1 South and East Beltway Public Hearing

           1                    PUBLIC HEARINGS

           2

           3   IN RE:  DRAFT ENVIRONMENTAL        )
               IMPACT STATEMENT AND DRAFT         )
           4   SECTION 4(F) STATEMENT             )
                                                  )
           5   SOUTH AND EAST BELTWAYS,           )
               LINCOLN, NEBRASKA                  )
           6   PROJECT NO. DPU-3300(1)            )

           7

           8
                  Hearings held April 23 and 24, 2001, at the
           9      Lincoln Berean Church, 6400 S. 70th Street,
                       Hearing Room 2, Lincoln, Nebraska
          10

          11

          12                 A P P E A R A N C E S
               
          13   HEARING OFFICER:          MR. PAUL H. LADEHOFF, J.D.
                                         Program Coordinator
          14                             The Mediation Center
                                         1120 K Street, Suite 200
          15                             Lincoln, NE 68508

          16   WITNESSES:                MR. ALAN FOSLER
                                         3801 Cape Charles Court
          17                             Lincoln, NE 68516
                                         MR. JOHN BECK
          18                             10100 Holdrege Street
                                         Lincoln, NE 68527
          19                             MS. NANCY BECK
                                         10100 Holdrege Street
          20                             Lincoln, NE 68527
                                         MR. WILLIAM SPEIDEL
          21                             10100 Pioneers Boulevard
                                         Lincoln, NE 68520
          22                             MS. LYN WINEMAN
                                         3005 South 138th Street
          23                             Walton, NE 68461
                                         MR. KEN REITAN
          24                             2310 South Canterbury Lane
                                         Lincoln, NE 68512
          25




                                                                2


           1             (At 5:05 p.m. on April 23, 2001, with

           2   Hearing Officer Ladehoff, Witness Alan Fosler, and

           3   the court reporter being present, the following

           4   testimony was given:)

           5             HEARING OFFICER LADEHOFF:  Let's go

           6        on the record then.  Any time -- any time

           7        you're ready.

           8             ALAN FOSLER:  Okay.  Thank you.

           9        Again, my name is Alan Fosler, and I'm

          10        appearing today on behalf of myself;

          11        however, I wanted to explain some of my

          12        background and exposure I have had to

          13        this project.  My occupation -- I'm a

          14        banker.  I work for Union Bank & Trust

          15        Company and -- and am head of their

          16        operations area.  As part of that, I have

          17        been involved with the Lincoln Chamber of

          18        Commerce and their Infrastructure

          19        Committee which is also studying the

          20        South and East Beltway Projects.  I have

          21        attended the Public Comment Forum on

          22        February 6th which was held at the Gere

          23        Library, and I've heard a presentation by

          24        Jim Linderholm which he gave to the

          25        Chamber of Commerce Subcommittee on March




                                                                3


           1        28th.  And in addition to that, I've read

           2        the various newspaper articles and

           3        visited with people about this topic and

           4        just wanted to come by today to voice my

           5        opinion on this project.

           6             Basically, I have two major issues

           7        that appear to be important to me.

           8        Again, these are from my own perspective

           9        and not any official capacity for those

          10        entities that I've worked with.  The

          11        first one would be that I think that the

          12        South Beltway should be separated from

          13        the East Beltway Project because they

          14        appear to be separate needs.  There

          15        appears to be an immediate need for the

          16        South Beltway based upon traffic, current

          17        traffic flows, and the general proximity

          18        that the Beltway is to the City of

          19        Lincoln.  I think it is a great

          20        improvement for safety and the handling

          21        of the large volume of truck traffic that

          22        exists today.  The area of town where I

          23        live -- I'm very close to Highway 2, and

          24        I see firsthand the truck traffic that

          25        exists on Highway 2.




                                                                4


           1             The second major issue I wanted to

           2        identify was in regards to the East

           3        Beltway and the obvious importance there

           4        is for selecting a final route of the

           5        three that exists today, and it is based

           6        on my own observations that the best

           7        route appears to be the Middle Route

           8        which appears to be the least intrusive

           9        and the most logical for a physical

          10        connection of the south traffic,

          11        potential future South Beltway, the

          12        existing Highway 2, and then north-south

          13        traffic off of this East Beltway.

