Skip to contentUnited States Department of Transportation - Federal Highway Administration FHWA HomeFeedback


Table of Contents | Previous | Next

CHAPTER 7: STEWARDSHIP & OVERSIGHT AGREEMENT PROGRAM AREAS

  1. AIR QUALITY PLANNING
  2. BRIDGE AND STRUCTURES
  3. CIVIL RIGHTS
  4. CONSTRUCTION AND CONTRACT ADMINISTRATION
  5. DESIGN
  6. EMERGENCY RELIEF
  7. ENVIRONMENT
  8. FINANCIAL MANAGEMENT
  9. INTELLIGENT TRANSPORTATION SYSTEMS
  10. LOCAL PUBLIC AGENCIES
  11. MAINTENANCE AND PRESERVATION
  12. PAVEMENT AND MATERIALS
  13. PLANNING
  14. RESEARCH, DEVELOPMENT, & TECHNOLOGY TRANSFER
  15. RIGHT-OF-WAY
  16. SAFETY
  17. SPECIFICATIONS
  18. TRAFFIC OPERATIONS

Top

AIR QUALITY PLANNING

  1. Program Overview:

    The primary focus of air quality in transportation planning is the process that results in a demonstration of conformity. Under the 1990 Clean Air Act Amendments, FHWA cannot fund, authorize, or approve Federal actions to support programs or projects that are not first found to conform to the Clean Air Act requirements or are exempt activities under those requirements. The transportation conformity process integrates transportation planning and air quality planning by requiring that transportation plans, programs, and projects demonstrate that emissions resulting from their implementation are consistent with and conform to the purpose of the State Implementation Plan. The Division and FTA Region V, in consultation with USEPA Region V, make joint conformity determinations on Plans, TIPs, and amendments to Plans and TIPS.

    Other air quality planning responsibilities include The Congestion Mitigation and Air Quality Improvement (CMAQ) program. The purpose of the CMAQ program is to fund transportation projects or programs that will contribute to attainment or maintenance of the National Ambient Air Quality Standards (NAAQS). The Division (jointly with FTA Region 5) determines eligibility for inclusion in this funding program on a project-by-project basis using criteria contained in 1999 Program Guidance issued jointly by the FHWA office of Planning and Environment and the FTA office of Planning. Key Division actions include project eligibility determinations and submittal of the annual State CMAQ Report to Headquarters.

  2. Applicable Laws, Regulations, and Procedures:

    Conformity

    • 42 USC 7401-7671q (Clean Air Act)
    • 40 CFR 51
    • 40 CFR 93
    • Transportation Conformity Regulation (August 15, 1997)
    • 23 CFR 450
    • 23 USC 134 - Metropolitan Planning
    • 23 USC 135 - Statewide Planning
    • 49 USC 53 - Mass Transportation

    CMAQ

    • 23 USC 104
    • 23 USC 110
    • 23 USC 149

  3. Program Approval Actions:

    The Division and FTA Region V, in consultation with USEPA Region V, make joint conformity determinations on Plans, TIPs, and amendments to Plans and TIPS for nonattainment and maintenance areas. Plans are updated on a four-yearcycle and must be amended when regionally significant transportation projects are added to the program. TIPs are also updated on a four-year cycle and must be amended when transportation projects are added to the program consistent with the MPO's policies and procedures.

  4. Project Approval Action:

    ODOT submits requests to the Division office on a project-by-project basis to determine their eligibility for funding through the CMAQ program. The Division (jointly with FTA Region 5 and in consultation with USEPA Region 5) determines eligibility of projects using criteria contained in the 1999 Program Guidance issued jointly by the FHWA office of Planning and Environment and the FTA office of Planning. Projects are submitted randomly throughout the year fordeterminations of eligibility.

  5. Monitoring:

    ODOT will monitor MPO Plan and TIP development activities to ensure that the work is being managed and performed satisfactorily and that conformity schedules are being met.

    FHWA and ODOT consult with USEPA and Ohio EPA and work closely with each MPO in non-attainment and maintenance areas.

  6. Performance Indicators:

    No areas in a conformity lapse.

  7. Business Standards:

    FHWA will review and take action on CMAQ projects within 30-days of receipt. FHWA will review and comment on the draft and final conformity documentation for Metropolitan Transportation Plans and TIPs within 60 days. This 60-day timeframe includes the 30-day FHWA review/comment period and a 30-day period to coordinate with the FTA and USEPA. ODOT will involve FHWA in decisions involving special and unusual circumstances at the earliest reasonable time to ensure thorough and appropriate decisions can be made.

    ODOT will provide the Division an annual report of the CMAQ program that meets the requirements of 23 USC 149 no later than January 31 of each calendar year. Additional guidance for preparing the annual report is discussed in the 1999 Program Guidance issued jointly by the FHWA office of Planning and Environment and the FTA office of Planning.

Activity/Requirement

FHWA Action

Frequency

Conformity

•42 USC 7401-7671q (Clean Air Act)

•40 CFR 51

•40 CFR 93

•August 15, 1997 Transportation Conformity Regulation

•23 CFR 450

•23 USC 134 - Metropolitan Planning

•23 USC 135 - Statewide Planning

•49 USC 53 - Mass Transportation

Conformity Determination

Not less than every 4 years

CMAQ Annual Report

•23 USC 149 (h) (2)

Review ODOT’s report and submit to HQ

Annually in February

CMAQ Eligibility

•23 USC 104

•23 USC 149 (primarily)

Eligibility Determinations

Periodically – individual submissions by ODOT

 

BRIDGE AND STRUCTURES

  1. Program Overview:

    The FHWA is responsible for administering the Highway Bridge Replacement and Rehabilitation Program (HBRRP). The purpose of the Program is to replace or rehabilitate public highway bridges over highways, railroads, waterways, or other topographical barriers, when it has been determined that a bridge is deficient because of structural or physical deterioration, or functional obsolescence.

    Reimbursable scopes of work include:

    • Replacement,
    • Rehabilitation, and
    • Low water crossing replacement.

    The FHWA is responsible for administering the National Bridge Inspection Standards (NBIS) and National Bridge Inventory (NBI). The NBIS requires that all highway bridges over 20 feet in length be inspected at least once every two years. Certain structures, such as box culverts, may be inspected at a lesser frequency if past experience and favorable past experience and analysis justify the increased interval of inspection. ODOT currently inspects all highway bridges over 10 feet in length every year.

    The NBI also requires the State to ensure that all bridges within its borders, including county and municipal owned bridges, are inspected in accordance with the NBIS. For bridges where the inspection responsibility belongs to a county or municipality, ODOT will annually provide a list of bridges that have not been inspected to FHWA and the responsible agency, per Ohio Revised Code 5501.47, and ODOT and FHWA will work together to resolve the issues. All bridges over 20 feet in length are also required to be listed on the State's inventory and their inventory information is to be submitted annually to FHWA to be included in the NBI.

    Other Federal aid highway funds administered by FHWA may also be used to construct or rehabilitate bridges. Project approval actions are similar to those that apply to the HBRRP program except the existing bridge need not be deficient.

    Federal bridge funds may also be used for preventive maintenance on bridges included in the national inventory that are not owned by a federal agency (with pre-approval by FHWA). Other eligible items include:

    • Seismic retrofits,
    • Scour countermeasures,
    • Bridge painting,
    • Bridge rail replacement or retrofit,

    In order to improve the nation's defense mobility, FHWA and ODOT have prioritized the elimination of vertical clearance deficiencies on the 16' component of the Strategic Highway Network (STRAHNET). FHWA and ODOT will coordinate on project-level decisions, based on a statewide overview of the 16' component of the STRAHNET, to eliminate vertical clearance deficiencies. ODOT management and FHWA will conduct outreach to the District Offices explaining the importance of eliminating this type of deficiency and the higher standard applied to this deficiency with Design Exception requests.

  2. Applicable Laws, Regulations, and Orders

    • Title 23 USC 144 Highway Bridge Replacement and Rehabilitation Program
    • Title 23 USC 151 National Bridge Inspection Program
    • 23 CFR 650 Bridges, Structures, and Hydraulics

  3. Program Approval Actions

    • FHWA will make an annual determination of compliance with the NBIS.
    • ODOT will submit the annual NBI data to FHWA Headquarters.
    • ODOT will submit bridge unit cost data, to be reviewed by the FHWA Division Office and forwarded to FHWA Headquarters.

  4. Project Approval Actions

    • FHWA will approve eligible bridge projects according to Section II of this Agreement.
    • Unusual or complex bridge projects on the Interstate System will require FHWA Headquarters review and approval of the preliminary Type Size and Location (TS&L) report.
    • Unusual, complex, or large bridges located off of the Interstate or NHS system may be designated for FHWA oversight.
    • Exceptions to three design features associated with bridges (structural capacity, bridge parapet/curb configuration, and vertical clearance) within the limits of proposed projects require the processing and approval of Design Exceptions. Any vertical clearance deficiencies proposed to remain will be coordinated with the military's Surface Deployment and Distribution Command (SDDC) by FHWA for Federal-aid projects and ODOT for non-Federal projects.


  5. Monitoring

    FHWA Ohio Division Office will:

    • Screen bridges for eligibility for HBRRP based on the selection list.
    • Review Preliminary Engineering Studies and Project Scopes
    • Review Type Size and Location reports
    • Review bridge design plans on FWHA Oversight Projects.
    • Provide oversight of bridge construction.
    • Review Critical Bridge Inspection reports.
    • Review Quarterly reports for bridge posting, critical findings, and inspection frequency.
    • Review semi-annual scour critical Plan of Action (POA) status.
    • Perform special process reviews of specific program elements such as hydraulics, geotechnical, design, or construction on a periodic basis.
    • Perform annual reviews to establish compliance with the NBI.
    • Review the annual inventory of bridges with deficient vertical clearances on the 16' component of the STRAHNET and associated maps, and coordinate with ODOT on the program of proposed projects.
    • Following completion of a project or maintenance work, ensure ODOT re-measures the vertical clearance of any bridge possibly affected.
    • Review Bridge Construction Unit costs submittal.
    • Perform Bridge Maintenance Inspections.
    • Provide technical assistance.

  6. Business Standards

    • FHWA will review and comment on Preliminary Engineering Studies and Project Scope Reports within 4 weeks of receipt.
    • ODOT will submit the annual update of NBI data to FHWA by April 1st of each year.
    • ODOT will submit the Construction Unit Cost data by March 1st of each year.

  7. Performance Indicators

    1. Track % of bridges Floor Condition deficient.
    2. Track % of bridges General Appraisal deficient.
    3. Track % of bridges Wearing Surface deficient.
    4. Track % of bridges Paint Condition deficient.
    5. Reduce the number of bridges with deficient vertical clearance on the 16' component of the STRAHNET.

  8. Approved Procedures/Agreements/Manuals

    • ODOT Bridge Design Manual
    • ODOT Location and Design Manual
    • ODOT Standard Specifications
    • ODOT Local Transportation Project Manual
    • ODOT Bridge Inspection Manual
    • FHWA Bridge Inspection Coding Guide
    • AASHTO Standard Specifications for Highway Bridges
    • AASHTO LRFD Bridge Design Specifications
    • Technical Advisory T 5140.21, REVISIONS TO THE NATIONAL BRIDGE INSPECTION STANDARDS

    PROJECT ACTIVITY APPROVAL CHART

    PROJECT ACTIVITIES
    AGENCY RESPONSIBLE
    Approval Action
    Reference Document

    FHWA Oversight:
    I-4R≥$5 m;

    I-3R≥$10m; Non-Interstate NHS≥$10m; ADHS Projects

    ODOT Oversight:
    I-4R<$5m;
    I-3R<$10m;

    Non-Interstate NHS<$10m

    ODOT Oversight:
    All

    Non-NHS Projects
    Other Projects Subject to FHWA Oversight by Mutual Agreement Other Projects Subject to FHWA Oversight by Mutual Agreement
    HBRRP eligibility determinations
    23 CFR 650
    Subpart D
    FHWA
    ODOT
    ODOT
    FHWA/ODOT

    Preliminary Engineering Studies and Project Scopes

     
    FHWA
    ODOT
    ODOT
    FHWA/ODOT
    TS & L 
    23 USC 106
    23 CFR 630
    FHWA
    ODOT
    ODOT
    FHWA/ODOT
    Structural Plans
    23 USC 106
    23 CFR 630
    FHWA
    ODOT
    ODOT
    FHWA/ODOT
    Construction
    Inspections
    FAPG G
    6042.8
    FHWA/ODOT
    ODOT
    ODOT
    FHWA/ODOT
    Exempt bridge
    from Coast Guard
    permit
    requirements
    23 CFR
    650.805
    FHWA
    FHWA
    FHWA
    FHWA

    PROGRAM ACTIVITY APPROVAL CHART

    PROGRAM
    REFERENCE
    AGENCY RESPONSIBLE
    NBIS Review
    23 CFR 650 Subpart C
    FHWA
    Inventory and maps of deficient
    bridges on the 16' component of
    the STRAHNET
    23 CFR 625
    ODOT
    Bridge Unit Cost submittal
    23 CFR 650 Subpart D
    ODOT
    Innovative Bridge Research and
    Deployment Program candidate
    submittals
    23 USC 503 (b)
    ODOT
    National Historic Covered Bridge
    Candidate submittals
    Section 1224 -
    TEA21
    ODOT
    Semi-Annual scour POA updates
     
    FHWA
    Reports for: Bridge Posting,
    Critical Findings, and Inspection
    Frequency
     
    ODOT

Top

CIVIL RIGHTS

  1. Program Overview:

    The FHWA Division Office is committed to effectively implementing and enforcing civil rights programs within ODOT in its planning, construction, and management of the multimodal Ohio transportation system. Federal law establishes the State as responsible for nondiscrimination as the recipient of Federal aid; however, the law does not allow the delegation of FHWA Civil Rights federal responsibilities to ODOT at any project level. If projects are managed by a sub-recipient, ODOT must ensure thatthe sub-recipient is well qualified and suitably equipped to perform the work (23 CFR 1.11). If sub-recipients are involved, ODOT is obligated to ensure nondiscrimination in all programs and activities, and in the provisions of all services and benefits, as a basis for continued receipt of FHWA funds. ODOT can delegate the activity but cannot delegate their responsibility.

  2. Applicable Laws, Regulations, and Orders

    • Title VI of the 1964 Civil Rights Act
    • Equal Employment Opportunity Act of 1964
    • Rehabilitation Act of 1973
    • Age Discrimination Act of 1975
    • Americans with Disabilities Acts of 1990
    • Civil Rights Restoration Act of 1987
    • 23 USC 140, 142, 324
    • 49 CFR Part 21 &26
    • 23 CFR Part 230, 633
    • 13 CFR Part 121
    • Executive Order 11246
    • Executive Order 12898


  3. Program Approval Actions

    PROGRAM ACTIVITIES
    AGENCY RESPONSIBILITY

    Approval Action

    Reference Document

    Review

    Approve

    Remarks

    Disadvantaged Business Enterprise Program, Goal, and Supportive Service Plans.

