | 12 | rb approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Grafton West | SHPO concur req | 42579 | 65-113 | 10-Dec-10 | 17-Dec-10 | 7 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Grafton West | CE determ form - V1 | 42579 | 65-113 | 31-Jan-11 | 02-Feb-11 | 2 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| 2nd Av, 25th-31st, Kearney | SHPO concur req | 42580 | 304-156 | 23-Nov-10 | 23-Nov-10 | 0 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| 25th - 31st, Kearney | Bio Doc vers 1 | 42580 | 102-119 | 10/18/2011 | 10/28/2011 | 10 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| 2nd Ave, 25th - 31st, Kearney | SHPO concur request | 42580 | 102-119 | 12/15/2011 | 12/20/2011 | 5 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| 25th - 31st St, Kearney | CE | 42580 | 102-119 | 2/27/2012 | 3/8/2012 | 10 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| 5th Ave, Kearney | DR-53 | 42585 | 304-156 | 17-Nov-10 | 23-Nov-10 | 6 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| 5th Ave, Kearney | Bio doc vers 1 | 42585 | 304-156 | 05-Jan-11 | 07-Jan-11 | 2 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| 5th Ave - Kearney | SHPO concur req | 42585 | 304-156 | 05-Jan-11 | 07-Jan-11 | 2 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| East Jct US-281 East | DR 53 | 42590 | 744-110 | 14-Dec-10 | 14-Dec-10 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation | |
| E Jct US-281 East | SHPO concur req | 42590 | 744-110 | 25-Mar-11 | 31-Mar-11 | 6 | comments emailed to Steve. | NDOR / address FHWA comments and resubmit |
| E Jct US-281 East | SHPO concur req - rev | 42590 | 744-110 | 08-Apr-11 | 13-Apr-11 | 5 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| In Geneva & West | DR 53 | 42591 | 415-107 | 5/24/2012 | 6/8/2012 | 15 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| In North Loup and South | DR 53 | 42593 | 113-120 | 11/15/2011 | 11/17/2011 | 2 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| North Loup and South | SHPO concur request | 42593 | 113-120 | 3/13/2012 | 3/15/2012 | 2 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| In North Loup & South | Bio doc | 42593 | 113-120 | 6/25/2012 | 7/2/2012 | 7 | letters sent to USFWS and NGPC | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| In Guide Rock & South | SHPO concur req | 42594 | 781-104 | 01-Apr-11 | 07-Apr-11 | 6 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| In Guide Rock & South | DR 53 | 42594 | 781-104 | 06-Apr-11 | 07-Apr-11 | 1 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Jct N-92 North | Bio doc vers 1 | 42595 | 112-118 | 18-Oct-10 | 21-Oct-10 | 3 | rb approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Hwy N-11, Jct N-92 N, Howard County | SHPO concur req | 42595 | 112-118 | 17-Nov-10 | 23-Nov-10 | 6 | letter to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Phillips East | Bio Doc | 42596 | 345-115 | 08-Nov-10 | 08-Nov-10 | 0 | rb approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| South Junction N-58 East | 106 Consultation Letter | 42597 | 924-109 | 14-Jul-10 | 26-Jul-10 | 12 | sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| N Jct N-14 to Genoa | DR-53 | 42600 | 225-116 | 4/2/2012 | 4/23/2012 | 21 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| E. Jct. US-30 South | DR 53 | 42601 | 102-120 | 12-Oct-10 | 13-Oct-10 | 1 | rb approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| E. Jct. US-30 South | SHPO concur | 42601 | 102-120 | 15-Oct-10 | 22-Oct-10 | 7 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| East Jct US-30 South | Bio doc vers 1 | 42601 | 102-120 | 14-Dec-10 | 20-Dec-10 | 6 | letters sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Loup City Northeast | DR 53 | 42614 | 2085-4 | 09-Jun-11 | 16-Jun-11 | 7 | mm concurred, added guidance regarding termini and 3R considerations | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| St. Paul East | DR 53 | 42618 | 924-112 | 11/15/2011 | 11/22/2011 | 7 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Giltner E & W | Bio doc vers 1 | 42630 | 807-158 | 24-Mar-11 | 01-Apr-11 | 8 | letters sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Giltner East & West | SHPO concur req | 42630 | 807-158 | 16-May-11 | 27-May-11 | 11 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Multi-location Resurfacing Hastings | DR53 | 42631 | 5516(8) | 06-Dec-10 | 14-Dec-10 | 8 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Hastings resurfacing | SHPO concur req | 42631 | 5516-8 | 14-Dec-10 | 17-Dec-10 | 3 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Resurf Hastings - mult. Locates | Bio doc vers 1 | 42631 | 5516-8 | 05-Jan-11 | 07-Jan-11 | 2 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| GI State & Capitol Av Trl | DR 53 | 42650 | 40-59 | 03-Feb-11 | 03-Feb-11 | 0 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| GI Connector Trail | SHPO concur req | 42650 | 40-59 | 06-Oct-11 | 07-Oct-11 | 1 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| State St & Cap Ave Connect Trail | Bio doc vers 1 | 42650 | 40-59 | 07-Oct-11 | 07-Oct-11 | 0 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| State Street & Capital Ave Connector Trail | 4(f) | 42650 | 40-59 | 10/28/2011 | 11/2/2011 | 5 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| State Street to Capital Ave Connector Trail | CE | 42650 | 40-59 | 12/29/2011 | 1/10/2012 | 12 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| 13th & Wheeler Dwntwn lighting | DR 53 | 42651 | 40-60 | 24-Jan-11 | 31-Jan-11 | 7 | mm approved to proceed as CE. Recommended early SHPO coordination | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| 3rd and Wheeler Downtown Historic Lighting | Bio doc version 1 | 42651 | 40-60 | 12/14/2011 | 12/20/2011 | 6 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| 3rd & Wheeler Downtown Historic Lighting Project | SHPO concur request | 42651 | 40-60 | 3/8/2012 | 3/15/2012 | 7 | comments sent back to NDOR | NDOR / address FHWA comments and resubmit |
| 3rd & Wheeler Downtown Historic Lighting | Revised SHPO concur request | 42651 | 40-60 | 3/16/2012 | 3/22/2012 | 6 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Kearney E Via removal | DR 53 | 42653 | 805-70 | 01-Oct-10 | 01-Oct-10 | 0 | rb approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Kearney E viad removal | Bio doc vers 1 | 42653 | 805-70 | 30-Nov-10 | 10-Dec-10 | 10 | letters to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Kearney E viaduct removal | CE doc | 42653 | 805-70 | 08-Apr-11 | 13-Apr-11 | 5 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| US-281 - Lawrence | SHPO concur req | 42654 | 44-108 | 24-Jan-11 | 31-Jan-11 | 7 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| US-281 - Lawrence | DR 53 | 42654 | 44-108 | 25-Jan-11 | 31-Jan-11 | 6 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Structures W of Aurora | DR 53 | 42661 | 807-160 | 04-Apr-11 | 11-Apr-11 | 7 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| I-80 Structures W of Aurora | SHPO concur req | 42661 | 807-160 | 12-Aug-11 | 17-Aug-11 | 5 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Rose Creek Bridge | Bio doc vers 1 | 42663 | 85-109 | 01-Oct-10 | 12-Oct-10 | 11 | letters to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Rose Creek Bridge | NEPA Determ form | 42663 | 85-109 | 01-Dec-10 | 14-Dec-10 | 13 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Rose Creek NE of Hubbell | SHPO concur req | 42663 | 85-109 | 31-Mar-11 | 31-Mar-11 | 0 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Rose Creek Bridge | NEPA CE | 42663 | 85-109 | 11-Jul-11 | 13-Jul-11 | 2 | mm reviewed CE, sent back comments | NDOR / address FHWA comments and resubmit |
| Rose Creek Bridge NE of Hubbell | CE form | 42663 | 85-109 | 29-Aug-11 | 06-Sep-11 | 8 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Mormon Island Trl Br | DR 53 | 42666 | 40-61 | 21-Mar-11 | 23-Mar-11 | 2 | comments sent to Allison | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Wood River - Grand Island | DR 53 | 42667 | 806-109 | 11-Feb-11 | 14-Feb-11 | 3 | approved, needs to be combined with 806-110 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| WoodRiver - Grand Island | Bio doc vers 1 | 42667 | 806-109 | 22-Feb-11 | 24-Feb-11 | 2 | sent comments to Eric - should be combined with 806-110 | NDOR / address FHWA comments and resubmit |
| Platte River - Phillips | DR 53 | 42668 | 806-110 | 11-Feb-11 | 14-Feb-11 | 3 | approved, needs to be combined with 806-109 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Platte Rvr to Phillips | Bio doc vers 1 | 42668 | 806-110 | 22-Feb-11 | 24-Feb-11 | 2 | sent comments to Eric - should be combined with 806-109 | NDOR / address FHWA comments and resubmit |
| Cotesfield N&S | DR 53 | 42681 | 112-119 | 14-Apr-11 | 15-Apr-11 | 1 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Waco Interchange Bridge | DR 53 | 42687 | 808-152 | 16-Sep-11 | 19-Sep-11 | 3 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Waco Interchange Bridge | SHPO concur req | 42687 | 808-152 | 26-Sep-11 | 26-Sep-11 | 0 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Waco Interchange Bridge | Bio doc version 1 | 42687 | 808-152 | 3/21/2012 | 4/20/2012 | 30 | NDOR / address FHWA comments and resubmit | |
| Waco Interchange Bridge | Bio doc version 2 | 42687 | 808-152 | 5/2/2012 | 5/10/2012 | 8 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Pioneer Spirit Trail Phase III | 4(f) exception | 42688 | Jan-50 | 12/16/2011 | 12/27/2011 | 11 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Waco Interchange | Bio doc vers 1 | 42689 | 808-151 | 19-Oct-10 | 21-Oct-10 | 2 | rb approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| 19th St., York | DR 53 | 42696 | 6312-2 | 13-Oct-10 | 21-Oct-10 | 8 | rb approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| 19th Street, Blackburn-Delaware, York | Bio doc version 1 | 42696 | 6312-2 | 10/28/2011 | 10/28/2011 | 0 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| 19th Street, Blackburn - Delaware, York | SHPO concur request | 42696 | 6312-2 | 12/21/2011 | 12/23/2011 | 2 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| 19th Street Blackburn to Delaware | Cat Ex | 42696 | 6312-2 | 4/12/2012 | 4/30/2012 | 18 | sent comments back to NDOR | NDOR / assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
| Marquis to US 34, York | DR 53 | 42697 | 6303-4 | 13-Oct-10 | 21-Oct-10 | 8 | rb approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Division Ave, Marquis - US 34, York | SHPO concur req | 42697 | 6303-4 | 6/25/2012 | 6/27/2012 | 2 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Little Blue Rvr Ped Trl | DR 53 | 42698 | 85-11 | 03-Feb-11 | 03-Feb-11 | 0 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| In Grand Island | DR 53 | 42699 | 304-157 | 06-Apr-11 | 12-Apr-11 | 6 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| In Grand Island | Bio doc version 1 | 42699 | 304-157 | 12/20/2011 | 12/23/2011 | 3 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Baltimore Ave, 12th - 14th | DR 53 | 42704 | 5505-4 | 27-Jun-11 | 30-Jun-11 | 3 | concurred | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| 9th St Burlington Ave to Elm, Grand Island | DR 53 | 42705 | 5514-4 | 30-Jun-11 | 01-Jul-11 | 1 | mm concurred | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| 9th St - Burlington to Elm Ave | SHPO concur request | 42705 | 5514-4 | 11/21/2011 | 11/25/2011 | 4 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| 9th St - Burlington to Elm Ave | Bio doc version 1 | 42705 | 5514-4 | 11/21/2011 | 11/25/2011 | 4 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| GI Resurf - various | DR 53 | 42706 | 5409-2 | 06-May-11 | 11-May-11 | 5 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Various Locations in Grand Island | Bio doc version 1 | 42706 | 5409-2 | 1/25/2012 | 2/3/2012 | 9 | letters sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Grand Island Resurfacing - Various Locations | SHPO concur request | 42706 | 5409-2 | 3/7/2012 | 3/15/2012 | 8 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Cap Ave - Webb Road to Broadwell, GI | DR 53 | 42707 | 5436-5 | 06-May-11 | 11-May-11 | 5 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Capital Ave - Webb Rd to Broadwell Ave | Env Class Request | 42707 | 5436-5 | 5/22/2012 | 6/6/2012 | 15 | comments sent to NDOR | NDOR / address FHWA comments and resubmit |
| North Loup - Ord resurfacing | Bio doc version 1 | 42708 | 113-121 | 12/19/2011 | 12/21/2011 | 2 | NDOR to resubmit once resurfacing vs EA project issue has been resolved | NDOR / address FHWA comments and resubmit |
| North Loup to Ord | DR 53 | 42708 | 113-121 | 12/21/2011 | 12/21/2011 | 0 | NDOR to resubmit once resurfacing vs EA project issue is resolved. | NDOR / address FHWA comments and resubmit |
| Superior Schools Safe Routes | DR 53 | 42718 | 65-24 | 10/21/2011 | 10/28/2011 | 7 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Osborne Drive East Guardrail | DR 53 | 42733 | 5519-5 | 6/6/2012 | 6/12/2012 | 6 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Hemingford to Berea | SHPO concur req | 51182 | 21-77 | 08-Dec-10 | 10-Dec-10 | 2 | letter to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Hemingford - Berea | Bio doc vers 1 | 51182 | 21-117 | 29-Dec-10 | 07-Jan-11 | 9 | letters sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Morril West | CE | 51216 | 261-153 | 04-Mar-10 | 17-Mar-10 | 13 | NDOR / address FHWA comments and resubmit | |
