Skip to contentUnited States Department of Transportation - Federal Highway AdministrationSearch FHWAFeedback

Pavements

<< PreviousContentsNext >>

Rehabilitation of Asphalt Concrete Pavements: Initial Evaluation of the SPS–5 Experiment—Final Report

APPENDIX A

Appendix A includes an overview and summary, as of the time of this report, of each SPS–5 project relative to the experiment plan. Each overview includes a general description of the project’s location and specific values for the key factors of the experiment factorial (table 1). Deviations from the initial project nomination and difficulties reported during construction are identified and briefly discussed. In addition, a summary of the materials data that are available is provided. As stated in chapter 2, the number of tests required for each project varies with the number of supplemental sections built within each project.

A summary of the data completeness for each project is presented in tabular format for construction and monitoring data elements. Data completeness and any project deviations are used in determining an adequacy code that is assigned to each project. This code represents a numerical scale from 0 to 5 and provides an overall rating of the project in regard to fulfillment of the original experimental objectives and expectations. This numerical scale is:

0 = The project will be unable to meet the experimental objectives and expectations or the project has been recently constructed and has only limited data at this time.
1= The project has major limitations in the data. There are significant data deficiencies/missing data that will have a significant detrimental impact on meeting the experimental objectives and expectations.
2= The project has missing data that will have an impact on the reliability of the results for achieving the experimental objectives and expectations.
3= The project has some missing data and deficiencies. However, assumptions combined with the existing data can be used to meet the experimental objectives and expectations.
4= The project has minor limitations, missing data, or data deficiencies that will have little impact on meeting the experimental objectives and expectations.
5= The project has adequate data to meet the experimental objectives and expectations.

ALABAMA

The Alabama project is located on U.S. 84 highway in the eastbound direction, between Do than and Enterprise. The original pavement was constructed on borderline fine/coarse loamy soil, and had about 700 mm of a predominantly coarse soil aggregate mixture base, and about 97 mm of an HMA surface.

Alabama elected to extend its SPS–5 project by adding two supplemental test sections to study the performance of other rehabilitation treatments of interest; these are identified in table 42. All test sections had been monitored and the data collected were available to the Department of Transportation (DOT) for evaluation.

Table 42. Alabama SPS–5 test section layout.
SECTION NO.SURFACE PREPARATIONOVERLAY MATERIAL THICKNESS
014155NoneControl section
010502Minimum51 mm RAP* overlay
010503Minimum127 mm RAP overlay
010504Minimum127 mm virgin overlay
010505Minimum51 mm virgin overlay
010506Intensive51 mm virgin overlay with milling
010507Intensive127 mm virgin overlay with milling
010508Intensive127 mm RAP overlay with milling
010509Intensive51 mm RAP overlay with milling
010563Intensive51 mm milling and inlay with virgin mix
010564Intensive51 mm milling and inlay with RAP mix
Notes: SHRP Sections (010501–09; 014155 is a General Pavement Studies (GPS) section that corresponds to 010501)
Alabama DOT Sections (010563–64)

* RAP = Recycled asphalt pavement.

Preconstruction Monitoring

Pavement surface distress was collected on each section of the project before overlay construction. Each test section was manually surveyed. Low–severity longitudinal cracking was the predominant distress.

Surface profile was also conducted on the project, utilizing the SHRP/LTPP profilometer. Deflection measurements were obtained with the FWD for the evaluation of the structural capacity of each test section. Material samples were obtained in accordance with the LTPP criteria.

Construction Difficulties

Milling operations used a drum width of 2.2 m, which required the contractor to make two passes per lane. On the first day of construction, the pump to be used to transfer water from the tanker was inoperable. Milling continued without the benefit of water as a cooling agent. Milling with water as a coolant was used the next day.

On the third day of construction on section 010507, a temperature of 119 °C was observed before laydown and 104 °C after laydown, which was below allowable limits. On the sixth day of construction, it was noticed during the milling operations that the sections located between Stations 365+00 and 395+00 exhibited some fatigue–like longitudinal cracking in both wheel paths following the milling operation. In addition, the surface layer (about 25 mm thick) appeared to be lifting in sheets due to delamination. The milling machine pulled up large chunks of asphalt concrete about 150 mm by 90 mm in size. Consequently, the contractor was required to use more material from the U.S. 84 highway to compensate for the large particles that would have been screened out when preparing for the recycled mix at the plant.

