Printable version of this page
Technical Advisory
Paved Shoulders
T 5040.29
February 2, 1990
Par.
- Purpose
- Cancellation
- Definition
- Background
- Shoulder Type Selection
- Design
- Common Distresses
- Summary
- References
- Figures
- PURPOSE. To outline recommended practices for the design of paved
shoulders.
- CANCELLATION. Technical Advisory T 5040.18, Paved Shoulders, dated
July 29, 1982.
- DEFINITION. Shoulder - the portion of the roadway contiguous with
the traveled way for accommodation of stopped vehicles for emergency use,
and for lateral support of the base and surface courses.
- BACKGROUND
- Over the years, the function of shoulders adjacent to mainline pavements
has broadened considerably. Some of the added functions of modern roadway
shoulders are: toaccommodate an increasing encroachment of traffic; to
expedite water runoff from travel lane pavement; to provide added space
for construction and maintenance activities; to provide other usage such
as bicycle paths or slow-moving vehicles and equipment lanes; to reduce
edge stresses and edge and corner deflections; and to reduce the development
of pavement edge dropoffs.
- Paved shoulders are required on all Interstate routes. The decision
to pave a shoulder on other routes is an engineering determination based
on traffic volume, past experience and availability of funds. Paved shoulders
are justified by improved and smoother traffic operations, expectation
of better pavement performance, increased pavement life, enhanced highway
safety and reduced maintenance. Studies included in TRB Special Report
214, "Designing Safer Roads - Practices for Resurfacing, Restoration,
and Rehabilitation" and Publication No. FHWA/RD-87/094, "Safety
Cost-Effectiveness of Incremental Changes in Cross-Section Design - Informational
Guide" have cited reduced accident rates with the use of paved shoulders.
- SHOULDER TYPE SELECTION
- It is recommended that the shoulder be constructed of the same materials
as the mainline pavement in order to facilitate construction, improve
pavement performance and reduce maintenance costs.
- The use of full-width paved shoulders is desirable. However, the additional
cost of this design may not be warranted on all projects. In those cases,
the use of widened lanes should be given strong consideration. Widened
lanes reduce edge stresses and the potential for edge drop-offs, increase
safety, and reduce maintenance costs. A monolithic widening of 2 to 3
feet outside of the traveled way is recommended. Widened lanes are only
effective when striped as 12-foot travel lanes. Consideration should be
given to the placement of rumble strips on the shoulder portion of the
widened lane.
- DESIGN
- General
- (1) Background. The structural design of shoulders has received
less attention than the mainline pavement. Shoulder design has developed
gradually through experience rather than from a rational pavementdesign
approach. There are currently no nationally recognized procedures
for designing shoulders. When designing a shoulder, the following
should be considered:
- (a) Consider whether the shoulder will be used as a temporary or
permanent traffic lane in the future.
- (b) Integrate shoulder drainage with the overall pavement subdrainage
design.
- (c) Avoid the use of aggregate base courses having more than 6
percent minus 200 mesh sieve materials to prevent frost heaving,
pumping, clogging of the shoulder drainage system, and base instability.
- (d) Have a definite program of shoulder mainte-nance.
- (e) Take advantage of the desirable performance of concrete shoulders
adjacent to concrete mainline pavements.
- (2) Width and Cross-Slope. Documents containing applicable
geometric criteria are listed in Federal-Aid Highway Program Manual
6-2-1-1, "Design Standards for Highways." The shoulder cross-slope
should be at least 1 percent more than the mainline pavement cross-slope
on tangent sections to facilitate drainage but should not be so steep
as to preclude the use of the shoulder as a temporary travel lane
during future construction. Asphalt and concrete shoulders should
be sloped from 2 to 6 percent, gravel or crushed rock from 4 to 6
percent and turf about 8 percent. However, care must be exercised
so that the algebraic difference in cross-slope at the pavement edge
does not exceed 0.08 in order to avoid a hazardous rollover effect.
- (3) Pavement Markings and Shoulder Texture Treatments
- (a) Distinguishing paved shoulders from the mainline pavement is
recommended to discourage the use of the shoulder as a travel lane
and provide guidance and warning to drivers. This can be accomplished
by pavement markings and differences in shoulder surface texture.
- (b) Shoulder texture treatments that provide an audible/vibrational
warning to errant drivers have proven effective in keeping traffic
off the shoulder and reducing accidents on long tangent or monotonous
highway sections with a history of run-off-the-road accidents. Attachment
1 (Figures 1 through 3) describes treatments used by States on bituminous
and concrete shoulders.