          14             Some of my reasonings for this:  I

          15        feel -- I've observed that it's the

          16        lowest or fewest residential relocations

          17        impact for the Middle Route and appears

          18        to be the fewest total acres needed to be

          19        obtained to build this route as well.

          20             I'm not as well-versed on some of

          21        the statistical information that I picked

          22        up upstairs --

          23             HEARING OFFICER LADEHOFF:  Uh-huh.

          24             ALAN FOSLER:  -- but it does appear

          25        that the Middle Route gives the highest




                                                                5


           1        daily time savings, but I also fall back

           2        to my personal opinion that it just

           3        appears to be most logical to me.

           4             As a southeast resident of Lincoln,

           5        for me to travel to Omaha, this would be

           6        an acceptable route, and, again, with the

           7        Near Route probably being most intrusive

           8        to existing residents and traffic flow,

           9        and the Far Route, in today's

          10        environment, just too far away.  Also, it

          11        did not appear logical to me to build a

          12        Far Route that would be basically within

          13        two blocks of an existing north-south

          14        paved highway which, I believe, is 148th

          15        Street which is currently in existence.

          16             So I guess in conclusion then, I

          17        support both projects, the East and South

          18        Beltways, specifically the Middle-East

          19        Route.  I believe it would be a great

          20        improvement for traffic safety, for

          21        handling not just truck but car traffic,

          22        and that it would be most convenient and

          23        an accessible route for me from my

          24        location to travel northeast from

          25        southeast Lincoln.  So those are my




                                                                6


           1        comments I would like to present to you.

           2             HEARING OFFICER LADEHOFF:  Okay.

           3        Well, we thank you for coming in this

           4        afternoon.  We can go off the record

           5        then.

           6           (Testimony concluded at 5:10 p.m.)

           7

           8

           9

          10

          11

          12

          13

          14

          15

          16

          17

          18

          19

          20

          21

          22

          23

          24

          25




                                                                7


           1             (At 5:42 p.m. on April 23, 2001, with

           2   Hearing Officer Ladehoff, Witness John Beck, and

           3   the court reporter being present, the following

           4   testimony was given:)

           5             HEARING OFFICER LADEHOFF:  Okay.

           6        Let's go on the record.  Any time you're

           7        ready, John.

           8             JOHN BECK:  Basically, most of

           9        the -- of the issues regarding the

          10        Beltway have been covered, and -- and I'm

          11        not going to go into all of that with you

          12        again.  It's -- we both know them.  There

          13        are two things that I'd like to bring up,

          14        though.  One is that in the meetings that

          15        I've attended recently -- "recently"

          16        being the last two years -- I've -- I've

          17        been troubled by an increasing confusion

          18        about what the purpose for a bypass would

          19        be serving -- or East Lincoln Bypass.

          20             HEARING OFFICER LADEHOFF:  Uh-huh.

          21             JOHN BECK:  And I -- all my comments

          22        are directed towards the East Bypass.

          23        The South is a separate issue and, I

          24        think, stands on separate merits.  The

          25        East Bypass will not -- and initially was




                                                                8


           1        not intended to -- alleviate traffic in

           2        Lincoln's core area.  In order to

           3        alleviate traffic on 27th Street, you've

           4        got to widen 27th Street; 48th Street,

           5        you've got to widen 48th Street.  And

           6        I -- in my written comments -- and I'll

           7        mention it verbally as well -- HWS did an

           8        origin destination study a number of

           9        years ago, and it -- it was -- you know,

          10        it was a terribly flawed study, and that

          11        was unfortunate, but one of the things

          12        that it did lead in the direction of --

          13        of establishing is that Lincolnites don't

          14        drive very far out of their way to go

          15        somewhere.  If they want to go north,

          16        they go north.  They don't go five miles

          17        east to go north to go back five miles

          18        west.  It's just not in their habits at

          19        this point in time.  I don't see any

          20        reason to think that that would change.

          21             What the East Bypass will serve, if

          22        it's built, is it will provide a

          23        connection between the populated areas

          24        south of Lincoln and I-80 East toward

          25        Omaha, and that's a valid purpose; but in




                                                                9


           1        order to achieve that purpose, there's no

           2        benefit in putting the Bypass further

           3        west.  People that are going from south

           4        Lincoln east to Omaha don't care about

           5        going east of Lincoln to get there.