    49 CFR Part 26
    Title VI of the 1964 Civil Rights Act
    23 CFR Part 230 Subpart B
    13 CFR Part 121 SBA, Size Standards

    FHWA

    FHWA

    Coordination of approval with FHWA HQ Review Team. Division Administrator approves program and Goal. Division office reviews DBE/SS work plan.

    State Highway Agency Affirmative Action (External/ Internal) Plans

    23 USC 140
    23 CFR Part 230 Subpart C
    Title VI of the 1964 Civil Rights Act
    Title VII
    Equal Employment Opportunity Act of 1964
    American with Disabilities Acts of 1990

    FHWA

    FHWA

    Programs are reviewed annually and approved by the Division Administrator

    Contract Compliance Review Program

    Section 22(a.) 1968 Federal-Aid Highway Act (23 USC 140)
    23 CFR Part 230 Subparts A & D
    Title VI of the 1964 Civil Rights Act
    Exec. Order 11246
    23 CFR Part 633

    ODOT

    FHWA

    Federal-aid highway contracts of $10,000 or more are monitored by ODOT. Contract compliance reviews/audits are conducted by ODOT. Reviews are audited by FHWA at annual review period.

    Equal Employment Opportunity On-the-Job Training/ Supportive Services Programs

    23 USC 140
    23 CFR Part 230 Subpart A & C
    Title VI of the 1964 Civil Rights Act
    Equal Employment Opportunity Act of 1972
    American with Disabilities Acts of 1990

    FHWA/ ODOT

    FHWA

    OJT Training Programs are reviewed and monitored by ODOT and FHWA concurrence. FHWA reviews the Supportive Services work plan and approves each year. ODOT does not specify OJT participation per contract, and implements it on a voluntary program basis.

    Title VI/Non-discrimination

    Title VI of the 1964 Civil Rights Act
    49 CFR Part 21
    23 CFR Part 200
    Section 504 of the Rehabilitation Act of 1973
    49 CFR Part 27
    Age Discrimination Act of 1975
    Civil Rights Restoration Act of 1987
    Uniform Relocation Act of 1987
    23 USC 142
    23 USC 324

    FHWA

    FHWA

    Programs are developed by ODOT and reviewed and approved annually by FHWA Division Office



  4. Project Approval Actions

    Not applicable for Civil Rights Program.

  5. Monitoring

    FHWA will review and approve ODOT's programs on an ongoing basis through process and program reviews and through active participation in continuous program evaluation and improvement. Appropriate FHWA representatives will actively participate in ODOT's initiated reviews, task forces, and other civil rights initiatives upon request and to the extent feasible. Finally, FHWA will analyze civil rights reports submitted by ODOT to help identify trends and provide feedback and recommendations to ODOT.


  6. Performance Indicators

    1. Monitor number of pre-qualified DBEs.
    2. Monitor DBE program race-neutral contributions.

  7. Business Standards

    WORK ACTIVITY

    ODOT ACTION

    FHWA ACTION

    REMARKS

    DBE Program Plan Revisions

    Prepare and Submit as Required

    Review and Act On (20 Days)

    Updates Accurately Reflect Appropriate Program Changes

    Title VI Program Update

    Prepare and Submit upon Completion

    Review and Act Upon (20 Days)

    Updates Accurately reflect ODOT's Title VI Program

    State Internal AA/EEO and Contract Compliance Program Reports (Title VII)
    (Includes EEO-4 Report)

    Prepare and Submit Within One Year From the Date of Approval of the Preceding Program

    Review and Act Upon (20 Days)

    Report is Accurate and Meets CFR Requirements

    Annual Contractor
    Employment Report-PR1392
    Prepare and Submit No Later
    Than September 25
    Review and File.
    Submit to
    FHWA HQ
     
    Contractor Compliance
    Review Schedule and
    Reports
    Prepare and Submit Upon
    Completion
    Review and Act
    Upon (14 days)
     

    DBE and OJT Supportive Service Work Requests/ Reports

    Prepare and Submit per Contract
    Review and Act Upon (14 days)
     
    On-the-Job Training
    Program
    Prepare and Submit (No Later
    than March 1)
    Review and Act
    Upon (20 Days)
     
    On-the-Job Training Goals
    and Accomplishments
    Prepare and Submit (No Later
    Than November 30)
    Review and Act
    Upon (14 Days)
    Previous year's
    accomplishments
    and current year's
    projection


  8. Approved Procedures/Agreements/Manuals

    • DBE Program Administration Document
    • EEO/Contract Compliance Manual

Top

CONSTRUCTION AND CONTRACT ADMINISTRATION

  1. Program Overview:

    The FHWA is required to assure compliance with Federal-Aid contract provisions on all projects that utilize Federal-Aid funds. Federal responsibility includes assurance that specific procedures are followed in the advertisement and award of Federal-Aid contracts. The FHWA specific contract administration responsibilities in accordance with Federal law include (but are not limited to):

    • Project Authorization
    • Competitive Bidding
    • Contract Awards
    • Buy America provisions

    By law, FHWA is responsible for the inspection of construction projects utilizing federal aid funds. The primary purpose of FHWA review and administration in construction is to protect the public investment, assure effective quality controls, and to verify that the project is completed in accordance with the plans, specifications and special provisions. ISTEA and TEA-21 allow the delegation of FHWA construction review, oversight and administration responsibilities, except those based on non-Title 23 Federal requirements to the state DOT. SAFETEA-LU does not substantially change this delegation. The FHWA specific construction monitoring responsibilities include stewardship in the following areas (but not limited to):

    • Quality Control and Improvement
    • Contract Claims
    • Change Orders
    • Payment to Contractor
    • Time Extensions
    • Liquidated damages

    FHWA also provides technical assistance in problem solving and recommendations for improvements to State and local construction programs to ensure that high quality products are constructed.

    FHWA also provides sharing of identified state-of-the-art practices and innovations in materials, equipment, construction practices and contracting methods for the purposes of highlighting best practices.

  2. Applicable Laws, Regulations, and Orders

    • 23 USC, 102, 106, 112, 114, 117, 121
    • 40 USC 276(a) Davis-Bacon Act
    • 23 CFR 635 Construction and Maintenance
    • 23 CFR 637 Construction Inspection and Approval
    • 29 CFR Parts 1, 3, 5, 6, & 7

  3. Program Approval Actions

    • FHWA will have specific approval authority for the authorization and obligation of Federal-Aid funds for all federal-aid projects.
    • FHWA will approve ODOT Standard Specifications and Supplemental Specifications on a program basis to facilitate project approvals.
    • FHWA will approve the updates to the Liquidated Damages specification every two years (Every even-numbered year).

  4. Project Approval Actions

    • FHWA will approve all project and construction authorizations.
    • FHWA will approve project agreements, modified project agreements and final vouchers on all projects.
    • FHWA will conduct routine project and final inspections on FHWA Oversight projects.
    • For all other Federal NHS and non-NHS projects, FHWA may conduct inspections, including finals, on a statewide sampling basis through QIR and QAR reviews.

  5. Monitoring

    FHWA Division Office will:
    • Evaluate ODOT's transportation construction program, including their staffing levels, procedures, and controls for assuring transportation improvements are constructed in accordance with approved standards and acceptable contracting methods.
    • Evaluate the quality of materials, equipment, construction practices, and work force used for the purpose of evaluating the quality of the constructed product.
    • Track the cost of a sample of construction projects to determine the relationship of the final cost to the amount bid for the project.
    • Gather information from the State DOT's on the usage and costs of various construction materials including aggregates, cements and bitumens, lumber and steel utilizing form FHWA 47.

  6. Performance Indicators

    1. Track % of change orders for projects greater than $10 million.
    2. Track % of projects completed by the revised completion date.

  7. Business Standards

    • FHWA will review and approve supplemental specifications, PS&Es, construction plans and major change orders within two weeks of receipt. The 2-week time frame may be reduced in emergency or unusual situations.
    • Form FHWA 45. ODOT will send "Bid Price Data" to FHWA within 2 weeks of award of contract.
    • Form FHWA 47 "Statement of Materials and Labor" is to be sent to FHWA within 4 months of completion of the project and receipt of final records on NHS projects greater than $1 million.

  8. Approved Procedures/Agreements/Manuals

    • ODOT Location & Design (L&D) Manuals
    • ODOT Construction Documentation Manual
    • ODOT Construction and Materials Specifications
    • ODOT Supplemental Specifications and Proposal Notes
    • FHWA Contract Administration Core Curriculum Manual
    • FHWA Construction Program Management and Inspection Guide
    • Federal-Aid Policy Guide

    PROJECT ACTIVITY APPROVAL CHARTS

    PROJECT ACTIVITIES
    AGENCY RESPONSIBLE

    Approval Action

    Reference Document

    FHWA Oversight:
    I-4R≥$5m;
    I-3R≥$10m;
    Non-Interstate NHS≥$10m;
    ADHS Projects

    ODOT Oversight:
    I-4R<$5m;
    I-3R<$10m;
    Non-Interstate NHS<$10m

    ODOT Oversight:
    All
    Non-NHS Projects

    Other Projects Subject to FHWA Oversight by Mutual Agreement

    Approve exceptions to competitive bidding

    23 CFR 635.104& 204

    FHWA

    FHWA

    FHWA

    FHWA

    Approve advertising period of <3 weeks

    23 CFR 635.112

    FHWA

    FHWA

    FHWA

    FHWA

    Concur in award of contracts

    23 CFR 635.114

    FHWA

    ODOT

    ODOT

    FHWA

    Concur in rejection of bids

    23 CFR 635.114

    FHWA

    FHWA

    FHWA

    FHWA

    Approve change and extra work orders

    23 CFR 635.120

    FHWA

    ODOT

    ODOT

    FHWA

    Approve time extensions

    23 CFR 635.121

    FHWA

    ODOT

    ODOT

    FHWA

    Accept material certifications

    23 CFR 637.207

    ODOT

    ODOT

    ODOT

    ODOT

    Concur in settlement of claims

    23 CFR 635.124

    FHWA

    ODOT

    ODOT

    FHWA

    Concur in termination of contracts

    23 CFR 635.125

    FHWA

    ODOT

    ODOT

    FHWA

    Final Acceptance/Inspection

    23 USC 114a & 121

    FHWA

    ODOT

    ODOT

    FHWA

    Construction inspections

    FAPG G 6042.8

    FHWA

    ODOT

    ODOT

    ODOT

    Determination of cost effective methods

    23 CFR 635.204& 104

    FHWA

    FHWA

    FHWA

    FHWA

    Emergency Relief *

    23 CFR 668

    FHWA

    FHWA

    FHWA

    FHWA

     

    PROGRAM

    REFERENCE

    AGENCY RESPONSIBLE

    Buy America

    23 CFR 635.410

    FHWA

    Local Public Agency Projects **

    23 CFR 635.105

    ODOT

    Project/ Construction Authorization

    23 CFR 635.106 (a)

    FHWA

    Quality Assurance (Program) reviews

     

    FHWA

    FHWA Form 45

    23 CFR 635.113

    ODOT

    FHWA Form 47

    23 CFR 6.35.126

    ODOT

    Labor Compliance

    29 CFR Parts 1, 3, 5, 6, & 7

    FHWA (Forwarded to HQ)

    * See Emergency Relief Section
    ** See Local Public Agencies section

Top

DESIGN

  1. Program Overview

    On the program level, the FHWA Ohio Division Office approves design standards for new construction, reconstruction, resurfacing, restoration, or rehabilitation of the Interstate System and other highways on the National Highway System (NHS) - excluding toll roads - within the State of Ohio. The FHWA provides guidance to ODOT and other public agencies on the implementation of and conformance to federal laws, regulations, and policies pertaining to preliminary and detailed design activities. The FHWA also shares technical information and provides training opportunities to facilitate professional development of engineering staffs from both the public and private sectors. Jointly, ODOT and FHWA staffs conduct concentrated Quality Assurance Reviews (QAR) of specific elements of design produced at the project level.

    On a project level, FHWA's common goal with ODOT is to develop safe, cost-efficient designs that meet the appropriate standards. Through full oversight on a limited number of major projects, and in conformance with the thresholds and stipulations established in this Agreement, the Ohio Division Office formally reviews and approves various engineering-related submissions, participates in project development decisions through routine review of design plans, and determines the eligibility of federal-aid participation in the cost for items of work.

    Design activities conducted during the Planning and NEPA phases begin with a conceptual outlook and elevate in detail as the project advances. The technical information is used to compare and evaluate the feasibility of alternatives. As a project advances and a preferred alternative has been identified, design work is conducted in greater detail to more fully delineate the footprint of the improvement and more accurately verify and assess the impacts. Included in this effort, as necessary, the Ohio Division Office will process and formally evaluate proposed exceptions to minimum design criteria (Design Exceptions) and Interchange Justification/Modification Studies (IJS/IMS).

    During the detail design phase, FHWA's Transportation Engineers ensure the design parameters and environmental commitments imposed on projects through the NEPA decision remain satisfied. With support from technical specialists in the Division Office and other offices, FHWA provides technical guidance to resolve issues as they arise, and makes certain the various categories of Federal-aid funds are properly invested in eligible items of work. These efforts are accomplished through active participation in routine plan reviews and ongoing coordination with ODOT's project-level staff. The final design product is then ready for estimation and subsequent PS&E approval.

  2. Applicable Laws, Regulations, and Orders

    • Title 23 USC, Chapter 1, Subchapter I, Section 109 - Standards
    • 23 CFR 109 Limitation on Federal Participation
    • 23 CFR 172 Administration of Engineering and Design Related Service Contracts
    • 23 CFR 620 Engineering
    • 23 CFR 625 Design standards for highways
    • 23 CFR 627 Value engineering
    • 23 CFR 630 Preconstruction procedures
    • 23 CFR 636 Design-build contracting
    • 23 CFR 645 Utilities
    • 23 CFR 646 Railroads
    • 23 CFR 470 Highway Systems
    • 23 CFR 650 Bridges, structures, and hydraulics
    • 23 CFR 652 Pedestrian and bicycle accommodations and projects
    • 23 CFR 655 Traffic Operations (MUTCD)
    • 23 CFR 658 Truck Size and Weight, Route Designations - Length, Width, and Weight Limitations
    • 23 CFR 710 Right-of Way and Real Estate
    • 23 CFR 752 Landscape and Roadside Development
    • 28 CFR 35 Nondiscrimination on the Basis of Disability in State and Local Government Services
    • 28 CFR 36 Nondiscrimination on the Basis of Disability by Public Accommodations and in Commercial Facilities
    • 49 CFR 27 Nondiscrimination on the Basis of Disability in Programs or Activities Receiving Federal Financial Assistance
    • 49 CFR 37 Transportation Services for Individuals with Disabilities (Americans with Disabilities Act)

  3. Program Approval Actions

    • ODOT Standard Drawings are reviewed and approved by FHWA on a program basis.
    • ODOT Standard Specifications for Road and Bridge Construction are reviewed and approved on a program basis.
    • FHWA accepts ODOT's consultant selection procedures, which are frequently applied in the design area.

  4. Project Approval Actions

    • FHWA will review and approve all FHWA Oversight projects and mutually agreed upon projects, final plans, estimates, and special provisions. Various project approval actions applicable to design are included in the Project Activity Approval Chart below.