| Morrill West | 106 Consultation Letter | 51216 | 261-153 | 15-Jul-10 | 26-Jul-10 | 11 | sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Morrill West | NEPA CE V2 | 51216 | 261-153 | 13-Aug-10 | 13-Aug-10 | 0 | rb approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Dix South & East | DR 53 | 51233 | 301-134 | 5/25/2012 | 6/8/2012 | 14 | approved; project comined with Kimball to Dix project (30-1(127)/51395). | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Scottsbluff West Viaduct | DR 53 | 51250 | 921-121 | 5/18/2012 | 6/5/2012 | 18 | comments sent to NDOR. need more information. | NDOR / address FHWA comments and resubmit |
| Scottsbluff West Viaduct | DR 53 - revised | 51250 | 921-121 | 6/19/2012 | 6/26/2012 | 7 | Still not enough information to determine if a CE is appropriate. requested additional informaiton regarding previous coordination with agencies and Tribes and also asked about status of existing MOA for arch site. | NDOR / address FHWA comments and resubmit |
| Oshkosh - Lewellen | DR 53 | 51261 | 261-157 | 4/11/2012 | 4/27/2012 | 16 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Oshkosh - Lewellen | SHPO concur request | 51261 | 261-157 | 5/21/2012 | 6/4/2012 | 14 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Oshkosh - Lewellen | SHPO Supplemental | 51261 | 261-157 | 6/25/2012 | 6/27/2012 | 2 | comments sent back to NDOR | NDOR / address FHWA comments and resubmit |
| Oshkosh - Lewellen | SHPO concur req - revised | 51261 | 261-157 | 6/29/2012 | 7/13/2012 | 14 | sent comments back to NDOR | NDOR / address FHWA comments and resubmit |
| Oshkosh - Lewellen | SHPO revised concur req | 51261 | 261-157 | 7/18/2012 | 7/26/2012 | 8 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| In Chadron | DR 53 | 51271 | 201-135 | 5/22/2012 | 6/4/2012 | 13 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Hay Springs South | DR 53 | 51284 | 874-116 | 25-Mar-11 | 29-Mar-11 | 4 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Hay Springs South | Bio doc version 1 | 51284 | 874-116 | 3/1/2012 | 3/8/2012 | 7 | comment sent back to NDOR | NDOR / address FHWA comments and resubmit |
| Rushville to Gordon | DR 53 | 51289 | 201-136 | 3/13/2012 | 4/5/2012 | 23 | sent back unapproved. questionable eligibility, and written statements that proponent trying to avoid ADA requirements. DR53 not approved. Proponent needs to review proposed project in light of ADA requirements and fed-aid eligibility requirements. | NDOR / address FHWA comments and resubmit |
| Harrison West | Bio doc vers 1 | 51290 | 201-137 | 21-Sep-10 | 29-Sep-10 | 8 | letters to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| In Bayard and South | DR 53 | 51292 | 261-160 | 4/6/2012 | 4/26/2012 | 20 | sent comments to NDOR | NDOR / address FHWA comments and resubmit |
| In Bayard & South | DR-53 resubmittal | 51292 | 261-160 | 6/5/2012 | 6/12/2012 | 7 | DR53 to be resubmitted with updated scope. | NDOR / address FHWA comments and resubmit |
| In Bayard & South | DR 53 | 51292 | 261-160 | 6/14/2012 | 6/26/2012 | 12 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| BNSF - Bridgeport Viad study | DR 53 | 51299 | 261-161 | 09-Mar-11 | 10-Mar-11 | 1 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Bushnell to W Kimball | Bio doc vers 1 | 51309 | 801-171 | 28-Sep-10 | 01-Oct-10 | 3 | letters to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Bushnell to W Kimball | Bio doc vers 2 | 51309 | 801-171 | 07-Dec-10 | 10-Dec-10 | 3 | letters to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| East Kimball - Potter | DR 53 | 51311 | 801-172 | 14-Apr-11 | 15-Apr-11 | 1 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| East Kimball - Potter | Bio doc version 1 | 51311 | 801-172 | 12/9/2011 | 12/15/2011 | 6 | letters to go to USFWS and NGPC | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| East Kimball - Potter | Bio doc version 2 | 51311 | 801-172 | 1/4/2012 | 1/9/2012 | 5 | letters sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Sidney Deadwood Trail | Bio Doc | 51326 | 17-24 | 13-Aug-10 | 20-Aug-10 | 7 | concur request to NGPC and fyi to USFWS | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Sidney Deadwood Trl - phase 3 | DR 53 | 51326 | 17-24 | 23-Jan-11 | 31-Jan-11 | 8 | concurred CE appropriate level for NEPA mm | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Sidney Deadwood Trail | Reeval | 51326 | 17-24 | 15-Apr-11 | 19-Apr-11 | 4 | letters sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Sidney Deadwood Trl, Phase 3 | SHPO concur req | 51326 | 17-24 | 06-Jun-11 | 10-Jun-11 | 4 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Sidney Deadwood Trl Ph. III | CE | 51326 | 17-24 | 03-Aug-11 | 05-Aug-11 | 2 | sent comments back to NDOR | NDOR / address FHWA comments and resubmit |
| Sidney Deadwood Trail Ph III | CE - version 2 | 51326 | 17-24 | 20-Sep-11 | 26-Sep-11 | 6 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| N-88 Jct North & South | Bio doc vers 1 | 51335 | 713-126 | 30-Sep-10 | 01-Oct-10 | 1 | letters to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| South Potash Ave, Alliance | DR 53 | 51347 | 6263-1 | 12-Oct-10 | 13-Oct-10 | 1 | rb approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| South Potash Avenue | SHPO concur request | 51347 | 6263-1 | 12/19/2011 | 12/21/2011 | 2 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| South Potash Ave, Alliance | Bio doc version 1 | 51347 | 6263-1 | 3/8/2012 | 3/15/2012 | 7 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Agate South | DR 53 | 51361 | 294-107 | 09-Feb-11 | 09-Feb-11 | 0 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Agate South | Bio Doc | 51361 | 294-107 | 20-Apr-11 | 27-Apr-11 | 7 | letters sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Sioux/Box Butte Co Line to N-2 | DR 53 | 51373 | 714-119 | 6/14/2012 | 6/26/2012 | 12 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Sunol and Lodgepole Links | DR 53 | 51389 | L17E-108 | 11/22/2011 | 11/28/2011 | 6 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Sunol and Lodgepole Links | SHPO concur request | 51389 | L17E-108 | 12/8/2011 | 12/9/2011 | 1 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Kimball to Dix | DR 53 | 51395 | 301-127 | 12/13/2011 | 12/20/2011 | 7 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Chadron North | 106 Consultation Letter | 51397 | 3854-133 | 15-Jul-10 | 26-Jul-10 | 11 | sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Chadron North | Bio doc vers 1 | 51397 | 3854-133 | 28-Sep-10 | 01-Oct-10 | 3 | letters to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Chadron South | DR-53 | 51398 | 3854-134 | 4/2/2012 | 4/6/2012 | 4 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Chadron South | Archeological testing plan | 51398 | 3854-134 | 7/12/2012 | 7/25/2012 | 13 | comments sent back to NDOR | NDOR / address FHWA comments and resubmit |
| Sidney West | DR 53 | 51402 | 301-130 | 07-Jul-11 | 11-Jul-11 | 4 | mm concurred with CE | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Sidney West | Bio doc version 1 | 51402 | 301-130 | 4/17/2012 | 4/23/2012 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA | |
| Berea North | DR 53 | 51403 | 3854-136 | 25-Jul-11 | 29-Jul-11 | 4 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Berea North | Bio doc version 1 | 51403 | 3854-136 | 1/23/2012 | 2/1/2012 | 9 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Gering Northfield | DR 53 | 51407 | 79-40 | 08-Apr-11 | 12-Apr-11 | 4 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| High Mast Towers | Effect Determ Pkg | 51413 | 5-101 | 12-May-10 | 21-May-10 | 9 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| L62A/US-385 - Alliance | NDOR Review request | 51432 | 3853-118 | 04-Nov-10 | 04-Dec-10 | 30 | NDOR / address FHWA comments and resubmit | |
| Jct L62A/US385 - Alliance | Purp and Need | 51432 | 3853-118 | 16-Mar-11 | 28-Mar-11 | 12 | comments sent back to Carin | NDOR / address FHWA comments and resubmit |
| Jct L62A/US-385 - Alliance | Purp & Need | 51432 | 3853-118 | 19-Apr-11 | 02-May-11 | 13 | sent comments back to Carin | NDOR / address FHWA comments and resubmit |
| Heartland Express Alliance Section | SHPO concur req | 51432 | 3853-118 | 01-Jun-11 | 10-Jun-11 | 9 | sent comment to Carin re scenic byway info | NDOR / address FHWA comments and resubmit |
| Heartland Expressway | Alternatives letter for agencies review | 51432 | 3853-118 | 12/20/2011 | 1/4/2012 | 15 | ok to send out | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Heartland Expressway | SHPO concur request | 51432 | 3853-118 | 1/4/2012 | 1/17/2012 | 13 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Heartland Expr, Jct L62A/US 385 to Alliance | THPO concur req | 51432 | 3853-118 | 7/20/2012 | 7/24/2012 | 4 | THPO letters sent out | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Broadway, 14th to 20th, Scottsbluff | Bio doc version 1 | 51449 | 5701-8 | 1/12/2012 | 1/16/2012 | 4 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Broadway, 14th to 20th, Scottsbluff | SHPO concur request | 51449 | 5701-8 | 3/7/2012 | 3/15/2012 | 8 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Emerson Ave, Alliance | DR 53 | 51450 | 6255-3 | 12-Oct-10 | 13-Oct-10 | 1 | rb approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Emerson Ave- 18th St to 25th St | SHPO Concur Req 106 | 51450 | 6255-3 | 10-Jun-11 | 10-Jun-11 | 0 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| 18th St. - 25th St. | Bio Doc V1 | 51450 | 6255-3 | 11-Jul-11 | 20-Jul-11 | 9 | approved. | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Potter - Brownson | DR 53 | 51451 | 801-178 | 02-Sep-11 | 14-Sep-11 | 12 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| BoxButte Historic lighting | DR 53 | 51453 | 6257-2 | 01-Mar-11 | 02-Mar-11 | 1 | approved with comments | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| 27th Ave I, to Hwy 26 | DR 53 | 51454 | 5720-1 | 18-Oct-10 | 21-Oct-10 | 3 | rb approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| 27th St, Ave I - Hwy 26, Scottsbluff | Bio doc vers 1 | 51454 | 5720-1 | 01-Feb-11 | 02-Feb-11 | 1 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| 27th, Ave I to Hwy 26, Scottsbluff | SHPO concur req | 51454 | 5720-1 | 25-Feb-11 | 28-Feb-11 | 3 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| 10th Ave, Sidney | DR 53 | 51456 | 6363-3 | 04-Jan-11 | 11-Jan-11 | 7 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| 10th Ave - Osage to Illinois, Sidney | SHPO concur request | 51456 | 6363-3 | 4/25/2012 | 5/8/2012 | 13 | reviewed today, will go out to SHPO tomorrow | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Sunol-Chappell | DR-53 | 51459 | 802-97 | 4/2/2012 | 4/20/2012 | 18 | None | |
| Wyoming Line - N-71 | DR 53 | 51460 | 881-108 | 01-Apr-11 | 05-Apr-11 | 4 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Wyoming Line - N-71 | Bio doc version 1 | 51460 | 881-108 | 12/14/2011 | 12/20/2011 | 6 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA | |
| Wyoming Line - N-71 | Bio doc version 2 | 51460 | 881-108 | 1/4/2012 | 1/9/2012 | 5 | letters sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| US-26 & N-71, Scottsbluff | DR 53 | 51464 | 261-165 | 28-Mar-11 | 29-Mar-11 | 1 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| US-26 and N-71, Scottsbluff | Bio doc version one | 51464 | 261-165 | 12/19/2011 | 12/22/2011 | 3 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Hemingford Non-infra | DR 53 | 51478 | Jul-58 | 08-Apr-11 | 12-Apr-11 | 4 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| In Melbeta | DR 53 | 51480 | 921-125 | 11/21/2011 | 11/25/2011 | 4 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| In Melbeta | SHPO concur request | 51480 | 921-125 | 2/21/2012 | 3/6/2012 | 14 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| In Melbeta | SHPO concur request | 51480 | 915-118 | 3/14/2012 | 3/15/2012 | 1 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Weyerts South | DR 53 | 51484 | ER 1140-4 | 23-Sep-11 | 23-Sep-11 | 0 | Signed by Cheyenne Co 11/12/10. Signed by NDOR 9/23/11 and emailed to FHWA 9/23/11. FHWA concurred to proceed as PCE/CE | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Ft Sidney Rd - Hwy 30 to 11th Ave, Sidney | DR 53 | 51486 | 6359-1 | 30-Jun-11 | 01-Jul-11 | 1 | mm concurred and added some guidance | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Sidney - Sunol | DR-53 | 51487 | 802-98 | 29-Sep-11 | 30-Sep-11 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation | |
| Ave I, West Overland - 27th, Scottsbluff | DR 53 | 51488 | 5703-2 | 09-Jun-11 | 16-Jun-11 | 7 | mm concurred | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| 10th St Crescent Dr to River Bridge, Gering | DR 53 | 51489 | 5701-9 | 30-Jun-11 | 01-Jul-11 | 1 | mm concurred and added some guidance | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| 10th Street, Crescent Dr to River Bridge | SHPO concur request | 51489 | 5701-9 | 12/9/2011 | 12/9/2011 | 0 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| 10th Street Cresent Drive - River Bridge | Bio doc version 1 | 51489 | 5701-9 | 1/4/2012 | 1/16/2012 | 12 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| 10th St Box Butte to Flack Ave, Alliance | DR 53 | 51490 | 6254-7 | 30-Jun-11 | 01-Jul-11 | 1 | mm concurred and added guidance | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| E Jct US-20 North | DR 53 | 51506 | 874-117 | 7/12/2012 | 8/8/2012 | 27 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| SB Valley Pathway N | DR-53 | 51512 | 79-42 | 4/3/2012 | 4/26/2012 | 23 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Scottsbluff Valley Pathway North | SHPO concur request | 51512 | 79-42 | 4/25/2012 | 4/27/2012 | 2 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Dunning Northeast | SHPO concur req | 60818 | 913-103 | 22-Feb-11 | 24-Feb-11 | 2 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Dunning Northeast | SHPO concur request | 60818 | 913-103 | 2/23/2012 | 3/6/2012 | 12 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Dunning Northeast | Bio doc version 1 | 60818 | 913-103 | 3/21/2012 | 4/20/2012 | 30 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA | |
| Dunning Northeast | Scope Change Memo | 60818 | 913-103 | 5/23/2012 | 5/25/2012 | 2 | letters sent to USFWS and NGPC | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Dunning Northeast | Cat Ex | 60818 | 913-103 | 6/18/2012 | 6/26/2012 | 8 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Merna - Broken Bow | DR 53 | 60938 | 23-117 | 28-Sep-10 | 04-Oct-10 | 6 | rb approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Merna-Broken Bow | Bio doc vers 1 | 60938 | 23-117 | 02-Nov-10 | 03-Nov-10 | 1 | letters to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Merna - Broken Bow | SHPO concur req | 60938 | 23-117 | 05-Jan-11 | 07-Jan-11 | 2 | comments sent back to Jon | NDOR / address FHWA comments and resubmit |
| Merna - Broken Bow | SHPO concur req | 60938 | 23-117 | 10-Jan-11 | 31-Jan-11 | 21 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Merna to Broken Bow | SHPO concur req | 60938 | 23-117 | 10-Jan-11 | 31-Jan-11 | 21 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Merna to Broken Bow | Scope Change Memo | 60938 | 23-117 | 4/25/2012 | 4/26/2012 | 1 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Big Blue Springs | SHPO concurrence letter | 60939 | 302(133) | 14-Sep-10 | 23-Sep-10 | 9 | to Sue for formatting of letter | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Big Springs-Brule | Bio doc vers 1 | 60939 | 302-133 | 19-Oct-10 | 22-Oct-10 | 3 | letters sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Sargent South | SHPO concur req | 60943 | 1833-113 | 18-May-11 | 19-May-11 | 1 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Seneca East & West | SHPO Concur | 61009 | 22-113 | 20-Aug-10 | 27-Aug-10 | 7 | sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Seneca East & West | DR 53 | 61009 | 22-113 | 25-Oct-10 | 26-Oct-10 | 1 | rb approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Seneca East and West | Bio Doc vers 1 | 61009 | 22-113 | 10/18/2011 | 10/28/2011 | 10 | letters sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Seneca East & West | CE | 61009 | 22-113 | 1/27/2012 | 2/7/2012 | 11 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| In Broken Bow | SHPO concur req | 61200 | 23-118 | 19-Jan-11 | 31-Jan-11 | 12 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| In Broken Bow | SHPO concur req | 61200 | 23-118 | 31-May-11 | 10-Jun-11 | 10 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| In Broken Bow | Bio doc vers 1 | 61200 | 23-118 | 18-Aug-11 | 23-Aug-11 | 5 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| In Broken Bow | 4(f) concur letters | 61200 | 23-118 | 1/3/2012 | 1/13/2012 | 10 | comments emailed back to NDOR | NDOR / address FHWA comments and resubmit |
| In Broken Bow | 4(f) de minimis forms | 61200 | 23-118 | 1/17/2012 | 1/25/2012 | 8 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| In Broken Bow | CE | 61200 | 23-118 | 1/31/2012 | 2/8/2012 | 8 | sent comments back to NDOR | NDOR / address FHWA comments and resubmit |
| In Broken Bow | CE - revised | 61200 | 23-118 | 2/27/2012 | 3/5/2012 | 7 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Sutherland North | DR 53 | 61231 | 1475-5 | 24-Jan-11 | 31-Jan-11 | 7 | sent back with non-concurrence. Recommending EA | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Sargent North | Bio doc vers 1 | 61232 | 1833-115 | 04-Oct-10 | 12-Oct-10 | 8 | rb sent eric comments | NDOR / address FHWA comments and resubmit |
| Sargent North | DR 53 | 61232 | 1833-115 | 08-Oct-10 | 12-Oct-10 | 4 | rb approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Sargent North | Bio doc vers 1 - revised | 61232 | 1833-115 | 15-Oct-10 | 19-Oct-10 | 4 | Eric Zach to revise according to discussion at env coordination meeting today. He is going to add a paragraph discussing the informal coordination between USFWS and a private landowner regarding the movement of fencing prior to construction. Once revise | NDOR / address FHWA comments and resubmit |
| Sargent North | Bio doc - revised | 61232 | 1833-115 | 22-Oct-10 | 22-Oct-10 | 0 | letters to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Sargent North | SHPO concur | 61232 | 1833-115 | 09-Nov-10 | 12-Nov-10 | 3 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Sargent North | CE | 61232 | 1833-115 | 16-Feb-11 | 22-Feb-11 | 6 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Overton Southwest | DR 53 | 61260 | 7024-22 | 1/18/2012 | 1/25/2012 | 7 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Hershey viaduct | DR 53 | 61277 | L56C-106 | 14-Mar-11 | 15-Mar-11 | 1 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Buffalo Bill | reeval for additl easement | 61283 | 5805(5) | 09-Mar-10 | 11-Mar-10 | 2 | NDOR / address FHWA comments and resubmit | |
| Anselmo Northeast | DR 53 | 61302 | 7021-27 | 11/25/2011 | 12/1/2011 | 6 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Anselmo Northeast | 4(f) concur memo | 61302 | 7021-27 | 1/19/2012 | 1/31/2012 | 12 | sent comments back to NDOR | NDOR / assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
| Anselmo Northeast | SHPO concur request | 61302 | 7021-27 | 1/25/2012 | 1/31/2012 | 6 | sent comments back to NDOR | NDOR / assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
| Anselmo Northeast | Bio doc version 1 | 61302 | 7021-27 | 3/23/2012 | 4/23/2012 | 31 | not sure if the person doing the BA visited the site; the doc didn't make a clear case that the stream wasn't suitable for the dace. Requested additl info. | NDOR / address FHWA comments and resubmit |
| Anselmo Northeast | Bio doc - version 2 | 61302 | 7021-27 | 6/27/2012 | 7/2/2012 | 5 | comments sent back to NDOR | NDOR / address FHWA comments and resubmit |
| Anselmo Northeast | Bio doc - version 2 | 61302 | 7021-27 | 7/3/2012 | 7/12/2012 | 9 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA | |
| Anselmo Northeast | SHPO concur req | 61302 | 7021-27 | 7/10/2012 | 8/8/2012 | 29 | comments sent back to NDOR | NDOR / address FHWA comments and resubmit |
| Ansley Southeast | DR 53 | 61303 | 7021-28 | 11/25/2011 | 12/5/2011 | 10 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Ansley Southeast | SHPO concur request | 61303 | 7021-28 | 12/7/2011 | 12/9/2011 | 2 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Ansley Southeast | Bio doc version 1 | 61303 | 7021-28 | 2/24/2012 | 3/8/2012 | 13 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| 13th St | bio memo | 61338 | 6556(4) | 10-Feb-10 | 22-Feb-10 | 12 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. | |
| North Platte East | Bio doc version 2 | 61339 | 803-136 | 7/26/2012 | 7/26/2012 | 0 | letters sent to USFWS and NGPC | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| 1st - 6th Sts., North Platte | DR 53 | 61359 | 832-128 | 7/30/2012 | 8/14/2012 | 15 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Lewellen South | Bio doc vers 1 | 61368 | 261-158 | 18-Oct-10 | 22-Oct-10 | 4 | verbally asked eric to fix the inconsistencies with the Gray Wolf and the Ferret and also add the USFWS range map reference and then resubmit. | NDOR / address FHWA comments and resubmit |
| Lewellen South | Bio doc - revised | 61368 | 261-158 | 22-Oct-10 | 22-Oct-10 | 0 | letters to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| North Platte - Maxwell | DR 53 | 61399 | 803-136 | 06-Oct-10 | 12-Oct-10 | 6 | rb approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| North Platte East | 106 Concur Req | 61399 | 803-136 | 3/29/2012 | 4/25/2012 | 27 | sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| North Platte East | Bio doc version 1 | 61399 | 803-136 | 7/23/2012 | 7/26/2012 | 3 | comment sent to NDOR | NDOR / address FHWA comments and resubmit |
| North Platte East | FHWA review req | 61399 | 803-138 | 7/19/2012 | 7/26/2012 | 7 | comments sent back to NDOR | NDOR / address FHWA comments and resubmit |
| Paxton East | DR 53 | 61401 | 803-149 | 14-Oct-11 | 17-Oct-11 | 3 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Maxwell SW | DR 53 | 61414 | 1480-11 | 01-Mar-11 | 02-Mar-11 | 1 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Maxwell Southwest | Bio doc vers 1 | 61414 | 1480-11 | 06-May-11 | 06-May-11 | 0 | letters sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Maxwell Southwest | SHPO concur req | 61414 | 1480-11 | 18-Jul-11 | 20-Jul-11 | 2 | ltr to SHPO on 7/21/11 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Maxwell SW | Categorical Exclusion | 61414 | 1480-11 | 12/21/2011 | 12/27/2011 | 6 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Bridwood Grade Separation | Reevaluation | 61416 | 1390-3 | 2/7/2012 | 2/15/2012 | 8 | provided comments to NDOR | NDOR / address FHWA comments and resubmit |
| Birdwood Grade Separation | Re-evaluation revised | 61416 | 1390-3 | 2/24/2012 | 3/8/2012 | 13 | comments sent back to NDOR | NDOR / address FHWA comments and resubmit |
| Bridwood Grade Separation | Re-eval version 2 | 61416 | 1390-3 | 6/18/2012 | 6/19/2012 | 1 | comments sent back to NDOR | NDOR / assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
| Bridwood Grade Separation | Re-eval version 2 | 61416 | 1390-3 | 6/21/2012 | 6/21/2012 | 0 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| OA project | Bio doc version 1 | 61424 | 804-136 | 06-Aug-10 | 11-Aug-10 | 5 | bio doc approved. Sue sending out agency letters. | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Bio doc vers 1 | Gothenburg E and W | 61425 | 804-137 | 28-Feb-11 | 01-Mar-11 | 1 | document needs to be combined with 804-138 and resubmitted | NDOR / address FHWA comments and resubmit |
| Bio doc vers 1 | Cozad to Darr | 61426 | 804-138 | 28-Feb-11 | 01-Mar-11 | 1 | document needs to be combined with 804-137 and resubmitted | NDOR / address FHWA comments and resubmit |
| Hershey East | DR 53 | 61427 | 803-140 | 11/22/2011 | 12/5/2011 | 13 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Paxton East | DR 53 | 61428 | 803-141 | 6/19/2012 | 6/27/2012 | 8 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Ash - Jefferson St, Lexington | NEPA & CE | 61433 | 2832-102 | 06-Apr-10 | 07-Apr-10 | 1 | NDOR / address FHWA comments and resubmit | |
| Sutherland West | DR 53 | 61442 | 803-143 | 21-Mar-11 | 21-Mar-11 | 0 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Sutherland West | SHPO concur request | 61442 | 803-143 | 5/23/2012 | 6/8/2012 | 16 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Lexington East Viad. | DR 53 | 61457 | 1705-3 | 27-Dec-10 | 05-Jan-11 | 9 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Ansley East | SHPO concur req | 61458 | 923-105 | 04-Jan-11 | 07-Jan-11 | 3 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Ansley East | DR 53 | 61458 | 923-105 | 11/1/2011 | 11/2/2011 | 1 | NDOR (or LPA) / Must prepare technical and NEPA documentation | |
| Overton East | DR 53 | 61460 | 303-115 | 10-Mar-11 | 10-Mar-11 | 0 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Overton East | SHPO concur req | 61460 | 303-115 | 23-Sep-11 | 26-Sep-11 | 3 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Overton East | Bio doc vers 1 | 61460 | 303-115 | 10/21/2011 | 10/28/2011 | 7 | letters sent agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Paxton to Sutherland | CE | 61461 | 302-138 | 22-Feb-10 | 17-Mar-10 | 23 | NDOR / address FHWA comments and resubmit | |
| Paxton - Sutherland | NEPA & CE | 61461 | 302-138 | 06-Apr-10 | 07-Apr-10 | 1 | NDOR / address FHWA comments and resubmit | |
| Paxton - Sutherland | CE v2 | 61461 | 302-138 | 12-Apr-10 | 15-Apr-10 | 3 | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required | |
| Stapleton North | SHPO concur req | 61463 | 833-108 | 28-Mar-11 | 31-Mar-11 | 3 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Stapleton North | DR 53 | 61463 | 833-108 | 30-Mar-11 | 31-Mar-11 | 1 | approved again - to be combined with Stapleton South 83-2(133), 61464 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Stapleton North & Stapleton South | CE | 61463 | 833-108 | 4/4/2012 | 4/23/2012 | 19 | "approved | |
| Documents saved to 833-108/env/nepa." | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required | |||||||
