Stewardship and Oversight Agreement
Percent of Projects Completed on Time
Based on Approved Construction Schedule
| FFY 06 | 69% |
|---|---|
| FFY 07 | 92% |
| FFY 08 | 86% |
| FFY 09 | 85% |
| FFY 10 | 98% |
Annually by Fiscal Year