           6        They're going that way anyhow.

           7             Moving the Bypass east will get it

           8        away from Lincoln's populated area, away

           9        from areas of potential future growth,

          10        prevent it from being enveloped by

          11        development which will slow down traffic

          12        on the Bypass and will route it through

          13        less populated and less expensive land.

          14             I'd go one step further than the

          15        proposed Far-East Route and say that

          16        Highway 63 and 42 are already State

          17        highways.  The State already owns

          18        right-of-way along those routes.  They

          19        are about -- I think.  I'm guessing.  I

          20        haven't measured it lately -- but three

          21        and four miles respectively east of the

          22        proposed Far-East Route which isn't much

          23        to be able to build on land where the

          24        right-of-way is already acquired.  And if

          25        a suitable exchange was built over




                                                                10


           1        Highway 34/O Street -- which is O Street

           2        and the -- it's about a six mile section

           3        between where Highway 42 sort of runs

           4        awry near A Street and Highway 2.  If

           5        that were built along a diagonal, you'd

           6        have a very nice route from whatever

           7        connective roadways are built in south

           8        Lincoln and I-80 going east.  Very little

           9        right-of-way to acquire, and also, that

          10        little short piece at the bottom end

          11        there could, I assume, be built as a

          12        priority part of the Project using the

          13        existing roadways as two lanes as they

          14        are to serve the needs and then build an

          15        additional two lanes, much as was done

          16        with Highway 2 between --

          17             HEARING OFFICER LADEHOFF:  Uh-huh.

          18             JOHN BECK:  -- Lincoln and Nebraska

          19        City.

          20             So in short, as far east as

          21        possible.  I don't think the study area

          22        right now is far enough east, and

          23        parenthetically, I'll just stick on there

          24        that I realize that puts you into Cass

          25        County.  Right now if you drive through




                                                                11


           1        southern -- the southern part --

           2        southwestern parts of Omaha, you drive

           3        between Douglas and Sarpy Counties, and

           4        you don't even notice that you did it.

           5        The fact that it crosses a county

           6        boundary, I think, is irrelevant.  I

           7        think it's very shortsighted for Lincoln

           8        and Lancaster County to not consult with

           9        Cass County on what is inevitably going

          10        to be a regional project that will affect

          11        both counties.

          12             The second point brings up an issue

          13        of -- of basic fairness, and I realize

          14        that it's not something the City really

          15        cares about.  It's something that -- and

          16        I don't mean that they're calloused

          17        people in city government, but I think

          18        there's a perception in city government

          19        that it's something that they can't and

          20        shouldn't care about.  I disagree.

          21             In 1986 my wife and I went looking

          22        for property to buy.  We found our

          23        current property on East Holdrege.  I

          24        talked with the City Planning Department

          25        about it.  I specifically discussed the




                                                                12


           1        1972 or 3 beltway study with them.  They

           2        very clearly articulated that Lincoln had

           3        no interest out there and that that

           4        beltway project was dead.  I accepted

           5        that.  In 1992 the Planning Department,

           6        the -- started another round of beltway

           7        studies.  We actually delayed

           8        construction on our house somewhat and

           9        started in 1993 after conversations with

          10        the Planning Department and Public Works.

          11        The -- their statement at that time was

          12        that if the Bypass were ever built it

          13        would be built way east of us and would

          14        not affect us, so we went ahead, and we

          15        built our house.

          16             We moved in in late 1994.  Ever

          17        since we moved in, we've been dealing

          18        with this.  We've put off improvements.

          19        I've got a front porch that's only half

          20        built, and I've got to be honest.  Part

          21        of the motivation -- lack of motivation

          22        to finish that project is that I think it

          23        might be more valid to put a gas pump,

          24        you know, somewhere and -- and start

          25        doing that.




                                                                13


           1             It's just not fair to have people

           2        make plans based on the best information

           3        they can get from the City offices that

           4        are responsible for -- for providing that

           5        information and then turn around two

           6        years later and pull the rug out from

           7        under them.  I just don't think it's

           8        right.  I don't think that it promotes an

           9        image that the City of Lincoln should be

          10        trying to promote.  I think we should be

          11        able to trust our city leaders and know

          12        that when they say something it's -- you

          13        can count on it.  Good night.