- (4) Drainage. The presence of free water beneath the pavement
and/or shoulder is detrimental to performance. Grooved shoulder texture
treatments, such as discussed in paragraph 6a(3)(b), can affect surface
drainage. It is recommended that these treatments be offset from the
longitudinal lane/shoulder joint to facilitate point sealing and minimize
surface water infiltration. An analysis to provide adequate surface
and subsurface drainage should be conducted on each project.
- Concrete Shoulders
- (1) General
- (a) Concrete shoulders should be tied to the mainline with properly
spaced and sized tiebars. Tied concrete shoulders will reduce pavement
stresses and edge deflections. Tied concrete shoulders will also
result in a tighter, easier to seal longitudinal joint that, when
properly maintained, will effectively reduce water infiltration
into the pavement structure.
- (b) Retrofitting tied concrete shoulders or lane widening will
reduce edge stresses and deflections. The age, condition and remaining
service life of the existing pavement play a significant role in
determining whether a retrofit is practical. It is recommended that
aretrofit be added only when an engineering and economic analysis
indicates it to be a cost-effective solution.
- (2) Thickness
- (a) Shoulders should be structurally capable of withstanding wheel
loadings from encroaching truck traffic. On urban freeways or expressways,
the shoulders should be constructed to the same structural section
as the mainline pavement to ensure adequate load capacity at the
interface between the mainline and shoulder; to provide for ease
and economy of construction; and to prevent a "bathtub"
condition under the pavement. This will also allow the shoulder
to be used as a temporary detour lane during rehabilitation or reconstruction.
- (b) As an option for other than urban freeways and expressways,
a tapered shoulder may be considered. Adjacent to the mainline,
the shoulder should be the same thickness as the mainline to permit
mid-depth tiebar placement and to provide structural support for
truck wheel encroachments. The shoulder may then be tapered to no
less than 6 inches at the outside edge. Care must be exercised with
a tapered section since a "bathtub" type condition can
result, ponding water in the area of the lane/shoulder interface.
- (3) Subbase. It is recommended that the same type of subbase
be used under the shoulder as under the mainline, especially on high-volume
facilities. Care must be taken in designing the subbase cross-slope
under concrete shoulders to avoid pocketing of water under the lane/shoulder
joint and at the shoulder edge. Problems are often encountered at
this location due to changes in subbase type,resulting in nonuniform
support or difference in drainage characteristics.
- (4) Transverse Joint
- (a) Mainline pavement joints should be extended across the shoulder.
All transverse shoulder joints should be sawed to a depth of 1/3
the slab thickness.
- (b) Where plain jointed concrete shoulders are used adjacent to
continuously reinforced mainline pavement, the shoulder joints should
be sawed at 15-foot intervals. Plain concrete shoulders should not
be constructed integrally with continuously reinforced concrete
pavement. Transverse saw cuts in the integrally constructed shoulders
will propagate cracks across the mainline.
- (c) Where plain jointed concrete shoulders are used adjacent to
jointed reinforced mainline pavement with skewed joints, intermediate
joints should not be sawed in the shoulder. Skewed intermediate
shoulder joints tend to propagate two parallel transverse cracks
across the mainline pavement.
- (d) Where plain jointed concrete shoulders are used adjacent to
jointed reinforced mainline pavement with perpendicular joints,
intermediate shoulder joints are optional. However, intermediate
joints should not be sawed if the shoulder is constructed integrally
with the mainline pavement. Intermediate transverse saw cut in integrally
constructed shoulders will propagate cracks across the mainline.
- (5) Longitudinal Joint. Combined lane and shoulder or lane
widening widths of 15 feet for the right (outside) lane and 16 feet
for the left (inside) lane have generally performed satisfactorily.
For widths greater than these, a longitudinal joint should be sawed
and sealed.
- (6) Keyway. Keyways are not recommended for use, and should
never be used for pavements less than 10 inches thick. If used for
pavements 10 inches or greater in thickness, keyways should be placed
at mid-slab depth to ensure maximum strength. Properconcrete consolidation,
both above and below the keyway, is essential.
- (7) Tiebars
- (a) Tiebars are needed between the mainline pavement and concrete
shoulders to keep the longitudinal joint tight so as to provide
the necessary load transfer. Tiebars are typically placed on 30-inch
centers at mid-slab depth. If tiebars are to be bent and later straightened
during construction, Grade 40 steel is recommended, as it better
tolerates the bending. When using Grade 40 steel, 5/8-inch by 30-inch
tiebars should be used. When using Grade 60 steel, 5/8-inch by 40-inch
or 1/2-inch by 32-inch tiebars should be used. These lengths are
necessary to develop the allowable working strength of the tiebar.
- (b) Tiebars should not be placed within 15 inches of transverse
joints. When using tiebars longer than 32 inches with skewed joints,
tiebars should not be placed within 18 inches of the transverse
joints.