Postconstruction Monitoring

Following construction, automated pavement distress surveys were to be obtained for all the test sections. Rod–and–level measurements were taken on the surface of all sections. In addition, the surface was profiled with the high–speed profilometer. Transverse profiles were taken using the automated method.

Structural capacity was evaluated using FWD measurements. Improvement in the structural capacity was noted in the overlaid sections, with the highest improvement in the sections with thicker overlays.

Coring was performed; 102–mm cores were obtained 15 m from approach and leave ends of each section following the outline in the material sampling plan.

Data Completeness

As shown in table 43, no thickness data were available from the L05B testing table. Thickness data from the SPS5_LAYER table were available, but were not reported here because L05B results are determinant values for the layer thickness.

Longitudinal profile monitoring was performed 6 months before overlaying, 6 months, and every 2 years after construction on all the sections except the control section, 014155.

FWD data were collected 6 months before and after construction on sections 014155 through 010503 and 010505. All other sections failed to meet either the preconstruction or the postconstruction monitoring requirements. Not all sections met the long–term requirements.

Distress monitoring was conducted 6 months before construction on all sections except section 010502. Only the control section was monitored for distress within 6 month after construction. The long–term monitoring requirement for distress was met for all sections after treatment.

Transverse profile monitoring was performed within 6 months after construction for all sections. Transverse profile was not measured on any section 6 months before construction. The long–term monitoring requirements for transverse cracking were met for all sections after treatment application.

No friction data were collected on any of the sections within 6 months before overlay. All core sections were monitored for friction data within 6 months after construction except the control, 014155, and the supplemental sections, 010563 and 010564. The long–term monitoring requirement was met for all sections after treatment.

No traffic data were available for this project except for the control section, which had 47 days of WIM and 2 years worth of monitored traffic data. There was one year with more than 45 days of AVC per year.

Table 44 summarizes the project testing data. It can be seen that only a small number of tests still needed to be conducted for the unbound base layers. However, almost no tests had been completed on the AC surface layers. Most of the available data were at Level E in the IMS database. No testing had been conducted on the overlay materials placed on this project.

Table 43. Key project information for the Alabama SPS–5.
ALABAMA SPS–5 PROJECT SUMMARY
Age as of Aug 1999:7.68Construction Date: 12/20/91
Subgrade Type:CoarseClimatic Zone: Wet–No–Freeze
Climatic Data Availability:NAAutomated Vehicle Class: None
Construction Problems:Some milling without water. Mix too cool at lay down.Weigh–In–Motion: None
Site Key Information Summary:
IDOverlay Thickness, mmMaterialMilledOriginal Pavement Structure
DesignActualDesignActualSurface Thickness, mmBase Thickness, mmBase TypeSubbase Thickness, mmSubbase Type
41550  0  97700Soil Agg  
50251 RAP*0  97700Soil Agg  
503127 RAP0  97700Soil Agg  
504127 Virgin0  97700Soil Agg  
50551 Virgin0  97700Soil Agg  
50651 Virgin51  97700Soil Agg  
507127 Virgin51  97700Soil Agg  
508127 RAP51  97700Soil Agg  
50951 RAP51  97700Soil Agg  
56351 Inlay Virgin51  97700Soil Agg  
56451 Inlay RAP51  97700Soil Agg  
Key monitoring data availability summary—Number of tests recorded in IMS to date
IDIRIFWDDistressTransverse ProfileFrictionTrafficAdequacy Code  
Manual Photographic
41556545 5421  
5024442 3201  
5034442 3201  
5044442 3201  
5054442 3201  
5064342 3201  
5074442 3201  
5084442 3201  
5095442 3201  
5632242 3101  
5642242 4101  
IDIRIDistress Transverse 
PrePostPrePostPrePost
415512/12/908/24/926/20/914/1/926/10/904/1/92 
5027/8/914/1/929/18/914/1/934/1/92 
5037/9/914/2/929/18/914/1/934/1/92 
5047/8/914/1/929/18/914/1/934/1/92 
5057/8/914/1/929/18/914/1/934/1/92 
5067/8/914/1/929/18/914/1/934/1/92 
5077/8/914/1/929/18/914/1/934/1/92 
5087/8/914/2/929/18/914/1/934/1/92 
5097/8/914/2/929/18/914/1/934/1/92 
5638/10/949/18/914/1/933/21/94 
5648/10/949/18/914/1/933/21/94 
Table 44. Alabama SPS–5 materials testing summary.
Alabama SPS–5 Materials Testing Summary—Preconstruction
Test Minimum No.
Per Layer
Number
Conducted
Percent at
Level E
Subgrade:Sieve Analysis39100.0
Hydrometer Analysis39100.0
Atterberg Limits39100.0
Moisture–Density Relations33100.0
Resilient Modulus34100.0
Natural Moisture Content312100.0
Permeability000
Unbound Base:Sieve Analysis39100.0
Atterberg Limits39100.0
Moisture–Density Relations3922.2
Resilient Modulus32100.0
Permeability300.0
Natural Moisture Content312100.0
Bound Base:Classification000.0
Asphalt Surface:Core Examination2815100.0
Bulk Specific Gravity900.0
Maximum Specific Gravity300.0
Asphalt Content300.0
Moisture Susceptibility000.0
Specific Gravity of Aggregate000.0
Aggregate Gradation300.0
NAA Test for Fine Aggregate Particle Shape300.0
Penetration of Asphalt Cement300.0
Specific Gravity of Asphalt Cement300.0
Viscosity of Asphalt Cement3120.0
Alabama SPS–5 Materials Testing Summary–Postconstruction
Asphalt Concrete:Core Examination 40 0 0.0
Bulk Specific Gravity40 0 0.0
Maximum Specific Gravity6 0 0.0
Asphalt Content6 0 0.0
Moisture Susceptibility6 0 0.0
Resilient Modulus00 0.0
Tensile Strength1800.0
Extracted Aggregate:Bulk Specific Gravity Fine Aggregate600.0
Bulk Specific Gravity Coarse Aggregate600.0
Aggregate Gradation600.0
NAA Test for Fine Aggregate Particle Shape600.0
Asphalt Cement:Abson Recovery600.0
Penetration of Asphalt Cement600.0
Specific Gravity600.0
Viscosity of Asphalt Cement600.0