  5. Monitoring
    • FHWA will monitor project design through step-by-step involvement in projects subject to FHWA Oversight. Please refer to the Project Activity Approval Chart below for specific FHWA activities.
    • For Federal-aid projects not subject to FHWA oversight, Design Exceptions will be monitored and reviewed on a periodic basis.

  6. Performance Indicators

    1. Monitor number of projects delivered based on the locked program.
    2. Monitor plan quality.

  7. Business Standards

    • FHWA will review and approve Design Exceptions within two weeks of receipt.
    • FHWA Division Office will review and approve Interchange Justification/Modification Studies within 30 days of receipt for those actions not requiring FHWA Headquarters approval. Additional time will be needed for those requiring FHWA Headquarters approval.
    • FHWA will review and approve Plans, Specifications, & Estimates (PS&E) within two weeks of receipt.
    • FHWA will provide written comments to ODOT on proposed changes to the Location & Design Manuals within 30 days of the request.

    ODOT and FHWA will share respective delivery and response time data, as well as other relevant information on a quarterly basis.

  8. Approved Procedures/Agreements/Manuals

    • ODOT Location & Design Manuals
    • ODOT Geotechnical Engineering Policy
    • ODOT Geotechnical Engineering Standard Procedure
    • ODOT Manual for Abandoned Underground Mines
    • ODOT Manual of Procedures for Earthwork Construction
    • Programmatic Agreement for Utility Agreements (ODOT/FHWA)
    • ODOT Utilities Manual
    • Ohio MUTCD
    • ODOT Right-of-Way Operations Manual
    • ODOT LPA Manual
    • ODOT Construction and Material Specifications
    • Federal-Aid Policy Guide

    PROJECT ACTIVITY APPROVAL CHART

    PROJECT ACTIVITIES
    AGENCY RESPONSIBLE

    Approval Action or Responsibility

    Reference Document

    FHWA Oversight: I-4R≥$5 m; I-3R≥$10m; Non-Interstate NHS≥$10m; ADHS Projects

    ODOT Oversight: I-4R<$5m; I-3R<$10m; Non-Interstate NHS<$10m

    ODOT Oversight: All Non-NHS Projects

    Other Projects Subject to FHWA Oversight by Mutual Agreement

    Limitation on Federal Participation

    23 CFR 1.9

    FHWA

    FHWA

    FHWA

    FHWA

    Design standards, policies and standard specifications, for applications to geometric and structural design

    23 CFR 625

    FHWA

    FHWA

    ODOT

    ODOT

    New or Modified Access to the Interstate System

    23 USC 111; Fed Reg February 11, 1998

    FHWA

    FHWA

    FHWA

    FHWA

    Design exceptions

    23 CFR 625.3(f)

    FHWA

    ODOT **

    ODOT ****

    ODOT ****

    Value engineering

    23 CFR 627.5

    FHWA

    ODOT

    ODOT

    FHWA & ODOT

    Monitoring federal-aid highway design projects

    23 CFR 630.106 & 112

    FHWA

    FHWA & ODOT

    FHWA & ODOT

    FHWA & ODOT

    PS&E review and approval / project authorization

    23 CFR 630.205

    FHWA

    ODOT ***

    ODOT ***

    FHWA

    Maintenance of Traffic Plans

    23 CFR 630.1002

    FHWA

    ODOT

    ODOT

    FHWA & ODOT

    Traffic Control (MUTCD)

    23 CFR 655

    FHWA

    ODOT

    ODOT

    FHWA

    Federal-aid Highway Systems

    23 CFR 470

    FHWA

    FHWA

    NA

    NA

    R/W Acquisition and Access

    23 CFR 710

    FHWA

    ODOT

    ODOT

    FHWA & ODOT

    Design-Build

    23 CFR 636 SEP-14

    FHWA

    ODOT

    ODOT

    FHWA

    Utilities

    23 CFR 645.113

    FHWA

    ODOT *

    ODOT

    ODOT

    Hydraulics design, erosion, and sediment control design

    23 CFR 650.115 23 CFR 650.211

    FHWA

    ODOT

    ODOT

    FHWA & ODOT

    Pedestrian and bicycle accommodations and design

    23 CFR 652.13

    FHWA

    ODOT

    ODOT

    FHWA & ODOT

    ADA criteria and design

    23 CFR 652 28 CFR 35 & 36 49 CFR 27 & 37

    FHWA

    FHWA & ODOT

    FHWA & ODOT

    FHWA & ODOT

    * Except on Interstate, where FHWA approval is required.
    ** Except Federal-aid Projects on the Interstate System.
    *** FHWA provides the final authorization electronically through FMIS.
    **** Except for deficiencies associated with the Interstate System.

    Major Projects - Project Management Plans

    Work Activity
    ODOT Action
    FHWA Action
    Major Projects (total
    cost≥$500 million) -
    Project Management Plans
    Prepare Project Management
    Plans (PMP) in accordance with
    SAFETEA-LU and FHWA-HQ
    Project Management Plan
    Guidance. PMPs must be
    completed and approved prior
    to issuing ROD or FONSI and
    prior to issuing request for
    authorization of Federal-aid
    funds for right-of-way
    acquisition or construction.
    Review and
    approve

Top

EMERGENCY RELIEF

  1. Program Overview

    Emergency Relief (ER) is a special program that uses non-formula funds for the repair or reconstruction of Federal-aid highways that have suffered serious damage as a result of (1) natural disasters or (2) catastrophic failures from an external cause. This program supplements the commitment of resources by States, their political subdivisions, or other Federal agencies to help pay for unusually high expenses resulting from extraordinary conditions.

    ER funds are not intended to cover all damage repair costs nor interim emergency repair costs that will necessarily restore the facility to predisaster conditions. Disasters must be of such magnitude as to be considered extraordinary to be considered for ER funding. To be considered extraordinary, the estimated Federal portion of the damage must meet a threshold of $700,000. Individual sites must have estimated repairs in excess of $5,000 in total cost to be eligible.

  2. Applicable Laws, Regulations, and Orders

    • Title 23, Section 125
    • 23 CFR 668

  3. Program Approval Actions

    • The ODOT must specifically request assistance under the ER program for each natural disaster or catastrophic event. This should be initiated with a letter of intent to seek ER funds as soon as it is evident that there is eligible damage. (See the FHWA ER Manual for sequence of events.)
    • FHWA will respond to written requests for ER assistance with a letter of acknowledgement and brief instructions on how to proceed.
    • Following an ODOT/FHWA/Local Public Agency (if applicable) site-by-site inspection, ODOT and FHWA will jointly prepare a Damage Survey Report to support the request for ER funding. The ODOT will then forward the report formally to FHWA with the request for ER funding.
    • FHWA will respond to the report with a determination of ER eligibility. The list of sites outlined in the report constitutes the program of projects required prior to authorization of permanent repairs.

  4. Project Approval Actions

    • FHWA's Acknowledgement Letter will establish a date of eligibility for those emergency repairs and protective measures that must be undertaken immediately. This type of work is categorically excluded from NEPA by definition. Contracts to do this type of emergency repair may be accomplished with abbreviated procedures; however, this permission will be indicated on the completed Damage Survey Report for each site.
    • FHWA's Determination of Eligibility letter will inform the ODOT of the projects which are to be considered full involvement by FHWA and which projects are to be state administered. Because of the nature of the ER program, thresholds and criteria used normally to determine federal oversight may not be applicable for a particular disaster or damaged site.
    • For ER projects requiring federal oversight, normal Federalaid procedures and requirements will apply.
    • All ER projects that do not fall into the category of emergency repairs required to protect the facility from further damage or keep the route open for the safe flow of traffic, require environmental approval per the established programmatic agreements between FHWA and ODOT.
    • FHWA will provide waivers of Federal-aid requirements on ER Projects when requested by ODOT on a project-by- project basis, if warranted by conditions and/or work characteristics.

  5. Monitoring

    • FHWA will jointly inspect with ODOT (and LPAs where applicable), the damaged sites during the development of the disaster estimate. Depending on the extent of damage, FHWA may elect to perform a sampling of site inspections.
    • FHWA will conduct final inspections of all ER projects requiring federal oversight.
    • FHWA will conduct final inspection of additional ER projects using a sampling method.

  6. Performance Indicators

    1. Track cost of ER projects from Damage Survey Report (DSR) to final completion.

  7. Business Standards

    • FHWA will respond to an ODOT Letter of Intent to seek ER funds within 3 working days with an Acknowledgement Letter.
    • The ODOT and FHWA will complete a reasonable survey of the damage and a Damage Survey Report within 4 to 8 weeks of the event. This may vary depending on the area of impact of the disaster.
    • FHWA will respond to ODOT requests for ER disaster eligibility supported by the Damage Survey Report within 2 weeks with a Determination of Eligibility.

  8. Approved Procedures/Agreements/Manuals

    • FHWA Emergency Relief Manual

    Top

    ENVIRONMENT

    1. Program Overview

      For projects using Federal Highway Trust Funds, the FHWA is the lead federal agency in integrating the full range of environmental requirements under a single, unified process that results in effective and sound transportation decisions.

      The FHWA Ohio Division Office has delegated approval authority to ODOT for Level 1, 2, and 3 categorical exclusions, programmatic Section 4(f) evaluations for projects being processed with a Level 1, 2, and 3 categorical exclusion and for Section 106. These delegations are described in the Programmatic Categorical Exclusion Agreement between FHWA and the ODOT (3/6/03), the Programmatic Agreement for Applicability Determination and Programmatic Section 4(f) Between FHWA and the ODOT (10/10/01) and the Section 106 Programmatic (7/17/06). FHWA retains its stewardship and oversight responsibility for these projects through biennial quality improvement reviews.

      The Ohio Division retains approval authority Environmental Impact (EIS) Statement-Record of Decision (ROD), Environmental Assessment (EA)-Finding of No Significant Impact (FONSI), level 4 categorical exclusion (CE) decisions, Section 4(f) evaluations (programmatic and individual) for projects being processed with a Level 4 categorical exclusion, EA or EIS. An EIS is applicable to projects that significantly affect the environment. An EA is applicable to projects where the significance of the environmental impact is not clearly established. A CE is applicable to projects that do not have a significant environmental effect (excluded from the requirement to prepare an EIS or an EA).

    2. Applicable Laws, Regulations, and Orders

      • Title 1, Clean Air Act Amendments of 1990
      • Section 404 of the Clean Water Act
      • Section 7 of the Endangered Species Act
      • 42 USC 4321-4347, National Environmental Policy Act as amended (P.L. 91-190) (P.L. 94-83?
      • 49 USC 303 and 23 USC 138, Section 4(f)
      • 16 USC 4601 Land & Water Conservation Fund Act, Section 6(f)
      • 23 USC 109(h), FHWA Environmental Guidelines
      • 23 USC 128 and 23 CFR 140, Public Hearings/Public Involvement
      • 23 CFR 771, 772, and 777, FHWA Environmental Regulations
      • 36 CFR 800 Section 106 of the National Historic Preservation Act
      • 40 CFR 1500, Council on Environmental Quality
      • Executive Order 11514, Protection and Enhancement of
      • Environmental Quality, as amended by Executive Order 11991
      • Executive Order 11990, Protection of Wetlands
      • SAFETEA-LU Sections 6001, 6002, 6007, & 6009, and implementing guidance and regulations

    3. Program Approval Actions

      • ODOT has been delegated programmatic approval authority for specific categorical exclusions.
      • ODOT has been delegated programmatic approval authority for specific Section 4(f) evaluations.
      • ODOT has been delegated programmatic approval authority for Section 106 determinations and specific consultation actions.
      • ODOT also acts as FHWA's non-federal representative for informal Section 7 ESA consultation.
      • ODOT public involvement procedures have been approved by FHWA (November 2002).

    4. Project Approval Actions

      • As early as practicable in a project's development, the ODOT and FHWA will collaborate on the proper environmental (NEPA) classification for a project: Class I = EIS, Class II = CE, Class III = EA.
      • For all projects that require an action be taken by FHWA, FHWA and ODOT will work together in the project preengineering phase to ensure compliance with NEPA and other applicable laws before an alternative is selected. The level of involvement is commensurate with the level of environmental impacts or project complexity.
      • FHWA will review and approve Level 4 Categorical Exclusions and associated Programmatic Section 4(f) Evaluations, EAs, EISs, Section 4(f) Individual Evaluations, net benefit Section 4(f) evaluations, and Section 4(f) de minimis determinations which are prepared by ODOT.
      • FHWA is also an active member of individual project teams and helps guide the project planning.
      • All documents requiring legal sufficiency review (Final EIS and Final Section 4(f) Evaluations) are sent to the Office of Chief Counsel in Olympia Fields, IL by the Division Office prior to approving these documents. The goal is to provide legal sufficiency review comments to the Division Office within 30 days after receipt of the document. Environmental re-evaluations are conducted through informal consultation and formal written documentation, when appropriate.

    5. Monitoring

      • The FHWA will monitor compliance with environmental requirements through project-by-project approval actions, biennial quality assurance reviews of the ODOT district offices, and biennial quality improvement reviews of the ODOT Office of Environmental Services. Additional monitoring may be done on a program-wide basis using process reviews.

    6. Performance Indicators

      1. Track % of NEPA documents completed on schedule.
      2. Track % of EAs and EIS' completed on schedule.

    7. Business Standards

      Work Activity
      ODOT Action
      FHWA Action
      Result

      Level 1, 2, or 3 Categorical Exclusion (CE)

      Prepare and Approve

      Periodic Audit

      Approved CE

      Level 4 CE

      Prepare, approve and submit to FHWA for approval

      Approve CE (30 days)

      Approved CE or instructions for revision

      Draft Environmental Assessment (EA)

      Prepare and submit to FHWA for comment

      Review and Comment (30 days)

      Comments

      EA

      Prepare, approve and submit to FHWA for approval

      Approve EA for circulation or return for revision (15 days)

      Approved EA or instructionsfor revision


      Work Activity
      ODOT Action
      FHWA Action
      Result

      Finding of No Significant Impact (FONSI)

      Prepare FONSI request and submit to FHWA

      Prepare and Issue FONSI or notify ODOT of need for EIS (30 days)

      FONSI or consider NOI

      Notice of Intent (NOI)

      Prepare Draft Notice of Intent and forward to FHWA

      Review and revise NOI and publish in the Federal Register (15 days)

      Published NOI in the Federal Register

      Cooperating and Participating Agency Request Letters

      Prepare and distribute request letters to State and Local agencies

      Prepare and distribute request letters to Federal agencies (15 days)

      Cooperating & Participating Agencies identified

      Preliminary Draft Environmental Impact Statement (DEIS)

      Prepare and submit to FHWA for review

      Review and comment (30 days)

      Written comments

      DEIS

      Prepare, approve, and submit to FHWA for approval

      Approve DEIS or return for revision (30 days)

      DEIS or instructions for revision

      Draft Final Environmental Impact Statement (FEIS)

      Prepare and submit to FHWA for review

      Review and comment (30 days)

      Written Comments

      FEIS Legal Sufficiency

      Prepare and submit to FHWA for review

      Request Legal Sufficiency review (15 days)

      FEIS Legal Sufficiency

      FEIS

      Prepare, approve, and submit to FHWA for approval

      Approve FEIS or return for revision (15 days)

      FEIS or instructions for revision

      Record of Decision (ROD)

      Prepare a Draft ROD and submit to FHWA

      Review, Revise, and Issue ROD
      (30 days)

      ROD

      Major Projects (total cost≥$500 million) – Project Management Plans

      Prepare Project Management Plans (PMP) in accordance with SAFETEA-LU and FHWA-HQ Project Management Plan Guidance. PMPs must be completed and approved prior to issuing ROD or FONSI and prior to issuing request for authorization of Federal-aid funds for right-of-way acquisition or construction.

