Printable version of this project (.pdf, 0.31 kb) Special Experimental Project (SEP-14)Alternative Contracting Program Proposal (Work Plan)Submitted by Montana Department of Transportation (MDT) IntroductionThe Montana Department of Transportation (MDT) submits this pavement alternate bidding work plan for review and approval as a programmatic procedure under the provisions of Special Experimental Project No. 14 (SEP-14). This will be applied to future projects in coordination with the FHWA Montana Division. Use of alternate pavement designs and bids are being considered using a Life Cycle Cost Analysis (LCCA) model. Recent unit cost increases in HMA bid prices has created a more competitive environment between Hot Mix Asphalt (HMA) and Portland Cement Concrete Pavement (PCCP) when considering an LCCA adjustment. In this proposal, MDT would assume long-term risks associated with the pavement designs, while contractors compete on the basis of the initial pavement costs adjusted by a life cycle equivalency factor. PurposeThis work plan identifies the use of alternate asphalt and concrete pavement sections on select future reconstruction and/or major rehabilitation projects. MDT will select projects to use alternative pavement sections based on cost and engineering analysis. The cost analysis will be used to select projects where PCCP is cost competitive with HMA pavements. The engineering analysis will be done after the cost analysis, and will consider PCCP pavement issues, such as differential roadbed settlement and traffic control. The selection of these projects will be coordinated with the FHWA Montana Division. Bid cost comparisons including a life cycle cost analysis (LCCA) will allow multiple surfacing alternatives to be compared on a life cycle equivalency basis. Using LCCA, bids having unequal service lives and maintenance costs can be compared on a cost per unit time basis. The proposed specification utilizing the alternate pavement bidding with bid adjustment approach (ATTACHMENT 1) is considered experimental and uses the following elements in determining the most responsive bidder:
The Life cycle equivalency factor (LCEF) is the present worth of the additional future rehabilitation and maintenance costs associated with the HMA alternative. This amount, or a component, will be added to total cost on bid proposals using the HMA alternate. MDT will accept the lowest responsible bid of the HMA + LCEF or PCCP alternates. Inclusion of the LCEF provides the benefit of documenting future rehabilitation strategies and anticipated pavement performance. The LCEF amount will be determined prior to the bid and included in the bid documents. The procedure used by MDT for LCCA is described in ATTACHMENT 2. The basis for the methodology used to conduct LCCA follows an interim technical bulletin published by the Federal Highway Administration as publication number FHWA-SA-98-079, Life Cycle Cost Analysis in Pavement Design. The experimental bidding method outlined in this work plan intends to capitalize on the cost competitive market emerging between hot mix asphalt (HMA) and Portland cement concrete pavement (PCCP). Due to oil price volatility and cost escalation HMA prices have been difficult to estimate. These increased prices have created a situation where PCCP is more cost competitive. In addition, increasing demands on limited highway funds necessitates methods to maximize use of highway tax dollars. As PCCP alternate surfacing projects are bid, MDT anticipates greater investment in PCCP surfacing capabilities within the contracting community which has the potential to lower bid prices ScopeThis work plan includes a request to authorize use of the outlined procedures on a programmatic basis to include future reconstruction and major rehabilitation projects. These projects will be coordinated with the FHWA Montana Division prior to final selection. Additional value engineering proposals related to pavement type changes will not be accepted for these projects. ScheduleMDT is requesting to apply the outlined alternate pavement bidding process to reconstruction and major rehabilitation projects between FY2010 through FY2015. Evaluation / ReportingDuring the evaluation period, between FY2010 through FY2015, MDT will develop project specific reports that assess various aspects of the alternate pavement bid projects. These areas include, but are not limited to, the following:
