|
Printable version (.pdf, 1.5 mb)
WORK PLAN FOR THE 183A NORTH EXTENSION PROJECT
Central Texas Regional Mobility Authority Application for SEP-14 Approval
A. INTRODUCTION
This work plan is submitted by the Central Texas Regional Mobility Authority ("Mobility
Authority") for review and approval by the FHWA of the proposed 183A North
Extension Project ("Project") as a project under the provisions of Special Experimental
Project No. 14 (SEP-14).
The proposed Project includes 5.1 miles of toll facility extending from north of FM 1431
in the City of Cedar Park to north of RM 2243 in the City of Leander in Williamson
County. The proposed improvements will consist of 3 tolled lanes in each direction,
ingress/egress access ran1ps for access to/from the facility, electronic toll collection
facilities, and a shared-use path. Local traffic will continue to access adjacent properties
by use of existing non-tolled frontage roads and signalized intersections. The tolled
main lanes with grade-separated interchanges will service through traffic.
To maximize expediency and flexibility in the implementation of the Project given the
pending environmental clearance and potential funding delays, the Mobility Authority is
currently designing the project in three segments:
- Segment 1 - 6 tolled mainlanes (from FM 143 I to north of RM 2243)
- Segment 2 - Reveille Boulevard (CR 269) Intersection and Overpass Bridge
- Segment 3 - San Gabriel Parkway (CR 274) (800 linear foot segment)
The successful implementation of the Project will relieve congestion and improve safety
on the 183A corridor by segregating through traffic and local traffic, and by providing
increased capacity for local traffic. The completion of the Project will result in enhanced
mobility and improved safety for the Central Texas region by providing an efficient link
between northwest Williamson County and the Austin area. Additionally, the proposed
improvements will sustain and stimulate regional growth.
B. SUMMARY OF EXPEIUMENTAL PROJECT FEATURES
The Mobility Authority requests FHW A to approve the following experimental aspects of
the Project:
Use of lump sum bidding: The bidders will be provided with a set of bid
documents including plans, specifications, and quantity estimates. The bidders
will be required to develop a unit price schedule for the work that will be
converted to a lump sum bid price for the selected contractor.
Use of no-excuse bonus: The Mobility Authority will give the contractor two
contract dates for substantial completion of the work. If the work is completed in
advance of the earlier date, the contractor will receive a bonus. There are no
excuses such as weather delays that may be claimed for not meeting the earlier
completion date. On the other hand, there are no disincentives (other than normal
liquidated damages) for not meeting the later completion date.
C. PURPOSE
The primary purpose for the use of lump sum bidding is to provide the Mobility
Authority greater cost certainty at an early stage. This approach allows a level of risk of
quantities to be placed on the contractor. Deferring this risk to the contractor should
establish a more accurate estimate of the total construction cost because variances
between plan quantities and as-built quantities, except significant changes as defined in
the contract, will not result in a contract value change. The Project will utilize a revenue
loaded schedule, based upon the lump sum price, for payment applications which will
reduce the cost of the construction management consultant in performing field
measurements and preparing pay documents. Burden of proving major quantity
differentials will be placed upon the contractor.
The primary purpose for the use of a no-excuse bonus is to provide the Mobility
Authority greater schedule certainty by increasing the probability of early or on-time
completion through contractor incentives.
D. SCOPE
The scope of this SEP-I4 request is limited to the Project. The TxDOT Standard
Specification Items I through 9 will be modified to provide for the lump sum bid and the
no-excuse incentive clause.
E. SCHEDULE
The Mobility Authority's goal is to complete the Project by the end of 20 II. To achieve
this goal, the Mobility Authority has established the following preliminary schedule (all
dates in the future are subject to change):
Environmental Clearance for Project:
- May 2009 – Concurrence with finding of Statement of Continuous
Activity issued by FHW A for Segment 1
- October 2009 – Finding of No Significant Impact issued by FHW A for
Segment 2
- December 2009 – Finding of No Significant Impact issued by FHWA for
Segment 3
Segment 1:
- June 2009 – Segment 1 Final PS&E documents complete
- June 2009 – Segment 1 Authorization of Federal Funds
- October 2009 – Segment 1 Start Construction
- October 2011 – Segment 1 Substantial Completion
Segment 2:
- June 2009 – Segment 2 Final PS&E documents complete
- October 2009 – Segment 2 Environmental Clearance
- October 2009 – Segment 2 Authorization of Federal Funds
- November 2009 – Segment 2 Start Construction
- October 2011 – Segment 2 Substantial Completion
Segment 3:
- June 2009 – Segment 3 Final PS&E documents complete
- December 2009 – Segment 3 Environmental Clearance
- January 2010 – Segment 3 Start Construction
- October 2011 – Segment 3 Substantial Completion
SEP-14 Report to FHWA
- January 2012 – Final report to FHWA (addressing all segments)
F. GOALS
The Mobility Authority anticipates that the experimental features described herein will
achieve the following goals:
- Improve the Mobility Authority's ability to forecast Project construction cost
accurately early on in the Project.