      Review and approve

      Approved PMP

      Programmatic Section 4(f) Evaluation with Level 1, 2,or 3 CE

      Prepare and approve,submit to FHWA for opportunity to object

      No action required. Division can object to ODOT's approval within 15 days

      Approved Section 4(f) evaluation


      Work Activity
      ODOT Action
      FHWA Action
      Result

      Draft Programmatic Section 4(f) Evaluation with Level 4 CE

      Prepare and submit for FHWA approval

      Approve ProgrammaticSection 4(f) Evaluation or return for revision
      (15 days)

      Approved
      Section 4(f) Evaluation or instructions for revision

      Draft Individual Section 4(f) Evaluation

      Prepare and submit to FHWA for review

      Review and comment (30 days)

      Comments

      Section 4(f) Legal Sufficiency

      Prepare and submit to FHWA for review

      Request Legal Sufficiency review (30 days)

      Section 4(f) Legal Sufficiency

      Final Section 4(f) Evaluation

      Prepare and submit for FHWA approval; acquire SHPO concurrence

      Review and approve or return for revision (15 days)

      Final Section 4(f) Evaluation or instructionsfor revision

      Section 106 Adverse Effect Determination

      Make determination and forward to the Advisory Council on Historic Preservation

      No action required.

      Adverse EffectDetermination

      Section 106 Memorandumof Agreement (MOA)

      Negotiate MOA with SHPO and consulting parties. If ACHP requests participation, FHWA and ACHP will be signatories to MOA.

      No action required, except when ACHP is a party to MOA.

      Executed Section 106 MOA or instructions for revision

      Draft written
      Re-evaluation

      Prepare and submit to FHWA for review

      Review and comment (30 days)

      Comments

      Written Re-evaluation

      Prepare and submit to FHWA for approval

      Approve Re-evaluation or return for revision
      (15 days)

      Re-evaluationor instructionsfor revision



      ODOT and FHWA will share respective delivery and response time data, as well as other relevant information on a quarterly basis.

    8. Approved Procedures/Agreements/Manuals

      • ODOT Project Development Process Manual
      • ODOT Location and Design Manual
      • ODOT Planning and Environmental Process Manual
      • ODOT Public Involvement Guide
      • ODOT Ecological Manual
      • ODOT Permit Manual
      • ODOT Cultural Resources Manual
      • Programmatic Categorical Exclusion Agreement between FHWA and ODOT (3/6/03)
      • Programmatic Agreement for Applicability Determination and Programmatic Section 4(f) Between FHWA and ODOT (10/10/01)
      • Programmatic Section 106 Agreement between FHWA, ACHP, SHPO, and ODOT (7/17/06)

      Top

      FINANCIAL MANAGEMENT

      1. Program Overview

        On August 10, 2005, the President signed into law the Safe, Accountable, Flexible, Efficient Transportation Equity Act: A Legacy for Users (SAFETEALU) and represents the largest surface transportation investment in our Nation's history. SAFETEA-LU builds on ISTEA and TEA-21 supplying the funds and refining the programmatic framework for investments needed to maintain and grow our nation's vital transportation infrastructure.

        SAFETEA-LU also provides greater emphasis on financial integrity, project delivery, and major project oversight. Annual reviews are required of State DOT financial management systems, minimum standards for estimating project costs are to be developed, and annual reviews of State project delivery systems are to be conducted. All major projects exceeding $100 million in total cost are required to have finance plans. These new provisions are designed to strengthen the oversight of projects and increase the accountability of the State in the project delivery process. Additionally, SAFETEA-LU affords the ODOT new financing options and greater fund transfer flexibility.

        ODOT recognizes that sound federal financial management stewardship and oversight encompasses the entire Federal-aid program from the authorization to proceed with preliminary engineering though construction and debt retirement. Further, that the correctness and propriety of all Federal-aid claims are its primary responsibility whether the primary cost document originates within ODOT or with some third party. This responsibility is fulfilled by ODOT maintaining adequate and tested financial and operating policies and procedures and a sound accounting system with proper internal controls together with suitable audit activities.

        FHWA is responsible for overall program oversight and ensuring compliance with Federal requirements in the delivery of the Federal aid highway program to protect the public investment and ensure accountability in Federal-aid expenditures. FHWA's responsibility is implemented through this agreement and oversight/stewardship activities performed by the FHWA Ohio Division.

        In addition, FHWA recognizes a need for complete understanding of all pertinent financial and operating policies and procedures of ODOT. It is FHWA's responsibility to provide technical assistance and advice in funding and financial areas in a timely manner to meet the processing needs of ODOT.

        The culmination of ODOT's and FHWA Financial Management Stewardship and Oversight is the annual Federal Managers' Financial Integrity Act (FMFIA) certification, completed by FHWA OH Division, of internal and financial controls to substantiate the financial statements.

      2. Applicable Laws, Regulations and Orders

        The Federal-aid highway program is a State administered, Federal assisted program. Federal-aid highway funds are authorized by Congress to assist the States in providing for construction, reconstruction, and improvement of highways and bridges on eligible Federal-aid highway routes and for other special purpose programs and projects. Below is a list of applicable laws, regulations, and policies used in implementing the Federal-aid program:

        • 23 USC
        • 23 CFR
        • 49 USC
        • 49 CFR
        • 48 CFR
        • Safe, Accountable, Flexible, Efficient Transportation Equity Act: A Legacy for Users (SAFETEA-LU)
        • Transportation Equity Act for the 21st Century
        • Chief Financial Officer Act of 1990
        • Federal Managers' Financial Integrity Act of 1992
        • Cash Management Improvement Act of 1990
        • OMB Circular A-87 (Cost Principles for State, Local and Indian Tribal Governments)
        • OMB Circular A-102 (Grants and Cooperative Agreements with State and Local Governments)
        • OMB Circular A-123 (Management Accountability and Control)
        • OMB Circular A-127 (Financial Management Systems)
        • OMB Circular A-133 (Audits of States, Local Governments, and Non- Profit Organizations)
        • Financial Integrity Review and Evaluation (FIRE) Program Order and Toolkit
        • FHWA SAFETEA-LU Implementing Guidance Memorandums

      3. Program Approval Actions

        • FHWA will approve the accounting process used to develop the payroll additive rates and indirect cost rates.
        • FHWA will approve the resolution of OIG and State audit findings
        • FHWA will approve the Federal-aid Current Billing

      4. Project Approval Actions

        • FHWA will approve final vouchers, project agreements, and modified project agreements on all projects.
        • FHWA will approve finance plans for major projects exceeding $500 million in total project costs.

      5. Monitoring

        FHWA will monitor all financial management and accounting activities through process reviews, improper payment reviews, inactive Federal-aid projects reviews, and Federal-aid billing reviews, as prescribed by the FHWA Financial Integrity Review and Evaluation (FIRE) program. FHWA will conduct verification activities to assure that the laws, regulations, policies and agreements are followed by ODOT in carrying out the assumed responsibilities.

        Reviews will encompass both ODOT and Local Agencies. Through periodic contact with ODOT personnel, FHWA will provide guidance and technical assistance in such areas as project finance plan preparation, fiscal document processing, cost eligibility determinations, financial management and reimbursement.

        FHWA will, to the maximum extent possible, utilize the work of ODOT and State auditors to limit the scope of FHWA reviews. Risk assessment techniques will be used where appropriate to determine areas for review. Additionally, FHWA will promote best practices in financial management and project funds management to improve the efficiency in the administration of the Federal-aid program. FHWA will also promote the use of innovative finance techniques that are effective in leveraging funds, reducing project costs, or expediting project completion.

      6. Performance Indicators

        1. Reduce unexpended obligations on inactive projects, where appropriate.
        2. No lapsing funds in Federal Fiscal Year.

        Business Standards

        WORK ACTIVITY
        ODOT ACTION
        FHWA ACTION
        REMARKS

        Rapid Approval State Payments System (RASPS) Billing

        Submits electronically as often as desired

        Act upon within the established deadline.

        Source documentation will be randomlysampled and reviewed by FHWA

        Federal-aid Billing Review

        Responds to requests for information and documentation tovalidate Federal-aid billing transactions from FHWA within 5 working days

        Provide a listing of transactions being reviewed. Upon completion of review provide ODOT with results of Federal-aid Billing Review.

        Results of review used to support annual FMFIA certification.

        SIB Annual Report Prepare annually within
        90 days from the end
        of the Federal FY
        Review the report and
        take appropriate action.
         

        Major Projects (total cost≥$500 million) - Financial Plans

        Prepare financial plans in accordance with SAFETEA-LU and FHWA-HQ Project Financial Plan Requirements Guidance Memorandum.Financial plan must be completed and approved prior to request for authorization of
        Federal-aid funds for construction

        Review and approve, as appropriate.

        Some Financial Plans in this category will require FHWA-HQ approval.

        Other Projects (total
        cost between $100
        million & $500 million)
        - Financial Plans
        Prepare financial plans
        in accordance with
        SAFETEA-LU and
        FHWA-HQ Project
        Financial Plan
        Requirements Guidance
        Memorandum.
        Financial plan are to be
        completed prior to
        request for
        authorization of
        Federal-aid funds for
        construction
        Review financial plans
        as part of
        stewardship and
        oversight responsibility
         

        Project Funds Management

        Review quarterly a designated list of inactive projects and submit to FHWA by last day of the month following the end of the quarter certification that the obligations are: (1) proper and valid; (2) the funds are

        Review and take appropriate action to provide reasonable assurance that the obligation amount is valid. Follow-up to ensure unneeded fundsare de-obligated promptly.

        Results of review used to support annual FMFIA certification.

          being used effectively; and, (3) unused funds are properly safeguarded and/or de-obligated to minimize misuse.    
        Funds TransferRequests Prepare and submit Funds TransferRequests Review and take appropriate action within 5 working days Endorsed Funds Transfer Requests are submitted to FHWA-HQ for further processing.
        ODOT Single Audit Ensure audit is completed as required and copies of audit reports are submitted Review and take action to ensure findings are resolved Results of review used to support annual FMFIA certification.
        ODOT Sub-Recipient/ Single Audits Review and take action to ensure findings are resolved, submit summary listing to FHWA Review and take action to ensure compliance  
        Final Vouchers/Final
        Acceptance
        Prepare and submit See Contract
        Administration Section
         
        Monthly Status of Funds, i.e. Advance Construction, etc. Prepare and submit Review and monitor
        provide appropriate
        feedback to ODOT.
         
        Year End Document for
        Utilization of Federalaid
        Funds
        Prepare and submit by September 15th Review and act upon within 5 working days Documents that require processing must be submitted to ODOT Planning by
        September 1
        Consultant Audits Annually conduct audits & submit listing of audits completed Review listing. Sample
        periodically to ensure
        compliance.
         



      7. Approved Procedures/Agreements/Manuals

        • ODOT Funds Management Allocation Manual
        • Transportation Review Advisory Council (TRAC) Policies and Procedures
        • ODOT Capital Programs Business Rules
        • ODOT Procedure for Construction Budget Estimating
        • ODOT Toll Revenue Credits Policy and Procedures
        • ODOT Federal Highway Funding Policy
        • ODOT Infrastructure Capitalization Policy
        • ODOT Cost Accounting Policy
        • ODOT State Highway Capital Improvement Bond and Grant Anticipation Revenue Vehicles (GARVEE) Bond Policy
        • ODOT Auditing Policy
        • Infrastructure Capitalization Procedure

        Top

        INTELLIGENT TRANSPORTATION SYSTEMS

        1. Program Overview

          ODOT works cooperatively with FHWA in development and implementation of Intelligent Transportation Systems (ITS) initiatives in Ohio. ODOT has established a multi-disciplinary ITS Core Team, of which FHWA is a member, to provide a technical screening and ITS oversight function.

          ODOT and FHWA work cooperatively with the Metropolitan Planning Organizations (MPOs) of the metropolitan areas of Akron/Canton, Cincinnati, Cleveland, Columbus, Dayton/Springfield, Toledo, and Youngstown, to promote ITS planning, regional architecture use, and adoption and integration of ITS at the local level. The seven metropolitan areas each have a regional ITS architecture and are actively implementing planning studies related to ITS deployment. ODOT and FHWA will work cooperatively to assure that ITS projects are consistent with the National ITS Architecture, incorporate ITS Standards and are fully integrated.

          A primary ITS goal of ODOT is to ensure that transportation facilities operate efficiently and that no opportunities to provide integrated ITS features are overlooked during reconstruction.

          ODOT and FHWA have formed partnerships in support of safety and congestion relief initiatives with other State and local agencies, including fire and law enforcement.

        2. Applicable Laws, Regulations, and Procedures

          • 23 USC Chapter 1
          • SAFETEA-LU
            Title I Subtitle B section 1201, and
            Title V Subtitle C
          • TEA - 21 Title V Subtitle C
          • 23 CFR Part 940

        3. Program Approval Actions

          • Regional ITS architectures for each of the Transportation Management Areas (TMA) must be developed and maintained to document the ITS integration strategies and guide the development of specific projects and programs. FHWA will serve as a technical resource during the development and revisions of the regional architectures and will be furnished a copy of the adopted regional architectures and any amendments. It will be up to the owners of the regional architecture to decide whether they want to request FHWA concurrence or acknowledgement of the regional architecture.

        4. Project Approval Actions

          • All ITS projects (stand alone or ITS incorporated in other work) need to accommodate the interface requirements and information exchanges specified in the regional ITS architecture and there must be a commitment to the operations, management and maintenance of the overall system. ODOT will make a determination of conformity of ITS Projects with the regional ITS architecture. FHWA will concur in the determination of conformity with the regional ITS architecture consistent with the project level oversight described in this Agreement.
          • All ITS projects need to be developed based on a systems engineering analysis. ODOT will make a determination of conformity of ITS Projects with the systems engineering analysis requirement. FHWA will concur in the determination of conformity with the systems engineering analysis consistent with the project level oversight described in this Agreement.
          • All ITS projects need to use applicable ITS standards and interoperability tests that have been officially adopted, by rulemaking, by US DOT. ODOT will make a determination of conformity of ITS projects with the ITS standards requirement. FHWA will concur in the determination of conformity with the ITS standards requirement consistent with project level oversight described in this Agreement.
          • Congressionally Designated Projects (i.e. ITS Integration Program) are normally non-construction projects and will be advanced/approved on a case-by-case basis. Typically, the projects are designated by earmark in appropriations acts with specific implementation processes issued by FHWA Washington Headquarters for each appropriation cycle.