| Stapleton South | 106 Consultation Letter | 61464 | 832-133 | 15-Jul-10 | 26-Jul-10 | 11 | sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Wellfleet North | DR 53 | 61466 | 832-134 | 12-Apr-11 | 12-Apr-11 | 0 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Wellfleet North | Bio doc vers 1 | 61466 | 832-134 | 27-Jun-11 | 30-Jun-11 | 3 | mm sent to resource agencies to consult 6/30 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Gothenburg West | DR 53 | 61467 | 302-140 | 12/5/2011 | 12/6/2011 | 1 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Halsey Spur Bridge | DR 53 | 61472 | S86B-102 | 2/2/2012 | 2/17/2012 | 15 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Hyannis North | SHPO concur req | 61473 | 613-109 | 29-Mar-11 | 01-Apr-11 | 3 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Hyannis North | Bio Doc Vers 1 | 61473 | 613-109 | 11/23/2011 | 11/28/2011 | 5 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Arnold West | DR 53 | 61474 | 922-109 | 12/7/2011 | 12/15/2011 | 8 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Arnold West | SHPO concur request | 61474 | 922-109 | 4/25/2012 | 4/27/2012 | 2 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Arnold West | SHPO concur req - revised | 61474 | 922-109 | 5/29/2012 | 6/4/2012 | 6 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| N Jct US-83 West | DR 53 | 61475 | 232-125 | 11/7/2011 | 11/14/2011 | 7 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| North Jct. US-83 West | SHPO concur request | 61475 | 232-125 | 12/13/2011 | 12/20/2011 | 7 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| North Jct. US-83 West | Bio doc version 1 | 61475 | 232-125 | 6/5/2012 | 6/12/2012 | 7 | letters sent to USFWS and NGPC | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Arnold East | DR 53 | 61477 | 923-106 | 5/18/2012 | 5/31/2012 | 13 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Gothenburg - Custer Co. Line | DR 53 | 61479 | 472-111 | 2/29/2012 | 3/8/2012 | 8 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Mullen east & west | DR 53 | 61481 | 22-116 | 06-Apr-11 | 12-Apr-11 | 6 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Mullen East and West | 106 | 61481 | 22(116) | 09-May-11 | 13-May-11 | 4 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Mullen East & West | SHPO concur req | 61481 | 22-116 | 1/18/2012 | 1/25/2012 | 7 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Oconto - Eddyville | DR 53 | 61482 | 403-106 | 7/30/2012 | 8/14/2012 | 15 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Sargent Safet Routes | DR 53 | 61483 | 21-24 | 11/25/2011 | 12/5/2011 | 10 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| North Platte Canal Trl | DR 53 | 61488 | 56-35 | 15-Dec-10 | 17-Dec-10 | 2 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| North Platte Canal Trail | 106 Concur Req | 61488 | 56-35 | 3/28/2012 | 4/25/2012 | 28 | sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Jackson St Improves | DR 53 | 61489 | 6561-2 | 22-Feb-11 | 23-Feb-11 | 1 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Jackson St Improvements | Bio Doc V1 | 61489 | 6561-2 | 22-Jul-11 | 29-Jul-11 | 7 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Jackson St, Lexington | SHPO concur req | 61489 | 6561-2 | 24-Aug-11 | 06-Sep-11 | 13 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Jackson Street Improvements | Cat Ex | 61489 | 6561-2 | 1/20/2012 | 1/25/2012 | 5 | sent comments back to NDOR | NDOR / assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
| Jackson St Improvements, Lexington | Cat Ex | 61489 | 6561-2 | 2/9/2012 | 2/17/2012 | 8 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| South Platte River Bridges North Platte | DR 53 | 61500 | 832-137 | 11/25/2011 | 12/1/2011 | 6 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Cozad South Bridge | DR 53 | 61501 | 212-110 | 3/13/2012 | 4/5/2012 | 23 | NDOR (or LPA) / Must prepare technical and NEPA documentation | |
| Cozad South Bridges | Section 106 consultation package | 61501 | 212-110 | 5/2/2012 | 5/9/2012 | 7 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| North Platte North | Bio Doc vers 1 | 61510 | 832-138 | 19-Jan-11 | 31-Jan-11 | 12 | letters sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Sutherland South | Bio Doc | 61511 | 252-108 | 20-Apr-11 | 27-Apr-11 | 7 | letters sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Sutherland South | Scope Change Memo | 61511 | 252-108 | 27-Jun-11 | 28-Jun-11 | 1 | mm forwarded the re-initiation of consultation material to USFWS and NGPC today | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Comstock South | DR 53 | 61513 | 1833-116 | 05-Apr-11 | 11-Apr-11 | 6 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Comstock South | SHPO concur req | 61513 | 1833-116 | 01-Aug-11 | 04-Aug-11 | 3 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Comstock South | Bio doc version 1 | 61513 | 1833-116 | 3/21/2012 | 4/20/2012 | 30 | NDOR / address FHWA comments and resubmit | |
| Comstock South | Bio doc version 2 | 61513 | 1833-116 | 5/2/2012 | 5/11/2012 | 9 | letters sent to the agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Lexington - Overton | DR 53 | 61531 | 805-74 | 12-Jan-11 | 26-Jan-11 | 14 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Lexington - Overton | Bio doc vers 1 | 61531 | 805-74 | 22-Feb-11 | 24-Feb-11 | 2 | letters sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Lexington, Walnut &17th | DR 53 | 61537 | 6558-1 | 16-Dec-10 | 17-Dec-10 | 1 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Lexington Resurfacing | SHPO concur | 61537 | 6558-1 | 25-Jan-11 | 31-Jan-11 | 6 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| 17th & Walnut, Lexington | Bio doc vers 1 | 61537 | 6558-1 | 22-Mar-11 | 23-Mar-11 | 1 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| North Platte East Bridge | DR 53 | 61539 | 804-142 | 11/15/2011 | 11/22/2011 | 7 | Sent comment to NDOR to consider combining all of the anti-icing projects into one NEPA effort. Also asked that the proejct description include alternatives for how the system may be installed. NDOR to get back to me with how they would like to proceed. | NDOR / address FHWA comments and resubmit |
| Brownlee Road South | DR 53 | 61540 | 974-111 | 10-Feb-11 | 16-Feb-11 | 6 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Brownlee Road South | Bio doc vers 1 | 61540 | 974-111 | 22-Feb-11 | 24-Feb-11 | 2 | letters sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Arthur - Grant Co, Hyannis | DR 53 | 61541 | 613-110 | 03-Feb-11 | 03-Feb-11 | 0 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Arthur-Grant Co Line | Bio doc vers 1 | 61541 | 613-110 | 22-Feb-11 | 24-Feb-11 | 2 | letters sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Tryon North | DR 53 | 61542 | 973-103 | 11/18/2011 | 11/23/2011 | 5 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Broken Bow 5th Ave Trail | DR 53 | 61548 | 21-27 | 08-Apr-11 | 12-Apr-11 | 4 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| 6th, Jackson St, 13th St Improvements | DR 53 | 61554 | 6552-1 | 30-Jun-11 | 30-Jun-11 | 0 | mm concurred | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Maxwell UPRR Bridge | DR 53 | 61557 | 302-141 | 8/2/2012 | 8/16/2012 | 14 | NDOR (or LPA) / Must prepare technical and NEPA documentation | |
| Platte River Bridge, South of Gothenburg | DR 53 | 61558 | 472-112 | 8/2/2012 | 8/15/2012 | 13 | approved, added comments | None |
| Broken Bow East | DR 53 | 61559 | 23-120 | 12/7/2011 | 12/15/2011 | 8 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| In Alma | DR 53 | 70460 | 1732-1 | 13-Jun-11 | 16-Jun-11 | 3 | mm concurred on CE | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Franklin South | DR 53 | 70510 | 101-104 | 12/1/2011 | 12/6/2011 | 5 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Oxford South Bridge | DR 53 | 70565 | 461-102 | 15-Dec-10 | 23-Dec-10 | 8 | comments sent back to Steve | NDOR / address FHWA comments and resubmit |
| Oxford South Bridge | DR 53 - revised | 70565 | 461-102 | 18-Jan-11 | 15-Feb-11 | 28 | approved with comments | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Oxford South Bridge | SHPO concur req | 70565 | 461-102 | 13-Jun-11 | 23-Jun-11 | 10 | 6/23 mm sent letter to AB for formatting/mailing | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Oxford South Bridge | Bio doc vers 1 | 70565 | 461-102 | 21-Sep-11 | 26-Sep-11 | 5 | letters sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Oxford South Bridge | Cat Ex | 70565 | 461-102 | 5/7/2012 | 5/9/2012 | 2 | comments sent back to NDOR | NDOR / address FHWA comments and resubmit |
| Benkelman South | DR 53 | 70696 | 342-124 | 04-Jan-11 | 21-Jan-11 | 17 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Benkelman South Section | SHPO Concur Req 106 | 70696 | 342-124 | 10-Jun-11 | 10-Jun-11 | 0 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Benkelman South | Bio doc vers 1 | 70696 | 342-124 | 07-Sep-11 | 15-Sep-11 | 8 | letters sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Benkelman South | CE | 70696 | 342-124 | 1/26/2012 | 2/8/2012 | 13 | sent comments back to NDOR | NDOR / address FHWA comments and resubmit |
| Benkelman South | CE 2nd Submittal | 70696 | 342-124 | 3/28/2012 | 4/9/2012 | 12 | comments sent back to NDOR | NDOR / address FHWA comments and resubmit |
| Benkelman South | Cat Ex - 3rd version | 70696 | 342-124 | 4/11/2012 | 4/19/2012 | 8 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Trenton Southeast | DR 53 | 70811 | 7044-27 | 1/18/2012 | 1/25/2012 | 7 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Palisade Southeast | DR 53 | 70862 | 7044-29 | 23-Sep-11 | 26-Sep-11 | 3 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Hendley East & West | DR 53 | 70871 | 893-108 | 4/10/2012 | 4/27/2012 | 17 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Hendley East and West | Public involve inq | 70871 | 893-108 | 5/29/2012 | 6/4/2012 | 6 | sent back comments to NDOR | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Elwood SW, Gosper Co. | DR 53 | 70877 | 1530-5 | 22-Oct-10 | 26-Oct-10 | 4 | rb approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Elwood SW | SHPO concur req | 70877 | 1530-5 | 29-Mar-11 | 31-Mar-11 | 2 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Elwood Southwest | Bio Doc V1 | 70877 | 1530-5 | 06-Jul-11 | 11-Jul-11 | 5 | mm reviewed/approved, AB is mailing today to USFWS/NGPC | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Culbertson to McCook | 106 Consultation Letter | 70881 | 62-122 | 14-Jul-10 | 26-Jul-10 | 12 | sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Moorefield E & W | DR 53 | 70889 | 232-121 | 14-Mar-11 | 15-Mar-11 | 1 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Moorefield East and West | SHPO Concur Req 106 | 70889 | 232-121 | 10-Jun-11 | 10-Jun-11 | 0 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Moorefield East and West | SHPO concur req | 70889 | 232-121 | 7/17/2012 | 7/26/2012 | 9 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| McCook North | SHPO concur request | 70923 | 1553-1 | 12/30/2011 | 1/3/2012 | 4 | comments sent to NDOR | NDOR / address FHWA comments and resubmit |
| McCook North | SHPO concur revised | 70923 | 1553-1 | 1/10/2012 | 1/17/2012 | 7 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| McCook North | Bio doc version 1 | 70923 | 1553-1 | 3/6/2012 | 3/15/2012 | 9 | letters sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Hildreth South | Bio doc vers 1 | 70952 | 1955-2 | 19-Oct-10 | 26-Oct-10 | 7 | rb approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Hildreth South | DR 53 | 70952 | 1955-2 | 06-Dec-10 | 15-Dec-10 | 9 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Minden E and S | Bio doc vers 1 | 71028 | 64-124 | 22-Feb-11 | 24-Feb-11 | 2 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Minden East & South | 106 Concur Req | 71028 | 64-124 | 26-Apr-11 | 27-Apr-11 | 1 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Stockville SW | DR 53 | 71037 | 7032-24 | 4/12/2012 | 4/23/2012 | 11 | NDOR (or LPA) / Must prepare technical and NEPA documentation | |
| Stockville Southwest | SHPO concur req | 71037 | 7032-24 | 4/18/2012 | 4/25/2012 | 7 | sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| In Naponee | DR 53 | 71043 | 1925-3 | 06-Dec-10 | 15-Dec-10 | 9 | approved with comments | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| In Naponee | SHPO concur req | 71043 | 1925-3 | 14-Oct-11 | 17-Oct-11 | 3 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| In Naponee | Bio doc version 1 | 71043 | 1925-3 | 1/10/2012 | 1/16/2012 | 6 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| In Naponee | Cat Ex | 71043 | 1925-3 | 7/9/2012 | 7/16/2012 | 7 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Holdrege Public Schools Safe Routes to School | DR 53 | 71070 | 69-27 | 10-Jun-11 | 16-Jun-11 | 6 | concurred on CE and provided some guidance.mm | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Holdrege Public Schools - Infrastructure | Bio doc version 1 | 71070 | 69-27 | 1/23/2012 | 1/25/2012 | 2 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Holdrege Public School SRTS | SHPO concur request | 71070 | 69-27 | 3/7/2012 | 3/15/2012 | 8 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Holdrege Safe Routes to School | Sect 4(f) Eval | 71070 | 69-27 | 6/6/2012 | 6/14/2012 | 8 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Franklin Sterner Trail | T&E consult update | 71079 | 31-2 | 14-Dec-10 | 17-Dec-10 | 3 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Jct US-34 North | DR 53 | 71084 | 611-110 | 11-Jul-11 | 12-Jul-11 | 1 | mm concurred | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Jct US-34 North | SHPO concur req | 71084 | 611-110 | 03-Aug-11 | 04-Aug-11 | 1 | comments sent back to NDOR | NDOR / address FHWA comments and resubmit |
| Jct US-34 North Section | SHPO concur req - 2nd | 71084 | 611-110 | 12-Aug-11 | 17-Aug-11 | 5 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Curtis East | SHPO concur req | 71102 | 232-124 | 15-Mar-11 | 16-Mar-11 | 1 | sent comments back to Carin | NDOR / address FHWA comments and resubmit |
