| FHWA > Engineering > Construction > Contract Admin > Canceled: Interim Owner Controlled Insurance Program Policy |
|
This memo is canceled on October 7, 2002 and superseded by the memo "Owner Controlled Insurance Program Policy"
BackgroundOwner Controlled Insurance Programs (OCIPs) are an effective way to improve the safety of construction operations and reduce the cost of insurance on large projects. The basic operational features of an OCIP are: (1) the owner purchases insurance coverage (all or some specific elements) to cover all contractors and subcontractors on a project; (2) there is an integrated owner-contractor managed safety program on the project; and (3) claims are processed centrally. Overall, the use of an OCIP can save money on large projects through lower bulk insurance rates, improved safety management processes, and reduced disputes between contractors over who was responsible for a particular loss. There are many variations in how an OCIP can be set up. For example, the project owner can purchase coverage, self-insure, or devise a program that blends the two. By retaining more of the risk (through self-insurance or higher deductibles) the owner can obtain lower premiums for the coverage actually purchased. When the insurance program contains a significant element of self-insurance (either a direct self-insurance program or a program with large deductibles) the owner is usually required to provide assurance they will have the money to make those long-term payments as they come due. The State Insurance Agency (and the insurance company, when it pays claims and then recovers deductibles from the owner), may require the owner to provide a letter of credit or establish a reserve account to guarantee it will have the resources to meet its obligations. The NCHRP is currently preparing a synthesis of best practices regarding the use of OCIPs on projects, and this report is scheduled to be released this winter. We have also procured consultant services to provide FHWA offices and our partners with best practices on the use of OCIPs on projects as well as programs. Upon the completion of this consultant activity, FHWA will issue more extensive information and guidance on how to establish OCIPs. However, there is a need for immediate interim policy regarding the appropriate use of Federal funds. PolicyFederal aid funds can be used to participate in OCIPs on Federal-aid projects. OMB Circular A-87 provides guidance and establishes limits on Federal reimbursement of insurance costs. Typical costs that may be eligible for Federal-aid funding include:
Costs that will typically not be eligible for Federal-aid funding include:
Insurance refunds must be credited against insurance costs in the year the refund is received. If annual actuarial reviews of reserve accounts disclose excess balances, the Federal share of the excess amount shall be promptly removed from the reserve account(s) and applied to other allowable project costs or returned to the State's Federal-aid account. |
EventsContactJerry Yakowenko |
|||||||||||||||
|
This page last modified on 03/13/08 | ||||||||||||||||