        5. Monitoring

          • FHWA will review project development and review and approved PS&Es for major ITS projects and other projects selected for FHWA oversight.
          • FHWA will provide ongoing technical assistance on the use of regional ITS architectures, systems engineering analysis, and ITS standards, include these areas in routine risk assessment evaluations, and work cooperatively with ODOT to use process review techniques to assess and improve processes and procedures.
          • FHWA will participate in project steering committees or other ongoing oversight processes for all major ITS projects and congressionally designated ITS projects.


        6. Business Standards

          • ODOT will provide FHWA with copies of ITS regional architectures or amendments within 30 days of adoption. If the owners of the regional architectures choose to have FHWA concur in the Architecture, FHWA will be allowed 3 weeks, from receipt date, to review and act on the document.
          • FHWA will follow prescribed processing requirements for individual project actions related to regional architecture conformity, systems engineering analysis completion, and standards conformity as defined in this partnership agreement.
          • FHWA will follow prescribed processing requirements for ITS "Earmark" projects as defined in Washington Headquarters instructions issued with each appropriations cycle.


        7. Approved Procedures/Agreements/Manuals

          • Ohio Procedures for Implementing ITS Regulations (23 CFR 940) - under development
          • Regional ITS Architectures for the metropolitan areas of Akron/Canton, Cincinnati, Cleveland, Columbus, Dayton/Springfield, Toledo, and Youngstown
          • Regional ITS Architecture Guidance (FHWA/FTA)


          PROJECT ACTIVITY APPROVAL CHART - ITS Infrastructure Projects

          ODOT assumes the FHWA responsibility for all reviews and approvals for design, construction and final inspection of all ITS projects that are not major ITS projects. This applies to all ITS projects on NHS and on non-NHS facilities. FHWA will retain full Federal oversight for major ITS projects, unless it is determined during project-by-project consultation and mutual agreement by FHWA and ODOT that ODOT assumes FHWA responsibility.

          Definitions:

          1. ITS Project
            An ITS project is one that funds the acquisition of technologies or systems of technologies that significantly contribute to the provision of one or more ITS user services as defined in the National ITS Architecture.
          2. Major ITS Project
            Major ITS project means any ITS project that implements part of a regional ITS initiative that is multi-jurisdictional, multi-modal, or otherwise affects regional integration of ITS systems.
          3. Minor ITS Project
            A minor ITS project means any ITS project that is not a major ITS project as defined above.


          PROJECT ACTIVITIES
          AGENCY RESPONSIBLE

          Approval Action

          Reference Document

          Major ITS Projects

          Minor ITS Projects

          Other Projects by Mutual Agreement

          Regional Architecture Conformity Determination

          23 CFR 940.11

          FHWA

          ODOT

          FHWA

          Systems Engineering AnalysisDetermination

          23 CFR 940.11

          FHWA

          ODOT

          FHWA

          ITS Standards Determination

          23 CFR 940.11

          FHWA

          ODOT

          FHWA

          Special instructions for ITS Projects:

          "ITS projects" can be stand-alone construction projects or may be larger projects that include ITS features. The above listed approval actions apply whether the ITS project is advanced on either a stand-alone or included basis. All other stewardship and oversight functions such as environmental determination, right of way clearance, etc. are project size, system and work type dependent with no other special processing requirements for ITS purposes beyond routine stewardship and oversight

          PROJECT ACTIVITY APPROVAL CHART - ITS Integration and Deployment Projects (Earmark Projects)

          PROJECT ACTIVITIES
          AGENCY RESPONSIBLE

          Approval Action

          Reference Document

          Major ITS Projects

          Minor ITS Projects

          Other Projects by Mutual Agreement

          Case-by-case determination

          Instructions issued annually by Headquarters

          FHWA and ODOT

          FHWA and ODOT

          FHWA and ODOT

        Top

        LOCAL PUBLIC AGENCIES

        1. Program Overview

          The Ohio Department of Transportation (ODOT) is responsible for all requirements of the Federal-aid program, except non-Title 23 actions, as described in Section II of this Agreement. Since Title 23 U.S.C. does not recognize local entities as direct recipients of Federal-aid funds, ODOT is ultimately responsible and accountable for ensuring that Federal-aid requirements are met on all Local Public Agency (LPA) projects. Although the ODOT cannot delegate responsibility, activities can be delegated and the local entities held accountable to the ODOT. In those cases where activities are delegated to LPAs, the ODOT will review and take actions necessary to assure local compliance with all requirements of State and Federal laws, regulations, and policies. The FHWA will work in partnership with the ODOT on these review and assurance actions.

          1. Local Public Agencies

          ODOT is permitted to delegate certain activities, under its supervision, to LPAs under federal regulation 23 CFR 1.11 and 635.105. The Ohio Revised Code, Section 5501.03 (C) authorizes ODOT to act as agent and to accept federal funds on behalf of public agencies for transportation projects. Public agencies include political subdivisions, other state agencies, boards, commissions, and transit and port authorities. Nearly all transportation projects under the jurisdiction of local agencies are projects off the NHS, or eligible projects on non- Federal-aid public roads or facilities. FHWA project oversight for LPA projects will follow the guidance in Sections II and V of this Agreement.

          Non-NHS projects administered through ODOT will be designed, constructed, operated, and maintained in accordance with State laws, regulations, directives, safety standards, design standards, and construction standards as permitted under 23 USC 109(o), in lieu of NHS-based Title 23 U.S.C. requirements (23 USC 106). Title 23 U.S.C. requirements that are applicable to all Federal-aid projects include, but are not limited to, transportation planning, procurement of professional services, Davis-Bacon wage rates (as applicable), advertising for bids, use of convict-produced materials, Buy America Act provisions, and other requirements. All Federal-aid projects must comply with applicable non-Title 23 U.S.C. requirements, as described in Section II of this Agreement.

          By written agreement with the local agency, ODOT may delegate all or some project activities to local agencies, whether or not Federal-aid is used for the activity. Those activities include, but are not limited to:

          • Environmental studies
          • Procurement of consultant services
          • Design
          • Surveying
          • Right of Way acquisition
          • Work by railroads or utility companies
          • Preparation of plans, specifications and estimates
          • Preparation of bid proposal package
          • Advertisement for letting
          • Contracting
          • Contract administration
          • Inspection

          ODOT retains its responsibilities under Federal law and regulations for all delegated activities. ODOT will provide the necessary processes, approvals, oversight, and review to ensure that delegated projects receive adequate supervision and inspection, and that they are completed in conformance with approved plans and specifications and applicable federal requirements.

          The following activities will not be delegated to local agencies:

          • NEPA Review and Approval
          • Design Exception Approval
          • Right of Way Certification
          • DBE Goals and Waivers
          • Final Inspection and Acceptance
          • Sole Source and Proprietary Justification Approval
          • Labor Compliance Enforcement
          • Rejection of Bids
          • Project Cost Eligibility
          • Federal-aid Payments


        2. Applicable Laws, Regulations, and Orders

          • 23 U.S.C. 106(c)(2)
          • 23 U.S.C. 109(o)
          • 23 U.S.C. 112
          • 23 CFR 1.11
          • 23 CFR 635 (for NHS routes only)
          • ORC 5501.03(C)


        3. Program Approval Actions

          To the extent permitted in 23 U.S.C. Section 109(o), non-NHS projects administered by ODOT or LPAs will follow state laws, rules, and standards for state-aid funded projects, in lieu of Title 23 requirements. For LPAadministered projects, ODOT shall maintain a Local Program Administration manual that encompasses the requirements of local governments to utilize Federal-aid funds. FHWA will review and concur in any additions, modifications, or changes to such manual. ODOT administered projects will follow ODOT procedures.

        4. Project Approval Action

          ODOT shall assume the responsibility and represent FHWA in behalf of administering the Federal-aid system to local governments. The following is a list of some specific project related actions that shall be performed on projects that use Federal-aid; however, this list is not a comprehensive list and is subject to change due to Federal law, regulation, and policy modification.

          • Environmental clearance must be obtained from FHWA or acquired through ODOT prior to the final design or right-of-way actions.
          • Projects will be developed in accordance with ODOT LPA and Location &Design Manuals, the appropriate AASHTO publication, or other ODOT-approved standards. ODOT will ensure that there are LPA written design standards or otherwise the LPAs must use AASHTO standards.
          • ODOT shall review and approve design exceptions and sole source requests by local agencies.
          • ODOT shall review plans, specifications, and estimates of projects prior to construction authorization for compliance with applicable State and Federal law, regulation, and policy.
          • Procurement of consultant services, to be reimbursed with Federalaid, will be performed in accordance with ODOT procedures and State Statutes.
          • Project funding will be in accordance with Federal and State requirements.
          • Projects will be let in accordance with State Statutes.
          • ODOT shall concur on award of projects let and awarded by local agencies.
          • Projects will be constructed in accordance with the current edition of ODOT's Standard Specifications or written local specifications. ODOT will ensure that there are LPA written local specifications or otherwise the LPAs must use ODOT Standard Specifications. ODOT oversight of the construction of local projects includes but not limited to the review and approval of billings; review and approval of change orders, time extensions, and claims; and final project acceptance.
          • For FHWA Oversight projects, review and approval actions will be undertaken as described elsewhere in this Agreement.


        5. Monitoring

          • FHWA shall review and concur with the ODOT LPA Manual for the administration of the Federal-aid program to local agencies.
          • FHWA may request data at any time to support the administration of the Federal-aid program.
          • FHWA will periodically perform Quality Improvement Reviews (QIR) to improve the efficiency and accountability of the program.


        6. Business Standards

          FHWA will review and comment on revisions to the LPA Manual and Policy within 30 days.

          Project level approvals will follow agreed business standards described elsewhere in this Agreement.

          ODOT will involve FHWA in decisions involving special and unusual circumstances at the earliest reasonable time to ensure thorough and appropriate decisions are made collectively.

        7. Approved Procedures/Agreements/Manual

          • ODOT Locally Administered Transportation Projects Manual of Procedures
          • ODOT Location & Design Manuals
          • ODOT Standard Specifications for Construction and Materials
          • Ohio MUTCD
          • FHWA Contract Administration Manual


        Top

        MAINTENANCE AND PRESERVATION

        1. Program Overview

          Title 23 USC defines maintenance as, " ...the preservation of the entire highway, including surface, shoulders, roadsides, structures, and such trafficcontrol devices as are necessary for safe and efficient utilization of the highway." Title 23 further requires a State transportation department to maintain each project constructed with Federal-aid funds until such time that it no longer constitutes a part of the Federal-aid system. It is FHWA's role to see that maintenance of Federal-aid projects is adequate and to provide technical assistance in disseminating information on successful maintenance techniques.

          Routine maintenance is not eligible for Federal-aid. Preventive maintenance activities are eligible for Federal-aid provided ODOT demonstrates to FHWA's satisfaction that the activity is a cost-effective means of extending the useful life of a Federal-aid highway.

          This section of the Agreement pertains to maintenance activities and the management of maintenance activities that are required to be accomplished by the ODOT (or caused to be accomplished by the ODOT) to fulfill its obligation under Title 23 without Federal-aid reimbursement.

        2. Applicable Laws, Regulations, and Orders

          • 23 USC 101 (a) (14)
          • 23 USC 109 (o)
          • 23 USC 116 Maintenance
          • 23 CFR 1.27 Maintenance
          • 23 CFR 633.208 Maintenance (Appalachian Contracts)
          • MUTCD
          • ORC Titles: 1, 3, 7, 15, 27, 41, 45, 49, 55, 57, and 61


        3. Program Approval Actions

          There is no reporting or approval actions associated with maintenance activities or the management of maintenance activities that are required to be accomplished by the ODOT (or caused to be accomplished by ODOT). Preventive Maintenance eligibility determinations will be made by FHWA.

        4. Project Approval Actions

          FHWA approval is not required on a project level for maintenance activities unless special or unusual circumstances exist. The maintenance agreement, which is part of the project agreement, is a project level agreement in which ODOT agrees to maintain the constructed facility.

        5. Monitoring

          As a condition of receipt of Federal funds, ODOT is required to maintain or cause to be maintained the Federally funded roadways and associated appurtenances in the state of Ohio. FHWA will review road and bridge maintenance through a sampling of field observations, process reviews, program reviews, and Quality Improvement Reviews. Any specific instances of inadequate maintenance or concerns regarding ODOTs overall maintenance program will be brought to the attention of ODOT by FHWA.

          ODOT, in compliance with 23 USC, formally conveys its maintenance obligation to the Locals through the use of various agreements.

        6. Business Standards

          ODOT shall provide FHWA County Work Plan summary data upon request.

          FHWA shall notify ODOT of instances of inadequate maintenance or concerns of ODOT's overall maintenance program.

          ODOT shall advise the FHWA Maintenance Program Manager of any major updates or changes to the ODOT Maintenance Program.

        7. Approved Procedures/Agreements/Manuals

          Not Applicable

          MAINTENANCE ACTIVITIES

          AGENCY RESPONSIBLE FOR MAINTENANCE/MONITORING

          Interstate
          (outside of corporation limits)

          Interstate (inside ofcorporation limits)

          State Highways (outside of corporation limits)

          State highways (inside corporation limits)

          Local Highways (outside and inside of corporation limits)

          FHWA/ODOT

          FHWA/ODOT/Locals

          FHWA/ODOT

          FHWA/ODOT/Locals

          FHWA/ODOT/Locals

        Top

        PAVEMENT AND MATERIALS

        1. Program Overview

          Pavement: 23 CFR 626 requires that pavements be designed in accordance with current and predicted traffic needs in a safe, durable and cost effective manner. The regulations do not specify the procedures to be followed to meet this requirement. ODOT is expected to use a design procedure that is appropriate for their conditions.

          Materials: Subsection (a) of 23 U.S.C. 109 requires that the FHWA ensure that the plans and specifications for all proposed Federal-aid highway projects provide for facilities that will adequately serve the existing and planned future traffic in a manner that is conducive to safety, durability, and economy of maintenance. To fulfill this requirement for all Federal-aid highway projects, the FHWA OH Division prime objectives are to:

          • Maintain a close working relationship with ODOT materials and construction staff.
          • Promote improvements when new approaches or technologies are developed and where deficiencies are identified.
          • Ensure that the materials incorporated in the construction work and the construction operations controlled by sampling and testing are in conformity with the approved plans and specifications.


          Furthermore, the FHWA is required, by means of an approved quality assurance program, to assure the quality of materials incorporated into Federal-aid highway projects on the National Highway System (NHS). For Federal-aid projects on the NHS, the primary objectives are to:

          • Assure that the materials incorporated in the construction work, and the construction operations controlled by sampling and testing are in conformity with the approved plans and specifications.
          • Provide oversight of construction materials and compliance with Federal requirements on a statewide basis.
          • Assure adequate and qualified staff to maintain ODOT's quality assurance responsibility as part of its Quality Control/Quality Assurance (QC/QA) program.
          • Assure compliance with, and assist in, maintaining the ODOT Transportation Technician Qualification Program


        2. Applicable Laws, Regulations, and Orders

          • Title 23 USC, 106, 109, 114
          • 23 CFR 625.4 Standards, policies, and standard specifications
          • 23 CFR 626 Pavement Policy
          • 23 CFR 635 Construction and Maintenance
          • 23 CFR 637 Construction Inspection and Approval


        3. Program Approval Actions

          • The ODOT Construction and Material Specifications are approved by FHWA on a program basis to facilitate project approvals (typically on a 2-4 year cycle).
          • Supplemental Specifications are approved by FHWA on a program basis.
          • Each State must develop a quality assurance program that will assure that materials and workmanship incorporated into each Federal aid highway construction project on the NHS are in conformity with the requirements of the approved plans and specifications. The program must be approved by FHWA.