| Curtis East | SHPO concur req | 71102 | 232-124 | 04-Apr-11 | 07-Apr-11 | 3 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Curtis East | SHPO Supplemental | 71102 | 232-124 | 5/8/2012 | 5/9/2012 | 1 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| US-6 West | Bio doc vers 1 | 71105 | 342-121 | 01-Oct-10 | 01-Oct-10 | 0 | letters to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| US-6 West | Bio doc vers 1 | 71105 | 342-121 | 17-Nov-10 | 23-Nov-10 | 6 | letters sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Farnam West | DR 53 | 71124 | 232-126 | 03-Aug-11 | 05-Aug-11 | 2 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Farnam West | SHPO concur req | 71124 | 232-126 | 31-Aug-11 | 06-Sep-11 | 6 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Wauneta - Hamlet | DR 53 | 71127 | 62-130 | 19-May-11 | 27-May-11 | 8 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Wauneta - Hamlet | SHPO concur req | 71127 | 62-130 | 03-Aug-11 | 04-Aug-11 | 1 | comments sent to NDOR | NDOR / address FHWA comments and resubmit |
| Wauneta - Hamlet | SHPO concur req - 2 | 71127 | 62-130 | 22-Aug-11 | 06-Sep-11 | 15 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Wauneta to Hamlet | Cat Ex | 71127 | 62-130 | 6/26/2012 | 6/27/2012 | 1 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Jct. N-21 to Elwood | DR 53 | 71131 | 232-127 | 12/7/2011 | 12/15/2011 | 8 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| H Street & Norris Ave, McCook | DR 53 | 71135 | 6154-1 | 25-Aug-10 | 01-Sep-10 | 7 | NDOR (or LPA) / Must prepare technical and NEPA documentation | |
| H Street Improvements - Norris Ave to Airport Road | Bio doc version 1 | 71135 | 6154-1 | 11/18/2011 | 11/25/2011 | 7 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| H Street Improvements, Norris Ave to Airport Road | SHPO concur request | 71135 | 6154-1 | 2/1/2012 | 2/3/2012 | 2 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| H Street - Norris Ave to Airport Road, McCook | Cat Ex | 71135 | 6154-1 | 4/10/2012 | 4/23/2012 | 13 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Alma North & South | DR 53 | 71137 | 1831-115 | 25-Oct-10 | 27-Oct-10 | 2 | rb asked steve to resubmit a completed form | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Alma North and South | DR53 | 71137 | 1831-115 | 27-Oct-10 | 27-Oct-10 | 0 | rb approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Alma North & South | SHPO concur | 71137 | 1831-115 | 09-Nov-10 | 12-Nov-10 | 3 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Alma North & South | Bio doc vers 1 | 71137 | 1831-115 | 05-Jan-11 | 07-Jan-11 | 2 | letters to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Minden Hike & Bike Trail | DR 53 | 71138 | 50-36 | 16-Feb-11 | 22-Feb-11 | 6 | approved with comments. | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Arapahoe South | SHPO concur req | 71139 | 2831-114 | 21-Sep-11 | 26-Sep-11 | 5 | letter sent to NDOR | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Jct N-46 - Holdrege | Bio doc vers 1 | 71144 | 63-125 | 07-Apr-11 | 08-Apr-11 | 1 | letters sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Jct. N-46 to Holdrege | DR 53 | 71144 | 63-125 | 20-Jun-11 | 28-Jun-11 | 8 | approved mm | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| 11th Av, Holdrege | DR 53 | 71145 | 6602-2 | 15-Dec-10 | 17-Dec-10 | 2 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| 11th Ave, Holdrege | SHPO concur req | 71145 | 6602-2 | 8/2/2012 | 8/16/2012 | 14 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA | |
| Stockville SW Road Repair | DR 53 | 71147 | ER 1460-2 | 20-Dec-10 | 27-Dec-10 | 7 | local project, but NDOR LPD coordinator signed the form for the local on 12/15/10. NDOR Env approved the form 12/20/11 and emailed to FHWA. FHWA approved 12/27/11 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Eustis SW | DR 53 | 71148 | ER 1675-3 | 16-Feb-11 | 16-Feb-11 | 0 | signed by NDOR 2/14/11, approved by NDOR 2/14/11, sent to FHWA 2/16/11. approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| E 7th/ Seminole, H St - Park Ave, McCook | DR 53 | 71151 | 6158-1 | 30-Jun-11 | 30-Jun-11 | 0 | mm concurred, included comments | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| 18th Ave, Burlington St to West Ave | DR53 | 71152 | 6606-2 | 09-May-11 | 13-May-11 | 4 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| 18th Ave, Burlington - West Ave, Holdrege | SHPO concur req | 71152 | 6606-2 | 7/11/2012 | 7/24/2012 | 13 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Ericson East | DR 53 | 80643 | 704-104 | 11/7/2011 | 11/14/2011 | 7 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Ericson East | Bio doc version 1 | 80643 | 704-104 | 3/21/2012 | 4/20/2012 | 30 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA | |
| Ericson East | 106 Concur Req | 80643 | 704-104 | 4/2/2012 | 4/25/2012 | 23 | sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Ericson East | Cat Ex | 80643 | 704-104 | 6/5/2012 | 6/11/2012 | 6 | comments sent back to NDOR | NDOR / address FHWA comments and resubmit |
| Ericson East | Cat Ex - 2nd submittal | 80643 | 704-104 | 6/27/2012 | 6/28/2012 | 1 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Niobrara River South | DR 53 | 80690 | 1834-109 | 7/27/2012 | 8/14/2012 | 18 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Burwell West | DR 53 | 80709 | 964-101 | 1/25/2012 | 2/13/2012 | 19 | did not concur with CE recommendation. Made comment for NDOR to proceed with EA. | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Nenzel West | Bio doc vers 1 | 80727 | 202-131 | 01-Oct-10 | 12-Oct-10 | 11 | letters to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| O'Neill West | DR 53 | 80758 | 7045-28 | 1/18/2012 | 1/25/2012 | 7 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Ericson South | DR 53 | 80785 | 2325-3 | 06-Dec-10 | 15-Dec-10 | 9 | approved with comments | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Ericson South | SHPO concur request | 80785 | 2325-3 | 12/19/2011 | 12/21/2011 | 2 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Ericson South | Bio doc version 1 | 80785 | 2325-3 | 3/23/2012 | 4/23/2012 | 31 | sent back to amend a cc so loophole gone | None |
| Ericson South | Bio doc version 2 | 80785 | 2325-3 | 5/4/2012 | 5/11/2012 | 7 | letters sent to the agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Burwell North | DR-53 | 80798 | 113-118 | 4/2/2012 | 4/23/2012 | 21 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Valentine East | DR-53 | 80799 | 122-104 | 4/2/2012 | 4/6/2012 | 4 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Valentine North | Bio doc vers 1 | 80800 | 834-112 | 08-Oct-10 | 13-Oct-10 | 5 | sent eric comments | NDOR / address FHWA comments and resubmit |
| Valentine North | Bio doc | 80800 | 834-112 | 13-Oct-10 | 27-Oct-10 | 14 | letters to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Valentine North | SHPO concur req | 80800 | 834-112 | 25-Oct-10 | 27-Oct-10 | 2 | letter to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Valentine North | Scope change memo | 80800 | 834-112 | 22-Apr-11 | 27-Apr-11 | 5 | comments sent to Eric | NDOR / address FHWA comments and resubmit |
| Valentine North | Scope Change Memo V2 | 80800 | 834-112 | 27-Apr-11 | 27-Apr-11 | 0 | memo sent to USFWS and NGPC | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Valentine North (scope change) | SHPO concur req | 80800 | 834-112 | 20-May-11 | 27-May-11 | 7 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Rose - Bassett | Bio doc vers 1 | 80801 | 1834-111 | 20-Sep-10 | 29-Sep-10 | 9 | letters to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Rose North | Bio doc vers 1 | 80802 | 1834-112 | 20-Sep-10 | 29-Sep-10 | 9 | letters to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Bristow East and West | DR 53 | 80805 | 124-107 | 07-Jul-11 | 08-Jul-11 | 1 | mm concurred | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Rose Mitigation Bank | Monitoring Report | 80810 | 75-7 | 07-Mar-11 | 21-Mar-11 | 14 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. | |
| Niobrara Scenic Rvr Corr Roads | SHPO concur req | 80817 | 16-36 | 13-Jul-11 | 19-Jul-11 | 6 | mm sent back for revision - scope of work in APE of site not clearly defined | NDOR / address FHWA comments and resubmit |
| Niobrara Scenic Rvr Roads | SHPO concur req - 8 ltrs | 80817 | 16-36 | 11-Aug-11 | 16-Aug-11 | 5 | comments sent back to NDOR | NDOR / address FHWA comments and resubmit |
| Niobrara ScenRvr Cor Rds | SHPO concur req - revised | 80817 | 16-36 | 26-Aug-11 | 06-Sep-11 | 11 | SHPO letter sent today; tribal letters going out tomorrow | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Niobrara, Cherry & Keya Paha Counties | Tribal coord request | 80817 | 16-36 | 12/1/2011 | 12/6/2011 | 5 | letters sent to the Tribes | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Niobrara Scenic River Corridor | Bio doc version 2 | 80817 | 16-36 | 5/7/2012 | 5/11/2012 | 4 | package sent to NPS, USFWS, and NGPC | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Merriman West | DR 53 | 80846 | 202-132 | 10/19/2011 | 10/28/2011 | 9 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Spencer North | Bio doc vers 1 | 80847 | 2814-117 | 22-Dec-10 | 27-Dec-10 | 5 | letters to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Spencer North | Scope Change memo | 80847 | 2814-117 | 07-Apr-11 | 15-Apr-11 | 8 | comments sent back to Eric | NDOR / address FHWA comments and resubmit |
| Spencer North | Bio Re-eval memo - vers 2 | 80847 | 2814-117 | 21-Apr-11 | 26-Apr-11 | 5 | email sent to USFWS and NGPC | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Chambers East | DR 53 | 80860 | 954-104 | 11/22/2011 | 11/28/2011 | 6 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Chambers East | SHPO concur request | 80860 | 954-104 | 12/8/2011 | 12/9/2011 | 1 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Chambers East | Bio doc version 1 | 80860 | 954-104 | 5/31/2012 | 6/8/2012 | 8 | letters sent to USFWS and NGPC | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Chambers East | Cat Ex | 80860 | 954-104 | 7/30/2012 | 8/14/2012 | 15 | provided verbal comment to NDOR - need the NDEQ correspondence referneced in the hazmat section attached to the CE. | NDOR / address FHWA comments and resubmit |
| Sheridan & Cherry Line East | DR 53 | 80861 | 202-136 | 09-Dec-10 | 13-Dec-10 | 4 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Sheridan Co Line East | Bio doc vers 1 | 80861 | 202-136 | 03-Feb-11 | 03-Feb-11 | 0 | letters sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Sparks West | DR 53 | 80877 | 122-105 | 26-Jul-11 | 29-Jul-11 | 3 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Sparks West | SHPO concur request | 80877 | 122-105 | 12/6/2011 | 12/9/2011 | 3 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Sparks West | Bio doc version 1 | 80877 | 122-105 | 5/31/2012 | 6/8/2012 | 8 | letters sent to USFWS and NGPC | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Crookston West | DR 53 | 80878 | 202-133 | 06-Oct-10 | 12-Oct-10 | 6 | rb approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Crookston West | Bio doc vers 1 | 80878 | 202-133 | 04-Feb-11 | 08-Feb-11 | 4 | letters sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Crookston West | SHPO concur req | 80878 | 202-133 | 24-Mar-11 | 31-Mar-11 | 7 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Crookston West | SHPO concur req | 80878 | 202-133 | 24-Mar-11 | 31-Mar-11 | 7 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Nenzel - Kilgore | DR 53 | 80879 | 202-134 | 11/7/2011 | 11/14/2011 | 7 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Wood Lake West | DR-53 | 80880 | 202-135 | 4/2/2012 | 4/23/2012 | 21 | comment sent to NDOR | NDOR / address FHWA comments and resubmit |
| Wood Lake West | SHPO concur request | 80880 | 202-135 | 5/4/2012 | 5/9/2012 | 5 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| S16B North & South | Bio doc vers 1 | 80881 | 834-114 | 06-Oct-10 | 13-Oct-10 | 7 | letters to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| S16B North & South | Bio doc vers 1 | 80881 | 834-114 | 06-Oct-10 | 13-Oct-10 | 7 | letters to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Valentine Cowboy Trl Conect Phs 1 | DR 53 | 80886 | 16-38 | 13-Jun-11 | 16-Jun-11 | 3 | mm concurred on CE | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Valentine Cowboy Trl Conect Phs 1 | DR 53 | 80886 | 16-38 | 13-Jun-11 | 16-Jun-11 | 3 | mm concurred on CE | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Valentine Cowboy Trail Connection - Phase 1 | 4(f) Exception Req | 80886 | 16-38 | 3/28/2012 | 4/25/2012 | 28 | comments sent back to NDOR | NDOR / assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
| Valentine Cowboy Trail Connection - Phase 1 | 106 Concur Req | 80886 | 16-38 | 3/28/2012 | 4/25/2012 | 28 | sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Valentine Cowboy Trail Phase 1 | 4(f) exempt request | 80886 | 16-38 | 5/18/2012 | 5/31/2012 | 13 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. | |
| North Loup Rvr North | Bio doc vers 1 | 80895 | 834-115 | 29-Dec-10 | 07-Jan-11 | 9 | comments sent to Eric | NDOR / address FHWA comments and resubmit |
| North Loup River North | bio doc version 2 | 80895 | 834-115 | 07-Jan-11 | 07-Jan-11 | 0 | letter sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| North Loup Rvr North | Bio doc vers 1 | 80895 | 834-115 | 29-Dec-10 | 07-Jan-11 | 9 | comments sent to Eric | NDOR / address FHWA comments and resubmit |