- Increase the probability of early or on-time completion.
- Provide additional support for Project financing through issuance of toll revenue
bond at more attractive rates.
G. DESCRIPTION OF BIDDING
The Mobility Authority will require bidders to be pre-qualified by TxDOT prior to
submitting their bid. The Mobility Authority will prepare a bid set of documents that will
include the plans, specifications, and an estimate of quantities for the Project. Bidders
will be required to submit unit prices for all quantities of work. The selection will be
based on the lowest responsive bidder. After contractor selection has been made, the
contract price will be converted to a lump sum bid price calculated by the unit prices and
plan quantities submitted with the bid.
H. SPECIAL PROVISIONS
Special Provisions and General Notes will be issued to implement the lump sum bidding
and the no-excuse incentive clause. The following is a summary of the General Notes
and Special Provisions to be used:
000-01 Measurement and Payment
The Special Provision defines the Project as a lump sum payment project.
It provides three mechanisms whereby the lump sum may be adjusted.
They are as follows:
- Provisions for "Special Measurement Items" — Prior to bid, the
Contractor will be provided an opportunity to review the plans and
inspect the jobsite to make an independent assessment of the proposed
project quantities for the purpose of presenting a lump sum bid. Three
"Special Measurement" items are included in the contract, excavation,
embankment, and drilled shafts, whose final quantities and associated
costs may be adjusted based on the actual quantity of work performed
at the end of the project.
- Provisions for owner or contractor initiated Change Order work.
- Provisions for bonus or liquated damage payments based on incentive
/discentive special provisions for completion of the work.
004-001 Scope of Work
The Special Provision establishes the "contract intent" of the Project as a
lump sum payment contract. The responsibility for the work quantities
belongs to the contractor, except for "changes in the work." The Special
Provision requires unit bid pricing for Change Order work, unless the
character of the work is significantly changed. The Special Provision
defines a significant change in the character of the work, thereby,
triggering a Change Order, when the character of the work is materially
changed, any of the three special measurement items (excavation,
embankment and drilled shafts) vary by more than 5% of the bid quantity,
or cumulative Change Orders affect the quantity of major item by more
than 25%.
008-001 Prosecution and Progress
The Special Provision defines the requirements for the contractor to
prepare the "revenue loaded" schedule and the process to submit a
monthly pay request. The Special Provision requires the monthly pay
request include certification by a principal representative of the contractor
affirming the pay request is accurate. The certification requirement should
increase the likelihood the contractor submitting accurate pay requests,
therefore, reducing costs to the Mobility Authority.
The Special Provision includes a clause where the schedule float is a
mutually shared resource between the contractor and the Mobility
Authority. This reduces the risk of delay claims and associated costs.
The Special Provision includes a no-excuse bonus incentive for early
completion, a daily incentive (if the no-excuse date is not met), and
liquidated damages for late completion.
009-001 Measurement and Payment
The Special Provision removes the requirement of the Engineer to
measure work items except for the Special Measurement Items and
removes the use of the "Plan Quantity Items." The Special Provision
defines the process of the contractor submitting and the Engineer
reviewing monthly pay estimates. These are required to be consistent with
Special Provision 000-001 Measurement and Payment and the needs for a
lump sum payment project.
I. MEASURES; EVALUATION
The Project, with the requested experimental features, will be evaluated on a range of
factors, including:
Construction Cost: When construction of the Project is complete, the final cost of
construction will be compared to the lump sum bid price for construction. This
will indicate how well the lump sum payment approach helped obtain the goal of
accurately forecasting the final Project construction cost.
Project Completion: The Mobility Authority will compare the actual Substantial
Completion Date to the Substantial Completion Milestone, originally set in the
contract for the no-excuse bonus, to determine what effect the clause had on
impacting the actual substantial completion date.
J. REPORTING
The Mobility Authority will submit a final report to FHW A upon completion of the
Project. The report will include an evaluation of the techniques used, the industry and
Agency reactions and issues, and a recommendation as to whether or not to use this
construction method on future projects.
K. CONCLUSION
We believe the procedures described herein will result in successf11l construction of the
next phase in the development of the 183A Turnpike Project. We look forward to
working with the FHW A as the Project progresses, and to providing you and others with
the benefit of our experiences utilizing approved innovative approaches to project
implementation.
|