        4. Project Approval Actions

          • FHWA will approve changes in project specifications for materials on FHWA Oversight projects.
          • FHWA will approve Supplemental Specifications for specific FHWA Oversight projects.


        5. Monitoring

          • FHWA will monitor ODOT's Quality Assurance Program through construction inspections on FHWA Oversight projects, as well as process reviews.
          • FHWA will monitor the acceptance and testing of materials in accordance with ODOT's Construction and Material Specifications and the ODOT Sampling and Testing Manual on Federal-aid projects through construction inspections and process reviews.


        6. Performance Indicators

          1. Track % of pavement conditions acceptable - General system.
          2. Track % of pavement conditions acceptable - Priority System.
          3. Track % of pavement conditions acceptable - Urban System.


        7. Business Standards

          • FHWA will review and respond within 2 weeks to ODOT for Supplemental Specifications revisions and project materials specifications.
          • FHWA will review and respond within 30 days to ODOT for substantive changes in its Quality Assurance Program.
          • Time to review and approve a complete revision of the Standard Construction and Material Specifications will be negotiated prior to the activity.
          • See Quality Assurance Program Summary Table for more business standard details.


        8. Approved Procedures/Agreements/Manuals

          • ODOT Construction and Material Specifications
          • ODOT Sampling and Testing Manual
          • ODOT Pavement Design and Rehabilitation Manual
          • FHWA Contract Administration Manual

         

        ALL NHS - ALL NON-NHS
        Activity/Item

        ODOT Action

        FHWA Action

        ODOT Action

        FHWAAction

        Quality Assurance Program
        Materials test methods and updates, Field Sampling and Testing Manual

        Maintain
        (on going)

        Review and Act Upon
        (10 Working Days)

        ODOT prepares and approves

        No action

        Transportation Technician Qualification Program

        Develop and implement

        Review and Act Upon when updated (10Working Days)

        Required by ODOT

        No action

        Qualified LaboratoryProgram

        Develop and implement

        Review and Act Upon when updated (10Working Days)

        Required by ODOT

        No action

        AASHTO accreditation inspectionreports, use ofoutside testing facility

        Maintain accreditation, submit inspection report, approve outside testing facility

        Review, make recommendations for consideration (as necessary)

        Required by ODOT

        No action

        Ohio Construction and Material Specifications (Supplemental Issues)

        Maintain
        (on going)

        Review and Act Upon
        (10 Working Days)

        Required by ODOT

        No action

        Material or Product Selection: proprietary products, recycled materials, public interestfindings (23 CFR 635.411)

        Develop and prepare

        Review and approve onFHWA Oversight projects only

        Developand prepare

        No action

      Top

      PLANNING

      1. Program Overview

        1. Work Programs
          Title 23 CFR, Part 420, Planning and Research Program Administration contains the policies and procedures for administering activities and studies undertaken by States and Metropolitan Planning Organizations (MPO) funded through their respective Work Program or as separate projects not included in a Work Program.

          1. Statewide Planning and Research (SPR) Work Program

            ODOT prepares the Work Program annually. FHWA provides pre-program guidance, draft review comments, approves the Work Program, and authorizes SPR funds. FHWA monitors the work throughout the year using dayto- day involvement as appropriate. ODOT submits progress reports to FHWA.

          2. MPO's Unified Planning Work Program (UPWP)

            The UPWP is prepared annually by each MPO and reviewed by ODOT, FHWA and Federal Transit Administration (FTA). FHWA and FTA comments are provided to the MPO jointly with ODOT's, or may be provided individually through the MPO's Technical Advisory Committee review process. FHWA authorizes Urban Planning Funds upon joint FHWA/FTA approval of the UPWPs. These funds are traditionally referred to as "PL" funds. ODOT and FHWA monitor the Work Program through progress and annual reports and by participation in MPO meetings.

        2. Statewide Transportation Planning

          Title 23 CFR, Part 450, Subpart B, addresses the requirements of the statewide transportation planning process.

          1. Statewide Long Range Transportation Planning

            Ohio DOT develops a Statewide Long Range Transportation Plan which considers all modes of transportation. The Plan (Access Ohio) covers at least a 20-year planning horizon, considers the eight planning factors as outlined in the CFR, and provides an opportunity for public comment.

          2. Statewide Transportation Improvement Program (STIP)

            Ohio DOT develops a STIP containing all projects to be funded by FHWA and FTA for a four (4) year period. The STIP is updated biennially by Ohio DOT and submitted to FHWA and FTA for approval every year. Projects contained in the STIP must be consistent with the Statewide Transportation Plan and the MPO TIPs, and must include public involvement and provide interested parties a reasonable opportunity to comment on the proposed program. Along with the STIP, Ohio DOT will certify that the projects in the STIP are based on a planning process that meets the requirements of 23 U.S.C. 134 and 135, 49 U.S.C. 5303, and 23 CFR 450.

        3. Metropolitan Transportation Planning

          1. MPO Long Range Transportation Plan Title 23, CFR Part 450, Subpart C, addresses metropolitan planning requirements. Each MPO must update their Long Range Transportation Plan every 4 years for non-attainment and maintenance areas and every 5 years for attainment areas which: covers at least a 20-year planning horizon, includes long range and short range strategies which lead to an integrated Intermodal plan; includes a financial plan which compares estimated revenues with costs of construction, maintenance, capital purchases and operations; considers the eight planning factors; and provides opportunity for public comment.

          2. MPO Transportation Improvement Program (TIP) Each MPO, in cooperation with the State and its public transit operators will prepare and update a TIP each year covering at least four (4) years. The TIP shall include all projects requiring FHWA and FTA approval; include a priority list of projects to be carried out in the first four (4) years; identify each project or phase; and be financially constrained by year. The TIP development process must provide a reasonable opportunity for public comment. Highway and transit projects must be selected in accordance with the specific funding programs.

          3. Consolidated Planning Grant (CPG) In 1997, the ODOT agreed to be a CPG pilot state and continues to be the lead Agency for carrying out all State and metropolitan planning activities between Ohio and the MPOs.

            The CPG program allows ODOT and MPOs to develop annual Unified Planning Work Programs (UPWPs) that will address intermodal transportation needs. Since all Federal FHWA and FTA planning funds, , are pooled in the CPG, this process eliminates the need of keeping track of the different categories of federal planning funds as they are spent on various UPWP activities. The accounting and billing process is simplified; and ODOT, as a lead agency, draws down the necessary funds to cover the expenditures as substantiated by MPO invoices and ODOT reimbursement payments.

        4. Traffic Monitoring

          Title 23 CFR, Part 500 provides the regulatory guidance for the development and operation of a traffic monitoring system for highways including traffic counting, vehicle classification, and weigh-in-motion programs. The system is guided by the "AASHTO Guidelines for Traffic Data Programs," augmented by the FHWA "Traffic Monitoring Guide" and the "Highway Performance Monitoring System Field Manual."

        5. Highway Performance Monitoring System (HPMS)

          Title 23 CFR, Part 420 addresses the policy for states to provide data that support FHWA's responsibilities to the Congress and to the public. The "Highway Performance Monitoring System Field Manual" provides instructions for collecting and reporting quality and timely data in the condition and performance of the highways and streets.

        6. Highway Statistics Reports

          Title 23 CFR, Part 420 addresses the policy for states to provide data that supports FHWA's responsibilities to the Congress and to the public. The "Guide to Reporting Highway Statistics" manual provides instructions for complying and reporting: motor fuel consumption, motor fuel tax revenues, motor vehicle registrations and fees, driver licenses and fees, highway income and expenditures, debt service, and highway capital outlay and maintenance expenditures which traditionally is referred to as the "500 series reports."

        7. Certification of Public Road Mileage

          Title 23 CFR, Part 460 addresses the policies and procedures for identifying and reporting public road mileage for utilization in the statutory formula for the apportionment of Highway Safety funds under 23 U.S.C. 402(C). By June 1 of each year, the Governor or ODOT Director certifies the public road mileage in the state as of the end of the previous calendar year. In Ohio, the ODOT Director has been selected as the Governor's designee.

        8. Certification of Enforcement of Heavy Vehicle Use Tax

          Title 23 CFR, Part 659 prescribes requirements for states to follow in order to annually certify that proof of payment of the Federal Heavy Vehicle Use Tax is obtained before individuals can register their heavy trucks. By July 1 of each year, the Governor or ODPS Director certifies that Ohio is obtaining proof of payment of the Heavy Vehicle Use tax as a condition of registration. The 12 month certification period ends May 31. In Ohio, the ODPS Director has been selected as the Governor's designee.

      2. Applicable Laws, Regulations, and Procedures

        • Title 23 CFR, Part 420
        • Title 23 CFR, Part 450, Subpart B
        • Title 23 CFR Part 450, Subpart C
        • Title 23 CFR, Part 460
        • Title 23 CFR, Part 470
        • Title 23 CFR, Part 500
        • Title 23 CFR, Part 659


      3. Program Approval Actions

        FHWA approval is on an annual basis for all the programs listed above and where noted on the following chart. As a condition for receipt of federal funds, ODOT agrees to develop plans and work programs for statewide, metropolitan, and other transportation planning activities. FHWA will review these plans and programs to assure they meet applicable laws and regulations.

        Programs requiring oversight include:
        1. State and metropolitan planning sub-programs under the State Planning and Research Program.
        2. Statewide transportation planning process, including the STIP.
        3. Metropolitan Planning Organization transportation planning process.


        ODOT must also submit other planning related reports to FHWA. The reports include information on public road mileage for apportionment of highway safety funds; information collected from the Highway Performance Monitoring System; and information relating to the identification of Federal-aid highways, the functional classification of roads and streets, the designation of urban area boundaries and the designation of routes on the Federal-aid highway systems.

        FHWA will serve on the MPOs Technical Advisory Committees as an advisor and not as a voting member. Through FHWA/ODOT's involvement with the MPOs, both agencies will continue to stress the importance of the public involvement process and will assist in applying appropriate levels of environmental consideration during the planning process to result in a more feasible, efficient, and acceptable transportation planning product.

      4. Project Approval Action

        Projects not originally included in an approved work program or TIP/STIP will need individual project approval from FHWA. An amendment to the appropriate planning document also needs to be processed.

      5. Monitoring

        ODOT will monitor all SPR activities, including those of subrecipients (local governments including county, municipalities, etc.) to assure the work is being managed and performed satisfactorily and that time schedules are being met. ODOT will submit a report annually to FHWA documenting the results of its monitoring process.

        ODOT will review its long-range transportation plan every 5-years to assure it still meets the goals and objectives in the plan. If necessary, the ODOT will update or rewrite the long range transportation plan.

        FHWA and ODOT periodically monitor MPO plans and activities to ensure they are in conformance with all applicable federal and state guidelines.

        FHWA conducts certification reviews of Transportation Management Areas (TMA) on a four (4) year cycle and periodic reviews of the non-TMAs.

      6. Performance Indicators
        1. Track % deviation from STIP - Total Program.
        2. Track % deviation from STIP - ODOT Program.
        3. Track % deviation from STIP - Local Program.


      7. Business Standards

        ODOT will provide FHWA at least 30 days to review and comment on the draft and final Statewide Transportation Improvement Program, Metropolitan TIPs, State Planning and Research Work Program, the MPO UPWPs and the Statewide and Metropolitan Long Range Transportation Plans.

        ODOT will involve FHWA in decisions involving special and unusual circumstances at the earliest reasonable time to ensure thorough and appropriate decisions can be made collectively.


      8. Approved Procedures/Agreements/Manual

        The ODOT is required to submit to FHWA and FTA, for joint approval, a Statewide Transportation Improvement Program. Under SAFETEA-LU, the ODOT is required to update the STIP and submit for approval to FHWA and FTA at least every 4-years.

        ODOT and the MPOs shall annually certify to FHWA that the planning process is addressing the major issues facing the area and is being conducted in accordance with all applicable requirements. This certification is submitted with the annual Unified Planning Work Programs.

        • Joint FTA/FHWA Planning Memorandum of Agreement (MOA)
        • ODOT's MPO Administrative Manual.


      PROGRAM ACTIVITIES
      AGENCY RESPONSIBLE

      Approval Action

      Ref.
      Source

      Review

      Approve

      Remarks

      20-YR Statewide TransportationPlan

      23 CFR 450.214

      FHWA

      ODOT

      FHWA reviews and comments on LRTP but no official approval action is taken.

      Statewide TransportationImprovement Prog. (STIP)

      23 CFR 450.216

      FHWA

      FHWA/FTA

      Minimum 4 year period; update required every 4years;

      State Planning& Research (SPR) Work Program

      23 CFR 420.11

      FHWA

      FHWA

      ODOT annuallydevelops work program.

      Highway Performance Monitoring System (HPMS) Annual Data Submittal from State and Field Verification Review and Report

      23 U.S.C. 307 (h)

      FHWA

      None

      FHWA HQ required Field Verification review to be conducted bythe Division Offices. Based on this review, the Division Office recommends the acceptance of theHPMS data for funding apportionment and allocationpurposes. ODOT submits HPMS Submittal by June 15th of each year.

      Certification ofPublic Road Mileage

      23 CFR 460.3

      FHWA

      None

      Due by June 1st of each year.

      Heavy Vehicle Use Tax Annual Certification byState & TriennialDivision Office Review

      23 CFR 669.21

      FHWA

      None

      State Department of Revenue required to certifythat HVUT is being collected. FHWA HQ recommends a review be completed every 3years.

      Highway Statistics: 500 Series Reports

      23 CFR 420.105

      FHWA

      None

      ODOT is required to submit several HighwayStatistics forms annually.

      Traffic volume MonthlyAutomated Traffic Recorder Data

      23 CFR 1.5

      FHWA

      None

      ODOT submits required ATR data reports directly to FHWA HQ.

      Annual Truck Weight Characteristics Data

      23 CFR 1.5

      FHWA

      None

      ODOT annuallysubmits required data directlyto FHWA HQ.

      Metropolitan 20-Year LongRange TransportationPlan (LRTP)

      23 CFR 450.322

      FHWA & ODOT

      MPO

      FHWA & ODOT reviews and comments on Metropolitan LRTPs but no official approval action is taken by FHWA.

      Metropolitan Transportation Improvement Program (TIP)

      23 CFR 450.324

      FHWA & ODOT

      Governor or Designee

      Minimum 4 year period; updatedat least every 4 ears.FHWA reviewsand comments on TIPs. All TIPsare developed bythe MPO and included in the STIP byreference which is approved by FHWA.