| North Loup River North | bio doc version 2 | 80895 | 834-115 | 07-Jan-11 | 07-Jan-11 | 0 | letter sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| North Loup Rvr North | SHPO concur req | 80895 | 834-115 | 10-Feb-11 | 15-Feb-11 | 5 | reviewed today and ok to send to SHPO. Will go out in mail tomorrow. | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| North Loup Rvr North | SHPO concur req | 80895 | 834-115 | 10-Feb-11 | 15-Feb-11 | 5 | reviewed today and ok to send to SHPO. Will go out in mail tomorrow. | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| North Loup Rvr North | Bio doc vers 3 | 80895 | 834-115 | 21-Mar-11 | 29-Mar-11 | 8 | letters sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| North Loup Rvr North | Bio doc vers 3 | 80895 | 834-115 | 21-Mar-11 | 29-Mar-11 | 8 | letters sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Kilgore East | Bio doc vers 1 | 80896 | 202-137 | 22-Dec-10 | 27-Dec-10 | 5 | letters sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Kilgore East | Bio doc vers 1 | 80896 | 202-137 | 22-Dec-10 | 27-Dec-10 | 5 | letters sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Inman East & West | Bio doc vers 1 | 80897 | 204-123 | 20-Dec-10 | 27-Dec-10 | 7 | letters sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Inman East & West | Bio doc vers 1 | 80897 | 204-123 | 20-Dec-10 | 27-Dec-10 | 7 | letters sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Brewster - Calamus River | DR 53 | 80899 | 73-102 | 25-Mar-11 | 29-Mar-11 | 4 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Brewster - Calamus River | DR 53 | 80899 | 73-102 | 25-Mar-11 | 29-Mar-11 | 4 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Brewster - Calamus River | Bio doc version 1 | 80899 | 73-102 | 6/1/2012 | 6/11/2012 | 10 | letters sent to USFWS and NGPC | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Brewster - Calamus River | Cat Ex | 80899 | 73-102 | 8/1/2012 | 8/13/2012 | 12 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Wheeler-Antelope Co. Line West | DR 53 | 80900 | 704-110 | 25-Jul-11 | 29-Jul-11 | 4 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Wheeler-Antelope Co. Line West | DR 53 | 80900 | 704-110 | 25-Jul-11 | 29-Jul-11 | 4 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Crookston - Valentine | DR 53 | 80901 | 202-138 | 09-Mar-11 | 10-Mar-11 | 1 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Crookston - Valentine | DR 53 | 80901 | 202-138 | 09-Mar-11 | 10-Mar-11 | 1 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Crookston - Valentine | Bio Doc | 80901 | 202-138 | 26-Apr-11 | 27-Apr-11 | 1 | letters sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Crookston - Valentine | Bio Doc | 80901 | 202-138 | 26-Apr-11 | 27-Apr-11 | 1 | letters sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Ewing Link | DR 53 | 80906 | ER SL45B-103 | 02-Sep-11 | 14-Sep-11 | 12 | state project - NDOR completed and approved form on 9/1/11. approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Ewing Link | DR 53 | 80906 | ER SL45B-103 | 02-Sep-11 | 14-Sep-11 | 12 | state project - NDOR completed and approved form on 9/1/11. approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Ewing Link, Loup County | SHPO concur req | 80906 | ER SL45B-103 | 11-Oct-11 | 12-Oct-11 | 1 | approved and procecssed. | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Ewing Link, Loup County | SHPO concur req | 80906 | ER SL45B-103 | 11-Oct-11 | 12-Oct-11 | 1 | approved and procecssed. | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Ewing Link | Bio doc version 1 | 80906 | SL45B-103 | 3/22/2012 | 3/22/2012 | 0 | letters sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| O'Neill SE | DR 53 | 80907 | ER 204-124 | 02-Sep-11 | 14-Sep-11 | 12 | state project- NDOR completed and approved their form on 9/1/11. approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| O'Neill SE | DR 53 | 80907 | ER 204-124 | 02-Sep-11 | 14-Sep-11 | 12 | state project- NDOR completed and approved their form on 9/1/11. approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| O'Neill Southeast | SHPO concur req | 80907 | ER 204-124 | 12-Oct-11 | 12-Oct-11 | 0 | approved and processed. | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| O'Neill Southeast | SHPO concur req | 80907 | ER 204-124 | 12-Oct-11 | 12-Oct-11 | 0 | approved and processed. | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| ER - Gracie Creek Culvert | DR 53 | 80908 | ER 964-103 | 02-Sep-11 | 19-Sep-11 | 17 | state project - NDOR completed the form on 9/1/11 and approved form 9/1/11. received at FHWA 9/2/11.comments sent to NDOR - coord with agencies quickly | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| ER - Gracie Creek Culvert | DR 53 | 80908 | ER 964-103 | 02-Sep-11 | 19-Sep-11 | 17 | state project - NDOR completed the form on 9/1/11 and approved form 9/1/11. received at FHWA 9/2/11.comments sent to NDOR - coord with agencies quickly | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Burwell Northwest | DR 53 ver 2 | 80908 | ER 964-103 | 07-Oct-11 | 07-Oct-11 | 0 | re-submittal of Doc occurred at stakeholder meeting today, signed at meeting, proceeding with CE | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Burwell Northwest | SHPO concur req | 80908 | ER 964-103 | 07-Oct-11 | 07-Oct-11 | 0 | approved | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Burwell Northwest | DR 53 ver 2 | 80908 | ER 964-103 | 07-Oct-11 | 07-Oct-11 | 0 | re-submittal of Doc occurred at stakeholder meeting today, signed at meeting, proceeding with CE | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Burwell Northwest | SHPO concur req | 80908 | ER 964-103 | 07-Oct-11 | 07-Oct-11 | 0 | approved | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| ER - North Loup River | DR 53 | 80909 | ER 1833-117 | 02-Sep-11 | 16-Sep-11 | 14 | State project- NDOR completed and approved doc on 9/1/11 aned emailed to FHWA. Approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| ER - North Loup River | DR 53 | 80909 | ER 1833-117 | 02-Sep-11 | 16-Sep-11 | 14 | State project- NDOR completed and approved doc on 9/1/11 aned emailed to FHWA. Approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| North Loup River, Taylor | SHPO concur request | 80909 | 1833-117 | 11/18/2011 | 11/25/2011 | 7 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| North Loup Taylor | Reevaluation Memo | 80909 | 1833-117 | 5/30/2012 | 6/5/2012 | 6 | comments sent to NDOR | NDOR / address FHWA comments and resubmit |
| North Loup Taylor | Reeval Memo | 80909 | 1833-117 | 6/12/2012 | 6/19/2012 | 7 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Thedford - Valentine | DR 53 | 80911 | 834-116 | 22-Aug-11 | 06-Sep-11 | 15 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Thedford - Valentine | DR 53 | 80911 | 834-116 | 22-Aug-11 | 06-Sep-11 | 15 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Thedford to Valentine | Bio doc version 1 | 80911 | 834-116 | 12/16/2011 | 12/23/2011 | 7 | letters sent to USFWS, NGPC, Valentine National Wildlife Refuge | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| SE Jct US275 Antelope Co Line | DR 53 | 80913 | 204-125 | 05-Oct-11 | 06-Oct-11 | 1 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| SE Jct US275 Antelope Co Line | DR 53 | 80913 | 204-125 | 05-Oct-11 | 06-Oct-11 | 1 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Ahntelope County Line | Bio doc version 1 | 80913 | 204-125 | 12/19/2011 | 12/23/2011 | 4 | letters sent to the agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Ewing East and West | DR 53 | 80914 | 2754-105 | 12/21/2011 | 12/6/2011 | -15 | The email was received on 11/21/11 and filed in project file, but not placed on the task bar until today. approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Ewing East & West | SHPO concur request | 80914 | 2754-105 | 5/21/2012 | 6/4/2012 | 14 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Loup County Line - Burwell | DR 53 | 80915 | 914-108 | 11/18/2011 | 11/23/2011 | 5 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Loup County Line - Burwell | Bio doc version 1 | 80915 | 914-108 | 6/26/2012 | 7/2/2012 | 6 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Merriman - Eli | DR 53 | 80916 | 202-140 | 30-Aug-11 | 06-Sep-11 | 7 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Merriman - Eli | DR 53 | 80916 | 202-140 | 30-Aug-11 | 06-Sep-11 | 7 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Merriman to Eli | Bio doc version one | 80916 | 202-140 | 12/19/2011 | 12/23/2011 | 4 | letters sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| N Jct. N-70 Northwest | DR 53 | 80917 | 2813-111 | 02-Sep-11 | 14-Sep-11 | 12 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| N Jct. N-70 Northwest | DR 53 | 80917 | 2813-111 | 02-Sep-11 | 14-Sep-11 | 12 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| N Jct. N-70 Northwest | Bio doc version 1 | 80917 | 2813-111 | 12/19/2011 | 12/23/2011 | 4 | letters sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Ewing Southwest | DR 53 | 80921 | ER 2260-2 | 23-Sep-11 | 23-Sep-11 | 0 | Signed by Holt Co 2/17/11. Signed by NDOR 9/22/11 and emailed to FHWA 9/23/11. FHWA concurred to proceed as PCE/CE | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Ewing Southwest | DR 53 | 80921 | ER 2260-2 | 23-Sep-11 | 23-Sep-11 | 0 | Signed by Holt Co 2/17/11. Signed by NDOR 9/22/11 and emailed to FHWA 9/23/11. FHWA concurred to proceed as PCE/CE | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Inman Northeast | DR 53 | 80922 | ER 2270-2 | 23-Sep-11 | 23-Sep-11 | 0 | Signed by Holt Co 2/17/11. Signed by NDOR 9/22/11 and emailed to FHWA 9/23/11. FHWA concurred to proceed as PCE/CE | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Inman Northeast | DR 53 | 80922 | ER 2270-2 | 23-Sep-11 | 23-Sep-11 | 0 | Signed by Holt Co 2/17/11. Signed by NDOR 9/22/11 and emailed to FHWA 9/23/11. FHWA concurred to proceed as PCE/CE | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Emmet South | DR 53 | 80923 | ER 2105-3 | 23-Sep-11 | 23-Sep-11 | 0 | Signed by Holt Co 2/17/11. NDOR signed 9/22/11 and emailed to FHWA 9/23/11. FHWA concurred to proceed as PCE/CE | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Emmet South | DR 53 | 80923 | ER 2105-3 | 23-Sep-11 | 23-Sep-11 | 0 | Signed by Holt Co 2/17/11. NDOR signed 9/22/11 and emailed to FHWA 9/23/11. FHWA concurred to proceed as PCE/CE | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Stuart Northeast | DR 53 | 80924 | ER 2115-4 | 23-Sep-11 | 23-Sep-11 | 0 | Holt Co signed 2/18/11, NDOR signed/approved 9/22/11 and emailed to FHWA 9/23/11. FHWA concurred to proceed as PCE/CE | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Stuart Northeast | DR 53 | 80924 | ER 2115-4 | 23-Sep-11 | 23-Sep-11 | 0 | Holt Co signed 2/18/11, NDOR signed/approved 9/22/11 and emailed to FHWA 9/23/11. FHWA concurred to proceed as PCE/CE | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Naper South | DR 53 | 80925 | ER 2115-5 | 23-Sep-11 | 23-Sep-11 | 0 | Signed by Holt Co 2/18/11. Signed by NDOR 9/22/11 and emailed to FHWA 9/23. FHWA concurred to proceed as PCE/CE | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Naper South | DR 53 | 80925 | ER 2115-5 | 23-Sep-11 | 23-Sep-11 | 0 | Signed by Holt Co 2/18/11. Signed by NDOR 9/22/11 and emailed to FHWA 9/23. FHWA concurred to proceed as PCE/CE | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Burwell NW Bridge | DR 53 | 80926 | 964(104) | 5/2/2012 | 5/11/2012 | 9 | approved with comments | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Bison Bridge | Cat Ex | RTP 2011-5 | 7/26/2012 | 8/9/2012 | 14 | CE approved | None | |
| Tier 1 - Chicago to Omaha Regional Passenger Rail System | Cooperating Agency request | 5/23/2012 | 7/18/2012 | 56 | letter mailed out today | None | ||
| D2-D1 Device Deployment | Bio doc vers 1 | 00649J | ITSN-209 | 26-Oct-10 | 27-Oct-10 | 1 | rb approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval |
| D1/D2 Device Deploy | SHPO concur req | 00649J | ITSN-209 | 02-Dec-10 | 10-Dec-10 | 8 | letter to SHPO | FHWA sent the material to the resource agency(s) for review/concurrrence, which takes up to 4 weeks. Once all tech reviews and concurrences complete, next step is for NDOR to review/ approve the NEPA doc. If not a PCE, NDOR will submit CE to FHWA |
| LPA/NDOR Statewide Workforce Development | DR 53 | 00841A | STWD-113 | 12-Jul-11 | 19-Jul-11 | 7 | mm approved dr53 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Alvo North Bridges | DR 53 | 11450A | 632-114 | 08-Oct-10 | 15-Oct-10 | 7 | rb approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Alvo North Bridge | Bio Doc vers 1 | 11450A | 632-114 | 20-Dec-10 | 27-Dec-10 | 7 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Alvo North bridges | SHPO concur req | 11450A | 632-114 | 15-Mar-11 | 16-Mar-11 | 1 | letter sent to SHPO | FHWA sent the material to the resource agency(s) for review/concurrrence, which takes up to 4 weeks. Once all tech reviews and concurrences complete, next step is for NDOR to review/ approve the NEPA doc. If not a PCE, NDOR will submit CE to FHWA |
| Alvo North bridges | CE | 11450A | 632-114 | 19-Aug-11 | 03-Sep-11 | 15 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| 14th St Br, Linc; Mahoney Intrch ramps | Reevaluation | 12482, 12312 | 809-855, -872 | 28-Apr-11 | 11-May-11 | 13 | sent comments back to Steve | NDOR / address FHWA comments and resubmit |
| Auburn E & In Auburn | DR 53 | 12994, 13062 | 1366(119), 1367(123) | 08-Mar-11 | 08-Mar-11 | 0 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Jct N-64 to Schuyler; Jct Us-34 North; Ewing East & West | Cat Ex | 13019; 71084; 80914 | 152-122; 611-110; 2754-105 | 7/31/2012 | 8/15/2012 | 15 | Batched: 152-122; 611-110; 2754-105. mm: had a couple items that had to be addressed, but will be quick fixes | None |
