Skip to contentU.S. Department of Transportation Federal Highways Administration Public Private PartnershipsFHWA HomeFeedback
 
PPP Home | Contact Us   
 
  PPP Case Studies

CASE STUDY NAME: I-15 CORRIDOR RECONSTRUCTION PROJECT « back
Location Salt Lake City , Utah
PPP Option Design-Build
Mode Highway
Description

The Interstate 15 reconstruction was the Utah Department of Transportation’s (UDOTs) first design-build procurement. The project involved the reconstruction of 26 kilometers of interstate mainline and the addition of new general purpose and high-occupancy-vehicle (HOV) lanes through the Salt Lake City metropolitan area. The project also included the construction or reconstruction of more than 130 bridges, the reconstruction of seven urban interchanges, and the reconstruction of three major junctions with other interstate routes, including I-80 and I-215. In addition, the project provides for the construction of an extensive regionwide advanced traffic management system.

UDOT’s decision to use the design-build model was motivated by two factors. The first was the strong public support for completing the project as soon as possible to minimize the period of severe traffic congestion resulting from the diversion of more than half of the traffic from I-15 during the construction period. The second factor was the need to have the project completed before the 2002 Winter Olympics in Salt Lake City. It was generally accepted that use of the design-build contracting methodology was the only way to satisfy these goals.

The design-build approach also relieved UDOT of many problems associated with the coordination of the design and construction of multiple individual projects in a congested urban setting. The state procurement laws were modified to clearly authorize the use of the design-build method of contracting and to permit the award of a contract to a firm that provided the "best value" proposal to the state even if another firm bid a lower initial cost.

Sponsor

Utah Department of Transportation (UDOT)

Cost $1.59 billion
Type of Finance

Traditional, Pay as you go

Revenue Sources $448 million in Federal funds $1.142 billion in state/local funds for the project
Project Delivery / Contract Method

Design-Build contract. Best value award.

Private Investor Partners

None

Design Build Contractor Wasatch Constructors – a joint venture of Peter Kiewit Sones’, Granite Construction Company, Inc. and Washington Construction Company
Program Manager Parsons Brinckerhoff
Physical Status

Construction began in April 1997 and was completed in May 2001

Financial Status

Paid in full

Innovations

The project was approved by the Federal Highway Administration (FHWA) as an experimental project under SEP-14. This approval permited the use of the design-build method, and required some deviations from normal federal-aid requirements dealing with the selection of contractors and consultants.

The I-15 design-build contract included provisions for payments of up to $50 million incentive bonuses for timely performance, quality of work, complying with project management requirements, and complying with requirements for community relations and maintenance of traffic.

While this approach was attractive to the owner, it created problems for the contractors who were not accustomed to bidding for work that would be performed up to 25 years later. When efforts to sufficiently raise the comfort level of the proposers failed, the maintenance period was reduced to a maximum of 10 years – an initial five-year maintenance option and five one-year renewable options covering years six through 10. Maintenance requirements and standards were restricted to pavement surfaces, structures, and drainage facilities and did not include any routine maintenance activities.

The use of performance specifications, as opposed to traditional prescriptive specifications, encouraged innovation in design and con- struction. A long contractor warranty or maintenance-after-construction period complements the use of performance specifications by compelling the design-builder to complete life-cycle-cost analyses of all design and construction options.

UDOT also derived approximately $30 million in savings by utilizing an Owner Controled Insurance Program (OCIP). The UDOT wrapped OCIP included pre-consruction survey, workers’ compensation, genral liability, and other miscellaneous coverage for all contractors working on the project. In exchange, the contractor was required to prepare a very extensive safety plan and submit it for approval early in the life of the contract. As an additional safety incentive, the received a share of all insurance premium rebates received after completion of the project. The OCIP was funded entirely with State monies through a separate procurement.
Related Links / Articles

A comprehensive listing and onward links to reports prepared on the I-15 project is available on UDOT’s website at: http://www.udot.utah.gov/index.php/m=c/tid=622

US Department of Transportation, Office of Inspector General, I-15 Audit Report, November 13, 2000
http://www.oig.dot.gov/show_pdf.php?id=168

Detailed I-15 case study prepared by FHWA Utah Division
http://www.tfhrc.gov/pubrds/pr97-12/p40.htm

Contacts

 

back to top

 
PPPS Defined | PPP Options | PPP Legislation | SEP-15 Program | Private Activity Bonds | PPP Case Studies | Links | Resources
Events Calendar | Contact Us | Glossary
 
FHWA Home | Feedback
FHWA
United States Department of Transportation - Federal Highway Administration