      Metropolitan Unified PlanningWork Program

      23 CFR 450.314

      FHWA & ODOT

      FHWA/
      ODOT

      MPOs annually develop andsubmit work program by MPO. FHWA & ODOT reviews and comments on UPWPs from each MPO.

      TMA Planning Certification Process Reviews in MPOs greater than 200,000.

      23 CFR 450.334

      FHWA & ODOT

      FHWA

      TMA Planning process reviews in Akron, Canton, Cincinnati, Cleveland, Columbus, Dayton, Toledo, andYoungstown are completed on a 4-year cycle.

      Vehicle (Truck) Size and WeightEnforcement Certification

      23 CFR Part 657

      FHWA

      FHWA

      State is responsible forenforcing vehicle size and weight laws. State is required to developa plan for maintenance of an effective enforcement process. Each State plan isapproved byFHWA and will then serve as a basis bywhich the annual State certification of enforcement will be judged. In Ohio, this Certification is completed by the State Highway Patrol.

      Top

      RESEARCH, DEVELOPMENT, & TECHNOLOGY TRANSFER

      1. Program Overview

        The purpose of the program is to implement the provisions of 23 U.S.C. 504 and 505 for research, development, technology transfer, programs, and studies undertaken with FHWA planning and research funds.

        1. State Planning and Research (SPR) Program

          The main requirements under 23 CFR 420 are to create a SPR Work Program, monitor planning and research activities, submit performance and expenditure reports, conduct peer exchanges, develop and maintain an FHWA approved research and development management process, and maintain program certification.

          The SPR Work Program consists of two parts: (1) Part I, Planning, which is prepared by ODOT's Planning Division and (2) Part II, Research, which is prepared by ODOT's Office of Research. ODOT is responsible for preparation and overall coordination of the Work Program in accordance with 23 CFR 420. The SPR Program operates on a state fiscal year basis with program approval every 2 years. Amendments and revisions are submitted periodically for approval.

        2. Local Technical Assistance Program (LTAP)

          LTAP was created to provide educational training, technical assistance and related support services for rural, small urban, tribal governments, consultants and contractors that do work for local agencies on roads, bridges, and public transportation. The LTAP program is regulated under 23 U.S.C. 504(b). The Ohio LTAP center is located within the Ohio Department of Transportation.

          The Ohio LTAP conducts biennial surveys of local agency training needs. The survey results are used as the basis for developing the curriculum of technical workshops and deployment training courses offered during the next two years.

      2. Applicable Laws, Regulations, and Procedures

        • 23 USC applies to all research and technology transfer activities
        • Title 23, CFR, Part 420 and 450 apply to State Planning and Research Program Administration
        • ODOT Research, Development and Technology Transfer Manual of Procedures
        • ORC, Section 5501


      3. Program Approval Actions

        ODOT will administer the research program in accordance with the ODOT Research, Development and Technology Transfer Manual of Procedures, which has been reviewed and approved by the Division Office. Significant changes to this manual shall be submitted to the FHWA Division Office for approval.

        The research work program is submitted to the Division Office as Part II of the ODOT's Planning and Research Work Program. Currently, the Division Office approves the research work program on a biennial basis. The ODOT's research work program shall meet the requirements of 23 CFR, Part 420.209(a)-(c).

        Ohio LTAP coordinates with the FHWA to draft an annual Work Plan based on the State fiscal year. FHWA reviews the draft LTAP Work Plan. FHWA comments are incorporated into the draft and the final version is approved by FHWA.

      4. Project Approval Action

        ODOT will identify and implement research projects that address high priority transportation issues. An interactive process involving ODOT management and Research Advisory Committee (RAC) members as described in the ODOT Research Program Manual shall be used for the identification and prioritization of projects to be included in the research work program. ODOT shall determine the funding level at which the identified and prioritized projects will be supported with FHWA research funds.

        Other types of projects, including Experimental Features, Demonstration Projects, Application Projects, Test and Evaluation Projects and Special Projects, will be approved by the FHWA Division Office.

      5. Monitoring

        In regards to the SPR, the FHWA exercises its oversight responsibilities through review of the work program prior to approval actions, review of SPR Work Program amendments prior to approval, and ongoing participation of its technical specialists in research study technical panels. As appropriate, FHWA personnel may participate in peer exchanges.

        The ODOT will submit, annually, to the FHWA Division Office performance and expenditure reports that meet the requirements of 23 CFR, Part 420.117, (a)-(c).

        The ODOT will host a peer exchange and report their findings to the FHWA Division Office in accordance with 23 CFR, Part 420.209. The interval between peer reviews will not exceed three years. In addition, the ODOT program manager participates in peer exchanges hosted by other States and uses the knowledge gained to improve the research program.

        FHWA participates in the ODOT RAC process which reviews research program progress and provides recommendations on program priorities and projects.

        FHWA provides oversight to the LTAP program through review of the annual work plan.

      6. Performance Indicators

        1. Track number of research studies that have results implemented.


      7. Business Standards

        FHWA will review and provide comments on the draft and final State Planning and Research Work Program within 30 days. ODOT will involve FHWA in decisions involving special and unusual circumstances at the earliest reasonable time to ensure thorough and appropriate decisions can be made collectively.

        FHWA will review and approve the LTAP annual work plan within 14 days.

      8. Approved Procedures/Agreements/Manual

        • ODOT State Research, Development, and Technology Transfer Manual of Procedures.


        PROGRAM APPROVAL CHART

        PROJECT ACTIVITIES
        AGENCY RESPONSIBLE

        Approval Action

        Ref.
        Source

        Review

        Approve

        Remarks

        State Planning & Research
        (SPR) Work Program Part II

        23 CFR 422.09

        FHWA

        FHWA

        Annually developed work program

        LTAP

        23 USC 504(b)(1) and (2)

        FHWA

        FHWA

        Annually developed work plan.

    Top

    RIGHT-OF-WAY

    1. Program Overview

      The purpose of this section is to address the right-of-way (ROW) functional areas of appraisal, acquisition and relocation, the principal activities used to acquire space for highway projects. These right-of-way activities are covered under Title 49 CFR (24), which has no provision for exemptions under Title 23 U.S.C. Therefore, the rules of Title 49 and Title 23 apply in the situation where Federal aid is being used to fund the right-of-way activity and/or if Federal-aid is being used to fund the project.

      The work activities listed below are covered under 23 CFR and require specific approval and/or oversight by FHWA:

      • ROW certification
      • State ROW operations manual
      • ROW authorization
      • Air rights on the interstate
      • Airspace leases/joint use agreements
      • Sale/transfer of excess ROW
      • Early acquisition, protective buying, and hardship
      • Functional replacement
      • Highway beautification


      The work activities listed below are covered in 23 CFR and do not require specific program or project approvals, but are not exempted from FHWA oversight under Title 23 U.S.C.:

      • Direct eligible costs including administrative, legal and court settlements.
      • Real property donations


    2. Applicable Laws, Regulations, and Orders

      • 49 CFR 24, Uniform Relocation Assistance and Real Property Acquisition for Federal and Federally Assisted Programs
      • 49 CFR 18, Uniform Administrative Requirement for Grants and Cooperative Agreements to State and Local Governments
      • 23 CFR 1.23, Use of Right of Way
      • 23 CFR 620, Subpart B, Relinquishment of Highway Facilities
      • 23 CFR 635.309, Right-of-Way Certification
      • 23 CFR 646.216, Railroad RW
      • 23 CFR 710, Right-of-Way and Real Estate
      • 23 CFR 750, Highway Beautification
      • 23 CFR 751, Junkyard Control and Acquisition


    3. Program Approval Actions

      The approval of the ODOT Right-of-Way Operations manual is a program approval action required by 23 CFR 710.201(c).


    4. Project Approval Actions

      FHWA project-level approval actions include authorization of federal-aid right-of-way activities, early acquisition approval, acceptance of project right-of-way certifications, etc. See the Project Activity Approval Chart for more detail.


    5. Monitoring

      • Even though there are no exemptions under the law for any functions covered in 49 CFR 24, for practical purposes there are two levels of review of those elements. One level depends on whether the project involves ROW acquisition and has Federal-aid in the ROW project phases. The second level relates to where Federal-aid funds are not used in right of way but are used for construction. Although the ROW regulations must be followed under both levels, less attention is given to the reasonableness of the actual dollar expenditures made for ROW activities on those projects where there is no Federal-aid in the ROW activities, provided they meet the minimum criteria of 49 CFR 24.

        For the first level of projects, there is a dual concern for the rights of property owners and displaced persons and the stewardship of the federal dollars. However, it should be stated that for all practical purposes, the ODOT R/W staff does not distinguish whether Federal funds are in the R/W phase and essentially treats all acquisitions the same. Continuous review by FHWA of the State's activities is accomplished through two primary review techniques. The first is through Quality Assurance Reviews (QARs) which are initiated by ODOT but in which FHWA personnel participates. The second is through Quality Improvement Reviews (QIRs) which are initiated by FHWA and cover topics of a particular function which are selected through a Risk assessment.

      • Local Public Agencies (LPAs), i.e., cities and counties, are required to comply with the Uniform Act and its governing regulations found in 49 CFR 24 in the same manner as ODOT. As stipulated in 23 CFR 710.201(b),ODOT is responsible for assuring that ROW acquisitions by local public agencies are made in compliance with Federal and State laws and regulations. However, FHWA continues to also monitor this process through periodic QIRs and both ODOT and local agency right-of-way program activity, as well as the ODOT's oversight of local agency ROW activity is subject to review by FHWA at any time. Review and technical assistance in the Highway Beautification program are also provided by FHWA.
      • Right-of-Way Operations Manual
        • ODOT is responsible for full compliance with FHWA requirements.
        • Future changes to a manual, because of new FHWA requirements or changes in State law, etc., will be submitted to FHWA for acceptance within a reasonable period of time.
        • In-house administrative manual changes should be transmitted to FHWA for informational purposes.
        • In accordance with 23 CFR 710.201(c), ODOT shall certify to the FHWA every five years that the Right-of- Way Operations Manual is current and in compliance with federal and state laws and regulations.


    6. Performance Indicators

      1. Monitor % of Right-of-Way acquisition cases filed for appropriation.


    7. Business Standards

      Work Activity ODOT Action FHWA Action Result
      Appraisals Review, Certification,
      and Approval – All
      Projects
        Appraisal Reports
      Acquisitions Performance and
      Approval – All
      Projects
        Property
      Ownership/Title,
      Easements
      Relocations Performance and
      Approval – All
      Projects
        Relocations

      ROW Authorizationsand Agreements

      Requests

      Authorize – All Projects (7 days)

      Authorization & Agreements

      ROW Certification

      Approve

      Approve (7 days)

      Certificates

      Functional Replacement

      Approval and Oversight

      Concur (14 days)

      Functional Replacement of Real Property

      Air Rights – Interstate

      Request

      Review and Approve (14 days)

      Airspace Agreement

      Airspace Leases/JointUse Agreements

      Approve & Oversight Non-Interstate

      Approve – Interstate (14 days)

      Leases/Agreements

      Disposal of Excess ROW

      Approve Non-Interstate, with no Federal funds in R/W

      Review and Approve Interstate or if Federal funds used and less than Fair Market Value

      Property Sale & Revenue to Transportation Fund

      Federal Land Transfer

      Prepare Request

      Review and Approve (90 days)

      Transfer Deeds

      Early Acquisition, Hardship, Protective Buying

      Prepare Submission

      Review, Approve, and Authorize (14 days)

      Property Ownership

      ROW Operations Manual

      Prepare Manual

      Review and Approve (30 days)

      Manual

      Highway Beautification

      Prepare Request

      Review and Approve (30days)

      Manual

      Administrative, Legal,and Court Awards

      Approve

      Stewardship & Oversight

      Property Acquisition

      Access Control – Disposal and Changes

      Approve Non-Interstate, with no Federal funds in R/W

      Review and Approve all Interstate or ifFederal funds used and less than Fair Market Value (14 days)

      Disposition/Change

      Early Acquisition Cost

      Approve

      Concur (14 days)

      Reimbursement/Matching Credit



    8. Approved Procedures/Agreements/Manuals

      • ODOT ROW Operations Manual
      • ODOT Local Public Agency Manual


      PROJECT ACTIVITY APPROVAL CHART

      PROJECT ACTIVITIES
      AGENCY RESPONSIBLE

      Approval Action

      Reference Document

      Interstate

      Non-InterstateNHS

      Non-NHS Projects

      Other Projects Subject to FHWAOversight byMutual Agreement

      Appraisals

      49 CFR 24

      ODOT

      ODOT

      ODOT

      ODOT

      Acquisitions

      23 CFR 710

      ODOT

      ODOT

      ODOT

      ODOT

      Relocations

      49 CFR 24

      ODOT

      ODOT

      ODOT

      ODOT

      ROW Authorizationsand Agreements

      23 CFR 710

      FHWA

      FHWA

      FHWA

      FHWA

      ROW Certification

      23 CFR 710
      23 CFR 635

      FHWA

      FHWA

      ODOT

      FHWA

      Functional Replacement (Federal Funds in ROW)

      23 CFR 710

      FHWA

      FHWA

      FHWA

      FHWA

      Air Rights – Interstate

      23 CFR 710

      FHWA

      N/A

      N/A

      N/A

      Airspace Leases/Joint Use Agreements

      23 CFR 710

      FHWA

      ODOT
      FHWA*

      ODOT
      FHWA*

      FHWA

      Disposal of Excess ROW

      23 CFR 620
      23 CFR 710

      FHWA

      ODOT
      FHWA*

      ODOT
      FHWA*

      FHWA

      Federal Land Transfer

      23 CFR 710

      FHWA

      FHWA

      FHWA

      FHWA

      Early Acquisition, Hardship, Protective Buying

      23 CFR 710

      FHWA

      FHWA

      FHWA

      FHWA

      Administrative, Legal, and Court Awards

      23 CFR 710

      ODOT

      ODOT

      ODOT

      ODOT

      Access Control – Disposal and Changes

      23 CFR 620
      23 CFR 710

      FHWA

      ODOT
      FHWA*

      ODOT
      FHWA*

      FHWA

      * Below fair market value if Federal funds used in R/W

    Top

    SAFETY

    1. Program Overview

      1. Strategic Highway Safety Plan (SHSP)

        Title 23 USC Section 148 requires that each state develop and implement an SHSP to ensure that the state focuses its resources on the most critical safety needs while addressing them from the perspectives of the "4E's" - engineering, education, enforcement and emergency medical services. Federal, State, local, and other stakeholder representatives comprise a Steering Committee which is responsible for developing and updating the SHSP. This document is required to be updated periodically (4-5 years but may be updated as needed) to ensure that it remains reflective of the State's safety problems. FHWA approves the process for the initial approval and serves as a member of the State's steering committee.

      2. Highway Safety Improvement Program (HSIP)

        Title 23 USC Section 148 establishes a program area for purposes of hazard elimination and rail-highway crossing safety. This program also includes addressing safety on High Risk Rural Roads. ODOT performs HSIP components of Planning, Implementation, and Evaluation to accomplish requirements of the program for highway locations; Ohio Rail Development Commission (ORDC) [statutorily, ORDC is an independent agency within ODOT] performs this for rail-highway grade crossing portion of this program. These components involve: identification of high-crash locations, developing an annual program to address the locations, and an annual report on progress and effectiveness. FHWA is involved in all components with both agencies, both formally and through informal technical assistance.