ARIZONA

The Arizona SPS–5 project is in the dry–no–freeze environmental zone. It is located on Interstate 8, approximately 27 km west of Casa Grande, AZ. The original pavement was placed on a silty gravel with sand subgrade, had 361 mm to 447 mm of a granular base of soil aggregate mixture predominantly coarse, and 107 mm to 140 mm of HMA surface.

Arizona elected to extend its SPS–5 project by adding two supplemental test sections to study the performance of other rehabilitation treatments of interest. Each of these treatments is identified in table 45. All of these test sections had been monitored, and the data collected were available to the DOT for evaluation. However, these supplemental sections were not included in this investigation.

Table 45. Arizona SPS–5 test section layout.
SECTION NO.SURFACE PREPARATIONOVERLAY MATERIAL THICKNESS
040501NoneControl section
040502Minimum51 mm RAP overlay
040503Minimum127 mm RAP overlay
040504Minimum127 mm virgin overlay
040505Minimum51 mm virgin overlay
040506Intensive51 mm virgin overlay with milling
040507Intensive127 mm virgin overlay with milling
040508Intensive127 mm RAP overlay with milling
040509Intensive51 mm RAP overlay with milling
040559Intensive51 mm milling and inlay with recycled mix
040560Intensive51 mm milling and inlay with Asphalt Rubber Asphalt Concrete (AR–AC) mix
Notes:SHRP Sections (040501–09)
Arizona DOT Sections (040559–60)

Preconstruction Monitoring

Monitoring data on rutting, roughness, and fatigue cracking were gathered on the sections before the application of overlays. At the time of construction, fatigue cracking was about 20 percent.

Surface profiling was conducted on the project utilizing the SHRP/LTPP profilometer. Deflection measurements were obtained with the FWD for the evaluation of the structural capacity of each test section. Material samples were obtained in accordance with the LTPP criteria.

Construction Difficulties

When paving the first of three lifts, the average temperature behind the paver was 107 °C, causing concern. There was some confusion about the calibration of the nuclear density for taking readings from the second lift of the overlays. An 80–kg/m3 correction was added to the density gauge. Later, the correction factor was determined to be 32 kg/m3. The compliance calculations were determined using 32 kg/m3 and subtracting the 80 kg/m3 only where data sheets noted that it had been added in.

Low stability was evidenced in the asphalt rubber concrete mix. The mix used in construction had a stability value of 49 kN. Milling on the minimum restoration sections was as high as 25 mm in some cases.