          14             HEARING OFFICER LADEHOFF:  Okay.

          15        So -- do you have anything else to add at

          16        this time?

          17             JOHN BECK:  No, I don't.

          18             HEARING OFFICER LADEHOFF:  Okay.

          19        Well --

          20             JOHN BECK:  So --

          21             HEARING OFFICER LADEHOFF:  And I've

          22        received your -- your written comments

          23        and appreciate --

          24             JOHN BECK:  Excellent.

          25             HEARING OFFICER LADEHOFF:  -- that.




                                                                14


           1             JOHN BECK:  And what was your name

           2        again?

           3             HEARING OFFICER LADEHOFF:  I'm Paul

           4        Ladehoff.

           5             JOHN BECK:  And you're with the City

           6        or with --

           7             HEARING OFFICER LADEHOFF:  I'm

           8        with --

           9             JOHN BECK:  -- HWS?

          10             HEARING OFFICER LADEHOFF:  -- The

          11        Mediation Center.  We're private

          12        nonprofit --

          13             JOHN BECK:  I see.

          14             HEARING OFFICER LADEHOFF:  -- and so

          15        we're not connected with the -- HWS or

          16        the City in terms of this.  We're neutral

          17        just here to help people --

          18             JOHN BECK:  Just paid to sit here

          19        and loosen your tie.

          20             HEARING OFFICER LADEHOFF:  That's

          21        right.  And we appreciate your coming in

          22        today --

          23             JOHN BECK:  Thank you very much.

          24             HEARING OFFICER LADEHOFF:  -- and

          25        sharing your thoughts.




                                                                15


           1             JOHN BECK:  And thank you very much.

           2             THE COURT REPORTER:  Thank you.

           3           (Testimony concluded at 5:50 p.m.)

           4

           5

           6

           7

           8

           9

          10

          11

          12

          13

          14

          15

          16

          17

          18

          19

          20

          21

          22

          23

          24

          25




                                                                16


           1             (At 6:28 p.m. on April 23, 2001, with

           2   Hearing Officer Ladehoff, Witness Nancy Beck, and

           3   the court reporter being present, the following

           4   testimony was given:)

           5             HEARING OFFICER LADEHOFF:  Then

           6        let's go on the record.  Any time you're

           7        ready to start.

           8             NANCY BECK:  I thought I'd start

           9        with a little history which you may have

          10        heard.  We bought our land in 1986 and

          11        did go to the Planning Commission and saw

          12        "beltway" in the plan and inquired as to

          13        where the Beltway may be going, and they

          14        said it wasn't in the plan, so we

          15        purchased five acres.  In 1993 we decided

          16        to dig a hole and start to build our

          17        house 'cause we had planted trees and

          18        wanted to let them grow.  So John went

          19        back to the Planning Commission and said

          20        "What about the Beltway?"  And they said,

          21        "It's not in the plan," not to worry.

          22             So we broke ground in '93.  We moved

          23        in '96, and six months after we moved in,

          24        we got a flier saying "There are three

          25        proposed plans for the Beltway.  One of




                                                                17


           1        those plans is 104 and Holdrege."  So our

           2        concern was we had tried to do everything

           3        correctly, you know, determine where our

           4        land should be, find out if there was

           5        anything that might be impacting our

           6        land, and were told again and again not

           7        to worry, that it was fine until, of

           8        course, we had moved in, and then, you

           9        know, guess what?  "This may be

          10        happening."

          11             I attended several meetings a couple

          12        years ago, and at one point someone from

          13        HMS (sic.) said "We have driven up and

          14        down Highway 2, and there are some very

          15        large, beautiful homes that have gone up

          16        along Highway 2, so putting in a beltway

          17        probably won't impact your property."

          18        And I said, you know, "Excuse me.  You

          19        are comparing apples and oranges.  People

          20        who are building beautiful houses along

          21        Highway 2 know they're building beautiful

          22        houses along Highway 2.  We bought five

          23        acres in the country.  We built a

          24        beautiful home because we wanted to be

          25        out where it's quiet without a lot -- a




                                                                18


           1        lot of light or -- or noise.  So you

           2        can't say that, you know, you can compare

           3        those two things."  And he said, "Well,

           4        I -- I guess you're right," but until

           5        maybe somebody questions it, it's okay.