      3. Safe Routes to School (SRTS)

        Section 1404 of SAFETEA-LU established this program to: (1) to enable and encourage children, including those with disabilities, in grades K - 8 to walk and bicycle to school; (2) to make bicycling and walking to school a safer and more appealing transportation alternative, thereby encouraging a healthy and active lifestyle from an early age; and (3) to facilitate the planning, development, and implementation of projects and activities that will improve safety and reduce traffic, fuel consumption, and air pollution in the vicinity of schools. FHWA is a member of the ODOT SRTS Advisory Committee, both formally and through technical assistance.

      4. Section 164 (Repeat Offender) Penalty Transfer Program

        A percentage of the State's Federal-aid funds from the Interstate Maintenance Program, Surface Transportation Program and/or National Highway System Program are transferred annually from those programs for highway safety purposes. These funds are eligible only for projects involving alcohol countermeasures or hazard elimination safety construction. This program is unique in that the transferred funds are taken from the FHWA apportionments and placed in the National Highway Traffic Safety Administration (NHTSA) Section 402 apportionment for fiscal delivery.

        Alcohol countermeasure projects are fully administered by NHTSA. Safety construction projects are partially administered by FHWA and partially administered by NHTSA. FHWA verifies eligibility of these projects and does a consistency review of the annual HSIP program to the Section 402 Program. Although funding for the safety construction projects is administered by NHTSA, FHWA remains involved in the same manner as described for the HSIP and 402 programs.


      5. 402 Highway Safety Program

        Title 23 USC Section 402 establishes a program area for roadway safety that is "non-construction" oriented. FHWA-funded activities target identification and surveillance of crash locations; highway design, construction, and maintenance; traffic engineering services; and pedestrian and bicycle safety

        NHTSA has been delegated the lead role in handling financial and administrative aspects of FHWA's portion of the program.

        ODPS prepares an annual Highway Safety Plan (HSP) as the planning component of the program, submits a certification statement, and issues a benchmark report. Federal approval is provided by NHTSA in the form of a letter acknowledging ODOT's submission. NHTSA is the lead agency in working with ODOT on using the results of the evaluation process, with FHWA available to provide technical support either to ODPS or NHTSA in the area of roadway safety.

      6. Crash Data Collection and Analysis

        Title 23 USC 148 requires each state to use data covering all public roads in order to ensure that ODOT is making funds available to the appropriate local political authorities to improve safety at these locations. FHWA serves member of the State's Traffic Records Coordinating Committee, which is charged with improving the quality and timeliness of crash data from all law enforcement agencies within the state.

    2. Applicable Laws, Regulations, and Orders

      • 23 USC Sections 130, 148, 159, 163, 164, 315, 402
      • 23 CFR Part 646, Part 924 and Part 1200


    3. Program Approval Actions

      • 23 USC Sections 130 and 148: ODOT provides an annual program evaluation report under the Highway Safety Improvement Program (HSIP), including Hazard Elimination Projects, High Risk Rural Roads, identification of the top 5% of the state's most hazardous locations, and Rail Crossing Improvement Projects. FHWA reviews the State's submission for compliance with the approved guidance regarding the annual reporting requirements.
      • 23 USC Section 148: ODOT will submit Ohio's SHSP to FHWA for approval that the State has followed the prescribed process for coordination with its safety partners as outlined. FHWA will review, and approve, the State's submission using the SHSP Checklist developed by FHWA HQ.
      • 23 USC Section 148: ODOT will submit an implementation plans for each emphasis area of Ohio's SHSP to FHWA for approval. FHWA will review the implementation plans to ensure that they meet both State & National emphasis areas.
      • 23 USC Section 159: ODPS will submit an annual certification to FHWA indicating either opposition to or enactment/enforcement of a law requiring the revocation or suspension of drivers' licenses of individuals convicted of drug offenses. FHWA will ensure that the certification language meets the requirements of 23 CFR 192.
      • -23 USC Section 163: ODOT must annually jointly notify FHWA and NHTSA of the intended use of the Section 163 incentive funds. FHWA will coordinate with NHTSA to ensure that the funds will be expended in accordance with this regulation
      • 23 USC Section 164: ODOT & ODPS must submit a notification to FHWA and NHTSA identifying how the Repeat Intoxicated Drivers penalty transferred funds will be used. ODPS will include all Section 164 penalty transfer projects in the annual Highway Safety Plan (HSP) developed under Section 402. It will also include any Section 164 Penalty Transfer Projects advanced as hazard elimination safety construction projects based on Section 148 criteria in the annual program of projects under the Highway Safety Improvement Program.
      • 23 USC Section 402: FHWA will coordinate with NHTSA on program based Federal actions necessary under the Section 402 Program.


    4. Project Approval Actions

      • FHWA will verify that projects are in the current HSIP, and approve project authorizations, modified project agreements and final vouchers on all Section 130 and 148 projects.
      • FHWA will collaborate with NHTSA on any project level action required for Section 402 projects.
      • Section 164 Penalty Transfer Projects, though handled by NHTSA due to transfer to Section 402, will be handled by FHWA similar to Section 148 projects, following partnership agreement procedures except that no financial actions will be taken by FHWA.


    5. Monitoring

      • FHWA participates as a team member in ODOT-led task forces and teams that are formed as needed to address perceived needs or problems.
      • FHWA participates as a member of the ODOT Traffic Control Review Team that is responsible for assessing work zone traffic control practices and safety, as well as new traffic and safety-related technology and devices
      • FHWA may conduct inspections, including finals, on a statewide sampling basis through annual and process reviews
      • FHWA will provide ongoing technical assistance in the planning, implementation, and evaluation components of the HSIP, and will work cooperatively with ODOT to use process reviews to assess and improve procedures.
      • FHWA will support NHTSA in monitoring of Section 402 Program activities by participating in periodic management reviews conducted by NHTSA and by working cooperatively with ODOT
      • ODOT will monitor the Safety and Congestion Work Plan


    6. Performance Indicators

      1. Reduce highway fatality rate.
      2. Reduce frequency of crashes 10% by 2015.
      3. Complete all high crash location studies by June 30th of each year.


    7. Business Standards

      • FHWA will review and approve future revisions to the SHSP and the process used to develop such revisions for compliance with 23 USC 148 within 30 days.
      • FHWA will approve revisions to the HSIP within 2 weeks


    8. Approved Procedures/Agreements/Manuals

      • ODOT Highway Safety Program (ODOT Policy 122-002(P))


      Section 130 Projects - Rail-Highway Grade Crossings:

      The ORDC uses the "simplified" procedure contained in 23 CFR 646.218 for advancing all rail/highway grade crossing projects to the construction stage. ODOT will work with the railroad and local road authority (when necessary) to develop a fully executed agreement, right of way certification and detail estimate for the project. Upon authorization by FHWA, ORDC will authorize the railroad to proceed with construction for each location.

      Section 130 projects are funded with a 90% Federal share and 10% State or Local match. It is ORDC and FHWA policy to assure that adequate warning devices are selected and installed when Federal funds are used at rail/highway grade crossings. The determination of adequacy is made cooperatively between the railroad company, the road authority having jurisdiction over the highway, ODOT and FHWA. As a condition of the construction funding request submitted to FHWA, ODOT and FHWA agree that FHWA obligation of funds serves as Federal approval of a determination of adequacy pursuant to 23 CFR 646.214(b).

    Top

    SPECIFICATIONS

    1. Program Overview

      Specifications provide for the basis of payment and facilitate the administration of contracts. Specifications delineate the means and methods for the work. They establish levels of acceptability. They serve as the basis for project decisions. In sum specifications serve as the basis for delivering the highway product to the end user. Specifications include: the Construction and Material Specification Book (C&MS), Supplemental Specifications, Supplements, and Proposal Notes.

      The regulations do not require ODOT to have standard specifications. However, the regulations do require that the PS&E for Federal-aid construction projects on the National Highway System be approved on a project-by-project basis prior to advertisement of the project. The FHWA approval of standard specifications is done as a convenience to simplify the PS&E review process. Once approved, the standard specifications can be used on Federal-aid projects without further review. In the absence of pre-approved standard specifications all of the required specification information would have to be included and approved as part of the PS&E package for each project.

      ODOT does not differentiate between NHS and Non-NHS projects when it comes to the development and implementation of Specifications, a single set of Specifications is used. State standard Specifications are developed in accordance with ODOT's Standard Procedure: 510-005(SP).

    2. Applicable Laws, Regulations, and Orders

      • 23 USC 106 and 109
      • 23 CFR 625
      • 23 CFR 630 Subpart B
      • 23 CFR 635.127 Federal-Aid Policy Guide Non-Regulatory Supplement NS 23 CFR 630B
      • FHWA, Technical Advisory T 5080.16, Development and Review of Specifications


    3. Program Approval Actions

      • The ODOT Construction and Material Specifications are approved by FHWA on a program basis to facilitate project approvals.
      • FHWA will approve updates to the Liquidated Damages Specification C&MS 108.7 every two years in accordance with the provisions at 23 CFR 635.127.


    4. Project Approval Actions

      • Non-standard Construction and Material Specifications are approved on a project-by-project basis at the time of PS&E, in accordance with the agreed level of project oversight


    5. Monitoring

      • The FHWA will participate in the various specification committees.
      • FHWA will assess the performance of individual specifications via the conduct of program and project reviews conducted in accordance with this Agreement.


    6. Business Standards

      • FHWA will perform a quality control review of proposed specifications and provide comments to ODOT within 30 days of receipt.
      • FHWA will approve revised specifications within 14 days of receipt.


    7. Approved Procedures/Agreements/Manuals

      • ODOT, Construction and Materials Specification Development Policy, 27- 005
      • ODOT, Construction and Materials Specification Development Standard Procedures, 510-005(SP)
      • ODOT, Specification Committee Supplemental Instructions
      • ODOT, Qualified Products List process
      • ODOT, Approved List Procedure
      • ODOT, Distribution of Standard Drawings, Design Manuals, Proposal Notes, & Supplemental Specifications Policy, 16-004(P)
      • ODOT, Distribution of Standard Drawings, Design Manuals, Proposal Notes, & Supplemental Specifications standard procedure, 122-004(SP)
      • ODOT, Locally-Administered Transportation Projects Policy, 25-001(P)
      • ODOT, Construction and Material Specification books, Supplemental Specifications, Supplements, and Proposal Notes


    Top

    TRAFFIC OPERATIONS

    1. Program Overview

      Traffic Operations is a cross cutting program area that touches many aspects of the highway program. Traffic operations contributes heavily to project development through engineering analysis of vehicle and pedestrian movement that are needed to produce sound project level decisions affecting safe and efficient highway operations. It is also an area that contributes heavily to the operations and physical maintenance of highway facilities by providing techniques, procedures, management practices/systems and inventory tools.

      ODOT and FHWA have formed partnerships in support of safety and congestion relief initiatives with other State and local agencies, including fire and law enforcement.

      In Ohio, the FHWA's Traffic Operations Program includes the following core elements and components:

      • Management of Non-Recurring Congestion
        • Traffic Incident Management Systems provide for identification and response to vehicle crashes and breakdowns with appropriate emergency services and to restore normal traffic flow and to reduce secondary crashes.
        • Work Zone Traffic Control helps to improve safety and efficiency of vehicular movement through work zones. A new federal regulation, 23CFR630, requires agencies receiving federal funds to implement certain procedures. FHWA is an active participant on ODOT committees and review teams that examine and improve on ODOT standards, practices, and applications of work zone traffic control and safety.
      • Management of Recurring Congestion
        • Freeway Management Operations improve traffic flow on high volume roads by monitoring traffic conditions and providing appropriate responses to those conditions, through the use of Traffic Incident Management programs, ramp metering, and Traveler Information Systems.
        • Arterial Management Systems involve traffic signal coordination and optimization of traffic flow by adjusting timing and patterns either based on time-of-day or in response to real-time traffic data.
      • Improving Day-to-Day Traffic Operations
        • Traffic Control and Standards includes the adoption and use of standard traffic control devices - such as signing, pavement markings, signals, and zones - detailed in the Manual on Uniform Traffic Control Devices (MUTCD), and the conformance of the State MUTCD to be in substantial conformance with the national MUTCD. Changes to the national MUTCD issued by the FHWA must be adopted by the states within two years of issuance. FHWA is an active participant in ODOT committees to prepare revisions to the Ohio MUTCD.


    2. Applicable Laws, Regulations, and Orders

      • 23 USC Chapter 1, Sections 101, 104, 109, 114, 116
      • SAFETEA-LU Title I, Subtitle A, Section 1110
      • 23 CFR Part 1.27, Part 630, and Part 655 Subpart F


    3. Program Approval Actions

      • FHWA will review and approve ODOT's work zone policies and standards for conformance with FHWA Work Zone Role (23 CFR 630)
      • FHWA reviews and approves the Ohio MUTCD for conformance to the national MUTCD. FHWA also reviews and approves modifications and supplements to the Ohio MUTCD.


    4. Project Approval Actions

      • FHWA's specific approval of traffic operations elements of project development will occur coincident with environmental approvals when the traffic operations studies are supporting alternative selection decisions.
      • FHWA's specific approval of traffic operations elements of project plans will be approved coincident with PS&E approval dependent on the project's exemption status.
      • FHWA's approval of traffic analyses that support interchange/access modification will be approved coincident to the interchange/access modification.


    5. Monitoring

      • FHWA will conduct routine project and final inspections of traffic operations aspects on FHWA Oversight projects. For all other projects, FHWA may conduct process reviews.
      • FHWA will conduct routine evaluation of the maintenance of traffic on active Federal-aid projects to assure traffic operations components are being adequately maintained.
      • FHWA will provide ongoing technical assistance in the area of traffic operations, will include this area in routine risk assessment evaluations, and will work cooperatively with ODOT to use process reviews to assess and improve processes and procedures.
      • FHWA will review and approve ODOT's workzone policies and standards for conformance with FHWA Work Zone Role (23 CFR 630)


    6. Performance Indicators

      1. Monitor % of daily travel under congested conditions.


    7. Business Standards

      • ODOT will notify FHWA of adoption or significant locally produced application of regulatory provisions including the MUTCD, AASHTO Policy and Work Zone Safety and Mobility Regulations within 30 days of adoption.
      • FHWA will follow prescribed processing requirements for individual project actions related to Traffic Operations as defined in this partnership agreement.
      • ODOT will fully involve FHWA in all aspects of freeway interchange addition or change studies and proposals


    8. Approved Procedures/Agreements/Manuals
      • ODOT Location & Design Manuals
      • ODOT Local Public Agency Manual
      • ITS Regional Architectures and Strategic Plans
      • ODOT Standard Specifications
      • ODOT Standard Detail Drawings
      • ODOT Maintenance Manual
      • ODOT Construction Manual
      • ODOT Supplemental Specifications and Special Provision
      • Ohio MUTCD

Top

 

 

Table of Contents | Previous | Next


FHWA Home | Ohio Division Home | Feedback
FHWA