- (c) The structural adequacy of tiebars can be reduced through corrosion.
Corrosion resistant tiebars are recommended.
- (8) Reinforcement. The majority of concrete shoulders are
plain with short joint spacing. They have performed well when placed
adjacent to either plain jointed, reinforced jointed, or continuously
reinforced concrete mainline pavements. The plain jointed design is
therefore recommended. In cases where jointed reinforced or continuously
reinforced shoulders are placed integrally with the same type of mainline
pavement, the steel in the shoulder is normally placed at the same
percentage as requiredfor the mainline pavement.
- (9) Lane Widening. A 2- to 3-foot integral widening of the
mainline slab will reduce edge strains and deflections. To be effective,
the travel lane should be striped at 12 feet with the edge of the
slab being moved into the shoulder and away from traffic load applications.
The remaining portion of the shoulder may also be paved.
- Flexible Shoulders
- (1) Types
- (a) Bituminous surface treated shoulders consist of an aggregate
shoulder on which coats of liquid bituminous material and aggregate
chips have been applied and rolled. Regional terminology such as
armor coat, double or triple surface treatment, or seal coat all
apply.
- (b) Bituminous aggregate shoulders consist of a bituminous mat
on top of an aggregate base course of variable depth that may or
may not contain a stabilizing agent.
- (c) Full-depth asphalt shoulders consist of asphalt mixtures for
all courses laid directly on the prepared subgrade.
- (d) Widened lanes consist of a 2- to 3-foot widening of the mainline
structural section with the remaining width of shoulder composed
of a bituminous surface treatment, bituminous aggregate section,
aggregate or turf. For the widening to be effective, the widened
lane should be striped as a 12-foot travel lane.
- (2) Thickness
- (a) Shoulders should be structurally capable of withstanding wheel
loadings from encroaching truck traffic. On urban freeways or expressways,
the shoulders should be constructed to the same structural section
as the mainline pavement to ensure adequate load capacity at the
interface between the mainline and shoulder; to provide for ease
and economy of construction; and to prevent a "bathtub"
condition under the pavement. This will alsoallow the shoulder to
be used as a temporary detour lane during rehabilitation or reconstruction.
- (b) For other than urban freeways and expressways, a structural
section less than that of the mainline may be warranted. It is recommended
that the thickness be based on an evaluation of life-cycle costs
and past performance under similar conditions. The use of widened
lanes should be considered in the life-cycle cost analysis.
- COMMON DISTRESSES
- Most shoulder deterioration is attributable to one or more of the following
causes: truck encroachments, water intrusion at the longitudinal joint,
use of lower quality materials, and inadequate thickness.
- Field observations have shown that shoulder distress is primarily concentrated
within 24 inches of the longitudinal mainline/shoulder joint.
- The longitudinal joint between a concrete mainline pavement and a flexible
shoulder is a primary source for infiltration of surface water into the
subbase. The longitudinal joint has proven to be one of the weakest parts
of the mainline/shoulder system. Distress in the form of excessive cracking,
breakage, and settlement is concentrated at this location. Separations
generally range from 1/8 to as much as 2 inches. The infiltration of water
can be minimized by a properly sealed and maintained joint. Some highway
agencies add a "wedge" (6 to 19 inches wide) of hot-mixed bituminous
material in the low areas where the flexible shoulder has settled. Tied
concrete shoulders in lieu of flexible shoulders will minimize the problem
associated with a longitudinal joint.
- 8.SUMMARY. Shoulders are an important element in theperformance and
overall service provided by highway pavements. Proper attention to the selection,
design, construction and maintenance of shoulders is an important part of
pavement management and can result in improved performance and service cost
effectiveness.
- 9.REFERENCES. Attachment 2 lists reference documents that should
prove useful in the area of design, construction and rehabilitation of paved
shoulders.
- 10.FIGURES. Attachment 1 (below) contains three figures which describe
shoulder surface treatments used by States on bituminous and concrete shoulders.
Thomas O. Willett
Acting Associate Administrator
for Engineering and
Program Development
Attachments
Attachment 1: Typical Shoulder treatments
Figure 1
Bituminous Shoulders

Figure 1. Indented Strip - A continuous stretch of indentations is impressed
in the shoulder through the use of a steel roller. In a method developed by
California, steel bars are welded to a vibratory roller to impress indentations.
Georgia specifies that a nominal 1 and ½ inch diameter pipe be welded to the
roller drum to form the indentations. Typically the indentations are spaced
8 inches apart (A) and 3/4 inch to 1 inch deep (B). Most States offset this
treatment 6 to 12 inches from the edge of the mainline pavement and the typical
treatment width is 3 feet.