           6        I did go to the Comprehensive Plan

           7        Workshops --

           8             HEARING OFFICER LADEHOFF:  Uh-huh.

           9             NANCY BECK:  -- last week, and I was

          10        reading all their information, and

          11        according to the plans, they are

          12        looking -- their planning area goes all

          13        the way to 134th Street, so I am assuming

          14        that the City is planning at some point

          15        to be incorporated all the way out to

          16        134th Street.  So if there is going to be

          17        a beltway, and if a beltway is a system

          18        that gets you around the City, one would

          19        think it should be beyond 134th Street in

          20        order to serve the purpose it might have

          21        been intended.

          22             Another piece of information they

          23        shared last week at the Comprehensive

          24        Plan Workshop was they are looking at

          25        traffic problems within the City of




                                                                19


           1        Lincoln.  And I know they often say that

           2        a beltway would alleviate internal

           3        traffic problems which is not true, and

           4        according to one of their fliers that

           5        they had posted when they listed the

           6        different plans for transportation, it

           7        said that a beltway was the most costly

           8        method to improve the transportation

           9        system and that it would have limited

          10        impact on internal traffic.  So if

          11        they're thinking that somebody who wants

          12        to go from 27th Street to 70th Street is

          13        going to go via even 104th on a beltway,

          14        that's probably not the case.

          15             So if a beltway indeed needs to be

          16        built, I would think it should be out at

          17        the edge of whatever our community might

          18        be in 2025 which, I believe, is what

          19        they're planning for right now.  So 104th

          20        Street would put it in town.  You know,

          21        the 120th would put it in town.  If

          22        you've got to have a beltway, which I am

          23        not convinced, it should go as far out as

          24        humanly possible indeed to make it a

          25        beltway.  So I was glad I went to those




                                                                20


           1        worksheets (sic.).  They were very nice,

           2        very informative.  And I guess that's it.

           3             HEARING OFFICER LADEHOFF:  Okay.

           4             NANCY BECK:  I wasn't anywhere close

           5        to seven minutes.

           6           (Testimony concluded at 6:32 p.m.)

           7

           8

           9

          10

          11

          12

          13

          14

          15

          16

          17

          18

          19

          20

          21

          22

          23

          24

          25




                                                                21


           1             (At 6:34 p.m. on April 23, 2001, with

           2   Hearing Officer Ladehoff, Witness William Speidel,

           3   and the court reporter being present, the

           4   following testimony was given:)

           5             HEARING OFFICER LADEHOFF:  Then

           6        let's go on the record.  Any time you're

           7        ready to start.

           8             WILLIAM SPEIDEL:  Don't think that

           9        this -- any of these will really be -- be

          10        too much of a problem 'cause by -- I

          11        think by the time it's -- that it will be

          12        built we'll be gone, so --

          13             PHYLLIS SPEIDEL:  We're in a nursing

          14        home.

          15             WILLIAM SPEIDEL:  But I've --

          16        we've -- we've been -- I've -- we have

          17        farmed on the farm at 98th and Pioneers.

          18        We've lived there fifty-six years now,

          19        and I had a dairy herd there for many

          20        years and now, I've -- I -- I don't farm

          21        anymore.  I seeded -- seeded most of it

          22        down now, so -- I still take the seed off

          23        of it, and that's about the only thing in

          24        farming that I -- I take -- take the

          25        grass seed off.




                                                                22


           1             I think the thing that probably

           2        bothers me most of -- about this is that

           3        the farther out -- just like the lady

           4        that spoke just before me said.  I think

           5        she -- that -- that -- that's kind of my

           6        intentions of what I'd be in favor of,

           7        the next one, the middle one.  Even

           8        the -- like I say, the closest one -- it

           9        would be -- it would be -- it wouldn't be

          10        on our farm.  It would be just across the

          11        fence, but I think there's -- they

          12        have -- at least we've heard this, that

          13        there will be a -- a big -- where you get

          14        on the Belt -- the Beltway there on

          15        Pioneers and would really increase the

          16        traffic there, of course, but as I said,

          17        we probably won't be here to -- to -- to

          18        gripe about it.

          19             But anyway, we -- we have been to a

          20        lot of -- in foreign countries, and we've

          21        been probably all over Europe, and the

          22        ones that I've seen this type of highways

          23        or beltways -- Paris has a great --

          24        really a great one.  London has a great

          25        one, and they're all a long ways out.