| Installation of Anti-Icing Systems | DR 53 | 13136; 42661; 61539 | 808-153; 807-160; 804-142 | 12/7/2011 | 12/15/2011 | 8 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Falls City to US-75; Kansas State Line to Auburn | DR 53 - resubmittal | 13205; 13206 | 731-117; 751-106 | 2/22/2012 | 3/5/2012 | 12 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Falls City-US75; K-State Line-Auburn | Bio doc version 1 | 13205; 13206 | 731-117; 751-106 | 3/5/2012 | 3/8/2012 | 3 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| N-133, N-36, North-Blair South | SHPO concur request | 21791- 21791a | 1333-102; 1333-103 | 4/5/2012 | 4/26/2012 | 21 | comments sent back to NDOR | NDOR / address FHWA comments and resubmit |
| N-36 North & Blair South | SHPO concur request - version 2 | 21791; 21791A | 1333-102; 1333-103 | 5/14/2012 | 5/25/2012 | 11 | comments sent to NDOR to address | NDOR / address FHWA comments and resubmit |
| Blair South / N-36 North Omaha | Noise Study | 21791; 21791A | 1333-102; 1333-103 | 5/23/2012 | 6/27/2012 | 35 | approved; minor comments sent as recommendations on future noise studies. | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| N-133, Jct. N-36 North, Omaha; Blair South | 4(f) req | 21791; 21791a | 1333-102; 1333-103 | 6/29/2012 | 7/11/2012 | 12 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| N-36 North and Blair South | Cat Ex Reeval | 21791; 21791A | 1333-102; 1333-103 | 7/17/2012 | 7/24/2012 | 7 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Blair South | Bio doc vers 1 | 21791A | 1333-103 | 14-Jan-11 | 31-Jan-11 | 17 | mm bio approved, based on verification NEPA questions are answered | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Oreopolis Wetland Mitigation Site | NEPA Det. Form V2 | 21849F | 752-168 | 10-Jun-10 | 10-Jun-10 | 0 | NDOR (or LPA) / Must prepare technical and NEPA documentation | |
| Oreapolis Wetland Mitigation site | Bio doc | 21849F | 752-168 | 14-Jun-10 | 22-Jun-10 | 8 | approved rb | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Omaha Riverfront Trail - Phase 4 | DR 53 | 21973A | 28-109 | 23-Sep-11 | 26-Sep-11 | 3 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Omaha Interstate projects | Grouping for NEPA Analysis | 22143, etc | 809-897 | 02-Nov-10 | 18-Nov-10 | 16 | NDOR (or LPA) / Must prepare technical and NEPA documentation | |
| Western Douglas Co. Trls; Phase 1 & 2 | SHPO concur req | 22227; 22227A | 28-87; 28-102 | 6/12/2012 | 6/14/2012 | 2 | letters sent to SHPO and THPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| WDCT Phase 1; WDCT Phase 2 | Bio doc version 1 | 22227; 22227A | 28-87; 28-102 | 7/5/2012 | 7/12/2012 | 7 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. | |
| WDCT - Valley to Waterloo, Ph 2 | DR 53 | 22227A | 28-102 | 09-Jun-11 | 10-Jun-11 | 1 | approved, to be combined with 28-87 | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Fremont Main St Hist Lighting | SHPO concur req | 22272A | 27-60 | 04-Apr-11 | 07-Apr-11 | 3 | comments sent to NDOR | NDOR / address FHWA comments and resubmit |
| Fremont Main St Hist Lighting | Bio doc | 22272A | 27-60 | 13-Oct-11 | 14-Oct-11 | 1 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| 36th St Roadway Impr Ph 1 & 2 | DR 53 | 22276 & 22288 | 5061-5, 3773-1 | 10-Jan-11 | 26-Jan-11 | 16 | sent comments to Allison | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Omaha Cocnrete Repair pkgs. | Bio doc vers 1 | 22498, etc | 5001-18, etc | 04-Aug-11 | 05-Aug-11 | 1 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Macy South | SHPO Concur | 30848B | 754-108 | 13-Sep-10 | 23-Sep-10 | 10 | mm sent email to clarify intent of letter to NDOR 9/13/10 | NDOR / address FHWA comments and resubmit |
| Macy South | Tribal Monitoring Agrmt | 30848B | 754-108 | 18-Oct-10 | 05-Nov-10 | 18 | sent back to NDOR for them to sign; asked for a signed version ASAP so we can send to tribe | NDOR / address FHWA comments and resubmit |
| Macy South | Tribal concur | 30848B | 754-108 | 08-Nov-10 | 09-Nov-10 | 1 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. | |
| Belden East Bridge | DR 53 | 31342A | 206-109 | 11/9/2011 | 11/14/2011 | 5 | sent comment back to NDOR to address. | NDOR / address FHWA comments and resubmit |
| Belden East Bridge | SHPO concur request | 31342A | 206-109 | 4/6/2012 | 4/25/2012 | 19 | sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| In Norfolk | Future bike trail accommodation request memo | 31416A | 353-107 | 5/4/2012 | 5/8/2012 | 4 | sent back comments to NDOR | NDOR / address FHWA comments and resubmit |
| Norfolk Ave, Norfolk | DR 53 | 31417A | 2755-143 | 15-Apr-11 | 21-Apr-11 | 6 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| 37th to Norfolk Ave, Norfolk | SHPO concur req | 31417A | 2755-143 | 01-Aug-11 | 04-Aug-11 | 3 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Norfolk SE, In Norfolk Norfolk NE | Bio doc version 1 | 31442, 31416A, 31416B | 353-105, 353-107, 353-108 | 10/24/2011 | 10/28/2011 | 4 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Norfolk SE, In Norfolk, Norfolk NE | CE | 31442, 31416A, 31416B | 353-105; 353-107; 353-108 | 11/21/2011 | 11/28/2011 | 7 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Newman Grove N Bridges | DR 53 | 31490a | 453-109 | 05-Nov-10 | 12-Nov-10 | 7 | rb approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Newman Grove North Bridges | Bio Doc | 31490A | 453-109 | 08-Nov-10 | 12-Nov-10 | 4 | rb approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Newman Grove North | SHPO concur req | 31490a | 453-109 | 15-Nov-10 | 15-Nov-10 | 0 | letter mailed to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Newman Grove N brdgs | 4(f) temp occpcy ltr review | 31490A | 453-109 | 10-Feb-11 | 16-Feb-11 | 6 | letter ok to go to City | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Hwy N-45, Newman Grove N brdges | 4(f) concur letter | 31490A | 453-109 | 10-Mar-11 | 10-Mar-11 | 0 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Tilden South; In Tilden & Battle Creek North | SHPO concur req - version 2 | 31808; 31897 | 453-107; 453-110 | 7/31/2012 | 8/16/2012 | 16 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Tilden South; In Tilden & BattleCreek North | SHPO concur req | 31808; 31897 | 453-107; 453-110 | 7/17/2012 | 7/26/2012 | 9 | comments sent back to NDOR | NDOR / address FHWA comments and resubmit |
| Juct N-52, W and E | DR 53 | 31833A | 915-124 | 04-Apr-11 | 11-Apr-11 | 7 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Wayne South & Wayne South Bridge | Bio doc version 1 | 31886, 31893 | 154-117, 154-118 | 1/13/2012 | 1/17/2012 | 4 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Wayne South and Bridge | DR 53 | 31886, 318933189 | 154-117, -118 | 09-Nov-10 | 12-Nov-10 | 3 | rb approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Fordyce E & W; Crofton East | SHPO concur req - revised | 31912; 32061 | 126-116; 125-115 | 6/7/2012 | 6/8/2012 | 1 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Columbus Viaducts | SHPO concur request | 31924, etc | 6061-8, etc | 30-Nov-10 | 02-Dec-10 | 2 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Columbus viaducts | HazMat Memo | 31924, etc | 6065-5, etc | 08-Dec-10 | 09-Dec-10 | 1 | comments sent to allison. Once comments are addressed the letters can go out - we don't need to see it again before the letters go out. | NDOR / address FHWA comments and resubmit |
| Columbus Viaducts | Draft EA | 31924, etc | 6065-5, etc | 06-Dec-10 | 10-Dec-10 | 4 | comments sent to Allison | NDOR / address FHWA comments and resubmit |
| Norfolk South | Bio doc vers 1 | 31941A | 813-139 | 02-Feb-11 | 02-Feb-11 | 0 | letters sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Dakota Ave resurv; Regency Prkwy | Bio doc vers 1 | 32081 and A | 5305-10, -11 | 03-Mar-11 | 08-Mar-11 | 5 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| Dakota Ave projects | DR 53 | 32081, 32081A | 5305-10 and -11 | 21-Oct-10 | 21-Oct-10 | 0 | rb approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Dakote Ave 29th to Regency Parkway to I-129 | SHPO concur req | 32081/32081A | 5305-10, -11 | 04-Apr-11 | 07-Apr-11 | 3 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Dakota Ave, 29th to Regency Prkwy to I-129 | SHPO concur request | 32081; 32081A | 5305-10; 5305-11 | 6/8/2012 | 6/14/2012 | 6 | comments sent back to NDOR | NDOR / assist locals in addressing FHWA comments; then NDOR reviews and approves locals re-submittal; then NDOR re-submit to FHWA |
| US-30 Drain Impr, GI | DR 53 | 40352A | 304-158 | 06-May-11 | 11-May-11 | 5 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| US-30 Drainage Improvements | Bio doc version 1 | 40352A | 304-158 | 12/7/2011 | 12/14/2011 | 7 | approved | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. |
| US-30 Drainage Improvements | SHPO concur request | 40352A | 304-158 | 2/7/2012 | 2/14/2012 | 7 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| US-30 Drainage Improvements, Grand Island | Cat Ex | 40352A | 304-158 | 5/8/2012 | 5/25/2012 | 17 | sent comments back to NDOR | NDOR / address FHWA comments and resubmit |
| US-30 Drainage Improvements | Cat Ex - revised | 40352A | 304-158 | 6/28/2012 | 7/2/2012 | 4 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Wood River W viaduct | SHPO concur req | 42-32 | 112-114 | 22-Feb-11 | 25-Feb-11 | 3 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Glenvil Spur & East Jct US-281 East | Bio doc vers 1 | 42421, 42590 | S18E-106 & 744-110 | 12/6/2011 | 12/14/2011 | 8 | letters sent to USFWS and NGPC | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Alexandria South Bridges | SHPO concur request | 42474 & 42533 | 531-103 & 531-104 | 5/21/2012 | 6/14/2012 | 24 | comments sent to NDOR | NDOR / address FHWA comments and resubmit |
| Alexandria South | SHPO concur req | 42474, etc | 531-103, -104 | 28-Jan-11 | 31-Jan-11 | 3 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Alexandria S and Alex S Bridges | SHPO concur req | 42533, 42474 | 531-103 & -104 | 12-Nov-10 | 15-Nov-10 | 3 | letter mailed to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Alexandria South & South Bridges | Purpose & Need for comments | 42533; 42474 | 531-103; 531-104 | 3/6/2012 | 4/20/2012 | 45 | NDOR (or LPA) / Must prepare technical and NEPA documentation | |
| E Jct US-281 East - Glenvil Spur | Cat Ex | 42590, 42421 | 744-110, S18E-106 | 2/7/2012 | 2/15/2012 | 8 | provided comments to NDOR. | NDOR / address FHWA comments and resubmit |
| E Jct US-281 East; Glenvil Spur | draft CE | 42590; 42421 | 744-110; S18E-106 | 2/21/2012 | 3/5/2012 | 13 | revised changes look ok. NDOR to resubmit document with changes and signatures. | NDOR / address FHWA comments and resubmit |
| E. Jct. US-281 East; Glenvil Spur | Cat Ex | 42590; 42421 | 744-110; S18E-106 | 3/7/2012 | 3/15/2012 | 8 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Platte River BR E of GI; N Loup W Brdge; Kearney S Platte Rvr BR; Rockville S Brdge | DR 53 | 42607; 42715; 42719; 42725 | 345-118; 224-111; 442-109; 682-104 | 8/6/2012 | 8/16/2012 | 10 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Bio doc vers 1 | Wood Rvr - GI; Platte - Phillips | 42667; 42668 | 806-109, -110 | 28-Feb-11 | 02-Mar-11 | 2 | letters sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Pioneer Spirit Trail Ph III | SHPO concur req | 42688, 42688A | 1-50, 1-51 | 13-Oct-11 | 14-Oct-11 | 1 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Pioneer Spirit Trail | SHPO concur request | 42688, 42688A | 1-50, 1-51 | 11/18/2011 | 11/25/2011 | 7 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Pioneer Spirit Trail Phase III | 4(f) | 42688, 42688A | 1-50; 1-51 | 12/7/2011 | 12/15/2011 | 8 | document wasn't submitted (only the transittal sheet was. | NDOR / address FHWA comments and resubmit |
| Pioneer Spirit Trail | Cat Ex | 42688a | 1-50 | 7/19/2012 | 7/26/2012 | 7 | approved | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Alexandria S and Alex S Bridges | DR 53 - revised | 442533, 42474 | 531-103 & -104 | 12-Nov-10 | 12-Nov-10 | 0 | rb approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Dix South & East; Kimball to Dix | SHPO concur req | 51233; 51395 | 301-134; 301-127 | 6/25/2012 | 6/27/2012 | 2 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| In Bayard & South; Sioux/Box Butte Co Line to N-2 | DR-53 approvals | 51292, 51373 | 261-160; 714-119 | 6/1/2012 | 6/12/2012 | 11 | projects are not to be combined. NDOR resubmitting DR53 as seperate projects. | NDOR / address FHWA comments and resubmit |
| D-5 I-80 Bridge repairs | DR 53 | 51431A | 801-182 | 18-May-11 | 27-May-11 | 9 | sent comments back to Sara | NDOR / address FHWA comments and resubmit |
| District 5 - I-80 Bridge Repair | Bio doc version 1 | 51431A | 801-182 | 12/13/2011 | 12/20/2011 | 7 | letters sent to agencies. | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| District 5 - I-80 Bridge Repair Part 2 | Bio doc version 2 | 51431A | 801-182 | 1/4/2012 | 1/9/2012 | 5 | letters sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Potter-Brownson Crossovers | SHPO concur request | 51451, 51451A | 801-178; 801-184 | 12/8/2011 | 12/9/2011 | 1 | comments sent back to NDOR | NDOR / address FHWA comments and resubmit |