Stone Aggregate Gradations (Percent Passing By Weight)
| STATE |
Appl |
1 |
3/4" |
1/2" |
3/8" |
#4 |
#8 |
#16 |
#100 |
#200 |
#/SY |
| NC |
1st |
90-100 |
20-55 |
0-10 |
0-5 |
--- |
--- |
--- |
--- |
0-1.5 |
45-50 |
| 2nd |
100 |
90-100 |
20-55 |
0-15 |
0-5 |
--- |
--- |
--- |
0-1.5 |
35-40 |
| 3rd |
--- |
100 |
98-100 |
75-100 |
20-95 |
0-15 |
--- |
--- |
0-1.5 |
17-22 |
| SC |
1st |
100 |
90-100 |
--- |
0-20 |
0-5 |
--- |
--- |
--- |
--- |
28-32 |
| 2nd |
--- |
100 |
95-100 |
80-100 |
20-50 |
--- |
0-6 |
0-2 |
--- |
18-22 |
Figure 2. Bituminous Surface Treatment - The effectiveness of a textured
shoulder is largely dependent upon the gradation of aggregate used. Treatments
containing 3/4 inch to 1 inch stone have been observed to be very effective
as an alerting texture.
Figure 3
Concrete Shoulders

Figure 3. Corrugations or rumble strips - The top configuration is the
one most commonly used. Most States build this type of section 3 to 6 feet wide
(C); 3 to 4 and ½ inches between corrugations (A); and 1 inch deep (B). Corrugations
generally extend the full width of the shoulder and are placed at 40 to 100
foot intervals. One variation of this treatment is to offset the section ½ to
4 feet from the edge of mainline pavement. The corrugations may also be placed
in the middle 1/3 of the shoulder, if desired, to accommodate traffic during
future rehabilitation or maintenance work or to accommodate bicyclists.
The bottom configuration is generally built 4 feet wide (D); 6 to 12 inches
between corrugations (E); and 3/4 to 1 inch deep (G). Corrugations are generally
offset ½ to 2 feet from the edge of the mainline pavement and are placed at
40 to 90 foot intervals.
Attachment 2
References
1. "AASHTO Guide for Design of Pavement Structures, 1986," American
Association of State Highway and Transportation Officials.
2. "Design and Use of Highway Shoulders," National Cooperative Highway
Research Program Synthesis Number 63, August 1979.
3. "Design Practices for Paved Shoulders," Transportation Research
Board 594, 1976, R. G. Hicks, Richard D. Barksdale and Donald K. Emery.
4. "State-of-the-Art Review of Paved Shoulders," Transportation Research
Record 594, 1976, J. M. Portigo.
5. "Thickness Design - Asphalt Pavements for Highway and Streets,"
The Asphalt Institute, Manual Series No. 1, September 1981.
6. "Current Practices in Shoulder Design, Construction Maintenance and
Operations," Highway Research Circular Number 142, April 1973.
7. "Design of Zero-Maintenance Plain Jointed Concrete Pavement,"
FHWA-RD-77-111, June 1977, Michael I. Darter.
8. "Structural Analysis and Design of PCC Shoulders," FHWA-RD-81-122,
April 1982, Jihad S. Sawan, Michael I. Darter, and Barry J. Dempsey.
9. "What We Have Learned to Date from Experimental Concrete Shoulder Projects,"
Highway Research Record 434, Edwin C. Lokken, 1973.
10. "Portland Cement Concrete Shoulder Performance in the United States
(1965-1980)," Proceedings, 2nd International Conference on Concrete
Pavement Design, Charles Slavis, 1981.
11. "Concrete Shoulders for CRC Pavements," Proceedings, Continuously
Reinforced Concrete Pavement Workshop, FHWA-78-80-231, June 1980, Gordon
Ray.
12. "Improved Pavement-Shoulder Joint Design," National Cooperative
Highway Research Program Report 202, Richard D. Barksale and R. G. Hicks.
13. "Paved Highway Shoulder and Accident Experience," Transportation
Engineering Journal of ASCE, Volume 100, 1974, C. L. Heimbach, W. W. Hunter,
and G. C. Chao.
14. "A Policy on Geometric Design of Highways and Streets, 1984,"
American Association of State Highway and Transportation Officials.
15. "Design and Performance of Highway Shoulders," Kentucky Research
Report UKTRP-87-8, David Q. Hunsucker, Gary W. Sharpe and Robert C. Deen.
16. "Shoulder Geometrics and Use Guidelines," National Cooperative
Highway Research Program Report 254, Hugh G. Downs, Jr., and David W. Wallace.
17. "Structural Design of Roadway Shoulders," FHWA/RD-86/089, Kamran
Majidzadeh and George J. Ilbes.