A 1.8–m milling width in one pass was used. This caused re–milling in several areas. Compacted density problems were encountered on the left lanes of sections 040507 and 040504.

Postconstruction Monitoring

Samples of the asphalt mix, granulated rubber, and reacted asphalt rubber binder material were taken. The AC–10 material was also sampled and sent to Central Materials for testing.

Data Completeness

As shown in table 46, thickness data were available from the L05B testing table. Thickness data from the SPS5_LAYER table were available, but were not reported here because the L05B results are the determinant values for layer thicknesses. It can be seen that the thicknesses were generally thicker than what was designed, especially with section 040506. This section’s thickness data were not yet at Level E in the IMS database.

Longitudinal profile data were collected within 6 months before and after overlaying on all the sections. The long–term monitoring requirement was not met except for section 040501.

FWD data were collected within 6 months before construction on all the sections. However, the requirements for postconstruction and long–term monitoring were not met for any of the sections.

Distress monitoring was conducted within 6 months before construction except for sections 040503, 040559, and 040560. Distress monitoring was not conducted within 6 months after construction. The long–term monitoring requirement for distress was met for all sections after treatment.

Transverse profile was not measured on any section within 6 months before or after construction. The long–term monitoring requirements for transverse cracking were not met for any section after treatment application.

No friction data were collected on any of the sections within 6 months before or after overlay. All core sections were monitored for friction data every 2 years after construction.

Approximately 5 years of traffic data and 290 days of WIM data were available for all sections. There were 4 years with more than 45 days of AVC per year.

Table 46. Key project information for the Arizona SPS–5.
ARIZONA SPS–5 PROJECT SUMMARY
Age as of Aug 1999:9.21Construction Date: 06/13/90
Subgrade Type:CoarseClimatic Zone: Dry–No–Freeze
Climatic Data Availability:29 YearsAutomated Vehicle Class: 409 Days
Construction Problems:Mix placed at low temperature.Weigh–In–Motion: 290 Days
Site Key Information Summary:
IDOverlay Thickness, mmMaterialMilledOriginal Pavement Structure
DesignActualDesignActualSurface Thickness, mmBase Thickness, mmBase TypeSubbase Thickness, mmSubbase Type
5010NA 0  107373Soil Agg
5025168.6RAP0  107373Soil Agg
503127119.4RAP0  107373Soil Agg
504127121.9Virgin0  107447Soil Agg
5055171.1Virgin0  104325Soil Agg
50651132.1Virgin51  102325Soil Agg
507127172.7Virgin51  109526Soil Agg
508127165.1RAP51  119381Soil Agg
5095199.1RAP51  119376Soil Agg 
55951 min Inlay152.4RAP51  104335Soil Agg442Soil Agg
56051 min Inlay55.9 51  104356Soil Agg
Key monitoring data availability summary—Number of tests recorded in IMS to date
IDIRIFWDDistressTransverse ProfileFrictionTrafficAdequacy Code  
Manual Photographic
5014523 4352  
5027743 7352  
5037742 7352  
5047743 7352  
5057743 7352  
5067743 6352  
5077743 7352  
5087743 7352  
5097843 7352  
5597742 4352  
5607742 4352  
IDIRIDistress Transverse 
PrePostPrePostPrePost
5012/5/909/21/9011/29/891/15/911/15/91 
5022/5/909/21/9011/29/8910/19/941/15/91 
5032/5/909/21/9011/29/8910/18/941/15/91 
5042/5/909/21/9011/29/8910/18/941/15/91 
5052/5/909/21/9011/29/8910/20/941/15/91 
5062/5/909/21/9011/29/8910/20/949/22/91 
5072/5/909/21/9011/29/8910/18/941/15/91 
5082/5/909/21/9011/29/8910/19/941/15/91 
5092/5/909/21/9011/29/8910/19/941/15/91 
5592/5/909/21/9010/20/9410/20/94 
5602/5/909/21/9010/20/9410/20/94 

Table 47 summarizes the testing data of the project. It can be seen that most of the required tests have been completed on this project. Most of the testing data are currently at Level E in the IMS database.