                                                                23


           1        And I think it's -- it's making it easier

           2        for people to get across town maybe, but

           3        they're not moving them probably to go to

           4        work as much.  And some other towns in

           5        Germany -- Berlin has got -- got a large

           6        one there, and -- and it's -- I think

           7        it's something that -- I -- with a

           8        population of -- of 220 or whatever

           9        Lincoln is now, it -- it shouldn't need

          10        this type of a thing yet, I don't think.

          11             I think the one on the west side and

          12        on the south side -- people are still

          13        going -- if they're going to get onto

          14        the -- I-80, which they would probably be

          15        doing and only if they were going to

          16        Omaha or east, would they even use the --

          17        go on the south and the -- and to the --

          18        the one west of Lincoln and -- and beyond

          19        the -- you know, on the -- of 81 (sic.)

          20        then?

          21             But I just feel that these -- as far

          22        as what I've learned so far, that -- it

          23        seems to me like it's going to be -- on

          24        the East Bypass it would be at least

          25        fifteen years, and I don't know why




                                                                24


           1        Lincoln didn't take ahold of this thing

           2        and -- when they -- they still don't have

           3        Highway 84 four lanes all the way

           4        through --

           5             PHYLLIS SPEIDEL:  Not highway.

           6        Street.

           7             WILLIAM SPEIDEL:  What?

           8             PHYLLIS SPEIDEL:  84th Street.

           9             WILLIAM SPEIDEL:  84th Street, yeah.

          10             HEARING OFFICER LADEHOFF:  Okay.

          11             WILLIAM SPEIDEL:  Excuse me.

          12             HEARING OFFICER LADEHOFF:  Uh-huh.

          13             WILLIAM SPEIDEL:  I'm sorry.  And

          14        just -- and 70th -- they still don't have

          15        that -- it goes clear -- they've got it

          16        partway but not all the way, but 80 --

          17        84th is -- I don't understand why they're

          18        just plugging away.  And they do about

          19        a -- started about two years ago, and

          20        they -- they've got about a -- a mile and

          21        a half extension now there, but that

          22        should have been done a long time ago,

          23        and -- because I think you're going to --

          24        if they open up the Stevens Creek area,

          25        why -- I mean for -- so it will be -- it




                                                                25


           1        will -- it will -- Lincoln will move in

           2        there as soon as they get a -- a new

           3        sewage plant out on about Cornhusker

           4        Highway and Stevens Creek.  And I guess

           5        probably about -- you can about guess

           6        that's where -- where it would be, but

           7        that will fill in just so quick that you

           8        won't -- if -- if you don't get out as

           9        far as you can, why, you're going to be

          10        right in the City.

          11             If they would have done it like

          12        Omaha did and put it right down through

          13        the middle to begin with -- I think that

          14        works pretty good in Omaha, and I don't

          15        know why -- but I think -- they -- they

          16        think they need something more than they

          17        really need.  And that's about all I have

          18        to say to that.

          19             HEARING OFFICER LADEHOFF:  Okay.

          20             WILLIAM SPEIDEL:  Thank you.

          21             HEARING OFFICER LADEHOFF:  Thank

          22        you, Mr. Speidel.

          23           (Testimony concluded at 6:40 p.m.)

          24

          25




                                                                26


           1             (At 6:47 p.m. on April 23, 2001, with

           2   Hearing Officer Ladehoff, Witness Lyn Wineman, and

           3   the court reporter being present, the following

           4   testimony was given:)

           5             HEARING OFFICER LADEHOFF:  Any time

           6        you're ready, unless you have any

           7        questions.

           8             LYN WINEMAN:  Great.  Okay.  My name

           9        is Lyn Wineman.  My husband, Neil, and I

          10        live at 3005 South 138th Street in

          11        Historic Stevens Creek Stock Farm.  And

          12        for the record, while we feel it's nice

          13        to have this opportunity to gather

          14        information and comment on the Draft

          15        Environmental Impact Study, we believe

          16        the setting does not represent a

          17        meaningful public hearing, and we were

          18        expecting to have the ability to share

          19        our views and hear the views of others

          20        regarding this important issue.  We,

          21        therefore, respectively request a public

          22        hearing before the comment time for this

          23        process is over on May 14th.