This report will be submitted to FHWA Montana Division at the conclusion of construction for each project. By September 30 of each year during the study period, MDT will consolidate the individual project reports and develop an annual summary. This report will consolidate information from the individual project reports; analyze the performance of the experimental bidding technique; summarize contractors and individual MDT comments and concerns; note any problems with the experimental bid process; and provide recommendation whether future use will be continued... Attachment 1Proposed Specification Language*
*Special Provision Language modeled after the Missouri Department of Transportation's specifications. Attachment 2Bidders may submit bids using one of the two pavement options under consideration for this project. Each bidder must choose its preferred pavement option and submit only one bid. The submission of more than one bid proposal for the same work from an individual firm or corporation under the same name or from an affiliated company will result in the rejection of the bids from those bidders. The basis for the added dollar value is the Department's estimated cost difference for the future rehabilitation needs of the two pavement options over the 40-year anticipated performance for each pavement option (Life Cycle Cost Equivalency Factor). The life cycle cost equivalency factor is using the following example as a guide: LCCA Example40-Year Life Cycle Cost Analysis
|
| Cost ($) | Type of Maintenance | Year of Maintenance | Present Worth | |
|---|---|---|---|---|
| Initial Construction | $1,695,000 | 0 | $1,695,000 | |
| Maintenance #1 | $595,000 | Mill & Fill (shoulders), Chip Seal, Concrete Rehab | 20 | $342,495 |
| Salvage Value | 40 | $0 | ||
| Total Cost | $2,037,495 |
| Cost ($) | Type of Maintenance | Year of Maintenance | Present Worth | |
|---|---|---|---|---|
| Initial Construction | $1,564,000 | 0 | $1,564,000 | |
| Maintenance #1 | $72,000 | Chip Seal | 7 | $59,345 |
| Maintenance #2 | $520,000 | Overlay, Chip Seal | 12 | $373,324 |
| Maintenance #3 | $780,000 | Mill & Fill, Chip Seal | 19 | $461,557 |
| Maintenance #4 | $72,000 | Chip Seal | 26 | $35,117 |
| Maintenance #6 | $1,309,000 | PMS Rehabilitation | 30 | $571,671 |
| Maintenance #7 | $72,000 | Chip Seal | 37 | $25,917 |
| Salvage value (20 years remaining on Year 30 Rehabilitation) | -$1,042,667 | 40 | -$345,478 | |
| Total Cost | $3,346,333 | $2,745,453 |
Life-Cycle Cost Analysis (LCCA) is a process for evaluating the total economic cost of a pavement by analyzing initial costs and discounted future maintenance costs over a pre-determined analysis period. The initial construction costs will be determined from the Engineer's estimate. The following LCCA procedure will be used to determine the discounted future maintenance costs for each pavement alternative.
The LCCA analysis period is 40 years. A 40-year LCCA corresponds with the PCCP structural design life. The future maintenance schedules have been developed based on historical performance. The future maintenance schedule for interstate and other heavy traffic routes is as follows:
Flexible Pavement Alternative
Rigid Pavement Alternative
To account for the time-value of money, all future maintenance work is discounted using the real discount rate for 30-year treasury notes and bonds (currently 2.8% annually). This rate is published by the White House Office of Management and Budget in OMB Circular No. A-94 Appendix C (http://www.whitehouse.gov/omb/circulars/a094/a94_appx-c.html).
The discounted future maintenance costs are then added to the initial construction costs and the net present value of the alternatives are compared. The LCCA equivalency factor is the difference between the rigid and flexible alternatives.
The formula for applying the discount rate is as follows:
(P/F,i%,n) = (1/(1 + i)n ) x Present Construction Costwhere:
Initial construction costs will include pavement material costs only based on the assumption that all other project costs will be equal. The initial construction costs will be calculated based on quantities and bid item prices found in the engineer's estimate.
Future maintenance work costs will be calculated using Plan quantities and average annual cost per square yard for each treatment type (i.e., chip seal, overlay, etc.) The cost per square yard is published annually by MDT's Pavement Analysis Section. Procedures used to calculate cost per square yard can be found at http://app.mt.gov/pvms/docs/2008_pavement_condition_report.pdf (.pdf, 0.4 mb).