| Date of Award: | June 22, 2010 |
|---|---|
| Task 1, Kick-Off Meeting: | July 8, 2010 |
| Task 2, Inventory of Information and Initial Database: | August 17, 2010 |
| Task 3, Establish Expert Working Group: - Meeting #1 - Meeting #2 - Meeting #3 - Meeting #4 | August 17, 2010
September, 2010 December, 2010 March, 2011 June, 2011 |
| Task 4, Initial Delivery of Website Content:
- Continued delivery of content, as available | August 17, 2010
Sept 2010 - June 2011 |
| Task 5, Determination of Control Points: | September 26, 2010 |
| Task 6, Recommendations for Public Involvement: | September 16, 2010 |
| Task 7, Determination of Study Alignments/Design Levels: | December 15, 2010 |
| Task 8, Detailed Spatial Database: (Sunday) | February 13, 2011 |
| Task 9, Draft Estimates of Costs and Steps to Complete: | February 23, 2011 |
| Task 10, Final Report: | April 14, 2011 |
| Task 11, Recommendations for Sub-Studies: (Saturday) | June 18, 2011 |