Table 47. Arizona SPS–5 materials testing summary.
Arizona SPS–5 Materials Testing Summary—Preconstruction
TestMinimum No. Per LayerNumber ConductedPercent at Level E
Subgrade:Sieve Analysis3683.3
Hydrometer Analysis3683.3
Atterberg Limits3683.3
Moisture–Density Relations3683.3
Resilient Modulus360.0
Natural Moisture Content3076.9
Permeability000.0
Unbound Base:Sieve Analysis35100.0
Atterberg Limits37100.0
Moisture–Density Relations36100.0
Resilient Modulus300.0
Permeability35100.0
Natural Moisture Content316100.0
Bound Base:Classification00.00.0
Asphalt Surface:Core Examination2628100.0
Bulk Specific Gravity98100.0
Maximum Specific Gravity32100.0
Asphalt Content350.0
Moisture Susceptibility300.0
Specific Gravity of Aggregate00100.0
Aggregate Gradation350.0
NAA Test for Fine Aggregate Particle Shape000.0
Penetration of Asphalt Cement3580.0
Specific Gravity of Asphalt Cement35100.0
Viscosity of Asphalt Cement35100.0
Arizona SPS–5 Materials Testing Summary–Postconstruction
Asphalt Concrete:Core Examination 32 40 100.0
Bulk Specific Gravity32 39 100.0
Maximum Specific Gravity6 6 100.0
Asphalt Content6 6 100.0
Moisture Susceptibility6 0 0.0
Resilient Modulus30 0.0
Tensile Strength300.0
Extracted Aggregate:Bulk Specific Gravity Fine Aggregate96100.0
Bulk Specific Gravity Coarse Aggregate96100.0
Aggregate Gradation96100.0
NAA Test for Fine Aggregate Particle Shape600.0
Asphalt Cement:Abson Recovery96100.0
Penetration of Asphalt Cement126100.0
Specific Gravity126100.0
Viscosity of Asphalt Cement126100.0

CALIFORNIA

The California SPS–5 project is in a dry–no–freeze environmental zone. It is located on Interstate 40 in San Bernardino County. The original pavement was constructed on poorly graded soil with silt, had 406 mm to 584 mm of predominantly coarse soil aggregate mixture subbase, 100 to 150 mm of cement aggregate mixture base, and 126 to 150 mm of AC surface.

California elected to extend its SPS–5 project by adding 13 supplemental test sections to study the performance of other rehabilitation treatments of interest; these treatments are identified in table 48. It should be noted that the control section, which was to receive no treatment, was also overlaid. All test sections had been monitored, and the data collected were available to the DOT for evaluation.

Preconstruction Monitoring

Preconstruction monitoring was performed on the above sections except two of the supplemental sections that were added before construction of the SPS–5 main sections. The preconstruction monitoring consisted of distress surveys, profile measurements, deflection measurements, and material sampling.

Distress surveys were performed using mostly automated surveys. Manual surveys were used when it was not possible to use automated surveys. Profile measurements were performed using a high–speed profilometer. Averaging the measurements over a moving 0.3–m interval provided the longitudinal profile of the travel lane for each section. Pavement deflections were measured using FWD. Two passes were applied: at mid–lane, and at the outer wheel path.

Sampling of materials was done by extracting 102–, 152–, and 305–mm diameter pavement cores; 152–mm auger probes; 305–mm bore holes, and 1.8–m by 1.2–m test pits to a depth of 305 mm below the top of the untreated subgrade.

Construction Difficulties

Overall, construction was not problematic, but some problems were encountered. There was segregation of the first lift and mat checking in the overlays that could be attributed to frequent starts and stops by the paver. There were also some problems during compaction of several sections. Several inconsistencies and incomplete work were encountered in the milling operations on sections 060502, 060503, and 060509. Slipping of the paver occurred on supplemental sections 060560 and 060561 resulting in torn pavement reinforcing fabric, which in some areas was removed, but not replaced.

Postconstruction Monitoring

The postconstruction monitoring performed on the California SPS–5 site consisted of a distress survey, profile measurements, deflection measurements, and 102–mm core sampling of the overlay material. The cores were taken 6 m from the beginning and end of each section.

