Pavements

Strategic Outcome 4A: Comprehensive guidelines for assessing the relative performance of different pavements.

The following boxes are specific analysis projects that fall under Strategic Outcome 4A.

Solid Pink Box: NCHRP 1-35A | Funding = $200,000 | Guide for Pavement Management. | Project completed. Dec. 1, 1997 | AASHTO Pavement Management Guide June 30, 2000 | Responsible Agency: Texas A and M U. | Principal Investigator/NCHRP Staff: Smith/Hanna

Solid Orange Box: FHWA | Funding = $55,838 | Analysis of LTPP Friction Data. | Project completed. Aug. 1, 1997| Report: FHWA-RD-99-037 July 1, 1998 | Responsible Agency: ERES | Principal Investigator/FHWA Staff: Glover/Richter

Solid Orange Box: FHWA | Funding = $100,000 | Study of LTPP Distress Data Variability. | Project completed. Jan 1, 1997 | Report: FHWA-RD-00-113  Dec. 1, 1998 | Responsible Agency: ERES | Principal Investigator/FHWA Staff: Evans/Richter

Solid Orange Box: FHWA | Funding = $141,000 | Distress Data Consolidation. | Project completed  Aug.15, 1998 | FHWA-RD-01-143 - Dec. 31, 2000 | Responsible Agency: Fugro-BRE | Principal Investigator/FHWA Staff: Simpson/Richter

Solid Orange Box: FHWA | Funding = $397,000 | LTPP Profile Variability | Project completed. July 28, 1997 | Report: FHWA-RD-00-113 Mar. 1, 2000 | Responsible Agency: ERES | Principal Investigator/FHWA Staff: Evans/Richter

Solid Orange Box: FHWA | Funding = $58,000 | Preliminary Evaluation and Analysis of LTPP Faulting Data | Project completed. May 1,1998  | Report: FHWA-RD-00-076  Dec. 31, 1998 | Responsible Agency: ERES | Principal Investigator/FHWA Staff: Tayabji/Richter

Solid Orange Box: FHWA | Funding = $196,000 | Characterization of Transverse Profiles. | Project completed. July 28, 1997| Report: FHWA-RD-01-024 : Sept. 1, 2000 | Responsible Agency: ugro-BRE | Principal Investigator/FHWA Staff: Simpson/Richter

Solid Orange Box: FHWA | Funding = $60,000 | Pavement Smoothness Index Relationships. | Project completed. Feb. 1, 2001| Report: FHWA-RD-02-057  Nov. 1, 2001 | Responsible Agency: ERES | Principal Investigator/FHWA Staff: Smith/Swanlund

Solid Orange Box: FHWA | Funding = $74,991 | Smoothness Index Differences Related to LTPP Equipment Type. | Project Completed - Jan 6, 2004 | FHWA-RD-05-054  April 30, 2005 | Responsible Agency: CTL | Principal Investigator/FHWA Staff: Perera/Wiser

Dashed White Box: Problem Statement Number 4A1 | Develop improved pavement performance default values or models for life-cycle cost determination.

Hashed Orange Box: Problem Statement Number 4A2 | Develop hierarchical data collection for network- and project-level pavement management considering types and frequencies of measurements. | Planned

Dashed White Box: Problem Statement Number 4A3 | Types and frequencies of measurements for accurate description of pavement condition.

Dashed White Box: Problem Statement Number 4A4 | Numerical pavement evaluation indices for pavement condition.


LEGEND

NCHRP project number | $ Funds | NCHRP Project Title | Effective Date | Completion Date | Responsible Agency | Principal Investigator/NCHRP Staff

Dashed light blue boxes are on-going NCHRP projects that were initiated by the LTPP ETG. Solid light blue boxes are completed projects.

NCHRP project number | $ Funds | NCHRP Project Title | Effective Date | Completion Date | Responsible Agency | Principal Investigator/NCHRP Staff

Dashed pink boxes are on-going NCHRP projects that were initiated by other agencies or work groups, but are directly associated with LTPP Data Analysis Plan Strategic Objectives and Analysis Outcomes. Solid pink boxes are completed projects.

Problem Statement Number, O_A_n, Proposed problem title
Project Duration, Anticipated Funds

Dashed white boxes are proposed Research Problem Statements that were developed at LTPP Workshops. See Note 1) for an explanation of the Problem Statement Numbering scheme.

FHWA Technical Support Contractor | O_A_n | Project Title | Planned Start Date | Responsible Agency | Principal Investigator/FHWA Staff

Hashed orange boxes are planned FHWA projects that will be funded using LTPP budgeted funds.

FHWA Technical Support Contractor, $ Funds, Project Title, Start Date, Completion Date, Responsible Agency, Principal Investigator/FHWA Staff

Dashed orange boxes are on-going FHWA projects that were funded using LTPP budgeted funds.

sample of box with thin solid border

Thin solid boxes are completed projects with reports pending.

sample of box with thick solid border

Thick solid boxes are completed projects with reports published.
Note:

1) Problem Statements are assigned a 3 character number using the convention ‘ O_A_n’.  ‘O’ is the associated Strategic Objective number (1 through 7); ‘A’ is the associated Analysis Outcome letter (A, B, C etc.) and ‘n’ is an arbitrarily assigned number used for identification purposes.  The number ‘n’ does not imply a sequence in which Problem Statements should be addressed.

 
This page last modified on 12/06/07
 

FHWA
United States Department of Transportation - Federal Highway Administration
FHWA-RD-99-037 FHWA-RD-99-074 FHWA-RD-01-143 FHWA-RD-00-113 FHWA-RD-02-057 Publication Listing FHWA-RD-02-057