| Potter - Brownson, Potter Brownson crossovers | SHPO concur request - revised | 51451, 51451A | 801-178, 701-184 | 12/19/2011 | 12/21/2011 | 2 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Potter - Brownson, Potter - Brownson Crossovers | Bio doc version 1 | 51451, 51451A | 801-178, 801-184 | 12/27/2011 | 1/3/2012 | 7 | discussed comments with NDOR | NDOR / address FHWA comments and resubmit |
| Potter - Brownson & Potter - Brownson Crossovers | Bio doc version 2 | 51451, 51451A | 801-178, 801-184 | 1/3/2012 | 1/3/2012 | 0 | letters sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Sunol-Chappell; Sunol-Chappell Crossovers | SHPO concur req | 51459; 51459A | 802-97; 802-99 | 6/5/2012 | 6/8/2012 | 3 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Cottonwood Crk N of Crawford; Crawford - SD line | DR 53 | 51499; 51505 | 714-120; 714-121 | 7/11/2012 | 7/13/2012 | 2 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Crawford Creek N of Crawford; Crawford - SD Line | SHPO concur - version 2 | 51499; 51505 | 714-120; 714-121 | 7/27/2012 | 8/17/2012 | 21 | reviewed this morning. should go out to SHPO tomorrow (8/17). | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Cottonwood Creek N of Crawford; Crawford - SD Line | SHPO concur req | 51499; 51505 | 714-120; 714-121 | 7/18/2012 | 7/26/2012 | 8 | comments sent to NDOR | NDOR / address FHWA comments and resubmit |
| Big Springs SW and Colorado Line NE | SHPO concur request | 61279, 61280 | 1382-107, 1382-108 | 11/18/2011 | 11/25/2011 | 7 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Big Springs SW; Colorado Line NE | DR 53 | 61279, 80 | 1382-107, -108 | 06-Oct-11 | 06-Oct-11 | 0 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Gothenburg E & W, Cozad - Darr | Bio doc vers 1 revised | 61425, 61426 | 804-137 & -138 | 16-Mar-11 | 16-Mar-11 | 0 | letters sent to agencies | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| North Platte | Bio Doc | 61449 & 61449A | 832-139 & 832-140 | 30-Sep-11 | 30-Sep-11 | 0 | this tech doc approved. Once NDOR completes all tech reviews, NDOR reviews/ approves NEPA. If not a programmatic CE, NDOR will then submit NEPA to FHWA for review/approval. | |
| S Platte Rvr N & In North Platte | DR 53 | 61449 and -A | 832-139, -140 | 06-Jun-11 | 10-Jun-11 | 4 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Stapleton North & Stapleton South | Bio doc version 1 | 61463, 61464 | 833-108, 832-133 | 12/6/2011 | 12/14/2011 | 8 | letters sent to USFWS and NGPC | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| O'Neill West | SHPO concur req | 7045-28 | 7045-28 | 7/10/2012 | 7/16/2012 | 6 | "letter sent to SHPO | |
| " | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA | |||||||
| Campbell West | CE | 70476a | 4-4(103) | 17-Feb-10 | 22-Feb-10 | 5 | signed | NEPA document approved, NDOR to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Stamford West | DR 53 | 70589A | 892-109 | 11/21/2011 | 11/25/2011 | 4 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Stamford West | Bio doc version 1 | 70589a | 892-109 | 4/20/2012 | 4/23/2012 | 3 | asked NDOR to amend the BA to match the PA requirements; no need to submit to FHWA or resource agencies if following the PA | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Bloomington to Franklin | DR 53 | 70592A | 1364-111 | 3/29/2012 | 4/20/2012 | 22 | DR53 sent back with questions that will hopefully clarify the anticipated impacts | NDOR / address FHWA comments and resubmit |
| Bloomington-Franklin | DR-53 resubmittal | 70592A | 1364-111 | 4/26/2012 | 5/8/2012 | 12 | approved with comments | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Bloomington to Franklin | Arechaeological testing plan - version 2 | 70592A | 1364-111 | 8/1/2012 | 8/16/2012 | 15 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Bloomington to Franklin | Archeological testing plan | 70592a | 1364-111 | 7/12/2012 | 7/25/2012 | 13 | comments sent back to NDOR | NDOR / address FHWA comments and resubmit |
| Danbury West; Danbury - Lebanon; Lebanon - Jct N-47 | DR 53 | 70727, 70890, 71099 | 892-108; -110; -112 | 1/31/2012 | 2/13/2012 | 13 | approved | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| Danbury West; Danbury-Lebanon; Lebanon-Jct N-47 | SHPO concur req - version 2 | 70727; 70890; 71099 | 892-108; 892-110; 892-112 | 5/11/2012 | 5/25/2012 | 14 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Danbury West;Danbury-Lebanon;Lebanon-Jct N-47 | SHPO concur request | 70727;70890;71099 | 892-108; 892-110; 892-112 | 4/18/2012 | 4/27/2012 | 9 | sent comments back to NDOR | NDOR / address FHWA comments and resubmit |
| Moorefield E & W; Curtis East | Bio doc - version 1 | 70889; 71102 | 232-121; 232-124 | 6/27/2012 | 7/2/2012 | 5 | letters sent to USFWS and NGPC | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| In Bassett and North | DR 53 | 80684A | 74-114 | 13-Jun-11 | 16-Jun-11 | 3 | mm concurred on CE | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| In Bassett & North | SHPO concur req | 80684A | 74-114 | 02-Sep-11 | 07-Sep-11 | 5 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Temporary Emergency Repair Projects | DR 53 | 80909T | ER 1833-117T | 12/20/2011 | 12/22/2011 | 2 | None | |
| ER 2010 Relief Projects | DR 53 -batched multiple projects | ER | ER | 01-Jul-11 | 08-Jul-11 | 7 | mm concurred | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| ER 2010 Relief Projects | DR 53 -batched multiple projects | ER | ER | 01-Jul-11 | 08-Jul-11 | 7 | mm concurred | NDOR (or LPA) / Must prepare technical and NEPA documentation |
| ER 2010 Relief Projects | SHPO Concur Req - batched multiple projects | ER | ER | 07-Jul-11 | 11-Jul-11 | 4 | this is a batch Section 106 consultation with SHPO for all the 2010 temp repair work completed. Batched at FHWA's request for expediency. mm reviewed 7/8, gave to front office to format for submittal. SHPO concurrence received in August | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| ER 2010 Relief Projects | SHPO Concur Req - batched multiple projects | ER | ER | 07-Jul-11 | 11-Jul-11 | 4 | this is a batch Section 106 consultation with SHPO for all the 2010 temp repair work completed. Batched at FHWA's request for expediency. mm reviewed 7/8, gave to front office to format for submittal. SHPO concurrence received in August | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| 2010 ER Temp Repairs | Bio doc - batched multiple projects | ER | ER 2010 | 07-Oct-11 | 07-Oct-11 | 0 | FHWA reviewed document and sent comments back to NDOR. NDOR didn't sign the document, changed the determinations agreed to by consulting parties without explanation, and needs to address previous resource agency comments | NDOR / address FHWA comments and resubmit |
| 2010 ER Temp Repairs | Bio doc - batched multiple projects | ER | ER 2010 | 07-Oct-11 | 07-Oct-11 | 0 | FHWA reviewed document and sent comments back to NDOR. NDOR didn't sign the document, changed the determinations agreed to by consulting parties without explanation, and needs to address previous resource agency comments | NDOR / address FHWA comments and resubmit |
| ER 2010 Temp repairs | batched bio doc for all 2010 temp repairs, ver 2 | ER | ER2010 | 11-Oct-11 | 11-Oct-11 | 0 | FHWA pulled up bio doc at Matrix meeting, helped NDOR to amend, with USFWS and NGPC. Then FHWA printed it off and all parties signed. Agency concurrence by sig. MM told NDOR to send the paragraph NEPA memo ASAP to complete process | awaiting submittal of NEPA memo from NDOR ( a quick paragraph summary of their "unusual circumstance" review) |
| ER 2010 Temp repairs | batched bio doc for all 2010 temp repairs, ver 2 | ER | ER2010 | 11-Oct-11 | 11-Oct-11 | 0 | FHWA pulled up bio doc at Matrix meeting, helped NDOR to amend, with USFWS and NGPC. Then FHWA printed it off and all parties signed. Agency concurrence by sig. MM told NDOR to send the paragraph NEPA memo ASAP to complete process | awaiting submittal of NEPA memo from NDOR ( a quick paragraph summary of their "unusual circumstance" review) |
| Wolff Trail Renovation, Lincoln | CE | RTP | RTP2010-007 | 06-Dec-10 | 16-Dec-10 | 10 | approved | NEPA document approved, NGPC to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Oak Park Trail | CE | RTP | RTP2010-003 | 06-Dec-10 | 16-Dec-10 | 10 | approved | NEPA document approved, NGPC to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Wolff Trail Renovation, Lincoln | CE | RTP | RTP2010-007 | 06-Dec-10 | 16-Dec-10 | 10 | approved | NEPA document approved, NGPC to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Oak Park Trail | CE | RTP | RTP2010-003 | 06-Dec-10 | 16-Dec-10 | 10 | approved | NEPA document approved, NGPC to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Bison Bridge Replacement | SHPO MOA Comments | RTP | RTP2011-005 | 15-Feb-11 | 28-Feb-11 | 13 | sent comments to Michelle Stryker for revising. | NGPC / address FHWA comments and resubmit |
| Bison Bridge Replacement | SHPO MOA Comments | RTP | RTP2011-005 | 15-Feb-11 | 28-Feb-11 | 13 | sent comments to Michelle Stryker for revising. | NGPC / address FHWA comments and resubmit |
| S Park Trl, Schuyler, Cole Prk Trl, Aurora | State T&E review | RTP | RTP2010-002, 006 | 28-Feb-11 | 07-Mar-11 | 7 | approved | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| S Park Trl, Schuyler, Cole Prk Trl, Aurora | State T&E review | RTP | RTP2010-002, 006 | 28-Feb-11 | 07-Mar-11 | 7 | approved | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NGPC review/ approve the NEPA document. 2) NGPC submit NEPA to FHWA |
| Deshler Park Trail | NEPA Compliance | RTP | RTP2011-003 | 26-Apr-11 | 12-May-11 | 16 | provided comment to Michelle | NGPC / address FHWA comments and resubmit |
| Deshler Park Trail | NEPA Compliance | RTP | RTP2011-003 | 26-Apr-11 | 12-May-11 | 16 | provided comment to Michelle | NGPC / address FHWA comments and resubmit |
| Cowboy Trail - RTP | NEPA compl docs | RTP | RTP2011-4 | 06-Jun-11 | 10-Jun-11 | 4 | approved | NEPA document approved, NGPC to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Cowboy Trail - RTP | NEPA compl docs | RTP | RTP2011-4 | 06-Jun-11 | 10-Jun-11 | 4 | approved | NEPA document approved, NGPC to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Motocross Track, Lincoln | Archeological Report | RTP | RTP2009-006 | 25-Jul-11 | 09-Aug-11 | 15 | mm reviewed report 7/25 and feels it is adequate. Mm needs to write the summary and recommendation into a letter to SHPO still | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Motocross Track, Lincoln | Archeological Report | RTP | RTP2009-006 | 25-Jul-11 | 09-Aug-11 | 15 | mm reviewed report 7/25 and feels it is adequate. Mm needs to write the summary and recommendation into a letter to SHPO still | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA |
| Streeter Park Trl, Aurora | NEPA compliance | RTP | RTP2010-004 | 16-Aug-11 | 07-Sep-11 | 22 | approved | NEPA document approved, NGPC to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Streeter Park Trl, Aurora | NEPA compliance | RTP | RTP2010-004 | 16-Aug-11 | 07-Sep-11 | 22 | approved | NEPA document approved, NGPC to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Hebron Rock Island Trail | NEPA compliance | RTP | RTP2010-005 | 19-Sep-11 | 20-Sep-11 | 1 | approved | NEPA document approved, NGPC to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| Hebron Rock Island Trail | NEPA compliance | RTP | RTP2010-005 | 19-Sep-11 | 20-Sep-11 | 1 | approved | NEPA document approved, NGPC to evaluate any project scope/condition changes through development and construction to determine if a re-evaluation is required |
| RTP Motocross parking lot report | Sect 106 final report | RTP | RTP2009-006 | 05-Oct-11 | 12-Oct-11 | 7 | mm, sent back to NGPC - signature missing from doc. Once corrected, will send to SHPO for concurrence | NGPC / address FHWA comments and resubmit |
| RTP Motocross parking lot report | Sect 106 final report | RTP | RTP2009-006 | 05-Oct-11 | 12-Oct-11 | 7 | mm, sent back to NGPC - signature missing from doc. Once corrected, will send to SHPO for concurrence | NGPC / address FHWA comments and resubmit |
| RTP Motocross parking lot report | Sect 106 final report2 | RTP | RTP2009-006 | 14-Oct-11 | 17-Oct-11 | 3 | mm, sent back to NGPC - signature missing from doc. Once corrected, will send to SHPO for concurrence | NGPC / address FHWA comments and resubmit |
| Bison Bridge Replacement | NGP Bridge Recordation Plan | RTP2011-005 | 12/1/2011 | 12/13/2011 | 12 | letter with enclosures to go to SHPO 12/13/11 | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA | |
| ER 2008-2010 Perm Repair Projects | SHPO concur request | 1/23/2012 | 1/25/2012 | 2 | letter sent to SHPO | FHWA sent material to resource agency(s) for consultation, which takes up to 4 weeks. Once all tech reviews complete, then: 1) NDOR review/ approve the NEPA document. 2) If not a PCE, NDOR submit NEPA to FHWA | ||
| AVERAGE FHWA TURNAROUND | 6.59 Calendar days | |||||||
* Note: DR 53 is a simple one page yes/no checklist, serving as an early concurrence point for determining if an action will likely be a CE, EA, or EIS. The DR 53 also serves as an early communication tool between FHWA, NDOR, and the project proponent. This is not a NEPA document, but is the "kickoff point" for the environmental review.
** Note: a 0 (zero) value in the Response Time column indicates a document received and responded to in the same day
*** To determine the next step for a project, read the info in this column for the last submittal received related to the project
Melissa Maiefski, Program Delivery Team Leader
(402) 742-8473
Melissa.Maiefski@dot.gov
Raegan Ball, Environmental Specialist
(402) 742-8465
Raegan.Ball@dot.gov