Table 48. California SPS–5 test section layout.
SECTION NO.SURFACE PREPARATIONOVERLAY MATERIAL THICKNESS
060501NoneControl section, 51 mm recycled asphalt pavement (RAP) overlay
060502Minimum51 mm RAP overlay
060503Minimum127 mm RAP overlay
060504Minimum127 mm virgin overlay
060505Minimum51 mm virgin overlay
060506Intensive51 mm virgin overlay with milling
060507Intensive127 mm virgin overlay with milling
060508Intensive127 mm RAP overlay with milling
060509Intensive51 mm RAP overlay with milling
060559Intensive9.5 mm chip seal on 51 mm virgin overlay
060560Intensive51 mm virgin overlay on pavement reinforcing fabric (PFR)
060561Intensive51 mm rubberized overlay on PFR
060562Intensive51 mm rubberized overlay
060563Intensive51 mm rubberized overlay on SAMI
060564Intensive51 mm virgin overlay on SAMI
060565Intensive19 mm open–graded AC on SAMI on 51 mm virgin overlay
060566Intensive19 mm open–graded AC on 51 mm virgin overlay
060567Intensive100 mm virgin overlay
060568Intensive51 mm virgin overlay on 100 mm virgin AC base with 38 mm max. agg.
060569Intensive51 mm stone mastic asphalt (Vestoplast) overlay
060570Intensive51 mm stone mastic asphalt (Modified) overlay
060571IntensiveStone mastic asphalt control section, 51 mm dense grade overlay
Notes:SHRP sections (060501–09)
CALTRANS sections (060559–71)
SAMI = stress absorbing membrane interlayer
The 38 mm max. agg. in section 060568 is also known as "Monster Rock"

Data Completeness

Table 49 shows the summary data pertaining to the California SPS–5 project in the IMS database, where it can be seen that the actual thicknesses for the core SPS–5 sections in California were substantially higher that the design values. It is also evident that the control section was overlaid. The construction report notes that a 58– to 71–mm recycle mix overlay was applied to the control section.

Longitudinal profile data were collected within 6 months before construction. However, even though the construction report mentions that the data were collected within 6 months after construction, the data in the IMS database do not show that. The frequency of the longitudinal profile data collection met the long–term monitoring frequency requirement.

FWD data were collected within 6 months before construction except for sections 060501, 060559, and 060564 through 060569. There were no data recorded within 6 months after construction. The data collection met the long–term monitoring requirement except for sections 060559, 060567, 060568, and 060571.

Distress surveys were conducted every 2 years after construction except for section 060560; however, no data were recorded for distress surveys within 6 months before and after construction.

Transverse profile data were collected within 6 months before construction and every 2 years after construction; however, there were no data within 6 months after construction.

The frequency of the friction data collection did not meet any preconstruction, postconstruction, or long–term requirements.

Only 1 year of traffic data was available, which includes 32 days of WIM and less than 45 days of AVC.

Table 50 summarizes the availability of materials testing data for the California SPS–5 project. It can be seen that there was a serious deficiency in the testing data for both the preconstruction and postconstruction data. In addition, none of the tests conducted were at Level E in the IMS database.