          24             We have found numerous and

          25        substantial errors and omissions in the




                                                                27


           1        Draft Environmental Impact Study and will

           2        be submitting those comments to Federal

           3        Highways in writing prior to the

           4        deadline.

           5             HEARING OFFICER LADEHOFF:  Okay.

           6        Thank you.

           7             LYN WINEMAN:  All right.  Thank you.

           8           (Testimony concluded at 6:48 p.m.)

           9

          10

          11

          12

          13

          14

          15

          16

          17

          18

          19

          20

          21

          22

          23

          24

          25




                                                                28


           1             (At 7:30 p.m. on April 23, 2001, with

           2   Hearing Officer Ladehoff, Witness Ken Reitan, and

           3   the court reporter being present, the following

           4   testimony was given:)

           5             HEARING OFFICER LADEHOFF:  Any time

           6        you're ready to begin.

           7             KEN REITAN:  Yeah.  I'm here to

           8        express my opposition to beltways in

           9        general.  I think Lincoln should take a

          10        serious look at the experience that

          11        Atlanta, Georgia has had with beltways

          12        and serious sprawl and traffic problems

          13        that have resulted.  Make no mistake

          14        about it.  Beltways create new sprawl and

          15        generate new traffic.  Atlanta's

          16        situation has become so serious that they

          17        are having ongoing legal problems with

          18        the federal government over air quality.

          19        In the next few years as the global

          20        warming debate heats up, it's anyone's

          21        guess what kinds of growth and road

          22        construction restrictions will come down

          23        from the federal government.  Lincoln can

          24        be better prepared for that type of

          25        future by choosing smarter types of




                                                                29


           1        growth.  And that's the end of my

           2        statement.

           3             HEARING OFFICER LADEHOFF:  Do you --

           4        do you have examples maybe of what types

           5        of growth you mean?

           6             KEN REITAN:  Well, I guess -- I

           7        guess I would like -- if we're going to

           8        spend lots of money on road construction,

           9        I'd like to see it spent on the interior

          10        streets of Lincoln 'cause I -- I just

          11        don't think that these beltways are going

          12        to solve a lot of the -- a lot of the

          13        traffic problems.  We're still going to

          14        have lots of frustrated motorists 'cause

          15        these beltways are going to be out there

          16        quite a ways.  You know, they're not

          17        going -- you're not going to save time by

          18        going way out to the -- you know, several

          19        miles out in the country if you've just

          20        got to go across town five, six miles.

          21             HEARING OFFICER LADEHOFF:  Okay.

          22             KEN REITAN:  You know, I mean that's

          23        all -- I -- I drive six miles to work.

          24        I'm not -- not about to -- to go out to

          25        one of those beltways to -- to go from --




                                                                30


           1        well, I live around Old Cheney Road and

           2        go up to East Campus University.  I'm not

           3        going to use one of those beltways.

           4             HEARING OFFICER LADEHOFF:  Uh-huh.

           5             KEN REITAN:  And -- and I just think

           6        that the vast majority of people aren't

           7        going to use them.  There will be some,

           8        certainly.  Truckers will use them.

           9             HEARING OFFICER LADEHOFF:  Okay.

          10        Anything else?

          11             KEN REITAN:  So I added a little

          12        extra there, I guess.

          13             HEARING OFFICER LADEHOFF:  Thank you

          14        for coming in tonight.

          15             KEN REITAN:  Sure.

          16           (Testimony concluded at 7:32 p.m.)

          17

          18

          19

          20

          21

          22

          23

          24

          25




                                                                31


           1                 C E R T I F I C A T E

           2        I, Jody J. White, Registered Professional

           3   Reporter, do hereby certify that the within and

           4   following complete transcript contains all the

           5   testimony requested to be transcribed by me and

           6   the comments of the hearing officer, from the

           7   public hearing held in this matter; and that said

           8   complete transcript is a correct and complete

           9   transcript of the testimony requested to be

          10   transcribed from the record made at the time of

          11   said public hearings.

          12        Dated this 26th day of April, 2001.

          13

          14

          15                         _____________________________

          16                                 Jody J. White

          17

          18

          19

          20

          21

          22

          23

          24

          25

back home top


HOME PAGE URL: http://www.fhwa.dot.gov/nediv