Office of Planning, Environment, & Realty (HEP)
Planning · Environment · Real Estate
April 28, 2011, 1pm-2:45pm
FHWA GA Division Office, Atlanta
Attendees:
Non-Federal EWG Members |
Federal EWG Members |
|---|---|
Augusta-Richmond Co. PC |
FHWA Eastern Federal Lands |
Project Team |
|
FHWA HQ |
|
The fourth meeting of the Expert Working Group (EWG) for the Third Infantry Division Highway Corridor Study was held on April 28, 2011, from 1:00pm to 2:45pm at the FHWA Georgia Division office in Atlanta. The purpose of the meeting was to review the corridors that were advanced for costing; discuss the cost estimating methodology and review the costs; and to discuss upcoming public involvement activities. The following is a summary of discussion topics, questions, and comments.
John Mettille, Project Manager for the ICF Team, opened the meeting and welcomed participants, who then went around and introduced themselves. Six EWG members attended the meeting in person. The majority of the EWG participated by remote access.
The meeting started with brief review of what the study is and isn’t and a recap of the third meeting. The study is a conceptual feasibility study that will form the basis of FHWA’s report to Congress (Phase 1). States and MPOs are not required to implement any of the corridors discussed. The report to Congress will not include any recommendations. The study team may recommend potential follow-on studies to FHWA as part of Phase 2 of the study.
The third EWG meeting focused on the corridors that were evaluated and screened against potential fatal flaws. Based on the study team’s evaluation and on input from the EWG, two corridors and a no build alternative were advanced for costing. Planning-level cost estimates were prepared for Corridor A West (entire length), Corridor B and B Bypass (Savannah to Millen only), and a No Build alternative (signing an existing route). Maps of Corridors A and B/B Bypass were reviewed with the EWG.
One new alternative was suggested by a member of the public through the project website. The route would parallel the Savannah River on new alignment through South Carolina from I-95 to I-85 near Greenville. The alternative would face the same type of challenges as Corridor D, thus it was not recommended for additional consideration.
Costs were estimated for the design levels (Interstate, Arterial, Super-2, and Context Sensitive) as applicable to each corridor. The Interstate design level would provide at least four travel lanes with grade-separated interchanges, designed to Interstate standards. The Arterial level provides four travel lanes with at-grade intersections at cross-streets. The Super-2 design level provides an enhanced two-lane highway (two travel lanes plus a third lane for passing, truck climbing, etc) with at-grade intersections. The Context Sensitive design level is the minimum level of improvement necessary to have a continuous two-lane highway along a corridor. If the existing facility provides better mobility than a design level proposed for a corridor, that segment was not included in the cost estimate for any lower design levels.
The study team looked at the state of the practice for cost estimating in Georgia and Tennessee. Planning-level cost estimating tools developed by GDOT and TDOT were used for segments of the corridors within their respective states. The estimates include costs for preliminary engineering, right-of-way and utilities, construction, construction engineering inspection (CEI), as well as contingency costs.
Costs: Preliminary Engineering – includes environmental/NEPA work, public involvement, and engineering design efforts. The TDOT tool estimates these as 10% of construction cost; the GDOT tool estimates these as 10% of the total project cost. The preliminary engineering/environmental costs resulting from the application of either model are consistent with estimates from previous FHWA reports to Congress, and comparable to the per-mile costs of some of the study team’s recent environmental projects.
Costs: Right-of-Way & Utilities – includes costs for acquiring new right-of-way and relocating utilities. TDOT estimates are adjusted for land use type. GDOT’s tool adjusts for land use, project type, and location; it also includes a 50% contingency for unknowns in ROW.
Costs: Construction – includes mainline construction, plus per-item costs for structures, interchanges, intersections, mitigation, and more. TDOT base estimates are adjusted for terrain and facility type; GDOT estimates are adjusted for area and facility type, and use per-item unit costs for bridges and interchanges.
Costs: Other – CEI is estimated at 10% of construction cost. Approximately 10-30% of project cost was added to account for contingencies, which are built into the GDOT model but not the TDOT model.
Corridor maps with cost estimates were reviewed and compared between control points as well as along the entire corridor length. Total project costs are shown in the table below:
| Corridor | Context Sensitive | Super-2 | Arterial | Interstate |
|---|---|---|---|---|
| A West | $694 million | $1.2 billion | $2.5 billion | $4.8 billion |
| A West (Dalton spur) | $562 million | $872 million | $2.0 billion | $4.2 billion |
| B/A West | N/A | N/A | $2.5 billion | $5.2 billion |
| B Bypass/A West | N/A | N/A | $3.1 billion | $6.1 billion |
| No Build | N/A | N/A | N/A | < $500,000 |
John Mettille pointed out that the project cost estimates become more accurate as projects advance through the project development process. Large contingencies have been used because there are a lot of unknowns at this very early conceptual planning stage.
Types of risks affecting costs could include unclear project definition; inflation; delays in implementation; and indirect risks. Costs could be significantly higher than the estimates shown in the presentation. The contingency factors built into the estimates (10% to 30%) help account for some of these risk elements.
Both state DOTs (GDOT and TDOT) have very complex project development processes. The final report to Congress will inform them of the complexity and will include both states’ flow charts. Similar features from both are summarized in the bullet points below:
Identify need – The first phase of study looks at route conditions and needs. Projects must meet one of the Long-Range Plan goals to move forward.
Program funds – Adequate funding must be identified in each state before a project can develop. GDOT and TDOT Long Range Plans identify needs over next 30 years and show large funding gap between needs and funds.
Planning – This step involves the development of project purpose and need, development of conceptual alternatives, and an overview of potential issues that must be considered.
Preliminary Design – This begins the evolution of design work. Alternatives are refined and evaluated; environmental analysis can begin as the project location is better defined.
NEPA – The NEPA phase involves analyzing and documenting project impacts. A tiered EIS could work if this project were to move forward, allowing for an overview of the entire corridor before advancing individual sections. It can take several years to progress through this phase.
Final Design – This step involves the development of detailed plans, specifications, and estimates necessary prior to construction.
Permitting – A number of permits would be required for each construction section. Permitting is often begun during final design, as soon as an adequate level of detail is known.
Construct Project – The final step, culminating in the project opening to traffic. Right-of-way acquisition and utility relocations must occur in this phase.
Project development is a 10-12 year process for a typical highway project, from planning to opening to traffic. Legacy projects can last much longer, 30+ years.
Three public webinars/Q&A sessions are scheduled for May 17-18. The EWG members have been asked to distribute fact sheets and flyers to their constituents. Comments will continue to be accepted through the public website.
The EWG was asked to review the information on cost estimating and next steps and provide any comments or concerns.
Next tasks: public involvement, assembling final report to FHWA, and possibly a final EWG call/webinar in late May/early June.
The meeting adjourned at 2:45pm.