Table 49. Key project information for the California SPS–.
CALIFORNIA SPS–5 PROJECT SUMMARY
Age as of Aug 1999:7.33Construction Date: 4/24/92
Subgrade Type:Fine/CoarseClimatic Zone: Dry–No–Freeze
Climatic Data Availability:17 YearsAutomated Vehicle Class: 32 Days
Construction Problems:Segregation in first lift. Tearing of reinforcing fabric. Incomplete milling on three sections.Weigh–In–Motion: 32 Days
Site Key Information Summary:
IDOverlay Thickness, mmMaterialMilledOriginal Pavement Structure
DesignActualDesignActualSurface Thickness, mmBase Thickness, mmBase TypeSubbase Thickness, mmSubbase Type
501045.7 0  109127CTB*422Soil Agg
5025176.2RAP0  112140CTB437Soil Agg
503127165.1RAP0  112140CTB526Soil Agg
504127144.8Virgin0  114124CTB538Soil Agg
5055191.4Virgin0  119132CTB508Soil Agg
50651109.2Virgin51  122135CTB505Soil Agg
507127170.2Virgin51  130137CTB493Soil Agg
508127167.6RAP51  137142CTB485Soil Agg
50951111.8RAP51  137135CTB495Soil Agg
55951203.2Virgin51  114147CTB500Soil Agg
56051109.2Virgin51  114147CTB493Soil Agg
56151106.7Rubber AC51  122142CTB508Soil Agg
56251111.8Rubber AC51  127104CTB566Soil Agg
56351101.6Rubber AC51  13097CTB582Soil Agg
56451109.2Virgin51  130112CTB582Soil Agg
56551109.2Virgin51  127119CTB544Soil Agg
56651109.2Virgin51  117142CTB508Soil Agg
567100101.6Virgin51  119140CTB503Soil Agg
56851152.4Virgin51  119127CTB498Soil Agg
56951182.9Stone Mastic51  137135CTB485Soil Agg
57051182.9Stone Mastic51  122140CTB500Soil Agg
57151246.4Stone Mastic51  109135CTB513Soil Agg
Key monitoring data availability summary—Number of tests recorded in IMS to date
IDIRIFWDDistressTransverse ProfileFrictionTrafficAdequacy Code  
Manual Photographic
5018653 8113  
5028653 8113  
5038753 8113  
5048853 8113  
5058753 8113  
5068753 8113  
5078753 8113  
5088753 8113  
5098753 8113  
5597542 4113  
5606542 5113  
5616752 6113  
5627652 6113  
5638742 5113  
5647552 5113  
5658652 5113  
5668652 4113  
5678542 4113  
5688542 4113  
5696542 5013  
5706642 5013  
5716542 5013  
IDIRIDistress Transverse 
PrePostPrePostPrePost
5012/11/922/2/9311/13/899/24/922/9/929/23/92 
5022/11/922/2/9311/13/899/24/922/9/929/23/92 
5032/11/922/2/9311/13/899/24/922/9/929/24/92 
5042/11/922/2/9311/13/899/24/922/9/929/24/92 
5052/11/922/2/9311/13/899/24/922/9/929/24/92 
5062/11/922/2/9311/13/899/24/922/9/92;9/24/92 
5072/11/922/2/9311/13/899/24/922/9/929/24/92 
5082/11/922/2/9311/13/899/24/922/9/929/24/92 
5092/11/922/2/9311/13/899/24/922/9/929/24/92 
5592/6/912/2/939/25/924/7/95 
5602/14/922/2/939/25/929/25/92 
5612/14/922/2/939/25/929/25/92 
5622/14/922/2/939/25/929/25/92 
5632/14/922/2/939/25/9210/28/94 
5642/14/922/2/939/25/9210/28/94 
5652/14/922/2/939/25/9210/28/94 
5662/14/922/2/939/25/9210/28/94 
5672/14/922/2/939/25/924/7/95 
5682/5/902/2/939/25/924/7/95 
5692/11/922/2/9311/2/9210/25/94 
5702/11/922/2/9311/2/9210/26/94 
5712/11/922/2/9311/2/9210/27/94 

*CTB = cement–treated base

Table 50. California SPS–5 materials testing summary.
California SPS–5 Materials Testing Summary—Preconstruction
TestMinimum No. Per LayerNumber ConductedPercent at Level E
Subgrade:Sieve Analysis330.0
Hydrometer Analysis330.0
Atterberg Limits330.0
Moisture–Density Relations330.0
Resilient Modulus330.0
Natural Moisture Content300.0
Permeability000.0
Unbound Base:Sieve Analysis000.0
Atterberg Limits000.0
Moisture–Density Relations000.0
Resilient Modulus000.0
Permeability000.0
Natural Moisture Content000.0
Bound Base:Classification300.0
Asphalt Surface:Core Examination2600.0
Bulk Specific Gravity900.0
Maximum Specific Gravity300.0
Asphalt Content300.0
Moisture Susceptibility000.0
Specific Gravity of Aggregate000.0
Aggregate Gradation300.0
NAA Test for Fine Aggregate Particle Shape300.0
Penetration of Asphalt Cement300.0
Specific Gravity of Asphalt Cement300.0
Viscosity of Asphalt Cement300.0
California SPS–5 Materials Testing Summary–Postconstruction
Asphalt Concrete:Core Examination 40 0 0.0
Bulk Specific Gravity40 0 0.0
Maximum Specific Gravity6 0 0.0
Asphalt Content6 0 0.0
Moisture Susceptibility6 0 0.0
Resilient Modulus60 0.0
Tensile Strength1800.0
Extracted Aggregate:Bulk Specific Gravity Fine Aggregate600.0
Bulk Specific Gravity Coarse Aggregate600.0
Aggregate Gradation600.0
NAA Test for Fine Aggregate Particle Shape600.0
Asphalt Cement:Abson Recovery600.0
Penetration of Asphalt Cement600.0
Specific Gravity600.0
Viscosity of Asphalt Cement600.0

COLORADO

The Colorado SPS–5 project is in the dry–freeze environmental zone. The project is located on Interstate 70 in Lincoln County. The original pavement rested on clayey soil mixed with coarse material ranging from sand to gravel. The original pavement had an AC surface thickness that ranged from 55 mm to 170 mm. The AC surface thickness rests on a 25 mm to 99 mm dense graded, hot laid, emulsion mixture treated base.

Colorado extended its SPS–5 project by adding two supplemental test sections to study the performance of other rehabilitation treatments of interest. Each of these treatments is identified in table 51. The SPS–5 control section also received a rut level–up course, although it was to receive no treatment. All of these test sections had been monitored, and the data collected were available to the DOT for evaluation.

Table 51. Colorado SPS–5 test section layout.
SECTION NO.SURFACE PREPARATIONOVERLAY MATERIAL THICKNESS
080501NoneControl section, 33 mm rut level–up course
080502Minimum51 mm RAP overlay
080503Minimum127 mm RAP overlay
080504Minimum127 mm virgin overlay
080505Minimum51 mm virgin overlay
080506Intensive51 mm virgin overlay with milling
080507Intensive127 mm virgin overlay with milling
080508Intensive127 mm RAP overlay with milling
080509Intensive51 mm RAP overlay with milling
080559None51 mm HMAC overlay on 108 mm HMAC overlay
080560None51 mm polymer–modified overlay on 108 mm virgin overlay
Notes:SHRP Sections (080501–09)
Colorado Department of Highways sections (080559, 080560)

Preconstruction Monitoring

Samples were collected according to the testing plan. The sampling was done outside the 152–m test sections. A distress survey, deflection, and profile measurements were done 3 months before rehabilitation.

Construction Difficulties

While treatment was not scheduled for the control section, the severity of its rutting caused a hydroplane concern; therefore, a rut level–up was placed on that section. No other construction difficulties were reported for the Colorado SPS–5 project.

Postconstruction Monitoring

Cores 162 mm in diameter were taken in the approach and leave areas around each test section after construction. The drilling locations were different because of weather conditions. Twenty additional 102–mm cores were taken at section 080504 for additional study at Pennsylvania State University. Profile, deflection, and distress survey measurements were performed less than one year after construction.

Data Completeness

Table 52 shows a summary of the key elements for the Colorado SPS–5 project. Layer thicknesses reported in the IMS were substantially larger than the design values. In addition to the overlay, a rut level–up layer of 33 mm was placed on the minimum surface preparation sections.

Longitudinal profile monitoring was performed within 6 months before and after treatment, and then at 2–year intervals after construction, thus meeting the data–collection requirements.

Deflection data were collected within 6 months before and after construction, and at a frequency of every 2 years afterwards.

Distress surveys for the Colorado SPS–5 project were collected within 6 months before and every 2 years after the construction of the overlays. However, surveys were not taken within 6 months after the placement of the treatments.

Transverse profile data were collected within 6 months before and after the application of treatments; however, the long–term frequency requirements were not met.

Friction data were collected at a 2–year interval after the placement of the treatments, but not within 6 months before or after overlays were placed.

For the control section, there were 1,181 days of WIM and 4 out of the 5 years’ worth of monitored traffic data had more than 45 days of AVC per year. For the treated sections, there were 1,058 days of WIM data. Among the 4 years of traffic data available for this project, 3 had more than 45 days of AVC per year.

Table 53 shows a summary of the testing material data collected on the Colorado SPS–5 project. It can be seen that most of the preconstruction testing had been completed. In addition, all of the available data were at Level E in the IMS. A similar observation can be made about the postconstruction testing. Only a few tests still needed to be done on the overlay AC and extracted aggregate, with the majority of the available data at Level E.

Table 52. Key project information for the Colorado SPS–5.
COLORADO SPS–5 PROJECT SUMMARY
Age as of Aug 1999:7.88Construction Date: 10/8/91
Subgrade Type:CoarseClimatic Zone: Dry–Freeze
Climatic Data Availability:23 yearsAutomated Vehicle Class: 1064 Days
Construction Problems:Rut level–up on control.Weigh–In–Motion: 338 Days
Site Key Information Summary:
IDOverlay Thickness, mmMaterialMilledOriginal Pavement Structure
DesignActualDesignActualSurface Thickness, mmBase Thickness, mmBase TypeSubbase Thickness, mmSubbase Type
501033.0 0  17091ATB*